Connection Engineering Study Report for AUC Application: Error! Reference source not found. Stage 3 Connection Study Scope [Insert Customer Name] [Insert Project Name] AESO Project Number: [000] Company Name Engineer Name P.Eng. Date Engineer Signature Date Signature [Studies Consultant] [AESO (Project Studies Engineer)] Company Name Name [Insert Customer Name] Document Release [R1] [insert date] Page 1 Project and System Access Studies (PSAS) Group Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Page 2 Project and System Access Studies (PSAS) Group Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Contents Introduction ......................................................................................................................................... 5 1.1. Project............................................................................................................................................ 5 1.1.1. Project Overview.................................................................................................................... 5 1.1.2. Load Component ................................................................................................................... 5 1.1.3. Generation Component ......................................................................................................... 6 1.2. Study Scope .................................................................................................................................. 7 1.2.1. Study Objectives .................................................................................................................... 7 1.2.2. Study Area ............................................................................................................................. 7 1.2.3. Studies Performed ............................................................................................................... 10 1.2.4. Studies Excluded ................................................................................................................. 11 2. Connection Alternatives Selected for Studies ............................................................................... 12 3. Criteria, System Data, and Study Assumptions ............................................................................. 13 3.1. Criteria, Standards, and Requirements ....................................................................................... 13 3.1.1. Transmission Planning Standards and Reliability Criteria................................................... 13 3.1.2. AESO Rules ......................................................................................................................... 14 3.1.3. Other Requirements ............................................................................................................ 14 3.2. Study Scenarios .......................................................................................................................... 15 3.3. Load and Generation Assumptions ............................................................................................. 15 3.3.1. Load Assumptions ............................................................................................................... 15 3.3.2. Generation Assumptions ..................................................................................................... 16 3.3.3. Intertie Flow Assumptions ................................................................................................... 17 3.3.4. HVDC Power Order (if applicable) ....................................................................................... 18 3.4. System Projects ........................................................................................................................... 18 3.5. Customer Connection Projects .................................................................................................... 19 3.6. Facility Ratings and Shunt Elements ........................................................................................... 19 3.7. Protection Fault Clearing Times .................................................................................................. 21 3.8. Voltage Profile Assumption ......................................................................................................... 21 3.9. Motor Starting Assumptions ........................................................................................................ 22 4. Study Methodology ........................................................................................................................... 22 4.1. Connection Studies Carried Out .................................................................................................. 22 4.2. Load Flow Analysis ...................................................................................................................... 23 4.2.1. Contingencies Studied ......................................................................................................... 23 4.3. Voltage Stability (PV) Analysis .................................................................................................... 23 4.3.1. Contingencies Studied ......................................................................................................... 