Stakeholder Comment and AESO Replies Matrix AESO Consultation – Market Participant Choice Discussion Paper Date of Request for Comment: 2011-09-29 Period of Consultation: 2011-09-29 through 2011-10-28 Discussion Paper – Executive Summary and Purpose Do stakeholders have any comments on the Executive Summary and Purpose sections? Stakeholder Stakeholder Comment Alberta Wind Energy Corporation As an overall comment, Participants building their own transmission facilities should not be treated as a TFO and be subject to all the regulations pertaining to TFO’s. Rather, it would be far easier to allow participants to build their own transmission connections (either for generation or load) to the existing TFO facilities and then meter their power at the point of connection and settle for it at that point rather than having to do all the reporting for Tariffs and Cost Recoveries. The Participant would then be in control of all costs for the connection and would build the capital costs into his costs of the project to determine the feasibility of the project. Therefore there would be no need for AESO to be involved in determining the effects on tariffs. AESO Replies Should another party want to tie into a line that had been built by a Participant, that party would reimburse the original owner for the original costs on the basis of the % of capacity used and the length of distance from connection AESO Replies to Stakeholder Comments: 2011-09-27 Page 1 of 119 point to connection with TFO. ATCO Power I do not believe that for a connection to one facility it is necessary to have all of these existing regulations apply. If we are going to change the procedures let’s simplify them as much as possible. ATCO Power suggests the term “transmission facility” be replaced with the term “generator connection facility” for the purposes of “market participant choice.” An example of this is displayed in following language changes (changes are italicized) for the first paragraph of Section 1: The AESO is initiating discussion and consultation on providing market participants the opportunity to construct, own, operate and maintain the generator connection facilities required to connect their facilities to the interconnected electric system; referred to as “market participant choice” for purposes of this discussion paper. The term “transmission facility” as defined in the Act specifically excludes a generating unit or an electric distribution system. While some connections may be “transmission facilities” others may not, so to meet the anticipated intent of the “market participant choice” process, the language should reflect all connection types. Additionally, the use of the term “transmission facility” in the context of a generator connection facility may introduce undue confusion as to the definition of existing load and generator connection facilities. In the third paragraph of Section 1, the discussion paper states: AESO Replies to Stakeholder Comments: 2011-09-27 Page 2 of 119 Should a market participant choose to provide its own connection project, the market participant would assume all accountabilities of TFO, including construction, ownership, operations and maintenance, and all other obligations stipulated in legislation and AESO authoritative documents. Capital Power Corporation ATCO Power would like to request clarification as to why the market participant would be required to assume all accountabilities of a TFO, even in cases when the connection is a sole use facility for the purpose of generator connection which cannot be anticipated to become transmission in the future. Historically, when a market participant has built their own connection facility at their own cost, the market participant was not obliged to be classified as a TFO. ATCO suggests that the assumption of all accountabilities of a TFO be considered on a case-by-case basis. Capital Power appreciates the opportunity to comment on the AESO’s Market Participant Choice (“MPC”) Discussion Paper (“discussion paper”), published on September 29th, 2011. The purpose section of the discussion paper document should provide more insight into the drivers of the MPC process and explain why the AESO has undertaken this analysis and consultation. In Capital Power’s experience, the fundamental flaw with the AESO connection process is that the parties that bear all of the risks (connection customer) of the inability to meet target inservice dates are unable to mitigate these risks. Therefore, a process that allows the connection customer to take control of specific connection process activities in situations where they are better equipped and willing to manage the AESO Replies to Stakeholder Comments: 2011-09-27 Page 3 of 119 timing and regulatory risks is essential and the MPC model must be developed with this goal in mind. Capital Power does not think that most market participants that have requested the development of this process would endeavor to own their transmission facilities and therefore become a transmission facility owner (TFOs) under the EUA. The comments made at the MPC stakeholder session on October 14th and the ongoing generator owner/ transmission owner discussions related to Alberta reliability standards support this view. Therefore, it is essential that the process is not so cumbersome that it is not likely to be employed by market participants that merely wish to take responsibility for some of the TFO activities for their own connection facilities but not become a TFO themselves. The determination of which party will be accountable for each activity can be negotiated between the connection customer and the incumbent TFO and the AESO’s process should be flexible enough to accommodate the agreed upon structure provided the applicable technical requirements are met. It is essential that the process accommodates arrangements where a generator can build the radial connection for their facilities in collaboration with the TFO and then transfer the ownership and operating obligations to the TFO upon energization. The process should not require connection customers that proposing to provide their own connection facilities to become a TFO. The connection customer could be treated like any subcontractor that the TFO hires to undertake some TFO activities, such as construction. There has been considerable AESO Replies to Stakeholder Comments: 2011-09-27 Page 4 of 119 discussion between generators and the AESO regarding the distinction between generators who own the radial lines connecting their generator to the Alberta grid and traditional TFOs when determining applicability of Alberta Reliability standards. Generators have resisted being deemed TFOs under the reliability standards due to the extremely burdensome requirements placed on TFOs. As Alberta reliability standards are just one area of requirements applicable to TFOs, a process that requires market participants wishing to provide their own connection facilities to satisfy all the obligations of a TFO is not likely to be utilized. In the Executive Summary section, the AESO states that “should a market participant choose to provide its own connection project, the market participant would assume all accountabilities of a TFO, including construction, ownership, operations and maintenance and all other obligations stipulated in legislation and AESO authoritative documents”. However, in the Introduction section of the discussion paper, the AESO highlights that the “end state should not result in any kind of patchwork operation of the interconnected electric system”. The two statements appear contradictory as the first implies that market participants that wish to provide their own connection facilities would be required to operate and maintain it, while the second statement implies that the process should not result in several new transmission operators. The purpose of this process should enable commercial arrangements to be implemented so that connection customers wishing to provide their own connection facilities may do so. AESO Replies to Stakeholder Comments: 2011-09-27 Page 5 of 119 FortisAlberta Inc. Industrial Power Consumers Association of Alberta AESO Replies to Stakeholder Comments: 2011-09-27 Capital Power urges the AESO to develop a flexible process that can accommodate reasonable arrangements negotiated between the incumbent TFOs and the connection customer. Capital Power understands the need to ensure that all transmission facilities are built to a minimum set of requirements and operated in a safe and reliable manner, but these requirements are not likely to remain the responsibility of the connection customer. The design of the connection facilities and subsequent operation and maintenance of them will likely remain the responsibility of the incumbent TFOs. At the core of FortisAlberta’s business is the provision of service to end use customers. FortisAlberta would support initiatives which assist such customers to receive prompt and economic service, and would be prepared to engage in such initiatives to that end. Our detailed comments follow. In the executive summary, the AESO points out that the legislative framework permits it to proceed with the discussed market participant choice initiative “provided there are not adverse impacts on the Alberta interconnected system and market participants.” FortisAlberta is generally supportive of initiatives that promote the orderly and economic development, as well as the safe and reliable operation of the Alberta interconnected system. Cost and schedule concerns can have an impact on orderly and economic system development and FortisAlberta is therefore interested in improvements that can be made on that front. IPCAA members have been concerned with the costs and long schedules associated with the current customer connection model. As such, Page 6 of 119 IPPSA we welcome this AESO initiative to examine customer choice. However, industrial loads are not interested in taking on the responsibilities of becoming TFOs. As such, the AESO should consider: (1) How can we enable customer choice without placing unnecessary burdens on the customers? And (2) Are there policy changes (beyond the current structure) that would enable market participant choice? IPPSA greatly appreciates the AESO’s efforts in undertaking the consultation related to confirming market participants’ (“MPs”) ability to construct, own, operate and maintain transmission facilities connecting their generation facilities (“Connection Facility(ies)”) with the bulk Interconnected Electric System (“AIES”) (Referred to hereinafter as the “MP Choice Model”.) We look forward to working with the AESO on developing this model. Joss Wind Power Inc. Mainstream Renewable Power MEG AESO Replies to Stakeholder Comments: 2011-09-27 We agree with the AESO’s point that this project is in response to participant concerns with schedule and costs related to construction of Connection Facilities. We are seeking an AESO process that enables choice, which we believe will improve schedule management, cost control and project control. However, we do express two concerns with the AESO’s proposed approach: 1) with the AESO’s suggestion that the MP Choice Model requires assumption of all Transmission Facilities Owner (“TFO”) duties, and 2) with the notion that changing ownership within the connection process necessitates a loss of position in the queue. We strongly support this initiative No MEG agrees with the AESO that market Page 7 of 119 participant choice is permitted in legislation and applauds the AESO’s initiative to implement customer choice in transmission interconnection to the grid. As interconnection to the grid is critical for both load and supply customers, MEG believes providing the means by which customers can better control both cost and schedule is imperative. Suncor Energy Marketing Inc. The Office of the Utilities Consumer Advocate AESO Replies to Stakeholder Comments: 2011-09-27 The simplest and most effective means for control of cost and schedule is competition in the traditional franchise owner utility model. We would discourage a framework that introduces options for competition in principle but that in practice is unworkable due to unnecessary, ineffective and non-value adding administrative burdens. Suncor applauds the AESO’s initiative to bring broader choice to transmission connection. Legislation does indeed permit transmission facilities to be built and owned by parties other than TFOs We would like to encourage a framework that permits such ownership without unnecessary burdens, and encourages the maximum use of the option by Market Participants as well as competition in the market for such facilities. The UCA notes AESO conclusion that the desire for an alternative to the status quo development of transmission projects by incumbent TFO’s is based on the general perception of “high cost” and “extensive schedule”. The UCA supports initiatives aimed at reducing overall transmission costs including cost savings that result from the efficient connection of load and generation facilities to the Interconnected System. In addition to cost Page 8 of 119 TransAlta Corporation savings associated with construction and timely service connections, the measure of overall transmission costs must consider any incremental administrative and technical costs resulting from an increasingly complex transmission system. TransAlta has long advocated for restoration of the right of customers to construct, own and operate connection transmission lines which was removed in the EUA revisions in 2003. We are appreciative of the AESO initiating consultation to advance the discussion on this matter. Discussion Paper – Introduction Do stakeholders have any comments on the Introduction Section? Stakeholder Stakeholder Comment ATCO Electric The AESO’s proposal to introduce Market Participant Choice represents a fundamental shift in the way that transmission development takes place within Alberta and has the potential to have negative consequences for all transmission customers. AESO Replies This proposal appears to be an attempt to meet the needs of a particular segment of the customer population – those with projects that qualify and the capability to manage their own connections - to the possible detriment of the larger population of customers who pay for transmission. Project proponents seeking to connect their project to the grid and who are clearly driven by cost and schedule will not necessarily act in the public interest. A multitude of players with a different focus from that of incumbent TFOs AESO Replies to Stakeholder Comments: 2011-09-27 Page 9 of 119 could have significant impacts on the broader transmission industry including: Impacting the marketplace for stakeholder consultation and landowner compensation in ways that increases costs, sets new precedents, presents stakeholders with a fragmented view of transmission development and increases saturation of consultation with stakeholders in busy areas. Introducing heightened competition for construction resources at a time when transmission development in Alberta is at an all time high, thereby increasing costs for transmission to all ratepayers. Increasing the cost to ratepayers of monitoring TFO compliance to AESO Rules and Reliability Standards; Increasing costs to ratepayers of additional regulatory proceedings; Exposing ratepayers to additional costs associated with duplicating the existing infrastructure (sparing, for example), systems and processes and other activities of incumbent TFOs; The use of substandard materials and designs to minimize project costs which could impact reliability; Incremental operational and health and safety risks associated with multiple Transmission Facility Owners operating within a particular geographic region. While various standards may exist on paper, concerns associated with the complexities and additional costs of integrating the operations of multiple TFOs cannot be overstated. The ability to operate a seamless integrated system and provide trained, experienced personnel that can respond to emergency situations could be AESO Replies to Stakeholder Comments: 2011-09-27 Page 10 of 119 compromised if matters are not handled carefully. Interconnecting market participants, who are not seeking to act in the best interests of the public, do not bring the same perspective as public utility TFOs whose mandate is to fulfill applicable legislative requirements. ATCO Electric acknowledges that the EUA provides the AESO with discretion to request a proposal from a market participant, other than the incumbent TFO in whose service area the project is located. In considering the exercise of its discretion, the AESO must be cognizant of the fact that there is a single legislative scheme that would be applicable to all TFOs – new or incumbents. The mandatory nature of the legislation must be respected and applied equally to all TFOs (see, for example, Sections 37 and 39 of the EUA). ATCO Electric is of the view that the overall public interest will be best served by ensuring that the AISE is constructed in an efficient, safe and reliable manner. The concept of market participant choice as set out by the AESO in this discussion paper clearly deviates from the direction set out in the 2003 Transmission Development Policy Paper that underpins the current legislative framework. Following are excerpts from that paper: “Transmission will continue to be regulated as a natural monopoly by the EUB to ensure open, non-discriminatory access and to protect the public interest. Since transmission is characterized by large economies of scale, there are efficiencies in having an incumbent Transmission Facility Owner (TFO) provide operations and maintenance services to new facilities that are required in a geographic area AESO Replies to Stakeholder Comments: 2011-09-27 Page 11 of 119 they currently serve. This localized “critical mass” of service infrastructure allows the incumbent TFO to respond to apparatus failures and other events that may jeopardize service to customers. A “patchwork quilt” of ownership does not have the same level of coordination or economy of scale and so it would not operate as reliably and efficiently. Contiguous ownership of lines, substation facilities and the associated operating infrastructure therefore provides the greatest assurance of reliable and safe operation of the transmission system for customers (and employees) and is therefore in the public interest. To accomplish this intent, all new transmission facilities, including radial interconnection facilities (emphasis added), will be direct-assigned to the incumbent TFO’s. Projects involving connections or upgrades to existing transmission facilities or use of existing right-of-ways will also be direct assigned to the incumbent TFO to ensure safe and reliable service.” The 2003 policy paper was clearly the product of exhaustive stakeholder consultation and deep consideration as to the direction that transmission development within the province of Alberta should take. The conclusions contained in this policy paper should not be disregarded in the absence of a full scale review at the policy level to ensure that adjustments such as that contemplated within the AESO’s discussion paper proceed in the context of a thoroughly vetted and broader framework for transmission development. This proposal should not proceed any further absent a comprehensive review that provides the following: AESO Replies to Stakeholder Comments: 2011-09-27 Page 12 of 119 Demonstrated benefits of the proposal to all transmission customers, particularly an examination of the legitimacy of the claim that market participants could improve cost and schedule. Many steps in the connection process are mandated in legislation and involve agencies like the AESO and the AUC. It is difficult to imagine how significant schedule improvements could be achieved without either allowing market participants to by-pass portions of the process or by activities of market participants that may have detrimental effects on other transmission customers. AESO Replies to Stakeholder Comments: 2011-09-27 Additionally, TFOs are currently bound through AESO Rules to adhere to strict competitive practices in relation to material and services that comprise the majority of transmission project costs. It is difficult to imagine where significant cost savings could be achieved without compromising quality of materials or construction, particularly given the purchasing power and readily available standards that can be leveraged by incumbent TFOs; A thorough analysis of risks and incremental costs associated with the introduction of new TFOs; A proposal to insulate other transmission customers from the additional costs caused by the few customers who would be positioned to take advantage of this proposal; Eligibility criteria for both participants Page 13 of 119 ATCO Power AESO Replies to Stakeholder Comments: 2011-09-27 and projects that minimizes operational risk; A thorough examination of all the possible consequences of proposal and proposed mitigation where necessary (adverse effects in the areas of consultation, compensation, competition for resources, etc.); Consideration of how market participants, who are often competitors, will be compelled to coordinate their project execution efforts where projects have the ability to impact another market participant’s connection. The cancellation or delay of one market participant’s connection could impact another’s connection project scope and/or schedule; and Consideration as to how responsibilities and obligations of new TFOs will be assured during the project development phase for new TFOs. Given the way TFO is defined under the EUA, obligations are only effective once a transmission facility is energized. In short, whether there are legislative barriers to the Market Participant Choice proposal or not, the AESO bears a burden of responsibility to ensure that it is the right course of action and clearly in the public interest. That burden of responsibility has not been met based on the discussion paper that the AESO has presented to stakeholders. ATCO Power would like to re-iterate the suggestion that the term “transmission facility” be replaced with “generator connection facility” for the purpose of “market participation choice.” A second example of language changes (changes are italicized) are shown below for the Page 14 of 119 first paragraph of Section 3: Market participant choice refers to providing the opportunity for a market participant to construct, own, operate and maintain (“own”) the generator connection facilities required to connect a market participant’s facilities to the interconnected electric system. For clarity, market participant choice does not include bulk transmission system projects. In addition, Paragraph 6 of Section 3 states: In addition, section 28(3) of the Transmission Regulation states that an owner of a generating unit interconnected to the transmission system may not prohibit interconnection or access to the interconnection facilities by other market participants. It is our interpretation that this section of the Transmission Regulation clearly indicates that there is a difference between a generator connection facility and a transmission facility. To insure consistency with the Regulation, ATCO Power suggests that the language used in the “market participant choice” process reflect that in the Regulation; and include the distinct differentiation between a generation connection and transmission. Capital Power Corporation Enbridge Pipelines AESO Replies to Stakeholder Comments: 2011-09-27 ATCO Power would like to request clarification regarding the term “bulk transmission system.” No comment In general we support the idea of participant choice to improve on cost and schedule and to help TFO’s manage the current growth cycle. However, we’ve two concerns: Schedules: in our experience the long timelines are due to the upfront TFO/AESO planning. Page 15 of 119 FortisAlberta Inc. Unless planning resources are beefed up what is the solution to shorten planning duration? Costs: If the AESO investment policy favors utility build as it currently does on substations with DTS & PSC then we’re not convinced there would be substantial savings with lines. Would the investment levels be same regardless who builds? Would Rider-A apply to reduce operating costs? While “market participant ownership of transmission facilities is not entirely new”, apart from ISDs, a “patchwork” of ownership of transmission facilities has the potential to create issues and concerns that are not readily addressed by the legislation. Under a patchwork of ownership structure, the assets and practices of the various owners need to be interconnected, coordinated and aligned, without restricting system access service and electric distribution service to future customers. Ultimately, ensuring the orderly and economic development of the Alberta interconnected electric system as a whole should continue to be the primary mandate when considering such an approach. For example, the AESO has indicated that gaining access to transmission facilities is not a barrier, since all TFOs will follow the same regulations. However, by failing to allow for adequate and suitable available land for future expansions, one market participant/TFO’s practice could create barriers for system access service and electric distribution service to other or future customers. As another example, FortisAlberta seeks to provide timely connections for new customer service requests in its service area. These AESO Replies to Stakeholder Comments: 2011-09-27 Page 16 of 119 Industrial Power Consumers Association of Alberta IPPSA customers’ project costs and schedules could be impacted by the various new entrants’ practices regarding crossing agreements, proximity to road allowance, and joint-use solutions (transmission lines and distribution lines sharing poles). IPCAA views the requirements associated with becoming a TFO as a serious barrier to market participant choice. Industrial customers may be interested in constructing connection facilities, but are significantly less interested in owning, operating and maintaining TFO facilities. If this issue is not addressed, we may end up with a MPC process and no market participants interested in exercising their choice and constructing their own connections. To the point, even though it would be reasonable to require operation of Connection Facilities in compliance with the Hydro and Electric Energy Act (“HEEA”) objective of observing safe and efficient practices, it is IPPSA’s view that reaching this objective does not necessarily require compliance with all of the extensive TFO duties under applicable legislation. For example, it does not make sense to require a Connection Facility owner to submit with the Commission a tariff for approval for rates payable by the AESO for using a Connection Facility, since no such rates will be payable by the AESO. Based accordingly on the AESO’s own distinction between Connection Facilities versus bulk facilities, it follows that different obligations for Connection Facilities owners vis a vis bulk facility owners (or TFO’s) should apply. We are concerned that the imposing all TFO obligations onto generators for their connection AESO Replies to Stakeholder Comments: 2011-09-27 Page 17 of 119 facilities will deter participants from seeking to exercise choice, thus resulting in a MP Choice Model without a real choice. Joss Wind Power Inc. Mainstream Renewable Power MEG Going forward, we recommend that the AESO define the minimum obligations it needs from Connection Facility owners, as it relates to the AESO’s responsibility to operate a reliable system. This initiative is an important step to improve the competitiveness and the cost and timing for new connections. At this stage in the process, it makes sense to exclude bulk transmission system projects. No MEG believes it would be helpful for the AESO to clearly define “bulk transmission system projects”. MEG believes it would be helpful for the AESO to identify specific transmission facilities, not are not part of an ISD, that have been designed/constructed/owned/operated by nonTFOs and to further clearly identify if any of these facilities have posed reliability, operational or planning concerns. This information would advance industry’s common knowledge on the extent of non-TFO ownership of transmission facilities and if non-TFO ownership poses higher reliability, operational and planning risks and concerns in comparison to TFO ownership. MEG believes all transmission facilities should meet technical and reliability standards but strongly encourages the AESO not to institute non-reliability requirements that are onerous, add little value and by their burdensome nature may discourage market participant customer choice. One such example of an onerous, no AESO Replies to Stakeholder Comments: 2011-09-27 Page 18 of 119 Suncor Energy Marketing Inc. value and burdensome requirement would be requiring a non-TFO market participant to file a tariff if there is only one market participant using the subject facilities. If there is more than one user of the facility, and commercial arrangements fail, a tariff may be required. Suncor agrees that all owners of transmission facilities should meet reliability standards. However Suncor disagrees that owners of transmission facilities related to market participant choice should be burdened with tariff filing. In the future, should there be more than one user of such a facility, then a tariff may be necessary, but only in the event the additional users are not able to connect under reasonable commercial terms and conditions. The Office of the Utilities Consumer Advocate AESO Replies to Stakeholder Comments: 2011-09-27 While the non-duplication of facilities and the right of adjacent market participants to access service, needs to be addressed, these issues should not necessarily cause an incumbent market participant line owner to be compelled to form a utility in order to provide service. Rather the participants should be allowed to make a commercial arrangement for access in a reasonable timeframe. If this is unsuccessful, the participant seeking service should be afforded the opportunity to appeal to the AUC for a ruling, and if necessary an order to provide service. However under no circumstances should the provision of such service cause economic loss to the incumbent line owner. The UCA would agree at this point that the Alberta Reliability Standards, ISO Rules and AUC Rules mitigate many of the concerns related to “patchwork” operation of the interconnected system associated with additional TFOs. With the variety of Page 19 of 119 TransAlta Corporation connection projects however, there may be operating complexities created where separate TFO facilities become intermingled within a specific substation. Presumably, Operating Agreements could ensure safe and reliable operation. We agree that the legislation is permissive. Discussion Paper – Eligible Market Participants Do stakeholders agree with the suggested eligible market participants? If you disagree, please provide supporting rational for that position. Stakeholder Stakeholder Comment ATCO Electric Eligibility of market participants should only be established after a more thorough examination of this proposed concept. Eligibility may be one way in which costs and risks are appropriately managed. Limitations based on market participants’ qualifications may be necessary and appropriate to effectively manage cost and operational risks. ENMAX Corporation EPCOR Utilities Inc. AESO Replies to Stakeholder Comments: 2011-09-27 AESO Replies ATCO Electric understands that no change to existing legislation is being considered as part of this overall process. As such, the existing rights of DFOs under s.101 of the EUA is not the subject of comment. With respect to the AESO's proposal, the wording of the legislation would not appear to exclude any market participant, including DFOs, from consideration within s. 1(l)(ee) of the EUA. Notwithstanding, that the legislation provides the AESO with discretion to request a proposal from a market participant, in reality, certain parties may not be appropriate candidates for receiving such a request (particularly if they are not the party directly associated with the subject interconnect). Agreed EPCOR believes further consultation and Page 20 of 119 consideration needs to be given as to which market participants should be eligible to participate in this initiative. FortisAlberta Inc. EPCOR wishes to understand the intent of including DFOs as eligible market participants for this initiative. Is it the intention of the AESO that a DFO could elect to own a new transmission connection (POD) rather than the incumbent TFO? If so, does the AESO consider this as fundamentally changing the concept of a TFO service area as it relates to such connections? If the AESO proceeds with the “market participant choice” initiative suggested in the discussion paper, FortisAlberta would submit that any AESO customer (market participant) who is an ISD or has received a EUA Section 101(2) release from the AESO and the distribution company should be provided an equal opportunity to be eligible for providing their own transmission extensions. Currently, FortisAlberta works with the incumbent TFO and the AESO to ensure the orderly, economic and efficient development of the interconnected electric system for all customers in a given area. FortisAlberta has also been open to providing Section 101(2) releases upon satisfying itself that a customer becoming a direct connected customer of the AESO does not impinge on that objective. The AESO also has the opportunity to determine who would be eligible, presumably based on satisfying itself that the orderly, economic development of the system and system access service for future customers is not threatened by doing so. Should the AESO proceed with the initiative, AESO Replies to Stakeholder Comments: 2011-09-27 Page 21 of 119 FortisAlberta agrees that DFOs be included in the list of eligible market participants as they are responsible for arranging system access service for all customers in their service area, as per the EUA. Further, the issues of cost and schedule, as raised by the paper, are as important to DFOs and their end-use customers, as to other large direct customers of the AESO. Accordingly, if market participant choice is made available, it should be made available as an option for DFOs as well. A patchwork of transmission line ownership introduces a number of concerns. A number of new entrants will be entrusted with operating transmission facilities for which operational problems could reach far beyond the new TFOowned facilities and impact the reliability of Alberta’s interconnected electric system (transmission and distribution) as a whole. Industrial Power Consumers Association of Alberta As stated in the discussion paper, these new entrants may be typically more motivated by the schedule and cost of their particular project and the reliable operation of greater system may not be of primary interest to them. Recognizing this element of future entrants being more focused on their projects rather than the greater system may have some bearing on the AESO’s eligibility requirements, if this initiative proceeds. IPCAA has no concerns with the list of eligible market participants. Concerns were raised at the stakeholder session regarding the reluctance for DFOs to provide waivers for direct connect loads under section 101 of the EUA. IPCAA believes this is an issue for Industrial System Designations (ISDs) as well and suggests that the AESO AESO Replies to Stakeholder Comments: 2011-09-27 Page 22 of 119 IPPSA Joss Wind Power Inc. Mainstream Renewable Power MEG SATL Inc. The Office of the Utilities Consumer Advocate TransAlta Corporation AESO Replies to Stakeholder Comments: 2011-09-27 request that the MSA to provide clarity on the ability for DFOs to “frustrate” this process – and the expected behaviour of all parties involved. As a generators’ association, IPPSA supports the inclusion of ‘direct connect generators’ and ‘dual use (generation and load)’ on the list of parties identified and will let other stakeholders speak for their inclusion. We agree. Yes. It is necessary however to clearly identify the administrative and technical requirements for becoming a TFO, as the time and costs required may make the option prohibitive. MEG agrees with the suggested list of eligible market participants. Similar to the types of Eligible Market Participants listed in this section, merchant transmission developers face the same issues (risk of regulatory delays and interconnection queue bottlenecks) and must comply with all industry standards, rules and operating procedures. For these reasons, merchant transmission developers should be included as Eligible Market Participants. The UCA agrees with the assessment that Distribution Facility Owners be considered eligible Market Participants for the purpose of this discussion. An opportunity may exist for a DFO to produce cost savings by participation in the construction, ownership or operation of transmission facilities and should not be precluded at this point. With regard to DFOs the outcome as we understand it is that the DFO, if not already a TFO, becomes a TFO. It is important to remember that the context of this is in regard to a Customer Connection and a DFO is not as such a customer. The choice being requested is to have a customer construct, own and operate connection transmission lines and not Page 23 of 119 have a public utility do this. If a customer is to have choice then it must be the decision of the customer and not the DFO. Discussion Paper – Eligible Connection Projects Do stakeholders agree with the suggested eligible connection projects? If you disagree, please provide supporting rational for that position. Stakeholder Stakeholder Comment Alberta Wind Energy Corporation New process could still delay Participant’s projects by having to work with an incumbent TFO. Project eligibility should only be established after a more thorough examination of this proposed concept. Eligibility may be one way in which costs and risks are appropriately managed. Limitations based on specific facilities and the degree of risk they present to costs, other market participants and / or system may be necessary. ATCO Electric Replies While the legislation is arguably broad enough to cover a variety of projects, the overall public interest should play a role in determining whether certain complex projects, that pose safety and reliability challenges if not coordinated properly, are viable candidates for market participant choice. Cenovus Energy Inc. Enbridge Pipelines AESO Replies to Stakeholder Comments: 2011-09-27 If an incumbent TFO were put in a position where the safety and reliability of its system and/or employees could be put in jeopardy, it may have no choice but to refuse to complete the contemplated interconnect with its main line. The AESO must be aware of such concerns and factor them into the exercise of its discretion. The AESO should seek to avoid such circumstances from arising. Agree that all projects should be eligible. Opening up the more complex connections that Page 24 of 119 ENMAX Corporation EPCOR Utilities Inc. involve In/Out and RAS schemes will add further complexity of added coordination between multiple TFOs to safely protect the system, load shed and respond to emergencies. Who would ensure assets are properly maintained? Who will take responsibility when things go wrong and risk bringing down the grid? Currently TFOs aggregate area customer load (that only they know) to propose the best planning solution. How would this central planning take place when new TFOs would not know the area load growth plans? Who would decide on fair line sharing costs on a line owned by a customer TFO. Who would scrutinize the original construction costs are not exaggerated to gain larger line share in future? Who would do line upgrades if an existing line owned by a customer TFO needs upgrading to connect a new load? Agreed This is a rather broad statement. As discussed in the response to question 3 above, EPCOR would like to better understand the intention behind choice for DFO connections. EPCOR presumes that the AESO is referring to connection for all “transmission” voltages. EPCOR believes that the AESO must develop a very clear and precise definition of what constitutes a transmission connection, e.g. where it would begin and end. EPCOR does not believe that it should include “system” infrastructure or refurbishments or extensions to existing transmission connections. The AESO must consider whether it would allow multiple TFOs owning and operating different assets within a substation. If such a scenario were to take place, coordinating access, work and AESO Replies to Stakeholder Comments: 2011-09-27 Page 25 of 119 approvals between differing entities would add to time and cost and increase the risk of an operational upset. FortisAlberta Inc. Industrial Power Consumers Association of Alberta IPPSA AESO Replies to Stakeholder Comments: 2011-09-27 EPCOR is also concerned about the possibility that customers which are currently serviced adequately at distribution voltages would seek to obtain service at transmission voltage. This would create the risk of a non-economic bypass, resulting in the duplication of assets and the potential for stranded distribution assets. The discussion paper does not comment specifically about the substations that will be associated with each of the contemplated transmission lines. Under the currently approved AESO tariff, customers have the option of owning and operating their own transformation substation and garnering a Primary Service Credit. FortisAlberta assumes that under the AESO’s initiative, if it were to proceed, new market participants who are TFOs building their own transmission extension could continue to choose the above option or alternatively include the transformation substation as a TFO cost. Similar to the comments regarding eligible market participants, with increasing complexity of projects, FortisAlberta has increasing concern regarding the market participants’ reliability programs, impacts of potential failures, and stocking of spare equipment, etc. IPCAA agrees that all transmission connection projects should be eligible for market participant choice. We support the AESO’s view that all Connection Facilities projects should be eligible for MP choice. Page 26 of 119 Joss Wind Power Inc. Mainstream Renewable Power MEG Suncor Energy Marketing Inc. The Office of the Utilities Consumer Advocate TransAlta Corporation We believe the proposal that MPs work with TFOs to coordinate construction, connection and operations of Connection Facilities appears reasonable, but we’ll defer to our members should they have any comments on this section based on their experiences or expectations. We agree. Yes MEG supports the proposal that market participants work with TFOs to coordinate construction, connection and operations of the facilities in a cooperative and collaborative manner. MEG would recommend exploration of approaches that would encourage cooperation and collaboration such that customer choice in a timely and cost effective manner can be an option. Suncor agrees with the suggested eligible connection projects but encourages greater clarity on definitions. The UCA suggests that eligible projects will be self eliminating on the basis of timing, scale or administrative complexity no matter what Model is chosen to facilitate Market Participant Choice. The challenge is to demonstrate improved costs and efficiencies from whatever Choice is made available. Directionally we agree that all connection projects should be eligible. We are, however, concerned that connections to the bulk system, which we would define as 240 kV or higher voltages, have higher requirements (and obligations) for such connections and that they may require as such a higher degree of scrutiny. We make this distinction in comparison to 138 kV and lower voltage customer connections. We also want to ensure connections are not AESO Replies to Stakeholder Comments: 2011-09-27 Page 27 of 119 made more complex and costly and more onerous than need be if the AESO or TFOs was to over specify the technical requirements. For example, insist on specification of a switching station at the tap point. As long as alternatives for connections are options consistent with customer risk assessment and decision-making then we believe the approach is workable. Discussion Paper – Model Do stakeholders agree with the suggested model? If you disagree, please provide an alternative model and the rational supporting that alternative model. Stakeholder Stakeholder Comment Replies Alberta Wind Energy Corporation ATCO Electric The process should consider two models: the “Own” model and an alternative model where the market participant transfers ownership of the built transmission facility to the incumbent TFO for operation going forward. This will likely be a typical scenario pursued by many market participants. ATCO Electric agrees that the AESO does not have the authority to approve, refuse or mandate transfers. The AESO also does not have the authority to compel TFOs to provide maintenance or operations services in relation to facilities that they don’t own, except insofar as operational coordination to ensure the safe and reliable operation of the transmission system. Transferring an asset, once built, to an incumbent TFO may assist in achieving some of the public interest objectives outlined in the Transmission Development Policy Paper. Provided that technical requirements of incumbent TFOs are met and suitable commercial terms reached, transfers may be desirable. However, based on ATCO Electric’s experience, the logistics of transferring an asset AESO Replies to Stakeholder Comments: 2011-09-27 Page 28 of 119 Capital Power Corporation Cenovus Energy Inc. Enbridge Pipelines AESO Replies to Stakeholder Comments: 2011-09-27 (ensuring technical requirements are met and suitable commercial terms reached) can be extremely complex. Although the “own” model may work for some connection customers that would like to become a TFO, in Capital Power’s view, the AESO should not assume this would be advantageous for all connection customers. The AESO’s process should adapt to the commercial contracts agreed to between connection customers and TFOs. An alternative that may be considered by Capital Power would include the following. The incumbent TFO would review the connection requirements and design the transmission facility. The connection customer would take responsibility for constructing the facility to the specifications provided by the