23 4.4. Transient Stability Analysis ......................................................................................................... 24 4.4.1. Contingencies Studied ......................................................................................................... 25 4.5. Short-Circuit Analysis .................................................................................................................. 25 4.6. Motor Starting Analysis [as required] .......................................................................................... 25 4.7. Effectiveness Factor Analysis Studies [as required] ................................................................... 25 4.8. Sensitivity Studies [as required] .................................................................................................. 25 4.9. Mitigation Measures .................................................................................................................... 26 1. Page 3 Project and System Access Studies (PSAS) Group Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Attachments Attachment A Transmission Planning Criteria – Basis and Assumptions (Reliability Criteria) Tables Table 1.2-1: Summary of System Projects ................................................................................................................... 10 Table 3.1-1: Post Contingency Voltage Deviation Guidelines ...................................................................................... 14 Table 3.2-1: List of the Connection Study Scenarios ................................................................................................... 15 Table 3.3-1: Forecast Area Load (201X LTO at AIL Peak) .......................................................................................... 15 Table 3.3-2: Local Generation (MW) in the Study Cases ............................................................................................. 16 Table 3.3-3: Intertie Assumptions – Example ............................................................................................................... 17 Table 3.3-4: HVDC Power Order by Scenario .............................................................................................................. 18 Table 3.4-1: Summary of System Projects Included in the Study Cases ..................................................................... 19 Table 3.5-1: Summary of Customer Connection Assumptions ..................................................................................... 19 Table 3.6-1: Summary of Transmission Line Ratings in the Study Area (MVA on 138 kV Bases) ............................... 20 Table 3.6-2: Summary of Transformer Ratings in the Study Area ................................................................................ 20 Table 3.6-3: Summary of Shunt Elements in the Study Area ....................................................................................... 21 Table 3.7-1: Summary of Protection Fault Clearing Times ........................................................................................... 21 Table 4.1-1: Summary of Studies Performed ............................................................................................................... 22 Page 4 Project and System Access Studies (PSAS) Group Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Introduction 1. This document presents the Project description, connection alternatives to be evaluated, technical criteria, assumptions and study methodology. 1.1. Project 1.1.1. Project Overview This section is to describe the following: • Organization submitting SASR • SASR request (load DTS, gen STS, transformer add, breaker add, new POD, …) and why needed (load growth, new load, new generator, DFO reliability – N-1, feeder loading, …) • location • Requested In-Service date [Market Participant Legal Name (Market Participant Short Name)] has submitted a System Access Service Request (SASR) to the Alberta Electric System Operator (AESO) for [Demand Transmission Service (DTS) and/or Supply Transmission Service (STS)] of [XXX] MW at [Project location, e.g., south of the City of Grande Prairie to serve oilfield loads] (the Project). The requested In-Service Date (ISD) for the Project is [Month, Day, Year of the In-Service date as per the SASR request]. 1.1.2. Load Component Describe the load component of the project. Include the following: • State existing Demand Transmission Service if applicable. • State estimated maximum amount of load to be connected along with the anticipated power factor; • Describe the type of load either Residential, Rural, Commercial, Industrial, and/or Oil Sands(these are the sectors identified in the LTO); o Motor sizes if applicable • State the magnitude of the potential Demand Transmission Service (DTS) that the Market Participant intends to apply for; and • Comment on possible future expansion plans and anticipated timing for such expansion. Below are two examples of the write up: [1. The requested load addition is 17.9 MW by August 17, 2016. R[x] Project and System Access Studies (PSAS) Group 5 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 2. Load Type: Residential, rural, commercial, and light industrial services. 3. DTS contract capacity at South Mayerthorpe 443S to remain at the existing level of 12.5 MW. 4. Currently there is no plan for future expansion. 