incumbent TFO just as any company contracted by the TFO would. Upon energization, both the ownership and operating responsibilities would be transferred from the connection customer to the incumbent TFO. In this scenario, the connection customer takes responsibility for some of the TFO requirements but ultimately it is the TFO that would be required to satisfy all the legislative and regulatory requirements. The AESO’s request requirements should be standardized and available before starting the project. Time is likely an issue to customer’s making this choice and it would be beneficial to be able to work on this proposal even before the AESO request. AESO should have published target dates for request approvals. The ability to transfer built assets to incumbent TFO is an important part of participant choice and we like to see TFO’s provide some guidance on what this may look like. TFO’s willingness to take over built assets would help Page 29 of 119 ENMAX Corporation EPCOR Utilities Inc. FortisAlberta Inc. garner wider support for this initiative. To sell to a TFO who would determine the sale price? Would sale price be based on TFO estimate or sale for a $1 and a Rider-A payment stream will apply to reduce operating costs? Would current TFO’s share their standards for customers to build to or would AESO draft new standards customer TFOs must meet to ensure an acceptable build quality? How would standards be enforced? Agreed EPCOR generally agrees with the suggested model which recommends that Rule 9.1 be amended (i.e. presumably to delete or modify AESO Rule 9.1.1.2(c)) allowing a market participant that requires an interconnection at transmission voltage to develop and own that interconnection without the need for the incumbent TFO’s consent and which does not prohibit that market participant from partnering with a third party (i.e. either as a subcontractor or through a joint-ownership arrangement) to fulfill all of its TFO responsibilities under existing legislation. FortisAlberta agrees that a market participant that proposes to become a TFO must demonstrate in its proposal readiness to perform the responsibilities of transmission facility ownership. The AESO has not identified the criteria under which they will review and accept or decline the market participant’s proposal. FortisAlberta believes this to be an important consideration that should be addressed, so that clear expectations of the TFO’s practices for construction and operation are proactively set. FortisAlberta understands that the AUC, and not the AESO, approves or refuses transfers of transmission facilities to other parties. AESO Replies to Stakeholder Comments: 2011-09-27 Page 30 of 119 Industrial Power Consumers Association of Alberta However, in the interest of safe and reliable transmission system operation, the AESO should play a role in reviewing every purchasing party’s readiness to perform the responsibilities of transmission facility ownership, and make submission to the AUC in that regard. IPCAA has some major concerns with the “Own” model. As pointed out earlier, Industrial customers are generally not interested in becoming TFOs and this model does not enable transfers of these assets to TFOs – nor does it compel incumbent TFOs to accept customerconstructed assets. Thus, a viable solution to customer problems would be the creation of “TFO Aggregators” who would take over ownership, operation and maintenance of these connection assets on behalf of customers who are not interested in assuming TFO responsibilities. These “TFO Aggregators” could be new market entities or existing TFOs. The AESO should consider whether there are existing restrictions to the creation of such entities. IPPSA AESO Replies to Stakeholder Comments: 2011-09-27 Alternatively, the AESO should provide a distinctive list of all the obligations a new “customer connection” TFO would be required to perform – and subsequently consider whether there are some obligations that will not add any value to the system and can essentially be eliminated. These “new TFOs” are not all building complicated assets (i.e. bulk system transmission), and as such, should not be required to assume the same responsibilities as incumbent TFOs. IPPSA supports the AESO’s model whereby a ‘MP assumes responsibility for all facts of the life cycle of the facility’, unless they voluntarily enter into an arrangement with the TFO to Page 31 of 119 transfer those responsibilities. Again, we are concerned with the AESO’s view that “a market participant – who is then, by definition, a TFO…” The AESO itself distinguishes between bulk and Connection Facilities and we agree that this distinction is important. Connection Facilities are small scale generatorpaid-for, radial wires usually used by one MP to carry that MP’s energy to the bulk AIES system. Bulk AIES facilities, on the other hand, are large scale, rate-payer funded interconnected facilities, often carrying energy from many generators to many end user customers. Accordingly, Connection Facilities have entirely different characteristics than the AIES – a regulated, bulk system. As an analogy, just because a homeowner owns his or her driveway, or commissions the construction of his or her driveway, it does not make the homeowner - by any stretch of the imagination - a professional road builder. We note that s. 17(m) of the EUA provides the AESO with a degree of latitude in carrying out its mandate. Recognizing the distinct obligations of market participant connection facilities owners is an area where such latitude is warranted. S. 17 m) states that an AESO duties is “…to perform any other function or engage in any activity the Independent System Operator considers necessary or advisable to exercise its powers and carry out its duties, responsibilities and functions under this Act and regulations.” AESO Replies to Stakeholder Comments: 2011-09-27 Page 32 of 119 Joss Wind Power Inc. Mainstream Renewable Power MEG Again, we request that the AESO define the obligations commensurate with Connection Facilities, as they differ from bulk AIES facilities. We generally agree with the model. However, there should be a recognition that transfer of the transmission facilities could occur at a few different stages, and not just upon energization and commissioning. We agree that the logistics of any transfers are outside the scope of the AESO, but the rules should not preclude transfers. The process should consider two models: the “Own” model and an alternative model where the market participant transfers ownership of the built transmission facility to the incumbent TFO for operation going forward. This will likely be a typical scenario pursued by many market participants. MEG supports the described “own” model – and believes that the own model permits the market participant to design/build/operate and maintain or to contract to, or divest, the “asset” at any point in the “design to maintain” cycle to a valid third party. The valid third party can be a TFO, DFO or a non regulated entity; if a regulated utility the transaction will need AUC approval. MEG does not support the suggestion that the a market participant needs to file a tariff in the circumstances that it is the only user of the facility or that it can provide service to another user under commercially agree to terms. In these circumstances, a tariff filing requirement would minimize the value of the self-connection option and would essentially, and unintentionally, support the present practice of assigning the facility to the incumbent TFO. MEG supports the flexibility to allow the market participant to contract to, or divest the asset to, AESO Replies to Stakeholder Comments: 2011-09-27 Page 33 of 119 SATL Inc. Suncor Energy Marketing Inc. the incumbent TFO or any other valid 3rd party at any point in the process providing technical and reliability standards are met. A TFO should not be required to have its own 24 hour control centre but should be able to contract for operations services (i.e. with another Alberta TFO). The aim of the market participant choice initiative should be to foster a simplified and commercially expedient manner in which market participants can connect to the grid, particularly in light of current market conditions and extended wait times for service. To this end market participants should not be mandated to become TFOs. This would be both a deterrent to use of the self-connection option and an added burden on a regulatory system that is already backlogged. Given this deterrent it is not likely that the self connection option would gain wide utilization and Suncor questions whether the effort to create the option would be worthwhile. Suncor appreciates the work done to date by the AESO on this initiative. However the option should be designed to exclude the need for the market participants to file a tariff and become a TFO. Suncor recognizes that this will require broader legislative change, but sees no reason why, analogous to the oil and gas sectors, market participants can not in effect build, own and operate their own 'gathering systems' for electricity without the burden of becoming TFOs. In addition, to open the market to competition, market participants should be allowed to contract to, or sell the line to any TFO or third party of their choice, and not simply the existing AESO Replies to Stakeholder Comments: 2011-09-27 Page 34 of 119 The Office of the Utilities Consumer Advocate TransAlta Corporation TFO in the area, under terms and conditions commercially acceptable to the parties involved and subject to approval by the AUC. The proposed “Own” model would be appropriate for larger single customer radial extensions where right of way and landowner relationships will be relevant to the long term operation of the facility. For connection projects with short extensions without a substantial substation component, the “Engineering, Procurement and Construction” (EPC) Model may be workable. The EPC Model is specifically designed to address cost and schedule issues without the ongoing TFO obligations. Significant cooperation with the incumbent TFO would be required to facilitate construction of facilities to acceptable TFO standards but the life time administration costs should be lower relative to the Own model for these types of projects. Subsequent transfer of ownership and so on are subject to a negotiated agreement and to regulatory approval of such transfer. There should be no obligation for a TFO to enter into such an agreement. There are many business models which may be negotiated in a competitive market with or without ownership change. Such agreements could cover operations, maintenance, and administration including regulatory compliance. We do not believe that customer contributed assets fit very well into a regulated ratebase business model (public utility model) and also have concerns about entities providing both regulated and non-regulated services. We believe that a competitive model can address any concerns market participants may have about taking on TFO obligations. AESO Replies to Stakeholder Comments: 2011-09-27 Page 35 of 119 Discussion Paper – Integration into the Existing AESO’s Connection Process Do stakeholders agree with the suggested key connection process procedural changes? If you disagree, please provide alternative procedures and the rationale supporting those alternative procedures. Stakeholder Stakeholder Comment Replies Alberta Wind Energy Corporation ATCO Electric The new option should be able to fit into the current AESO interconnection process. The decision point for the transmission ownership should be required during Stage 2 and be a requirement for passing Gate 2 (not at Stage 0). Without knowing what’s involved in the scope of the interconnection, it is not possible to know whether the market participant has the appetite to build and operate the transmission facilities. In addition, the incumbent TFO should be a participant in the process through Stage 2 to understand the impact the new power plant and transmission facilities will have on their network. ATCO Electric agrees that all stages of the process must be met by any market participant seeking to become a TFO. This would apply to the filing of facilities applications as well as rate matters. As long as the new TFO meets all of the requirements and is treated in a manner consistent with existing TFOs, the interconnection process should apply. While ATCO Electric agrees that a market participant should understand and be prepared to accept all responsibilities and obligations of a TFO prior to making a decision, the full scope of these responsibilities will not be clear until the scope of a connection is defined, which takes place after Gate 0. The decision as to whether a connection is eligible or an eligible market participant chooses to be a TFO should be made in the context of some understanding of the scope of the interconnection. This decision should however, be made prior to an incumbent AESO Replies to Stakeholder Comments: 2011-09-27 Page 36 of 119 TFO undertaking significant estimating, preliminary design, or route selection activities. Capital Power Corporation Cenovus Energy Inc. Enbridge Pipelines ENMAX Corporation EPCOR Utilities Inc. AESO Replies to Stakeholder Comments: 2011-09-27 It should also be clear that any work (estimates, preliminary engineering, siting and route selection, etc.) undertaken by an incumbent TFO with respect to an interconnection remains the property of the TFO and will not be transferred to a market participant who elects to change their decision about the entity providing their connection, regardless of who has paid for the work. Capital Power agrees that in order to ensure that all obligations are completed, Stage 0 would require written confirmation of which entity will be responsible for each activity involved in the connection process. However, the MPC process should be flexible enough to accept the various arrangements that may be negotiated between connection customers and the incumbent TFOs. The AESO would reference the document provided in Stage 0 to determine which party will be responsible for each activity including providing the PPS and filing the facility application with the AUC for Stage 3 of the process. Disagree with the requirement to have choice made in Gate 0. Customers have no knowledge of cost or schedule restraints until process is beyond Gate 0 and therefore no basis for decision making. Agreed. A new process will further complicate an already complex world of interconnections Agreed EPCOR generally agrees with the concept of using the existing connection process for market participant choice projects. This is not dissimilar to current entities that act as both Page 37 of 119 Industrial Power Consumers Association of Alberta IPPSA Joss Wind Power Inc. AESO Replies to Stakeholder Comments: 2011-09-27 TFOs and DFOs. However, EPCOR believes that if a market participant chooses to follow the Market Participant Choice process they should not be required to solely own and operate the connection transmission facilities. The connection process at stage 0 should allow for the market participant to either jointly-own connection facilities with a third party TFO or to solely own them and subcontract TFO operation and maintenance responsibilities to a third party TFO who may subsequently take ownership through transfer of the facilities upon energization and commissioning. The main concern with this process is that the market participant will have to commit to the MPC model at Stage 0, before they necessarily have reason to do so. IPCAA expects that Industrials will opt for the MPC route if they receive higher than expected costs and slower than expected schedules from the incumbent TFO – likely to be known after Stage 1. The AESO should consider if Stage 1 is a better time for the market participant to confirm it is interested in the MPC option. IPPSA agrees that the AESO’s existing connection process can integrate the MP Choice Model. At stage 0, we would prefer an approach whereby the market participants signals its intent to be the owner of the Connection Facility and adhere to the appropriate obligations associated with the ownership of those connection facilities. Again, we do not support the idea that a market participant must assume the same responsibilities of a bulk system TFO to own connection facilities. We generally agree, although there should be an explicit option to select the incumbent TFO, another potential TFO or to select the ”own Page 38 of 119 Mainstream Renewable Power MEG model”. The new option should be able to fit into the current AESO interconnection process. The decision point for the transmission ownership should be required during Stage 2 and be a requirement for passing Gate 2 (not at Stage 0). Without knowing what’s involved in the scope of the interconnection, it is not possible to know whether the market participant has the appetite to build and operate the transmission facilities. In addition, the incumbent TFO should be a participant in the process through Stage 2 to understand the impact the new power plant and transmission facilities will have on their network. MEG supports the AESO’s proposal for integrating market participant choice within the existing AESO connection process. MEG disagrees with the requirement to elect the self-connection option at stage 0 and believes that such election can be made at any point up to the closure of stage 2. SATL Inc. Suncor Energy Marketing Inc. AESO Replies to Stakeholder Comments: 2011-09-27 MEG does not support the loss of queue position if the self-connection choice is reversed at any point before the closure of stage 2. While the milestones identified with each stage are realistic the underlying process can be bureaucratic and filled with uncertainty and delays. This process should have defined target time lines for each milestone event with exception reporting and AESO performance metrics around each milestone. The focus of the overall process should be one of continual improvement and efficiency gain. We would prefer to make the ownership decision at stage 3. SATL also supports the concept of filing both the facility and needs application to the AUC concurrently by the proponent. Suncor disagrees with requirement to initially Page 39 of 119 declare at stage 0. The Office of the Utilities Consumer Advocate TransAlta Corporation The option to delegate the construction or ownership of the project to an existing TFO under substantially similar technical parameters, should be open up to the closure of Stage 2, without the penalty of queue position loss. The Connection Process changes to accommodate the Own model require the Market Participant to commit at Stage 0 to the Assumption of TFO obligations with little certainty with respect to the required facilities or their cost. When the project facility requirements are identified, the market Participant would be in a better position to make commitments. This would also be the time for the market Participant to bring forward an EPC proposal for comparison to costing provided by the incumbent TFO. Even if these estimates are not at the PPS level they may be indicative enough for the AESO to pursue a more detailed comparison from both the incumbent and market participant in Stage 3. It may be reasonable to compensate the incumbent for costs incurred to provide the PPS estimate if the market participant is subsequently directed to construct the facility. Where the incumbent is directed to construct the market participant would bear its own costs. If a workable EPC and Own options are available to the market participant then it would be appropriate at Stage 0 to require a commitment to provide an EPC estimate based on the Connection Study. Agreed Discussion Paper – Request for Proposal Approach Do stakeholders agree with the suggested Request for Proposal approach? If you disagree, please provide supporting rational for that position. AESO Replies to Stakeholder Comments: 2011-09-27 Page 40 of 119 Stakeholder Stakeholder Comment Alberta Wind Energy Corporation Agreed. If the market participant takes the responsibility to build the transmission facility at their cost, it is their responsibility to get the best price through their own procurement process. As outlined in comments in the introduction, the decision about eligible recipients for requests for proposals should only be made in the context of a comprehensive review, adjustment to policy, and thorough examination of risk and associated mitigation. No comment Agreed Yes IPCAA agrees with the AESO approach in this section. IPPSA agrees with the AESO that the MP seeking connection service be the only party allowed to prepare a proposal to meet the need for that service. ATCO Electric Capital Power Corporation ENMAX Corporation EPCOR Utilities Inc. Industrial Power Consumers Association of Alberta IPPSA Mainstream Renewable Power MEG SATL Inc. AESO Replies to Stakeholder Comments: 2011-09-27 Replies Allowing anyone else – such as other MPs or a TFO - to submit a competing proposal would defeat the efficiency, choice and costs control sought under the banner of the MP Choice Model. Agreed. If the market participant takes the responsibility to build the transmission facility at their cost, it is their responsibility to get the best price through their own procurement process. MEG agrees with the Request for Proposal approach, provided however that the proposal can come from either the market participant or any 3rd party that the market participant nominates as its agent/representative in the own model. SATL supports the request for proposals from both the market participant and also the Page 41 of 119 incumbent TFO. Upon receiving the proposals the “Ownership” decision should be made by the market participant rather than being mandatory at Stage 0. Suncor Energy Marketing Inc. Suncor agrees with the Request for Proposal approach, provided however that the proposal can come from either the market participant or any TFO that the market participant nominates as owner or operator of the line. The Office of the Utilities Consumer Advocate See comments above. TransAlta Corporation Agreed Discussion Paper – Connection Queue Administration Do stakeholders agree with the suggested project cancellation and revoking of queue position? If you disagree, please provide an alternate approach and supporting rational for that alternate approach. Stakeholder Stakeholder Comment Replies Alberta Wind Energy Corporation ATCO Electric AESO Replies to Stakeholder Comments: 2011-09-27 As stated in the previous comment, the decision should be taken at Stage 2 as a requirement for Gate 2. Therefore there should be no need to cancel an application due to this decision. The participation by the incumbent TFO should be a requirement through Stage 2 to understand the impact the new power plant and transmission facilities will have on their network. Therefore there should not be any wasted costs incurred by the incumbent TFO. ATCO Electric agrees that if a project is cancelled the market participant should generally lose its queue position. A valid exception may be in circumstances where the TFO is able to accommodate the project (assuming the market participant wishes to move forward) and has the ability to respond to the identified need. Such situations could provide the most efficient and economic result, depending on the specific circumstances. The choice of proceeding in this manner must be that of the TFO and it cannot be required to assume responsibility for the project, the market Page 42 of 119 ATCO Power Capital Power Corporation AESO Replies to Stakeholder Comments: 2011-09-27 participants cost estimates or the forecast timeline. ATCO Power disagrees with the opinion regarding revoking queue position. The queue position should be based on the facility, rather than the owner. For example, if a market participant had initiated the interconnection process, and at a later time was able to enter an agreement with the incumbent TFO for the remaining balance of the project, the queue position should remain, and vice versa. If the participant cancelled the project, then they should be removed from the queue as there is no longer an intention for interconnection. Queue position should be based on whether or not the effort is progressing. This concept aligns with the idea that the market participant may transfer the facility to the incumbent TFO or other party after energization and commissioning. Capital Power does not agree with the proposed connection queue administration process. The approach to connection queue administration proposed by the AESO penalizes connection customers that may be willing to take on some of the connection process responsibilities at a later stage. The AESO explained at the stakeholder session on October 14th, 2011 that the intent of the cancellation policy was to discourage connection customers from using incumbent TFOs to “jump the queue” and then taking ownership of the lines further in the process. In this scenario, the incumbent TFO would likely have negotiated the terms for transfer of responsibility for some connection process activities with the connection customer. Therefore, adequate compensation for activities already completed would be included in the negotiation. The AESO’s MPC process should Page 43 of 119 not impede the possibility for reasonable agreements to be accepted. Cenovus Energy Inc. Enbridge Pipelines ENMAX Corporation AESO Replies to Stakeholder Comments: 2011-09-27 If the responsible party for each connection process activity changes through agreement by the parties, then the document originally submitted at Stage 0 would need to be updated to reflect the agreed upon changes in accountability. However, this should not require the project to be cancelled and the connection queue position revoked. In many cases the connection customer would not be in a position to determine if it would makes sense to provide its own connection facilities until further on in the process. To the extent that the commercial agreement allows the parties responsible for each activity to change, the scheduling of the facilities construction should be determined between the connection customer and the incumbent TFO, not by the AESO’s administrative process. Disagree. Unnecessarily punitive to customers who must rely on incumbent TFOs for cost and schedule information before proceeding. Customers should expect to pay for all study work completed by incumbent TFOs. AESO should utilize completed studies and not require duplicate. In general we support the queue admin approach presented; however, selection decision should be delayed to stage-2 so market participants have an opportunity to understand the “final” project scope and change their mind if req’d especially in cases where a simple T-tap in Stage-0 turns into a complex In/Out with RAS in Stage-2. A cancelled project should be treated as a cancelled project. A project that is delayed or transferred from a potential TFO to an incumbent or existing TFO should not lose their Page 44 of 119 EPCOR Utilities Inc. FortisAlberta Inc. Industrial Power Consumers Association of Alberta AESO Replies to Stakeholder Comments: 2011-09-27 place in the connection queue. ENMAX recommends that the project be moved back to the last completed stage of the AESO Interconnection process, and it can progress from that stage once resumed or by the existing or new TFO. No. EPCOR believes that if a market participant chooses to own the transmission facilities at Stage 0 and before Stage 4 determines that it does not want to own the transmission facilities, the AESO should cancel the project resulting in the loss of the market participant’s connection queue position. If the project is past stage 4, EPCOR does not believe the project’s queue position should be lost. FortisAlberta understands that the AESO presently has time limits and other checks for movement through the project stages and gates in the connection process. If a market participant and an incumbent TFO agree to transfer a connection project to the incumbent TFO in a close-to-seamless fashion, then FortisAlberta sees no obvious reason why the queue position should be revoked, provided that the time limits are not violated. IPCAA believes that if a market participant wishes to opt for the MPC alternative later on in the process (i.e. after Stage 0) due to high costs and long schedules from the incumbent TFO, this should be allowed without loss of queue position – as long as the market participant is able to continue within the expected schedule, without negatively impacting other customers. As long as the project is built to the AESO’s expected standards, there should be no queuing concerns. The market participant should not be disadvantaged by an unfavourable cost and schedule quote from a monopoly, if they are prepared to perform the Page 45 of 119 work themselves without inconveniencing other customers. IPPSA With regards to the market participant who attempts to go the MPC route and later opts back into the TFO alternative, IPCAA agrees with the AESO that it is the responsibility of the market participant to understand its obligations and “TFO” responsibilities. However, if the change in option has no negative impact on other customers, IPCAA has no concerns with leaving the queue position as it stands. MPC is a new process and there will be a learning curve on all sides. To penalize a market participant for not fully understanding a new and untried process is unnecessarily harsh. The most we can ask for is that they do not negatively impact other market participants. We strongly disagree with the AESO’s view that changing the ownership of the connection facilities during the connection process would necessitate the participant losing its place in the connection queue. It is IPPSA’s view that the terms of commercial arrangements for the construction of Connection Facilities is outside the AESO’s jurisdiction. Joss Wind Power Inc. AESO Replies to Stakeholder Comments: 2011-09-27 We do not understand the bearing that a change in ownership of connection facilities has on the queue position. We do not see a reliability issue resulting from a change of ownership as the design of the facility will ultimately be vetted by the AESO anyway. We disagree. Stage 0 is too early to make a binding irrevocable commitment to the incumbent TFO. This Customer Choice initiative is mainly about schedule and cost performance. However, estimates from the Page 46 of 119 Mainstream Renewable Power MEG SATL Inc. Suncor Energy Marketing Inc. The Office of the Utilities Consumer Advocate AESO Replies to Stakeholder Comments: 2011-09-27 incumbent TFO are not available at Stage 0. There needs to be explicit transfer rights, recognizing that the incumbent TFO should not be required to pick-up a project in mid-course. However, there may be cases where the parties agree to transfer a project from the incumbent TFO to another party or vice versa. This should not send a project back to the start. Projects should be cancelled only if a qualified party is not in place for performing the task at hand (planning and permitting, construction, and operating and maintenance each have different core competencies to a certain degree). As stated in the previous comment, the decision should be taken at Stage 2 as a requirement for Gate 2. Therefore there should be no need to cancel an application due to this decision. The participation by the incumbent TFO should be a requirement through Stage 2 to understand the impact the new power plant and transmission facilities will have on their network. Therefore there should not be any wasted costs incurred by the incumbent TFO. We do not support the AESO’s view that changing the ownership of the connection facilities would necessitate losing a participant’s place in the connection queue. SATL believes that the start over approach will aggravate congestion in the queue and market participant frustration whereas the ability to make “ownership” choice at Stage 3 will stream line queue process. Example -several market participants may realize they share a common interconnection need and assignment to incumbent TFO may be a logical option. Suncor does not agree that the queue position needs to be revoked as per our previous comments. Offering a workable EPC model to market participants as well as the Own model may Page 47 of 119 reduce the consequences associated with a firm commitment to assume TFO obligations at Stage 0. We disagree that a customer decision on switching between owning and not owning or vice versa should lose their queue position in the connection process. One of the purposes of the process is to study and gather more information to inform subsequent decisions. TransAlta Corporation One would expect that changing a decision in and of itself will cause some delays but this should not result in loss of queue position. Discussion Paper – TFO Requirements and Obligations – Legislative Domain Do stakeholders agree that new TFOs should be subject to the same legislative requirements and obligations as incumbent TFOs? If you disagree, please provide rationale supporting that position. Stakeholder Stakeholder Comment Replies Alberta Wind Energy Corporation ATCO Electric The administrative and regulatory requirements to become a TFO may be too onerous for a Participant who may, for example, have a relatively short transmission line to build in order to connect their project. Consideration should be given to the scale of the transmission development in regards to subjecting a Participant to the rigors of becoming a TFO. Legislative requirements are placed on TFOs to ensure the orderly development and safe, reliable operation of the transmission system. The creation of a sub-class of TFO to whom these requirements do not apply clearly compromises these objectives and is not in the public interest. As indicated above, there is a single legislative scheme that would be applicable to all TFOs as defined in legislation. Finally, any relaxation of legislative requirements and / or obligations should not be granted in such a way as to create a perverse AESO Replies to Stakeholder Comments: 2011-09-27 Page 48 of 119 ATCO Power Capital Power Corporation Cenovus Energy Inc. Enbridge Pipelines ENMAX Corporation EPCOR Utilities Inc. FortisAlberta Inc. AESO Replies to Stakeholder Comments: 2011-09-27 incentive to by-pass incumbent TFOs. If a comprehensive review determines that relaxation is warranted under particular circumstances based on project scope and associated risk, such relaxation should apply equally to any party building the transmission connection, regardless of whether they are the applicant for system access service or not. ATCO Power would like request clarification regarding all connection facilities being classified as transmission facilities. If a sole use connection is fully paid for by the connecting party, then tariff issues, which relate to the “transmission system” should not apply. Capital Power agrees that if a connection customer wishes to become a TFO, compliance with the applicable legislative requirements necessary to ensure the reliable operation of the Alberta power system is imperative. Assuming requirements are related to reliability etc then yes, obligations that are related to how customer’s are treated seem unnecessary. Difficult to comment on tariff due to lack of detail – how would new TFO tariffs be treated – become part of Alberta-wide postage stamp rates? If customer owners are req’d to act as TFO’s then the regulatory work needed for tariff filing, cost recovery and following ISO/AUC Rules would be prohibitive for all but a few largest projects. Independent ownership not easily workable on a shared asset. Allowing customers to build and transfer ownership to a TFO is probably more practical and efficient. Agreed Yes If the AESO proceeds with this initiative, FortisAlberta agrees with the application of the same legislative requirements for all TFOs. There may be additional opportunity for the Page 49 of 119 Industrial Power Consumers Association of Alberta IPPSA AUC to streamline the regulatory processes for TFOs. The AESO needs to consider this section in the context of the overall objectives of the MPC initiative. If we are trying to help customers address time and cost concerns, why are we requiring them to be subject to the same legislative requirements and obligations as incumbent TFOs? This will only make their activities slower and more costly without adding any additional benefit to the system overall. If the AESO views that these TFO obligations cannot be avoided under the current framework, some stakeholders may be willing to request larger policy changes. Alternatively, the AESO should consider other options that would help facilitate the MPC process – such as enabling “TFO Aggregators”, etc. For reasons already set out herein, small scale radial Connection Facilities are clearly distinctive from large scale interconnected bulk AIES facilities. Based on the AESO recognizing these distinctions, the AESO should continue that distinction in defining the minimum obligations it needs from a Connection Facility owner, in terms of the AESO’s mandate to safely and reliably operate the AIES. In terms of those obligations the AESO lists in its discussion paper, IPPSA anticipates that its members would accept AESO ‘direction to perform activities’ on their Connection Facilities. In terms of the cost recovery and tariff obligations that the AESO describes, it is IPPSA’s view that a Connection Facility owner should not be required to adhere to section 40(1) and 41(1) or T-Reg since a generation AESO Replies to Stakeholder Comments: 2011-09-27 Page 50 of 119 customer pays 100% of the cost of its Connection Facilities. Similarly, it is IPPSA’s view that a generation customer should not have to file a tariff in association with a Connection Facility for which it pays 100% of the cost. These two obligations proposed by the AESO risk undermining the objectives of minimizing costs and controlling the schedule for construction of Connection Facilities intended by the MP Choice Model. Quite the opposite, these obligations will add cost and time to market participants. Mainstream Renewable Power We submit that such obligations for Connection Facilities do not pass the efficiency test, as they will absorb resources and time of the MP, AESO and AUC, and to what end? Participants who build their own transmission connections ( either generation or Load) to the existing TFO facilities will meter their power at the point of connection and settle for it at that point. The participant would be in control of all costs for the connection and would build the capital costs into the costs of the project to determine the feasibility of the project. Therefore there would be no need for AESO to be involved in determining the effects on tariffs or for the participant to do all the reporting for Tariffs and Cost Recoveries. Should another participant want to use a line that had been built by a participant that had surplus capacity they would reimburse the original owner for the original costs on the basis of the % of capacity used and the length of distance from connection point to connection AESO Replies to Stakeholder Comments: 2011-09-27 Page 51 of 119 MEG SATL Inc. Suncor Energy Marketing Inc. The Office of the Utilities Consumer Advocate TransAlta Corporation AESO Replies to Stakeholder Comments: 2011-09-27 with TFO. As per previous comments MEG believes that the market participant that selects the selfconnection option must meet the technical and reliability standards but not the other administrative requirements such as filing a tariff. A tariff is required only if there is to be more than one user of the facility and the users cannot reach satisfactory commercial terms. SATL believes that any interconnection cost that will be ultimately added to the rate base should go through a prudency and tariff fairness assessment process. The converse is also true in that if the market participant is bearing all the interconnection costs then what is the purpose of filing a separate tariff? Any interconnection, regardless of who builds it must not adversely impact AIES. Developers/owners of merchant interties are considered to be TFO. Therefore, the merchant intertie developers will have to file a tariff. In this case, can the AESO confirm that there will not be a need to file two tariffs based on the Market Participant Choice initiative? As per previous comments Suncor does not believe it should be necessary for a line owner to become a TFO and that except for technical and reliability standards, the line owner should be exempt from the all other TFO related legislative standards. The fundamental obligations would be common with incumbents but depending on the facility, efficiencies may arise from reduced compliance requirements as they may not be applicable The purpose of a customer connection is to serve the customer themselves. Given this as the envisioned basis for ongoing operation it would not be expected that the AESO would direct the customer to undertake activities on Page 52 of 119 behalf of the AESO. We do appreciate that the AESO has the right to do so and, for example, requires this of ISDs. Requiring a tariff for self serving facilities imposes an administrative burden on the customer, the AESO, and the AUC. A tariff is for a public utility and what is intended with Choice is to serve one customer and not multiple customers. We see little merit in a tariff under expected operations. We would also point out that a tariff is not required of ISDs which is not a dissimilar concept in many ways to Choice. We can visualize where a tariff process could be abused. The AESO DTS tariff is a blend of various vintages of transmission facilities and in the ratebase at depreciated costs. A customer building new transmission facilities would establish a ratebase at full cost and propose a revenue requirement including return, depreciation and other costs including regulatory applications. It can be visualized that the customer will receive more from its tariff than if the traditional TFO owned the facilities. We would not expect that the increase in the AESO blended tariff due to the addition of the customer tariff would be more than the amount the customer TFO would receive from their tariff. This would crossover at some point but for part of the facility life other customers would be paying for dedicated customer facilities. We do not think that this is the intent of a tariff which should be to recover the cost of the shared or common system and not dedicated facilities. We foresee the only future TFO-like situation being where another entity – load or generator AESO Replies to Stakeholder Comments: 2011-09-27 Page 53 of 119 – wishes to connect to the facilities of the existing customer. This situation needs to be further discussed as to whether the existing customer would take on greater TFO obligations or whether the common facilities would become systematized by the traditional TFO purchasing them from the existing customer. Again concepts similar to those required of ISDs may be useful. Our view is that if an existing customer has contributed facilities, i.e. paid for, whether owned by the traditional TFO (as now) or by a customer TFO the customer should recover the costs, i.e. customer contributions, of facilities which become common, i.e. systematized. Discussion Paper – TFO Requirements and Obligations – AESO Documents Do stakeholders agree that new TFOs should be subject to the same requirements and obligations set out in AESO Documents as incumbent TFOs? If you disagree, please provide rationale supporting that position. Stakeholder Stakeholder Comment Replies Alberta Wind Energy Corporation ATCO Electric See above AESO authoritative documents exist so that the AESO can fulfill their mandate of ensuring the orderly development and safe and reliable operation of the transmission network in the public interest. Exemption from any of the AESO’s authoritative documents on any basis other than applicability (like exemption from a reliability standard on the basis that a particular TFO does not have the kind of facilities to which that particular standard applies) would clearly compromise the safe and reliable operation of the transmission system and hence is not in the public interest. Any relaxation of requirements under AESO documents should not be granted in such a way as to create a perverse incentive to by-pass AESO Replies to Stakeholder Comments: 2011-09-27 Page 54 of 119 Capital Power Corporation Cenovus Energy Inc. ENMAX Corporation EPCOR Utilities Inc. FortisAlberta Inc. Industrial Power Consumers Association of Alberta IPPSA incumbent TFOs. If a comprehensive review determines that relaxation is warranted under particular circumstances based on project scope and associated risk, such relaxation should apply equally to any party building the transmission connection, regardless of whether they are the applicant for system access service or not. No comment As above, agree to the extent that these requirements impact other market participants. Requirements and obligations must be standardized for all incumbents and new TFOs. Agreed Yes In principle, the requirements and obligations should be the same for new TFOs as for incumbent TFOs; however every reasonable opportunity for streamlining the regulatory processes should also be explored. Again, the AESO should consider the end goal here. We are interested in faster and less costly connections. As long as there is no negative impact on the system, there will be no benefit to having market participants complete unnecessary paperwork to comply with obligation that will not make the system any safer or more reliable. There should be some requirements, obviously, but a drastically reduced amount from what incumbent TFOs must provide. IPPSA disagrees with the AESO’s approach that owners of Connection Facilities should comply with all AESO documents applicable to TFOs. We recommend that the AESO define the minimum obligations it needs from MP Connection Facility owners, as it relates to the AESO’s responsibility to operate a safe and AESO Replies to Stakeholder Comments: 2011-09-27 Page 55 of 119 Mainstream Renewable Power MEG SATL Inc. Suncor Energy Marketing Inc. The Office of the Utilities Consumer Advocate TransAlta Corporation reliable system. Agree As per previous comments MEG believes that the market participant that selects the selfconnection option must meet the technical and reliability standards but not the other administrative requirements such as filing a tariff. A tariff is required only if there is to be more than one user of the facility and the users cannot reach satisfactory commercial terms. See