5. The load will be studied assuming a 0.9 power factor (pf) lagging.] or [Current DTS is 14 MW. There will be an addition four 6600 HP motors with three in operation at any one time. All motors will have dedicated Variable Frequency Drives (VFDs). The requested DTS increase is for an additional 25 MW for a total DTS 29 MW.] 1.1.3. Generation Component Describe the generation component of the project. Include the following: • State size of the generator(s) and estimated Maximum Authorized Real Power (MARP) and Maximum Capability (MC) levels;1 • Describe type of generator(s); • State estimated reactive power capability of the generator(s) when producing MARP. If this value does not meet the generation interconnection standard specify the intended supplemental strategy. If available, provide maximum capability curve based on pf/temperature. • State the potential magnitude of the Supply Transmission Service (STS) that the Market Participant intends to apply for and operate at when connected to the grid; • State the seasonal generator capacity (if information available); • State station service load if applicable; and • Comment on possible future expansion plans and anticipated timing for such expansion; Below is an example of the write up: [Market Participant Short Name plans to install a co-generation facility consisting of a single 85 MW (nominal) natural gas fuelled combustion turbine-generator. With the addition of this generator, Market Participant Short Name has requested an anticipated STS capacity of 85 MW. 1. Generators: Designation Type Model G1 Round Rotor GE 7A6 2. Supply Transmission Service (STS): 85 MW 3. Rated Nameplate Capacity: 93.9 MVA @ 0.85 pf, nominal 1 Maximum Authorized Real Power (MARP) and Maximum Capability (MC) are defined in the Consolidated Authoritative Document Glossary posted on the AESO website: http://www.aeso.ca/downloads/Consolidated_Authoritative_Document_Glossary.pdf R[x] Project and System Access Studies (PSAS) Group 6 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 4. Maximum Authorized Real Power (MARP): 100 MW 5. Maximum Capability (MC): 85 MW 6. Reactive Power Capability (preliminary): 48 MVar (0.9 pf lagging) / 33 Mvar (0.95 pf leading) at MARP, 7. The customer advised that there is no future expansion planned.] 1.2. Study Scope 1.2.1. Study Objectives The objective of the study is as follows: 1. Evaluate the Project connection alternatives based on technical performance. 2. Assess the impact of the Project connection on the AIES by Identifying any pre- and post-connection constraints 3. Recommend mitigation measures if required. 1.2.2. Study Area 1.2.2.1. Study Area Description Define and describe the Study Area. Include a diagram of the Study Area that clearly shows salient features such as transmission lines, substations, generating assets, and reactive elements in the area and indicates their voltage classes. In the Single Line Diagram (the Study Area diagram) show how the Study Area is connected to the rest of the Alberta Interconnected Electric System (AIES). The Project is located in the AESO planning area of [AESO planning area, e.g., Grande Prairie (Area 20)], as part of [The AESO region, e.g., the AESO Northwest (NW) Region]. This section will then describe the Study Area and the ‘Overview of existing system’. Please describe the Key substations/lines in the Project area and intertie connection with neighbouring areas. Below is an example of the write up: [The Study Area for the Project consisted of the Grande Cache (Area 22) and Grande Prairie (Area 20) areas, including the tie lines connecting the two planning areas to the rest of the AIES. All transmission facilities within the two planning areas will be studied and monitored for violations of the Reliability Criteria (defined in Section 3.1.1). The five 144 kV transmission lines connecting the Grande Cache and Grande Prairie areas to the rest of the AIES (namely transmission lines 7L73, 7L32, 7L45, 7L46 and 7L40) will also be studied and monitored to identify any violations of the Reliability Criteria. The H.R. Milner generation facility, with connection to the H.R. Milner 740S substation, connects to the Alberta Interconnected Electric System (AIES) through two 144 kV transmission R[x] Project and System Access Studies (PSAS) Group 7 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. lines: one is transmission line 7L20, which connects the HR Milner 740S substation to the Big Mountain 845S substation in the Grande Prairie area; the other is transmission line 7L80, which connects the HR Milner 740S substation to the Simonette 733S substation, which further connects to the Little Smoky 813S substation in the Valleyview planning area (Area 23) via the 144 kV transmission line 7L40. R[x] Project and System Access Studies (PSAS) Group 8 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Figure 1-1: Existing Study Area Transmission System ] R[x] Project and System Access Studies (PSAS) Group 9 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 1.2.2.2. Existing Constraints If Applicable, describe any known constraint(s) in the Study Area. Explain how the constraint(s) are managed. Discuss any Operating Policies and Procedures (OPPs) and Information Documents (IDs)/Authoritative Documents (ADs) presently applied in the area. Outline relevant existing manual or automatic Remedial Action Schemes (RASs) in the Study Area. Below is an example of the write up: [The existing constraints in [AESO Region where the Project is located, e.g., the Northwest Region] are managed in accordance with Section 302.1 of the ISO Rules, Real Time Transmission Constraint Management (TCM).] 