comments above. Suggest that one logical metric to define what is considered part of the market participant’s facilities and what is part of the transmission system is the point of settlement (metering point). The majority of energy is bought and sold at the metering point. In this case, tapping a line moves the metering point and redefines market participant’s facilities and transmission system. Please refer to the above comments The fundamental obligations would be common with incumbents but depending on the facility, efficiencies may arise from reduced compliance requirements as they may not be applicable See our comments under 10.1 and 11.0 of the Discussion Paper. Discussion Paper – ISO Rules 9.1 Changes Do stakeholders agree that ISO rules 9.1 should eventually be changed to apply to new TFOs removing references to incumbent TFOs and the respective service areas? If you disagree please provide rationale supporting that position. Stakeholder Stakeholder Comment Replies Alberta Wind Energy Corporation ATCO Electric AESO Replies to Stakeholder Comments: 2011-09-27 Agree ATCO Electric believes that the AESO has a clear obligation to undertake a much more comprehensive study of this proposal as outlined above to ensure that the introduction of Choice for Market Participants is in the public Page 56 of 119 Capital Power Corporation Cenovus Energy Inc. ENMAX Corporation EPCOR Utilities Inc. FortisAlberta Inc. Industrial Power Consumers Association of Alberta IPPSA interest. No comment Agree Agreed EPCOR agrees that Rule 9.1.1.2 c) should be deleted or changed to allow for TFOs, other than incumbent TFOs, to build transmission facilities provided the rule clearly states when this may occur. Any changes should be done within the context of ensuring the continued orderly and economic development of the Alberta interconnected electric system transmission and distribution), with full engagement of the AESO, incumbent TFO and DFO to whose service area the transmission connection pertains. IPCAA does not believe large-scale rule changes should be necessary in order to enable MPC. These are not bulk system assets. IPPSA does not support the idea that Connection Facilities should face the same reporting standards as the AIES bulk system facilities. Again, generator paid for, small-scale radial Connection Facilities are simple facilities to connect generators to the large scale interconnected bulk AIES system. As also stated, IPPSA views Connection Facilities as analogous to a driveway connecting a home to the street. IPPSA submits that driveways are more part of homes than the highways that the AESO and TFOs plan and operate, and whose costs are born by third parties. The AESO has made distinctions between these facilities (in terms of who can build what under Section 35.1) and we urge the AESO to continue with its distinction when it comes to defining the minimum obligations it AESO Replies to Stakeholder Comments: 2011-09-27 Page 57 of 119 Mainstream Renewable Power MEG Suncor Energy Marketing Inc. The Office of the Utilities Consumer Advocate TransAlta Corporation needs related to operation of Connection Facilities. Agree Some changes may be required in order to facilitate adoption and flexibility. Some changes will be required in order to facilitate the flexibility described without adding undue administrative burden. This will include changes to rule 9 to exempt new line owners from requirements of existing TFOs as well as allowing existing TFOs to compete for market participant line construction and ownership under commercial terms. In addition sections of the Energy Utilities Act will have to be amended to allow for the exemption of new line owners under market participant choice initiative from the requirement to file tariffs. ISO rules 9.1 would require changes to facilitate administrative efficiencies for facilities that may not require full compliance reporting. References to service areas need to be removed. There are significant differences between transmission built dedicated to a single customer and a transmission system to serve wide geographic areas. The dedicated transmission is paid for by the specific customer whereas the transmission system is paid for by all customers. Much of Rule 9.1 is based on oversight and prudency of costs given the tariff process affecting customer rates. Given a view that common facilities are systematized this obviates the need for Rule 9.1 treatment. Discussion Paper - Other ISO Rules Do stakeholders think any new ISO rules are required, or any existing ISO rules need changing to support market participant choice? Stakeholder AESO Replies to Stakeholder Comments: 2011-09-27 Stakeholder Comment Replies Page 58 of 119 Alberta Wind Energy Corporation Capital Power Corporation Enbridge Pipelines ENMAX Corporation EPCOR Utilities Inc. Industrial Power Consumers Association of Alberta Mainstream Renewable Power MEG Suncor Energy Marketing Inc. TransAlta Corporation Agree No comment Like to see a discussion on treatment of AESO’s investment policy. Existing ISO Rules should be modified to reflect any changes EPCOR does not believe any existing ISO rules, other than Rule 9.1, are required to be changed to support market participant choice. No Agree Some changes may be required in order to facilitate adoption and flexibility. See above comments The language in legislation and rules seems to be focused on those who provide services for others and are compensated through a regulated tariff, i.e. they are a public utility. The intent in Choice is not to have those who serve only themselves go through an administrative paper chase in a zero sum tariff game. Where there is not clarity in the legislation and rules then modifications are needed so that unintended results are avoided. We would point out that carve-out or designation of facilities not to be public utilities already exists through the ISD designation. Consideration needs to be given to modification of the ISD or creation of other designations which would meet the intent of customers being able to construct, own, operate and maintain dedicated facilities, and not become a public utility. Discussion Paper - Other Comments AESO Replies to Stakeholder Comments: 2011-09-27 Page 59 of 119 Do stakeholders have any other comments regarding market participant choice? Stakeholder Stakeholder Comment Alberta Wind Energy Corporation Clarification needed on how a Participant may build transmission to a distribution system. A reasonable alternative to the proposal outlined in this discussion paper may be for eligible market participants to use incumbent TFO standards to build transmission facilities that would be transferred to the incumbent TFO upon completion. Such a model could meet the needs of market participants respecting cost and schedule control, maintain the public interest objectives outlined in the 2003 policy paper and alleviate market participants of the onerous obligations associated with being a TFO. ATCO Electric Replies Such a model requires significant up-front planning and process definition to address the aforementioned complexities that have been experienced previously in attempting to transfer assets to a TFO. Under such a model the incumbent TFO should retain accountability for securing right of way. Consultation and compensation for rights of way is an area where tremendous risk could be introduced to all transmission customers by having multiple parties participating in this exercise. In ATCO Electric’s experience the area of consultation and compensation for right of way is also an area which, if not considered at the outset, can make a transfer of an asset to an incumbent TFO extremely complex. This alternative should be well defined at the outset to ensure seamless transfer of assets including items such as: AESO Replies to Stakeholder Comments: 2011-09-27 Page 60 of 119 Capital Power Corporation Cenovus Energy Inc. ENMAX Corporation EPCOR Utilities Inc. Industrial Power Consumers Association of Alberta IPPSA Pro-forma agreements; Mechanisms to ensure compatibility of design with standards, specifications, maintenance practices, etc.; and Mechanisms to ensure other rate payers of cost prudence. No comment We support market participant choice. AESO should be the sole approver of customer choice. ENMAX supports this initiative. EPCOR believes the market participant choice process should be flexible to allow a market participant to partner with third parties to fulfill its TFO responsibilities. This should include options for the timely transfer of ownership and responsibility of being a TFO to a third party if necessary. IPCAA reiterates that the overall objective here is to enable customers to have control over the costs and schedules associated with their connections. Industrials are generally not interested in becoming TFOs; hence, the MPC process should be compiled in a way that avoids this. IPCAA would be happy to work with the AESO to develop this process further. Thank you for the opportunity to comment. IPPSA would appreciate the AESO keeping in mind the objectives that were set out to be reached by the MP Choice Model, i.e., the objective of improving schedule management and cost control, without compromising safety and reliability. We appreciate the AESO’s recognition that legislation allows for choice. AESO Replies to Stakeholder Comments: 2011-09-27 Page 61 of 119 Joss Wind Power Inc. Mainstream Renewable Power SATL Inc. TransAlta Corporation AESO Replies to Stakeholder Comments: 2011-09-27 We wish to work with the AESO in defining a mechanism to enable MP choice, with the goals of cost control, schedule improvement and choice in mind. We support this initiative and any rule changes or legislative changes that are reasonably required to advance the goal of increased competition. How long before the new model can be implemented? Can the scope be broadened to investigate the possibility of a participant TFO connecting to the distribution network? Will there be a provision for the possibility of merchant transmission? Why preclude market participant choice / merchant transmission developers from bulk transmission development? TransAlta continues to advocate that transmission lines which are 138 kV and 69 kV should receive the same regulatory oversight as distribution lines. The AUC does not approve distribution lines and these can be characterized as wood pole structures installed in public road allowances. The concerns about wood pole lines are few and, for example, most landowner objections arise where a transmission line is proposed to cross their land. Such lines are typically on metal lattice towers for transmission lines 240 kV and higher. In large part customer connections are to 138 and 69 kV transmission systems. Streamlining the regulatory process to deal with objections by complaint rather than by the full need and facilities application process would deal appropriately with this class of project. Such a change would benefit both regulated and customer connection proposed transmission lines. Page 62 of 119 TransAlta also believes that the need for a transmission line to connect a customer whether load or generation is self-evident by virtue of the customer request for connection. As such we question why 34(1)(c) and 35 in the EUA are necessary for customer connection lines. General Comments Do stakeholders have any other comments regarding market participant choice? Stakeholder Stakeholder Comment AltaLink I. Introduction and Overview Replies 1. AltaLink Management Ltd. (AltaLink) has reviewed the Alberta Electric System Operator’s (ISO’s or AESO’s) discussion paper entitled “Market Participant Choice to Construct, Own, Operate and Maintain Transmission Lines Connecting its Facilities to the Interconnected Electric System” (Discussion Paper). The AESO encouraged stakeholders to respond to the Discussion Paper using the stakeholder comment matrix attached to the Discussion Paper. Given the nature and focus of AltaLink’s comments, the comment matrix has proven to be a challenging framework for AltaLink’s submissions. Therefore, AltaLink is responding to the Discussion Paper in the form of this Submission. 2. AltaLink has organized its Submission under the following four headings: (a) The applicable legislative scheme constitutes a barrier to implementing market participant choice as proposed in the Discussion Paper. AESO Replies to Stakeholder Comments: 2011-09-27 Page 63 of 119 (b) Implementing market participant choice as proposed in the Discussion Paper is inconsistent with the economic, orderly and efficient development of the transmission system. (c) The material change in the structure of the transmission function proposed in the Discussion Paper fails to address resulting risks, inefficiencies and unintended consequences. (d) The AESO has considered but one option to address the perceived concerns of customers. 3. For ease of reference, the words and phrases used in this Submission, that are defined in the Discussion Paper will have the same meanings attributed to them in this Submission as were assigned to them in the Discussion Paper, unless separately defined in this Submission or the context otherwise requires. 4. AltaLink considers the proposal for market participant choice described in the Discussion Paper to be fundamentally flawed. AltaLink does not support the proposal for the following reasons: • The applicable legislative scheme constitutes a barrier to implementing market participant choice as proposed in the Discussion Paper. • The Discussion Paper fails to demonstrate how the proposal for market participant choice is in the public interest as being either consistent with or enhancing the economic, orderly and efficient development and operation of the transmission system in Alberta. AESO Replies to Stakeholder Comments: 2011-09-27 Page 64 of 119 • The Discussion Paper fails to address or justify with fact-based evidence and analysis the material incremental costs, inefficiencies and unintended consequences that would result from implementation of the AESO’s proposal. • The Discussion Paper fails to address with fact-based evidence and analysis the real potential for increased risk to the safe and reliable operation of the interconnected transmission system that would arise from the implementation of the AESO’s proposal. 5. In view of AltaLink’s position respecting the Discussion Paper, as outlined above and elaborated upon later in this Submission, AltaLink considers it premature to address other topics raised in the Discussion Paper such as eligible market participants, eligible connection projects, integration with the existing AESO connection process, connection queue administration and ISO rule changes. 6. AltaLink is prepared to work with the AESO and customers, collaboratively, to continue to seek simple and workable solutions to concerns regarding customer interconnections. AltaLink is confident that there are an array of potential options to what is proposed in the Discussion Paper that are simpler, consistent with the existing legislative scheme, more flexible for customers and which do not impose significant incremental costs and risk on the operation of the interconnected transmission system. II. The applicable legislative scheme constitutes a barrier to implementing market participant choice as proposed in the Discussion Paper AESO Replies to Stakeholder Comments: 2011-09-27 Page 65 of 119 A. Overview 7. Among other things in the Executive Summary and Introduction sections of the Discussion Paper, the AESO stated the following: The AESO is initiating discussion and consultation on providing market participants the opportunity to construct, own, operate and maintain the transmission facilities required to connect their facilities to the interconnected system; referred to as “market participant choice” for the purpose of this discussion paper. The AESO is commencing discussion and consultation on market participant choice as it believes it is permitted within the existing legislative framework and can be implemented providing that there are no adverse impacts on the Alberta interconnected system and market participants. … Section 35(1) of the EUA provides authority for the AESO either to direct a TFO to prepare a facility application or to request a proposal from a market participant. Therefore, the legislative framework fundamentally supports market participant choice. … In the AESO’s view, no barriers exist to advancing market participant choice and as such the AESO wishes to AESO Replies to Stakeholder Comments: 2011-09-27 Page 66 of 119 discuss and seek feedback from stakeholders on matters relating to market participant choice.1 8. In this section of its Submission, AltaLink addresses: • the legislative framework for the consideration of the AESO’s proposal for market participant choice, as outlined in the Discussion Paper; • the AESO’s conclusions that there are no barriers to the implementation of market participant choice; and • specifically, the AESO’s conclusion that the applicable legislative scheme, which includes but is not confined to the EUA, authorizes the implementation of market participant choice. 9. The AESO has erred in concluding that the applicable legislative scheme does not constitute a barrier to implementing market participant choice as proposed in the Discussion Paper. Consistent with the public policy, which finds its expression in applicable legislative scheme, which includes the Electric Utilities Act (EUA),2 theHydro and Electric Energy Act3 (HEEA) and the Transmission Regulation4 (TReg), incumbent TFOs alone are eligible to construct, own, operate and maintain transmission facilities5 determined on the basis of the geographic areas under sections 28 and 29 of the HEEA, with four legislated exceptions.6 The legislated exceptions are limited to the following: • where the Independent System Operator grants or provides for an exception authorizing AESO Replies to Stakeholder Comments: 2011-09-27 Page 67 of 119 alternative arrangements or agreements between TFOs;7 • the construction, upgrading or enhancement of an intertie;8 • critical transmission infrastructure in respect of which the Minister has made a determination under section 24.1(2) of the TReg;9 and • a transmission facility that is the subject of an industrial system designation.10 B. Statutory Interpretation 10. The purpose of statutory interpretation is to discover the intent of the legislature and the true purpose of the statute while preserving the harmony, coherence and consistency of the legislative scheme.11 11. The Supreme Court in Re Rizzo & Rizzo Shoes Ltd.12 articulated the modern approach to statutory interpretation, as follows: Today there is only one principle or approach, namely, the words of an Act are to be read in their entire context, in their grammatical and ordinary sense harmoniously with the scheme of the Act, the object of the Act, and the intention of Parliament. 12. The Supreme Court of Canada in Canada Trustco Mortgage Co. v. Canada13 provided further direction as to how this method should be employed, noting that the ordinary meaning of the words in a statutory provision play a dominant role in the analysis. The Court stated: AESO Replies to Stakeholder Comments: 2011-09-27 Page 68 of 119 It has been long established as a matter of statutory interpretation that “the words of an Act are to be read in their entire context and in their grammatical and ordinary sense harmoniously with the scheme of the Act, the object of the Act, and the intention of Parliament”: see 65302 British Columbia Ltd. v. Canada, [1999] 3 S.C.R. 804, at para. 50. The interpretation of a statutory provision must be made according to a textual, contextual and purposive analysis to find a meaning that is harmonious with the Act as a whole. When the words of a provision are precise and unequivocal, the ordinary meaning of the words play a dominant role in the interpretive process. On the other hand, where the words can support more than one reasonable meaning, the ordinary meaning of the words plays a lesser role. The relative effects of ordinary meaning, context and purpose on the interpretive process may vary, but in all cases the court must seek to read the provisions of an Act as a harmonious whole. C. The Legislative Scheme Regulating Transmission 13. Statutes must be interpreted to achieve their intent. All legislation is presumed to have a purpose. Interpretations that are consistent with, or promote a purpose should be adopted. Interpretations that undermine legislative purpose should be avoided.14 To achieve a sound interpretation of legislative text, a court called upon to consider the matter will identify AESO Replies to Stakeholder Comments: 2011-09-27 Page 69 of 119 and take into account the purpose of the legislation. 14. In the case of the regulation of electricity in Alberta, there are a number of interconnected statutes, regulations, rules and policies that give rise to a larger legislative scheme within which participants in the electricity industry are governed. The principles of statutory interpretation require that a court make a purposive interpretation of all the elements of this legislative scheme in order to give effect to the objects and purpose of any one component piece. In performing this analysis, a court will presume that the legislative scheme is “rational, coherent and conomical.”15 15. The Alberta Court of Appeal in Bur v. Alberta (Energy and Utilities Board)16 (the Bur Case) considered the legislative scheme for the regulation of electricity in Alberta. The Court stated that provisions of the EUA, the HEEA and the TReg were to be considered together to give effect to a single scheme. The Court held: Each statute must be read in the context of the others, and with a view to the overall regime. Statutes enacted by a legislature that deal with the same subject are presumed to be drafted with one another in mind, so as to offer a consistent treatment of the subject. In effect, the statutes are construed together as if they constituted a single piece of legislation. Section 14(3) of the HEEA must be therefore be read in the context of section 34 of the EUA and the Transmission Regulation.17 D. The Components of the Legislative AESO Replies to Stakeholder Comments: 2011-09-27 Page 70 of 119 Scheme Regulating Transmission 16. Transmission in Alberta is governed by provisions of the EUA, the HEEA, the TReg and ISO Rule 9.18 Provisions relating to the ISO’s duties and responsibilities, as the administrator of the Alberta Interconnected Electric System (AIES) including transmission, are set out in the EUA and the TReg. The Electric Utilities Act (EUA) 17. The phrase “transmission facility” is defined in section 1(1)(bbb) of the EUA. As the AESO points out in its Discussion Paper, the essential underpinning for the AESO’s conclusion, that the legislative framework fundamentally supports market participant choice, is the AESO’s view that section 35(1) of the EUA provides authority for the AESO either to direct a TFO to prepare a transmission facility proposal or to request a proposal from market participants.19 18. With respect, the AESO has misinterpreted section 35(1) of the EUA and as result has come to the incorrect conclusion that the legislative framework fundamentally supports market participant choice, as that phrase is used in the Discussion Paper. Section 35(1) of the EUA reads as follows: 35(1) The Independent System Operator may, at the time of preparing a needs identification document, after submitting a needs identification document to the Commission or after receiving Commission approval of a needs identification document, AESO Replies to Stakeholder Comments: 2011-09-27 Page 71 of 119 (a) direct the owner of a transmission facility to submit, for Commission approval under the Hydro and Electric Energy Act, a transmission facility proposal to meet the need identified, or (b) request market participants to submit, for approval by the Independent System Operator, a proposal to meet the need identified. [Emphasis supplied] 19. What is obvious from a plain reading of section 35(1)(a) and (b) of the EUA, and what, fundamentally, was overlooked by the AESO in its analysis, is that the phrase “transmission facility” proceeds the word “proposal” in section 35(1)(a) and is not found in section 35(1)(b). 20. There are two reasons the omission of the phrase “transmission facility” before the word “proposal”, in section 35(1)(b), is (i) determinative of the correct interpretation of section 35 of the EUA and (ii) demonstrates the AESO’s erroneous conclusion in respect of the existence of authority for the AESO to request a “transmission facility” proposal from market participants that are not TFOs. First, based on the well accepted rules of statutory interpretation discussed above, the omission must be read as having been intended. There is a presumption that, because the legislature thought of including a word or phrase in one section of an act but not in a related section of the act, the legislature intended the exclusion of the word or phrase in the related section. Otherwise stated, “legislative exclusion can be implied when an express reference is expected but absent”.20 Second, on a plain reading of section 35(1)(b), the only proposals that can be requested by the AESO from market AESO Replies to Stakeholder Comments: 2011-09-27 Page 72 of 119 participants, that are not owners of a transmission facility, are proposals that do not include a “transmission facility” as that phrase is defined in the EUA. As is discussed later in this Submission, this interpretation of section 35(1) of the EUA, is (i) evident from a plain reading of the section in the context of the EUA, (ii) consistent with the legislative scheme applicable to transmission development in this province and (iii) consistent with the expression of government policy found in the Transmission Development Policy.21 21. It is respectfully submitted that, on a plain reading of section 35 of the EUA within its proper context, the only proposals that the AESO is empowered to request from market participants that are not owners of transmission facilities are proposals which do not include a “transmission facility” as that phase is defined in the EUA. 22. Further, the AESO’s proposal to allow “…a market participant to choose to provide its own connection project…”22 is inconsistent with a plain reading of the clear language of section 35(1)(b) of the EUA, which provides that the AESO may request “market participants” to make a proposal to meet a need. The EUA does not empower the AESO to enable a market participant to choose to provide its own connection project. 23. Section 35 must be read in its plain and ordinary meaning and in harmony with the other provisions of the EUA and the other components of the legislative scheme governing the development of electric transmission in Alberta. Later in this Submission AltaLink will address other elements of the AESO Replies to Stakeholder Comments: 2011-09-27 Page 73 of 119 legislative scheme, which properly interpreted, support the plain reading of section 35 described above. 24. Section 3 of the EUA makes it clear that nothing in the EUA requires any change in the boundaries of the service area of an electric distribution system.23 This section provides important context for the discussion below of the HEEA provisions that deal with electric distribution service areas and section 24 of the TReg that establishes general rules for the construction and operation of transmission facilities “…determined on the basis of geographic areas under section 28 and 29 of the Hydro and Electric Energy Act…”.24 25. Section 35 is the key to this analysis and has been discussed earlier in this Submission. Interpreting section 35(1)(b) as restricting proposals to meet AESO identified needs to proposals that do not include a “transmission facility”, as that term is defined in the EUA, is reinforced by section 36 of the EUA. Section 36 is found under a heading entitled “Other proposals to alleviate transmission constraints”. Plainly read in the context of section 35(1)(a) and (b), “other proposals” must refer to proposals referred to in section 35(b) which, when contrasted with the proposals referred to in section 35(1)(a), are proposals other than “transmission facility” proposals. 26. Section 40 deals with the obtaining of access to transmission facilities that are part of an industrial system. As is elaborated upon below, where industrial systems are addressed in the context of the HEEA, industrial systems are one of the limited number of legislated exceptions to the general scheme of the AESO Replies to Stakeholder Comments: 2011-09-27 Page 74 of 119 applicable legislation, which general scheme provides that only incumbent TFOs are empowered to seek authorization to construct, own, operate and maintain transmission facilities. Enabling the ownership and operation of transmission facilities by a number of TFOs, that may be anyone of several types of market participant, creates a “patchwork quilt” of transmission, within the AIES. Addressing issues of access to a patchwork of transmission facilities is one of the challenges to the economic, orderly and efficient operation of the AIES, which would arise if an attempt were made to implement the proposal outlined in the Discussion Paper. The Hydro Electric and Energy Act (HEEA) 27. There are two aspects of the HEEA that are important in the consideration as to whether the applicable legislative scheme is a barrier to the implementation of the AESO’s proposal described in the Discussion Paper. The two important aspects are industrial systems and service areas. 28. The HEEA empowers the Commission to designate the whole or any part of an electric system as an industrial system.25 As discussed above, industrial systems, which may include transmission facilities, are one of the four legislated exceptions to the general scheme of the applicable legislation. The legislative scheme implements the public policy, which recognizes that the economic, orderly and efficient development of transmission facilities in the province is best achieved through authorizing incumbent TFOs alone to construct, own, operate and maintain transmission facilities, determined on the basis of the AESO Replies to Stakeholder Comments: 2011-09-27 Page 75 of 119 geographic areas under sections 28 and 29 of the HEEA. 29. The fact that the applicable legislative scheme creates limited legislated exceptions to the general statutory scheme reinforces the plain reading of section 35 of the EUA. As addressed earlier in this Submission, on a plain reading of section 35, apart from fitting within one of the legislated exceptions, only incumbent TFOs are empowered to seek authorization to construct, own, operate and maintain transmission facilities. As is noted in the Transmission Development Policy (referenced above and discussed separately later in this Submission), “Generators (and customers) will continue to own and operate transmission facilities on their own property for their own use (as per the Hydro Electric Energy Act)”.26 30. It is also instructive to consider the Industrial Systems Policy Statement, which states that the exemption provided for industrial systems “… is not intended to facilitate development of independent electricity systems driven by the avoidance of system costs, therefore administration of the industrial system exemption should avoid un-economic bypass”.27 This public interest and public policy determination is reflected in the HEEA, in section 4(2)(c) and (d), as follows: 4(2) Where the Commission is considering an application for designation as an industrial system, the Commission shall have regard to the following principles: … (c) the designation must not facilitate AESO Replies to Stakeholder Comments: 2011-09-27 Page 76 of 119 (i) the development of independent electric systems that attempt to avoid costs associated with the interconnected electric system, and (ii) uneconomical by-pass of the interconnected electric system; (d) duplication of the interconnected electric system must be avoided where it is more economical to use the transmission facilities or electric distribution systems owned by persons in whose service areas the industrial system is or will be located. 31. The significance of these provisions is twofold. First, the provisions demonstrate that, even for the legislative exception of industrial systems, the public policy embedded in the Transmission Development Policy, is honoured by the avoidance of the development of independent electric systems (the patchwork quilt addressed in the Transmission Development Policy), the avoidance of uneconomic by-pass and the avoidance of duplication. Second, the provisions focus on ensuring the adherence to the public policy of economic, orderly and efficient development of transmission facilities in the Alberta public interest, an underlying purpose of the HEEA. The policy objective embodied in these legislative provisions is critical to a consideration of the public interest in implementing the proposal in the AESO’s Discussion Paper, examined later in this AESO Replies to Stakeholder Comments: 2011-09-27 Page 77 of 119 Submission. 32. Equally important, and for the same reasons, is the requirement in section 4(3)(g) of the HEEA, that: (g) where an industrial operation extends beyond contiguous property, the owner of the industrial operation satisfies the Commission that the overall cost of providing the owner’s own distribution or transmission facilities to interconnect the integral parts of the industrial operation is equal to or less than the tariffs applicable for distribution or transmission in the service area where the industrial operation is located. 33. Section 14 of the HEEA provides that no person shall construct a transmission line or any part of a transmission line unless the person is a holder of a permit issued by the Commission. Section 15 of the HEEA provides that no person shall operate a transmission line unless the person is a holder of a subsisting licence to operate the transmission line. 34. Section 15.3 of the HEEA reads as follows: 15.3 When considering an application for an approval, permit or licence under this Part in respect of a transmission line or part of a transmission line that the Independent System Operator has directed the owner to submit for Commission approval under section 35(1)(a) of the Electric Utilities Act, the Commission may approve incentives, including incentives proposed by the AESO Replies to Stakeholder Comments: 2011-09-27 Page 78 of 119 applicant, that are intended to result in cost savings or other benefits associated with the project. [Emphasis supplied] 35. It is instructive that section 15.3 of the EUA makes no mention of section 35(1)(b) of the Electric Utilities Act. Consistent with the scheme of the applicable legislation this Submission examines, the only rational explanation for the omission of a reference to section 35(1)(b) in section 15.3 is that the proposals referred in section 35(1)(b) do not include transmission facilities. 36. It is also instructive to note that section 16 of the HEEA, states that sections 14 and 15 (the requirements to obtain a permit and licence for a transmission facility) do not apply to a person transmitting or proposing to transmit electric energy over the person’s own land solely for the person’s own use by means of a line or to the owner of an industrial system transmitting electric energy or proposing to transmit electric energy over the land of the owner of the industrial system solely for use by the industrial system.28 37. It is clear that the owner of a transmission facility directed to submit a transmission facility proposal under section 35(1)(a) of the EUA must apply to the Commission for a permit and licence under the HEEA.29 However, there is no similar requirement made of a market participant that is requested to make a proposal under section 35(1)(b). This is entirely consistent with the plain reading of section 35, addressed above, which leads to the inescapable conclusion, as a matter of statutory interpretation, that proposals referred to in AESO Replies to Stakeholder Comments: 2011-09-27 Page 79 of 119 section 35(1)(b) of the EUA do not include transmission facilities. Section 36(2) of the EUA merely provides that: The Independent System Operator may specify the time within which the person who obtains an approval of a proposal must apply to the Commission for approval under the Hydro and Electric Energy Act, if approval is required under that Act. 38. If it were to be suggested that section 35(1)(b) should be read as including transmission facility proposals, in the same manner as does section 35(1)(a) of the EUA, one would have expected a reference to section 35(1)(b) would have been included in section 35(3) and there would have been no need for section 36(2). 39. The second important aspect of the HEEA that must be considered is Part 3 – “Electric distribution systems” and the provisions under this Part that define service areas for distributors and establish the rules for distribution system service areas. 40. It is instructive in this context to observe that the applicable statutory scheme creates a clear distinction between distribution systems and transmission systems. Significantly, section 1(1)(b) of the HEEA defines an electric distribution system as follows: “electric distribution system” means any system, works, plant, equipment or service for delivery, distribution, or furnishing of electric energy directly to the consumers, but does not include a AESO Replies to Stakeholder Comments: 2011-09-27 Page 80 of 119 power plant or a transmission line. [Emphasis supplied] 41. In view of the fact that the HEEA, and the applicable statutory scheme, draws a clear distinction between distribution systems and transmission systems and between owners of distribution systems and owners of transmission systems, it is impossible to reconcile the AESO’s proposal,30 that owners of distribution systems be authorized to construct, own, operate and maintain transmission facilities, with the clear provisions of the applicable legislation. 42. Sections 25 through 29 of the HEEA, provide for the designation of service areas for each distributor;31 allow a distributor to construct and operate an electric distribution system in the service area of another distributor only if approved by the Commission32 and enable the Commission to alter the boundary of a service area.33 The critical importance of these sections of the HEEA, addressing distribution service areas, becomes apparent when one considers section 24 of the TReg, discussed in the following section of this Submission. 43. The TReg, and particularly section 24 of the TReg, plays an important part in this analysis. Interestingly, there is no mention of section 24 of the TReg in the Discussion Paper. 44. As discussed at the outset of these submissions respecting Legislative Framework for the AESO’s proposal, it is clear from section 24 of the TReg that incumbent TFOs alone are eligible to construct, own, operate and maintain transmission facilities34 determined on the basis AESO Replies to Stakeholder Comments: 2011-09-27 Page 81 of 119 of the geographic areas under sections 28 and 29 of the HEEA, with four legislated exceptions.35 As discussed above, the legislated exceptions are limited to the following: • where the Independent System Operator grants or provides for an exception authorizing alternative arrangements or agreements between TFOs;36 • the construction, upgrading or enhancement of an intertie;37 • critical transmission infrastructure in respect of which the Minister has made a determination under section 24.1(2) of the TReg;38 and • a transmission facility that is the subject of an industrial system designation.39 ISO Rule 9 45. As the AESO states on its website: …the AESO is given authority through legislation to make ISO Rules, adopt Reliability Standards and to prepare the ISO Tariff. These documents are referred to as the AESO’s authoritative documents. Authoritative documents are used by the AESO to communicate the binding and legal rights, requirements and obligations of market participants and the AESO. Compliance with the requirements set out in authoritative documents is mandatory. 40 AESO Replies to Stakeholder Comments: 2011-09-27 Page 82 of 119 46. ISO Rule 941 is part of the AESO’s authoritative documents and governs certain transmission related activities of market participants. Rule 9.1 governs “transmission facility projects.” Rule 9.1.1.1 states that “Subject to rule 9.1.1.2 b), c), d) and e) each service area shall have one TFO eligible to apply for the construction or operation of transmission facilities in such area”. Rule 9.1.1.1 goes on to state that “For the purposes of Rule 9.1.1.1, the following TFOs are eligible for the referenced service area”: TFO AltaLink L.P. ATCO Electric Ltd. ENMAX Power Corporation EPCOR Distribution & Transmission Inc. City of Red Deer City of Lethbridge Service area FortisAlberta Inc. ATCO Electric ENMAX Corp. EPCOR Distribution & Transmission Inc. City of Red Deer City of Lethbridge 47. Rule 9.1.1.1 b) deals with transmission facilities that existed as of August 12, 2004 and provides that the owner of such facilities, or its successors or assigns, shall be the eligible TFO receive directions from the AESO. Rule 9.1.1.1 c) enables the AESO to issue a direction to a TFO, other than a TFO that is eligible, if such TFO and the TFO in whose service area the project is located enter into an arrangement or agreement which would result in the safe, reliable and efficient operation of the transmission system and such arrangement or agreement has been filed with the Commission. Rule 9.1.1.1 d) enables the AESO to issue a direction to one or more TFOs, or a separate entity created for that purpose, where the project is located in more than one service area, AESO Replies to Stakeholder Comments: 2011-09-27 Page 83 of 119 provided that an arrangement of the nature referred to in Rule 9.1.1.1 c) is in place. Rule 9.1.1.1 e) addresses the circumstance where all but a small portion of a project is locate in the service area of a TFO and enables the AESO to provide a direction to the TFO in whose service area in which the largest portion of the project is located. 48. What is significant about ISO Rule 9.1.1 is that is entirely consistent with the legislative scheme outlined above and in particular section 24 of the TReg. The AESO references a potential need to amend ISO Rule 9.1 to enable implementation of its proposal as outlined in the Discussion Paper. However, as discussed above, the Discussion Paper makes no mention of section 24 of the TReg, which, consistent with the scheme of the applicable legislation, mandates by regulation that the ownership, construction, operation and maintenance of transmission facilities is restricted to incumbent TFOs, determined on the basis of the geographic areas under sections 28 and 29 of the HEEA, with four legislated exceptions. The AESO focus in the Discussion Paper, on its ability to amend ISO Rule 9.1 to enable the implementation of its proposal, ignores the scheme of the applicable legislation as reflected in section 24 of the TReg and ISO Rule 9.1. E. The Transmission Development Policy – The Policy Context for the Legislative Scheme Regulating Transmission 49. Issued in November, 2003 and remaining on the Department of Energy’s website as a statement of government policy, the Transmission Development Policy establishes the “foundation principles, recommendations AESO Replies to Stakeholder Comments: 2011-09-27 Page 84 of 119 and supporting rationale for a sustainable transmission development policy.”42 The primary “Foundation Principle” is “… to ensure that consumers are served with reliable, reasonably priced electricity, and to support continued economic growth in Alberta.”43 A key supporting principle and one stated “to further articulate this goal” is that “Transmission is a monopoly service.”44 50. The Transmission Development Policy states that: Transmission will remain a regulated monopoly. Transmission assets should be planned by the ISO and approved by the EUB. The EUB will regulate rates of return and recovery of transmission costs. Transmission facility applications will be reviewed and approved by the EUB in an open and transparent process. The regulatory and approval process must be timely and efficient.45 51. Further, the Transmission Development Policy states the following respecting transmission ownership: Transmission will continue to be regulated as a natural monopoly by the EUB to ensure open, nondiscriminatory access and to protect the public interest. Since transmission is characterized by large economies of scale, there are efficiencies in having an incumbent Transmission Facility Owner (TFO) provide operations and maintenance services to new facilities that are AESO Replies to Stakeholder Comments: 2011-09-27 Page 85 of 119 required in a geographic area they currently serve. This localized “critical mass” of service infrastructure allows the incumbent TFO to respond to apparatus failures and other events that may jeopardize service to customers. A “patchwork quilt” of ownership does not have the same level of coordination or economy of scale and so it would not operate as reliably and efficiently. Contiguous ownership of lines, substation facilities and the associated operating infrastructure therefore provides the greatest assurance of reliable and safe operation of the transmission system for customers (and employees) and is therefore in the public interest. To accomplish this intent, all new transmission facilities, including radial interconnection facilities, will be directassigned to the incumbent TFO’s. Projects involving connections or upgrades to existing transmission facilities or use of existing right-of-ways will also be direct assigned to the incumbent TFO to ensure safe and reliable service.46 The Discussion Paper ignores the policy rationale that underlies the Transmission Development Policy. Specifically, the Discussion Paper fails to address, with factbased analysis, the issues of the need to ensure efficiency, economies of scale and coordination in the provision of operation and maintenance services and the fact that the Transmission Development Policy determined that a “patchwork quilt” of ownership would not AESO Replies to Stakeholder Comments: 2011-09-27 Page 86 of 119 operate reliably or efficiently. F. The Legislative Evolution 52. The current EUA came into force on March 27, 2003. Of the provisions relevant here, only section 35(1) has been amended since. In 2007, this provision was amended to allow the ISO to direct a TFO (per (a)) or make a request of a market participant (per (b)) prior to the Commission’s receipt of the needs identification document. 