1.2.2.3. AESO Long-Term Transmission Plans (LTP) Describe the relevant AESO long-term transmission development plans for the Study Area and its vicinity (either approved NID System Projects or developments identified in the AESO’s most recently published Long Term Plan). List the anticipated in-service dates of those plans. Use a table. Discuss the known impact(s) of any delays in the AESO Long-term Transmission Plans (LTP) for the area on the project. Please specify if the AESO LTP topologies are included in the study scenarios here. Table 1.2-1: Summary of System Projects Project Area Project Name 1.2.3. In-Service Date Studies Performed Provide a high-level summary of the system conditions (20XX WP for example) and the studies performed, such as analysis of the existing system before the connection and analysis of the system performance after the connection. Include the contingency categories applicable to the project. Below is an example. Please delete the bullets that are not relevant to the project: The following studies will be performed in the connection study: • Load flow analysis (Category A, Category B, and selected Category C5), pre-Project and post-Project conditions • Voltage stability analysis (Category A, Category B, and selected Category C5), post-Project conditions • Transient stability analysis (Category B, and selected Category C5), post-Project conditions • Motor starting analysis, post-Project conditions • Short-Circuit fault studies, pre-Project and post-Project conditions R[x] Project and System Access Studies (PSAS) Group 10 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. • In cases where transmission congestion is identified through the connection studies conducted, the AESO will provide further direction on additional studies to identify mitigation measures for congestion management under system normal (N-0) and abnormal conditions (N-1). 1.2.4. Studies Excluded Provide a high-level summary of the studies excluded. See below for an example: [The following studies will not be performed in the connection study: • Load flow analysis (Category C) • Voltage stability analysis (Category C) • Transient stability analysis (Category C)] R[x] Project and System Access Studies (PSAS) Group 11 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 2. Connection Alternatives Selected for Studies Describe each connection alternative separately. Only include alternatives that will be studied and evaluated as part of the NID filing. These alternative numbers should be consisted with the Connection Assessment Recommendation and Connection Assessment Results reports. For each alternative, include a connection diagram that shows the main transmission network in the Study Area post-connection. Provide single-line diagrams (SLDs) for the proposed facilities. Below is an example of such a write up: [Four alternatives were identified for this Project, two of which were selected for further study. The details of this connection alternative selection are addressed in the Connection Assessment Recommendations Report. The following two alternatives will be studied: Alternative 3: Add a new point of delivery (POD) substation, and connect the new POD to the existing 144 kV transmission line [Line name] via an in/out connection configuration. Alternative 4: Add a new point of delivery (POD) substation, and connect the new POD to the existing 144 kV transmission line [Line name] via a T-tap connection configuration. ] R[x] Project and System Access Studies (PSAS) Group 12 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 3. Criteria, System Data, and Study Assumptions 3.1. 3.1.1. Criteria, Standards, and Requirements Transmission Planning Standards and Reliability Criteria The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions (Reliability Criteria)2 will be applied to evaluate system performance under Category A system conditions (i.e., all elements in-service) and following Category B and Category C5 contingencies (i.e., single element outage), prior to and following the studied alternatives. Below is a summary of Category A, Category B and Category C5 system conditions. Category A, often referred to as the N-0 condition, represents a normal system with no contingencies and all facilities in service. Under this condition, the system must be able to supply all firm load and firm transfers to other areas. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of service, result in the loss of any single specified system element under specified fault conditions with normal clearing. These elements are a generator, a transmission circuit, a transformer, or a single pole of a DC transmission line. The acceptable impact on the system is the same as Category A. Planned or controlled interruptions of electric supply to radial customers or some local network customers, connected to or supplied by the faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) transmission service electric power transfers. Category C5 events [NOTE: Category C wording may need to be adjusted on a project-by-project basis] results in loss of two circuits of a multiple circuit tower. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. For Category C5, the controlled interruption of electric supply to customers (load shedding), the planned removal from service of certain generators, and/or the curtailment of contracted firm (non-recallable reserved) transmission service electric power transfers may be necessary to maintain the overall reliability of the interconnected transmission systems. The Alberta Reliability Standards include the Transmission Planning (TPL) standards that specify the desired system performance under different contingency categories with respect to the Applicable Ratings. The transmission system performance under various system conditions 2 Please refer to Attachment A R[x] Project and System Access Studies (PSAS) Group 13 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. is defined in Appendix 1 of the TPL standards. For the purpose of applying the TPL standards to this study, the Applicable Ratings shall mean: Seasonal continuous thermal rating of the line’s loading limits. Highest specified loading limits for transformers. For Category A conditions: Voltage range under normal operating condition should follow the AESO Information Document ID# 2010-007RS. For the busses not listed in ID#2010-007RS, Table 2-1 in the Reliability Criteria applies. For Category B and Category C5 conditions: The extreme voltage range values per Table 2-1 in the Reliability Criteria. Desired post-contingency voltage change limits for three defined post event timeframes as provided in Table 3.1-1. Table 3.1-1: Post Contingency Voltage Deviation Guidelines Time Period Parameter and reference point Post Transient (up to 30 sec) Post Auto Control (30 sec to 5 min) Post Manual Control (Steady State) Voltage deviation from steady state at POD low voltage bus. ±10% ±7% ±5% 3.1.2. AESO Rules The AESO Voltage Control Practice ID # 2010-007RS will be applied to establish precontingency voltage profiles in the Study Area. The Section 302.1 of the ISO Rules, Real Time Transmission Constraint Management (TCM) will be followed in setting up the study scenarios and assessment of the impact of the Project connection. In addition, due regard will be given to the AESO’s Connection Study Requirements and the AESO’s Generation and Load Interconnection Standard. The Reliability Criteria is the basis for planning the AIES. The transmission system will normally be designed to meet or exceed the Reliability Criteria under credible worst-case loading and generation conditions. 3.1.3. Other Requirements Other AESO requirements to be applied when performing connection studies are outlined below: if applicable Describe in detail the application of any other AESO requirements, criteria, standards, rules, practices, and guidelines (market or otherwise) when the connection studies will be carried out. Use subsection headings that clearly identify the requirement being discussed or add another bullet. R[x] Project and System Access Studies (PSAS) Group 14 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 3.2. Study Scenarios Outline the scenarios (system conditions) studied and the study years. These scenarios should represent a range of potential system conditions, assumed loading conditions, and assumed generation dispatches sufficient to allow an analysis of the transmission system performance in the Study Area. The scenarios may include the following: • Low and high loading levels • Low and high generation levels • Interchange conditions (for example, high, medium, or low export from Alberta to British Columbia or high, medium, or low import from British Columbia to Alberta) • Transmission flow variations, such as South of Keephills/Ellerslie/Genesee (SOK), Fort McMurray transfer in and out, HVDC power order and other relevant area transfers [Table 3.2-1 provides a list of the study scenarios. Scenarios 1 and 2 are the pre-Project scenarios for 2016 SP and WP. Scenarios 3 and 4 are the post-Project scenarios for 2016 SP and WP with the requested DTS 20 MW addition at the Thornton 2091S. A power factor of 0.9 lagging will be used for the new Project load] Table 3.2-1: List of the Connection Study Scenarios Condition Project Load (MW) Project Generation (MW) 2016 SP Pre-project 0 0 2 2016 WP Pre-Project 0 0 3 2016 SP Post Project 20 0 4 2016 WP Post-Project 20 0 Scenario Year/Season Load 1 3.3. 3.3.1. System Generation Dispatch Conditions High Wind, High Import High Wind, High Import Load and Generation Assumptions Load Assumptions The Study Area and Region load forecasts used for this connection study is shown in Table 3.3-1 and is from [The AESO Forecast specified in the Study Scope, e.g., the AESO 2014 Longterm Outlook (2014 LTO)]. In this study the active power to reactive power ratio in the base case scenarios will be maintained when modifying the planning area loads. Table 3.3-1: Forecast Area Load (201X LTO at AIL Peak) Forecast Peak Load (MW) Area or Region Name and Season Area 37 (Provost) 2018 SP WP R[x] Project and System Access Studies (PSAS) Group 2016 15 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Forecast Peak Load (MW) Area or Region Name and Season 2016 2018 SL SP WP Central Region SL SP South Region WP SL SP AIL w/o Losses WP SL 3.3.2. Generation Assumptions Describe the generation assumptions (including N-G) and the AESO forecast applied (e.g., 2014LTO). Present existing and future units for consideration in the project studies (local generators) and the dispatch level of each. Describe the notable features of the