53. The relevant provisions were amended in 2007, but these amendments did not change the substantive meaning of these provisions, but merely were changed to reflect the introduction of the AUC as the electricity regulator. 54. The TReg. was introduced on April 11, 2007.47 Section 24(1) has not been amended substantively since. Section 24.1 and 24.2 were added to the TReg in 2010.48 55. ISO Rule 9 was implemented on August 25, 2005 and underwent one change on November 13, 2008. This change was inconsequential for this analysis. 56. In conclusion, the legislative evolution since the introduction of the current form EUA in 2003 has been inconsequential respecting the relevant legislative provisions. G. Conclusion 57. It is clear that the AESO has erred in concluding that the applicable legislative scheme does not constitute a barrier to AESO Replies to Stakeholder Comments: 2011-09-27 Page 87 of 119 advancing or implementing market participant choice as proposed in the Discussion Paper. Consistent with the public policy embodied in the Transmission Development Policy, which finds expression in applicable legislative scheme, incumbent TFOs alone are eligible to construct, own, operate and maintain transmission facilities determined on the basis of the geographic areas under sections 28 and 29 of the HEEA, with four legislated exceptions that do not support the AESO’S view. III. Implementing market participant choice as proposed in the Discussion Paper is inconsistent with the economic, orderly and efficient development of the transmission system. 58. As the AESO explains in the Discussion paper, the rationale for its proposal is to provide “…the opportunity for a market participant to construct, own, operate and maintain (“own”) the transmission facilities required to connect a market participant’s facilities to the interconnected electric system”.49 Should the market participant choose to do so, that market participant will become a TFO, with all the commensurate obligations and accountabilities of a TFO, “…including construction, ownership, operations and maintenance and all other obligations stipulated in legislation and AESO authoritative documents.”50 59. AltaLink further understands the reason the AESO has brought forward the Discussion Paper is that the “…AESO understands this desire results generally from both the perceived high cost and extensive schedule associated with the incumbent TFO’s constructing the connection projects”.51 AESO Replies to Stakeholder Comments: 2011-09-27 Page 88 of 119 60. In section II of this Submission, AltaLink provided a comprehensive analysis of the legislative framework for transmission of electricity within this province. A fundamental underpinning of that legislative scheme is that transmission is to be developed in a manner that provides for the economic, orderly, efficient development and operation of the transmission system in Alberta. 61. The AESO indicates that the proposal outlined in the Discussion Paper is in response to an expressed desire on the part of market participants for an alternative, to TFO’s constructing, owning, maintaining and operating transmission facilities required to connect their facilities to the interconnected electric system, arising out of a “…the perceived high cost and extensive schedule associated with incumbent TFO’s constructing the connection projects.”52 62. The Discussion Paper neither contains nor references any evidence or fact-based analysis that demonstrates the AESO’s proposal will either ensure or enhance the economic, orderly, and efficient development and operation of the interconnected transmission system, when compared to the current industry approach where connection facilities that include transmission facilities are constructed, owned, operated and maintained by incumbent TFOs. 63. It is essential to any meaningful assessment of the public interest in implementing the AESO’s proposal that such fact-based analysis be undertaken and the results distributed to stakeholders for their consideration as part of the consultation process. AltaLink would expect that any such analysis, undertaken by the AESO Replies to Stakeholder Comments: 2011-09-27 Page 89 of 119 AESO, would include consideration of the basic factors germane to any meaningful assessment of reasonableness of project schedule and project cost. In addition, given the AESO’s position that any market participant choosing market participant choice, as defined by the AESO, would become a TFO and be subject to all of the obligations and accountabilities of a TFO, any analysis of cost/benefit of the AESO proposal must include an assessment of the costs a market participant would incur carrying out the obligations and accountabilities of a TFO. A. Misperceptions Respecting the Schedule Associated with the Incumbent TFO’s Constructing the Connection Projects 64. The AESO and industry have been working collaboratively to improve the customer interconnection process and corresponding timelines. 65. The AESO is keenly aware of the challenges it faces in moving a customer request for an interconnection through its own process. There are five industry players whose involvement impacts the overall timeline to move a customer interconnection through the AESO’s process. These five industry players include the customer, the AESO, the DFO, the TFO and the AUC. 66. Notwithstanding this, the role of the TFO is the sole focus of AESO’s Discussion Paper. There is no mention of the roles of the customer, the AUC, the AESO, the DFOs and the important impact that each of these entities has on the length of any interconnection schedule. AESO Replies to Stakeholder Comments: 2011-09-27 Page 90 of 119 67. On October 4, 2011, the AESO provided a stakeholder update on the progress being made in optimizing the connection process. In that paper, the AESO indicates that the industry working group had worked on a redesign process under which the target time for the connection process was to be reduced from 36 to 24 months. The AESO report indicates that, on average, the total duration of the connection process has been reduced to approximately 25 months. The AESO points out that, for most projects, stage durations typically fall between the target timelines and the maximum stage guidelines, with the exception of Stage 1. As a result, it appears that the AESO and industry efforts would be better focused on improvements to Stage 1, which is the Connection Study Scope. Stage 2 results are hitting slightly above the target timeline. Stage 3, NID and FA timelines, are currently low and below the target timeline. Stage 4, Application Filings and Approvals, are landing between target and maximum, and the AESO indicates that this stage is mainly dependent on the timing of AUC approvals. This is outside the control of both the TFO and the customer. Stage 5, construction, is hitting between target and maximum, and industry teams consistently discuss the critical nature of completing the prior stages in a timely manner given that construction in many areas of the province requires frozen soil conditions. B. Perceived High Cost Associated with the Incumbent TFO’s Constructing Connection Projects 68. The Discussion Paper refers to the perceived high cost associated with incumbent AESO Replies to Stakeholder Comments: 2011-09-27 Page 91 of 119 TFO’s constructing connection projects. AltaLink acknowledges that the perceived high cost of incumbent TFO’s constructing transmission infrastructure has been an industry topic for several years, notwithstanding the many layers of oversight, reasonableness reviews by the AESO and prudence reviews by interested parties and the AUC in the course of General Tariff Applications and Capital Deferral Account Reconciliation proceedings. To justify a structural change of the significance suggested by the AESO, an analysis would have to demonstrate that market participants can consistently construct interconnections, that include transmission facilities, and meet all the obligations of a new TFO at a cost that is materially lower than costs being incurred by incumbent TFOs. AltaLink expects that an analysis would have been undertaken to address the following factors, among others: (a) The TFO currently constructs transmission facilities at cost, there is no return or margin included in the TFO’s cost to construct transmission facilities when such facilities are included in rate base. (b) The AESO determines the scope of the transmission facilities required to be built through the project functional specifications, not the TFO. (c) The AESO determines the technical standards to which the incumbent TFO must construct transmission facilities, including such key cost standards as return periods and ice/snow/wind loadings, transmission line standards, and protection and control standards. AESO Replies to Stakeholder Comments: 2011-09-27 Page 92 of 119 (d) The customer determines the schedule for the requested in service date. (e) The TFO is currently required to bid into the market for material and construction contractors for transmission projects. The TFO competitively procures or negotiates within the market 75%-80% of the total transmission project costs incurred. (f) There are numerous safety, environment, consultation, permitting, and regulatory obligations, under a myriad of statutes, regulations and rules, with which TFOs must comply when constructing transmission facilities in Alberta. (g) The average customer interconnection total project cost is approximately $15 million. (h) In AltaLink’s in excess of 10 years as a regulated TFO, whose costs are rigorously scrutinized by the AESO and the AUC, there have been no findings of imprudent cost incurrence or the disallowance of costs related to transmission projects. 69. Since 75% to 80% of the cost of interconnection projects, averaging $15 million, must be competitively bid into the market, any possible efficiency gains could only potentially have an impact on $3 to $4 million. Given that the project scope and technical standards are defined by the AESO, and market participants would be obligated to meet the same scope and standards as would incumbent TFOs, there is little room to achieve cost savings within the $3 to $4 million of the cost of an interconnection project that is not required to be competitively bid. It is difficult to rationally contemplate how a AESO Replies to Stakeholder Comments: 2011-09-27 Page 93 of 119 market participant that is a new TFO, with likely little to no experience in constructing transmission facilities, no procurement experience in the transmission market, and no experience in delivering on all the safety, environment, consultation, permitting, regulatory and construction obligations, would be able to bring material cost efficiencies to an interconnection project. 70. AltaLink submits that meaningful consideration of the public interest in the AESO’s proposal for market participant choice cannot reasonably proceed in the absence of substantive evidence and fact-based analysis that demonstrates that market participants will be able to consistently and materially reduce the costs associated with the incumbent TFO’s role in delivering customer interconnections. Without such analysis and evidence, there exists no demonstrable value in the AESO’s proposal to reduce customer interconnection costs nor a rational basis upon which stakeholders can assess whether the AESO’s proposal will result in or enhance the economic, orderly and efficient development of the transmission system. C. The Ongoing Costs Associated with Being a TFO Must be Taken into Account 71. The AESO acknowledges in the Discussion Paper that that any market participant that chooses to construct and own its interconnection becomes a TFO subject to all of the obligations and duties imposed on TFOs by the applicable statutory scheme. 72. There are numerous obligations imposed upon a TFO as the owner and operator of regulated transmission facilities in Alberta. Any AESO Replies to Stakeholder Comments: 2011-09-27 Page 94 of 119 rational and comprehensive analysis of the cost versus benefit of the AESO’s proposal, in terms of its impact on the economic, orderly, and efficient development of the interconnected transmission system, must consider the incremental costs and potential for duplication of processes that would result from numerous market participants choosing to construct interconnection facilities and becoming TFOs. AltaLink would expect the AESO, as part of its analysis, would have considered the incremental cost and potential for duplication of processes that would result from the introduction of potentially 10 to 30 individual new TFOs. Such an analysis would need to fully account for the incremental costs to the AESO, AUC and MSA in their various roles of oversight and regulation of TFOs. 73. As a minimum, AltaLink would expect the AESO to incorporate within its analysis, the costs associated with the obligations every new TFO would be required to meet, which include but are not limited to the following: (a) preparation, approval and administration of an Inter-Affiliate Code of Conduct, and all associated obligations of a Compliance Plan, quarterly reporting to the AUC, confirmation of all employees acknowledgement of the Code and all obligations to demonstrate compliance; (b) filing and processes for AUC approval of TFO Terms and Conditions of service; (c) filing and processes for AUC approval of a tariff, including all revenue requirements necessary to deliver on all the obligations as a TFO. Related processes would include the establishment of necessary accounts and AESO Replies to Stakeholder Comments: 2011-09-27 Page 95 of 119 processes and reporting in compliance with the Uniform System of Accounts and Minimum Filing Requirements; (d) internal processes and external review and compliance enforcement processes to demonstrate compliance with the Alberta Reliability Standards, including the AESO’s, MSA’s and AUC’s incremental costs to audit, assess compliance, and determine sanctions. Currently, there are 12 standards in place and up to 30 additional standards in development; (e) internal processes and external review and compliance enforcement processes to ensure compliance with all AUC Rules including Rule 007, Rule 012, and Rule 027 to name but a few; (f) internal processes and external review and compliance enforcement processes to ensure compliance with all ISO Rules, including direct assign rules, technical standards and operating procedures; (g) internal processes and external review and compliance enforcement processes to ensure compliance with Industry Canada’s metering regulations including the Electricity and Gas Inspection Act; (h) internal processes and external review and compliance enforcement processes to ensure the safety of employees and the public by ensuring the TFO meets all obligations within the Alberta Safety Codes Act, the Alberta Occupational Health and Safety Code –Part 40 Utility Workers Electrical, the Alberta Electric Utility Code and its referenced standards, such as: AESO Replies to Stakeholder Comments: 2011-09-27 Page 96 of 119 (i) the Canadian Electrical Code Part 1; (ii) CSA C22.3 No. 1 “Overhead Systems”; (iii) CSA C22.3 No. 6 “Principles and Practices of Electrical Coordination Between Pipelines and Electric Supply Lines”; and (iv) CSA C22.2 No. 41 “Grounding and Bonding Equipment”; (i) operating the transmission facilities on a real time basis, monitoring the facility on a 24 hour, 7 day a week basis and as directed by the AESO; (j) maintaining the transmission facilities reliably and safely, including regular patrols and inspections; (k) submitting quality of service reports to the AUC and performance statistics to the CEA; (l) internal processes and external review and compliance enforcement processes to ensure compliance with environmental legislation such as the Migratory Birds Convention Act, the Fisheries Act, the Species at Risk Act, the Reclamation Act, the Weed Control Act, the Wildlife Act, the Water Act and the Historical Resources Act, to name but a few; and (m) obligation to maintain access to debt markets including maintenance of credit ratings to enable the issuance of debt on reasonable terms during all phases of the business cycle. 74. Many of the above obligations result in AESO Replies to Stakeholder Comments: 2011-09-27 Page 97 of 119 annual costs that the TFO must incur. What is provided here are only a few of the basic obligations a TFO has to meet, which have the potential to add incremental costs for the transmission of electricity. Should the AESO consider proceeding with its proposal, AltaLink will expect that the AESO’s analysis to include all TFO obligations in order to ensure the AESO’s proposal can confidently demonstrate no overall increase in costs to ratepayers. 75. In order for the AESO’s proposal to demonstrate an economic advantage to customers, the incremental costs savings associated with the AESO’s proposal must materially exceed the incremental benefits. This is because the fact that incremental costs will be incurred by new TFOs under the AESO’s proposal is real, demonstrable and inevitable while the potential for incremental benefits have not been demonstrated. IV. The material change in the structure of the transmission function proposed in the Discussion Paper fails to address resulting risks, inefficiencies and unintended consequences. 76. The Discussion Paper fails to address or reference any comprehensive fact-based analysis of the risks, inefficiencies and the unintended consequences of implementing the AESO’s proposal. No meaningful assessment of the public interest in implementing the AESO’s proposal can be made in the absence of such a comprehensive analysis. 77. Since the AESO released its Discussion Paper, AltaLink has identified a few potential risks, unintended consequences, and AESO Replies to Stakeholder Comments: 2011-09-27 Page 98 of 119 inefficiencies associated with the AESO’s proposal, as follows: (a) There does not appear to be any current AESO tariff that would enable the proposal. The market participant must become a TFO and file a TFO tariff. As such, the market participant would be a customer to the AESO with a DTS or STS tariff through which it must pay for transmission service to the AESO and it will also be a TFO that has a tariff approved by the AUC to recover all its costs as a TFO. This is very inefficient and can only be expected to result in incremental costs to ratepayers. (b) The electric industry structure in Alberta has been established to ensure there is open access to transmission for all participants. This structure is facilitated by the fact that incumbent TFOs, who are the owners of the transmission system, are either stand-alone transmission utilities or divisions of integrated regulated utilities, in each case subject to codes of conduct. The AESO’s proposal enables market participants to become TFOs in circumstances where the market participant could include entities competing in the energy market, such as generators, or industrial customers participating in industrial markets, such as oil and gas companies that directly compete with each other. The AESO proposal is not related to industrial systems nor transmission facilities on a customer’s own property. It is related to transmission facilities that will be used by other ratepayers, customers and the public. It is unclear how the AESO intends to ensure open access to market participant owned transmission facilities for other competing market participants who may wish to connect to these transmission facilities in the future. While AESO Replies to Stakeholder Comments: 2011-09-27 Page 99 of 119 legislated remedies may exist to enable the obtaining of access, pursuing such remedies consumes resources, takes time and leads to uncertainty, which are not characteristics or challenges under the current regime. Often delay can amount to effective denial of timely access and provide an advantage to a competitor that is the TFO owning the connection facilities. (c) The Discussion Paper fails to address how the AESO intends to pre-qualify market participants that will become new TFOs. The AESO’s requirement to meet its duty and obligation to ensure the safe, reliable and timely development of the interconnected system requires that the AESO establish a rigorous prequalification process for market participants choosing to become TFOs. Any such prequalification process should be as extensive as that being proposed by the AESO in its Competitive Bid process as the end result of both is the same, a new TFO. (d) It is apparent that the AESO’s proposal for market participant choice contemplates that a market participant that chooses to construct an interconnection will be enabled to construct, own, operate and maintain the interconnection without any process for testing to ensure that market participant ownership is consistent with economic, orderly and efficient development of the interconnected system, both in near and longer term. There is no way for the AESO to ensure, on behalf of ratepayers, that the market participant can construct and own such transmission facilities more cost effectively than the incumbent TFO. (e) There have been primarily two major TFOs AESO Replies to Stakeholder Comments: 2011-09-27 Page 100 of 119 within Alberta for decades, along with four smaller TFOs for a total of six TFOs. The AESO has coordinated the operation of the power system in Alberta with primarily two experienced TFOs for many years. A power system is a complex, networked, integrated system that provides a critical service to all Albertans. Seamless coordination of activities, processes, accountabilities and execution on a minute by minute, day-by-day basis is necessary to ensure a reliable grid. The Discussion Paper neither includes nor references any fact-based analysis undertaken by the AESO demonstrating that the addition of 10 to 30 new TFOs intermingled into incumbent TFO service areas will result in an improvement to the reliable, safe, orderly, economic and efficient operation of the transmission system. (f) There are significant economies of scale that arise from incumbent TFO’s constructing, owning, operating and maintaining transmission facilities within a service region. Incumbent TFOs have control centers for real time operation, which are operated 24 hours a day and seven days a week, field resources for emergency response and maintenance, critical spares and inventory, and experienced asset managers and engineers to maintain transmission facilities. The Discussion Paper neither contains or references any assessment or analysis of how specifically a proliferation of small TFOs scattered across the province of Alberta, imbedded within an incumbent TFO’s service areas, will impact the current operation of the system and the economies of scale that are currently achieved. V. The AESO has considered but one option to address the perceived concerns of AESO Replies to Stakeholder Comments: 2011-09-27 Page 101 of 119 customers 78. AltaLink is confident that there are an array of potential options to what is proposed in the Discussion Paper that are simpler, consistent with the existing legislative scheme, more flexible for customers and which avoid duplication of processes and do not impose significant incremental costs and risks on the operation of the interconnected transmission system. 79. As a next step, AltaLink proposes that the AESO and stakeholders work together in an expeditious manner to seek simple and workable solutions to concerns regarding customer interconnections. VI. Summary 80. AltaLink considers the proposal for market participant choice described in the Discussion Paper to be fundamentally flawed. AltaLink does not support the proposal for the following reasons: • The applicable legislative scheme constitutes a barrier to implementing market participant choice as proposed in the Discussion Paper. • The Discussion Paper fails to demonstrate how the proposal for market participant choice is in the public interest as being either consistent with or enhancing the economic, orderly and efficient development and operation of the transmission system in Alberta. • The Discussion Paper fails to address or justify with fact-based evidence and analysis the material incremental costs, inefficiencies AESO Replies to Stakeholder Comments: 2011-09-27 Page 102 of 119 and unintended consequences that would result from implementation of the AESO’s proposal. • The Discussion Paper fails to address with fact-based evidence and analysis the real potential for increased risk to the safe and reliable operation of the interconnected transmission system that would arise from the implementation of the AESO’s proposal. 81. AltaLink supports continuing to work with the AESO and customers, collaboratively, to seek simple and workable solutions to concerns regarding the cost and schedule related to customer interconnections. AltaLink fully supports solutions to such concerns that can be implemented in a reasonable timeframe, effectively and efficiently, while respecting the strong policy foundation expressed in the legislative scheme for this province and the electricity market. That strong policy foundation requires that the economic, orderly and efficient development and regulation of the AIES be preserved and respected. 1 Discussion Paper pages 3 and 4. 2 Statutes of Alberta c. E.5.1, 2003, as amended. 3 Revised Statutes of Alberta 2000, c. H-16, as amended. 4 Alberta Regulation 86/2007, as amended. 5 The phrase “transmission facility” is defined in section 1(1) (bbb) of the EUA. 6 TReg, Part 4, section 24. 7 TReg, Part 4, section 24(2). 8 TReg, Part 4, sections 24(3) (a) and 27. 9 TReg, Part 4, sections 24(3)(b), 24.1(2). 10 EUA section 1(1)(x), defines an “industrial system; EUA section 40, among other things, imposes certain duties AESO Replies to Stakeholder Comments: 2011-09-27 Page 103 of 119 on owners of industrial systems, empowering the ISO to apply for certain orders related to the use of industrial systems for system access service, the granting of access to industrial systems for system access service and the establishment of rates and terms and condition for service. 11 City of Calgary v. ATCO Gas and Pipelines Ltd. [2006] 1 SCR 140 at paragraph 49. 12 Re Rizzo Shoes Ltd. (Re), [1998] 1 S.C.R. 27, paragraph 21. 13 [2005] 2 S.C.R. 601, paragraph 10. 14 R. Sullivan ed., Sullivan on Construction of Statutes, 5th ed. (Markham: LexisNexis, 2008 (Sullivan on Construction of Statutes), page 255. 15 Sullivan on Construction of Statutes, page 366. 16 2007 ABCA 210. 17 The Bur Case, paragraph 22. 18 AESO Rules, part of the AESO’s Authoritative Documents published on the AESO website. 19 Discussion Paper page 3. 20 Sullivan on Construction of Statutes, page 244; University Heath Network v. Ontario (Minister of Finance), [2001] O.J. No. 4485 at paragraph 31 (Ont. C.A.); and Conservative Fund Canada v. Canada (Chief Electoral Officer), 2010 ONCA 882, paragraphs 76 and 77. 21 Transmission Development, The Right Path for Alberta, a Policy Paper, Alberta Energy November 2003 (Transmission Development Policy), found at http://www.energy.alberta.ca/Electricty/539.asp, page 4. 22 Discussion Paper page 3. AESO Replies to Stakeholder Comments: 2011-09-27 Page 104 of 119 23 EUA, section 3(1)(b). 24 TReg, section 24. 25 EUA, section 4. 26 Transmission Development Policy, page 4. 27 Industrial Systems Policy Statement, found at http://www.energy.alberta.ca/Electricty/539.asp, section 2.0, second bullet. 28 HEEA, sections 16(1) and (2). 29 EUA, section 35(3). 30 Discussion Paper, section 4, Eligible Market Participants, page 4. 31 HEEA, section 25. 32 HEEA, section 26. 33 HEEA, section 29(1). 34 The phrase “transmission facility” is defined in section 1(1) (bbb) of the EUA. 35 TReg, Part 4, section 24. 36 TReg, Part 4, section 24(2). 37 TReg, Part 4, sections 24(3) (a) and 27. 38 TReg, Part 4, sections 24(3)(b), 24.1(2). 39 EUA section 1(1)(x), defines and “industrial system; EUA section 40, among other things, imposes certain duties on owners of industrial systems, empowering the ISO to apply for certain orders related to the use of industrial systems for system access service, the granting of access to industrial systems for system access service and the establishment of rates and terms and condition for service. 40 http://www.aeso.ca/rulesprocedures/15981.html . 41 ISO Rules Part Two – Market Participation. Note that AESO is currently undertaking a comprehensive review of its authoritative documents, including the ISO AESO Replies to Stakeholder Comments: 2011-09-27 Page 105 of 119 Rules to achieve several objectives, including clarifying mandatory requirements, standardizing structure and form, eliminating duplication and inconsistencies, addressing gaps and improving the overall organization. ISO Rule 9 remains to be transitioned. 42 Transmission Development Policy, page 2. 43 Transmission Development Policy, page 2. 44 Transmission Development Policy, page 2. 47 Alberta Regulation 86/2007. 48 Alberta Regulation 153/2010. 49 Discussion Paper, page 3. 50 Discussion Paper, page 3. 51 Discussion Paper, page 3. 52 Discussion Paper, page 3. AESO Replies to Stakeholder Comments: 2011-09-27 Page 106 of 119 Benign Power Inc. The purpose of this correspondence is to provide stakeholder comment and recommendations on what is now being called “Market Participant Choice,” but what was originally requested of AESO and ADOE was simple “COMPETIVE PROCUREMENT””. On a very high level, B9 Power finds this initiative commendable and one of the most constructive, proactive tasks AESO has undertaken since its inception, and Alberta deregulation of electrical generation occurred. Therefore, AESO is encouraged to use the KISS principle and get this long overdue industry request completed by December 31, 2011. BACKGROUNDER 1) The Alberta Government deregulated generation but missed deregulation of transmission. This failure to deregulate transmission ultimately has become the single largest flaw in the government’s initiative and the resultant massive, continuous re-regulation. 2) As a result of the major flaw, neither generators, and now it appears, load businesses can or could, build their own short transmission connect to the AESO governed grid. 3) Transmission monopolies were created. 4) As a result of transmission monopolies, AESO determined that it must create the most contentious issue in the Alberta electricity market called “Direct Assign.” 5) The flawed concept of “direct assign” to a monopoly has been problematic for all Albertans, generators, load businesses and the AESO Replies to Stakeholder Comments: 2011-09-27 Page 107 of 119 Alberta consumers since inception, and has never truly been in the public interest due to excessive cost overruns and scheduling by the monopolies. 6) As a result of the major flaws, industry has requested that it simply be allowed to do what it had the right and capability to do before “direct assigns” to monopolies, which was to obtain its own costs through a competitive bidding process, award the contract to the lowest qualified bidder, and build the short connection to the AESO mandated grid. 7) Arguably, ADOE, AUC, AESO, and MSA are all on the same team given they all report to the Minister of Energy and moreover, all have a duty and responsibility to act in the public interest of lower or lowest reasonable possible costs, which direct assign by AESO monopolies has not done. THE PATH FORWARD OUTSIDE THE BOX INNOVATION 1) A renowned legal team, and arguably industry’s leading electncal association at November 2010, had already scoped all the legal realities and the process to achieve a "process to enable market participants to meet need for their own connection facilities". Prior to this, a market participant had already proven the legal capability for generators (and presumably load businesses) to build their own transmission and connection to bulk transmission point facilities (i.e. via competitive procurement, which is/was the path forward initiated by Mr. S. Battacharya and Mr. C Monar). AESO Replies to Stakeholder Comments: 2011-09-27 Page 108 of 119 It is now November 2011 and the path forward continues to be re-invented, and will at this pace, take two or more years to fruition. The question then becomes how did this simple project task get off the rails and from a simple "competitive procurement process" to over complicated "market participant choice for transmission connections" where every load business and generator, large or small, has to become a TFO and all the myriad of bureaucratic complications therein? The facts are no small load business, nor do most small or large generators want to become TFO's They just want the lowest possible, reasonable, bid connection cost period, and which 1n fact, ultimately results in becoming in the public Interest as mandated by ADOE, AUC, MSA, AESO and the Minister. 2) How then does industry achieve the lowest, reasonable, costs for competitive procurement for both the public interest and itself? Answer: Simply have the AESO mandate five (5) bids: Four (4) from qualified connection/transmission corporations, and One (1) from the incumbent TFO itself, rather than the direct assignment process, which now occurs with no true accountable costs, no bids, no scheduling, and no accountability. The business owner, in load scenarios or the generator, it is submitted, will be pleased to have achieved the lowest possible reasonable, qualified connection cost. This then also provides comfort to ADOE, UC, MSA, and AESO whose mandates all require acting in the public interests that the lowest possible costs were achieved. The AESO has previously argued to date this is not in its mandate. Contrary, and arguably, it is absolutely within AESO Replies to Stakeholder Comments: 2011-09-27 Page 109 of 119 the AESO mandate given they, like AUC, MSA, and ADOE, all report to the same Minister, the Alberta Government, thus ultimately the public. The no bid monopoly system has never been in the public interest. 3) The paper and the power point presentation of 2011 10 14 appear to indicate that minor regulation changes may need to be modified to achieve what industry had the right and the capability to do (competitive procurement) before deregulation, and resultant massive reregulation and excessive rules. Under the Alberta legislative framework, simple regulation changes can be made expeditiously without having to go through the Alberta legislature and political process. This being the case, then ADOE, AUC, MSA, and AESO are all on the same team. All report to the same Minister and ought to be able to get this accomplished and reduce red tape using the KISS principle in an expeditious timeline by the end of 2011. Moreover, given that most of the consternation appears to be with AESO's own created rules Appendix 2- 9.3 at pages 13 to 18 VS ADOE, AUC, MSA, then they ought to be easily changed or deleted, especially since the legal team and industry association did not request any of this at November 2010. It simply already set the clear path forward. 4) Given the overall intention of the now called "market participant choice for transmission connection” has now been deemed as constructive (above introductory para 1), it appears as if this thanksgiving bird is a bit over cooked, over thought, over legalized and is constrained or hide-bound by over complicated regulation and rules, when the simple AESO Replies to Stakeholder Comments: 2011-09-27 Page 110 of 119 "competitive procurement" is all that was asked for and simply achievable by the AESO refusing all further direct assignments other than bulk transmission. (Likely that ought to go to competitive bidding as well). The November 2010 legal and industry association paper did not request any load side dynamics and so how did the simple process request get bogged down to where it now is? Moreover, the AESO new request for simple connections proponents to become TFO's is overkill and overt complication in its finest form when it is not required, nor requested by business or generators. 5) Demanding simple business owners, large and small, and generators both large and small, becoming TFO's borders on the ridiculous, given the massive bureaucratic complications of becoming a TFO. Moreover, this gives existing TFO's listed at page 13 of the paper distinct advantages, and given they were TFO's prior to deregulation and subsequent over reregulations and rules. Demanding business and generators become TFO's just so they can achieve competitive procurement is plain wrong, and not the deal requested nor that anyone really wants to do. AESO INSIDE THE BOX DEMANDS WITHOUT SIMPLE INNOVATION AESO questions: 1) "Do stakeholders have any comments?" YES 2) "Do stakeholders have comments on the intro section?" YES AESO Replies to Stakeholder Comments: 2011-09-27 Page 111 of 119 3) "Do stakeholders agree with the suggested market participants?" NO Forcing business owners large and small and generators large and small to become TFO's just so they can obtain "competitive procurement" of their connection at lowest reasonable bid costs instead of monopoly procurement costs borders on insanity? 4) "Do stakeholders agree with the suggested eligible connection projects?" NO As above in 4 5) "Do stakeholders agree with the suggested model?" NO! As above, use the KISS model to have AESO do its job in the public interest, the same as AUC, ADOE, MSA, Minister of Energy and Alberta Government for its citizens, and demand five bids for all connections (bulk transmission excepted), Four bids from qualified connection/transmission firms, and One from the incumbent TFO. This meets the test for AUC as its current mandate, ADOE, MSA and the Minister and the Government. With lowest possible reasonable costs everyone wins VS direct assignment to monopoly costs, where no one wins in the end. The legal teams and the industry association did not ask for this overcomplicated model. 6) "Do stakeholders agree with the suggested key connection process procedural changes?" Possibly, provided there are no massive changes to the connection model AESO rolled AESO Replies to Stakeholder Comments: 2011-09-27 Page 112 of 119 out March 31 2010. At the connection process, update held by AESO October 12, 2011 , the moderator advised AESO has got the message to stop changing the connection process, given it has undergone continuous change since 2003 dozens of times. Moreover, no one is asking for change in the connection process but rather only "COMPETITIVE PROCUREMENT" without any and all of the rules and legalese provided in the paper. Again, the KISS principle is reiterated without more excessive bureaucracy and more red tape. 7) "Do stakeholders agree with the suggested request for proposal approach?" NO This section lacks adequate detail, intent, understanding to make any informed response. Moreover, it locks participants into the blackmail threat of getting punted out of the queue for changing industry and global market conditions outside the control of the business. Just eliminate the direct assign practice and this is not required. 8) "Do stakeholders agree with the suggested project cancelation and revoking of queue position?" NO The AESO needs to be a lot less dictatorial and understand that globally, all business face extreme global market conditions, largely not of their own making and control. The AESO ought not to have the right for punting Alberta business out of the queue, and/or killing their business opportunities. That is not what the Alberta government is about, nor any other provincial or Federal Government is about. This AESO Replies to Stakeholder Comments: 2011-09-27 Page 113 of 119 needs a severe reality check if not by AESO itself, then ADOE and the Minister. 9) "Do you agree that new TFO's should be subjected to the same legislative requirements as incumbent TFO's?" NO! First, most business who want a simple load connection, and most, if not all, generators who are not already TFO's, have absolutely no desire to become a TFO with all of their bureaucratic complications. The more important and better question is who came up with this insane scenario? Clearly, the legal teams and association generators did not ask anyone to become TFO's, but rather only fairness, restore the previous capability for lowest cost simple connection, and "competitive procurement" mandated by AESO as already mandated by AUC. If a business wants to get into the business for the sole purpose of becoming a TFO, then absolutely all the same rules ought to apply as applicable to existing TFO's . 10) "Do stakeholders agree that new TFO's should be subject to the same requirements and obligations set out in AESO Documents as incumbent TFO'S?" NO Same comments as in 10 above apply. Virtually no one wants to become a TFO other than those already listed in the paper at page 13 Appendix 2. All business and the public want is to delete the AESO "direct assignment" to no bid monopolies, and give back to Albertans the competitive procurement principles they had previously, and that exist in every large oil and gas, pipeline company, every municipal organization, and indeed the Alberta AESO Replies to Stakeholder Comments: 2011-09-27 Page 114 of 119 government itself. The direct assignment system is the root cause of dissatisfaction, so just fix it. 11) "Do stakeholders agree that ISO rules 9.1 should eventually be changed to apply to new TFO's removing references to incumbent TFO's and the respective service areas?" YES Utilizing the KISS principle likely fifty to sixty percent of these AESO rules could be thrown out and miniscule changes made to allow competitive procurement. 12) "Do stakeholders think any new ISO rules need changing to support "market participant choice?" NO Typically less rules and constantly changing rules are preferred by business. The Prime Minister of Canada, the Government of Alberta (attached), the Mayor of Calgary, and the former Minister of Energy, are all on the record for "reducing red tape". The AESO needs to seriously comprehend this 'reduce red tape' message and get with the program in this regard. Realistically, and at a high level, to achieve competitive procurement, the only rule needed is to allow the five bids process which arguably it should have been doing since its inception. Had this been done multi-millions of dollars would have been saved by Albertans and businesses throughout Alberta. 13) "Do stakeholders have any other comments regarding market participant choice?" YES Call it what it was and is all about in the first place, which is "competitive procurement," and AESO Replies to Stakeholder Comments: 2011-09-27 Page 115 of 119 bids as started by the legal team, the association, at ADOE, and later by Mr. S. Battacharya and Mr. C. Monar for all connections to the grid. This is simple, exists already in almost all businesses, and ought to have been already completed. 2011 10 19. **2 pages of attachments** AESO Replies to Stakeholder Comments: 2011-09-27 Page 116 of 119 TransCanada Energy Ltd. TransCanada Energy Ltd. (TCE) appreciates the opportunity to comment on the discussion paper referenced above. Generally, connections have become more of a challenge, especially around cost overruns and schedule management. Both have negative consequences to market participants that desire to connect. TCE is therefore supportive of this initiative and presents the following comments: 1. Legislation and Policy Objectives While TCE supports allowing market participants to submit a transmission solution to meet "need", it disagrees with the AESO's interpretation of Section 35(1) of the EUA that a market participant would be required to become a new TFO and be subjected to all the requirements of a TFO. Nothing ins. 35(l)(b) requires that the market participant own, operate and maintain the transmission facilities. TCE believes that taking such a narrow interpretation of the provision could lead to an early failure of this initiative. This concern is discussed further below. 2. Market participants who build their own facilities would need to own, operate and maintain such facilities unless a private sale of the assets occurred. TCE does not agree that market participants, who wish to manage the costs and schedule of their connection, need to own, operate and maintain the connection. TCE suggests an evaluation be done to determine if, under the current legislation, the AESO could continue to direct the incumbent TFOs to meet "need", but require TFOs to allow market participants to lead the project, in essence having the TFO act AESO Replies to Stakeholder Comments: 2011-09-27 Page 117 of 119 as the "general contractor" for key technical requirements. The AESO Rules may be the mechanism to implement this option, and if so should be reviewed and updated accordingly. 3. Market participants who choose to build their own facilities and, under the above restriction to then own, operate and maintain the facilities, would therefore be TFOs and would need to comply with all requirements and obligations as do incumbent TFOs. As discussed above, TCE's view is that this requirement goes beyond what is provided for in the legislation and may restrict participants from electing to build their own transmission connection. The AESO and industry should define the minimum connection requirements in order to enable market participant choice while maintaining grid reliability and operability. In addition, if an agreement with the incumbent TFO can be reached, the participant developing the connection might sell the facilities to the incumbent TFO, either at market value for loads or negligible value for generators. 4. Market participants must declare at Stage 0 of the connection process that they will build their own transmission TCE suggests that this decision should be made prior to passing Gate 2 and would likely not be made prior to reviewing connection alternatives as well as cost and schedule estimates. TCE believes the incumbent TFOs will work with the market participant in a collaborative manner to get to that decision point and does not agree with the AESO's position that the TFOs may be uncooperative. AESO Replies to Stakeholder Comments: 2011-09-27 Page 118 of 119 TCE notes that several mechanisms to improve transmission cost and/or schedule management are currently in place or in development Transmission Cost Monitoring Committee, Transmission Competitive Procurement Process, Abbreviated Need Identification Rule, and Market Participant Choice. Consideration should be given to the overlap or gaps between each of these areas with the overall objective of facilitating customer choice regarding their connections. AESO Replies to Stakeholder Comments: 2011-09-27 Page 119 of 119