local generators, as required. Below is an example of the write up: [The generation conditions for this connection study are described in Table 3.3-2. The study identified the HR Milner Generator at H.R. Milner 740S substation as the critical generator and it is turned off to represent the N-G study condition in the Grand Cache area for all analysis except for the short circuit analysis] Table 3.3-2: Local Generation (MW) in the Study Cases Existing/ Future Unit Name Bus Number Area Pmax (MW) Existing Gen A … … … Gen B #29 … … … Gen C … … … Gen D … … … Gen E … … … Future 20xx SL Unit Net Generation3 (MW) 20xx SP Unit Net Generation (MW) 20xx WP Unit Net Generation (MW) 20yy SL Unit Net Generation (MW) 20yy SP Unit Net Gener -ation (MW) 20yy WP Unit Net Generation (MW) Total 3 Unit Net Generation refers to Gross Generating unit MW output less Unit Service Load. R[x] Project and System Access Studies (PSAS) Group 16 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 3.3.3. Intertie Flow Assumptions Indicate the assumptions regarding the intertie flow between Alberta and neighbouring jurisdictions. Below are examples of the write up: [Intertie assumptions are included for the B.C., MATL, and Saskatchewan interties. Details on the assumptions can be found in Table 3.3-3.] or [The intertie points are deemed to be too far away to have an effect on the assessment of the proposed connection. The flows in the Study Area are not influenced by the AIES HVDC facilities. As a result, the intertie and HVDC assumptions are kept consistent with that in the AESO planning base cases and not adjusted for this study.] Table 3.3-3: Intertie Assumptions – Example Intertie Case No. Year / Condition 1 2016 SL Import (+) /Export (-) to BC Import (+) /Export (-) to Import (+) /Export (-) to MATL -800 -150 0 480 150 300 480 150 300 -800 -150 0 480 150 300 480 150 300 -800 -150 0 480 150 300 480 150 300 Saskatchewan (Pre-Project) 2 2016 SP (Pre- Project) 3 2016 WP (Pre- Project) 4 2016 SL (Post- Project) 5 2016 SP (Post-Project) 6 2016 WP (Post-Project) 7 2018 SL (Post-Project) 8 2018 SP (Post- Project) 9 2018 WP (Post- Project) R[x] Project and System Access Studies (PSAS) Group 17 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. HVDC Power Order (if applicable) 3.3.4. In general, the majority of connections to the AIES will not require adjustment to the planned load flow order levels for the WATL and EATL HVDC links during studies. For major projects and where the scoped study scenarios require adjustments to the pre-set HVDC flow level provided by the AESO in the Base Cases, the AESO studies engineer will provide guidance as to the new flow settings and associated VAR adjustments as required. In these cases, below are examples of wording: [The power orders shown in Table 3.3-4 will be assumed in this Study. HVDC dispatch aligns with the AESO’s planned HVDC operating procedures. Under some scenarios, EATL will be dispatched to a higher power order in a South-to-North direction to reduce congestion on the Central East 138/144 kV existing transmission system. The pre-Project and post-Project dispatches will be the same for each alternative.] or [The HVDC power orders will be set based on the minimum loss per the assumptions in preand post-Project study scenarios.] Table 3.3-4: HVDC Power Order by Scenario 3.4. Case No Scenario WATL4 (MW) EATL5 (MW) 1 2016 SL (Pre-Project) 475 N S6 Blocked 2 2016 SP (Pre- Project) 250 S N 450 S N 3 2016 WP (Pre- Project) 475 N S Blocked 4 2018 WP (Post- Project) 250 S N 800 S N System Projects List the relevant transmission facilities that are not in service but will be included in the study cases. Use a table. Briefly discuss any relevant information regarding system projects, such as developments proposed for each project. Below is an example of the write up: [Table 3.4-1 lists the system reinforcement subprojects that are part of the CETD and that have been included in this study.] 4 Western Alberta Transmission Line (the west HVDC line) 5 Eastern Alberta Transmission Line (the east HVDC line) 6 N S: HVDC flow direction is North to South S N: HVDC flow direction is South to North R[x] Project and System Access Studies (PSAS) Group 18 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Table 3.4-1: Summary of System Projects Included in the Study Cases Project Subproject 1 P850 South and West Edmonton Reinforce ment Subproject Name In-Service Date Harry Smith Sub New Saunders Lake 240/138kV Substation; re-terminate 910L, 914L, 780L & 858L at Saunders Lake; build lines between Nisku & proposed Saunders Lake; and reconfiguration of affected substations. New 138kV Lines from 780L to Cooking Lake & 174L; and reconfiguration of affected substations 2 3 4 133L from Wabamun to 234L tap 5 New Capacitor Bank at Leduc 325S September 2017 Customer Connection Projects 3.5. List the relevant customer connection facilities that are not in the existing system but will be included in the study cases. Use a table. Include relevant information such as size of the load and/or generation for each project. Below is an example of the write up: [The list of the customer projects included in the study is shown in Table 3.5-1.] Table 3.5-1: Summary of Customer Connection Assumptions Planning Area Queue Position* Planned In-Service Date Project Name Project # Gen (MW) Load (MW) Included/Excluded from Studies 53 54 Jul. 2017 RESL McLaughlin WAGF 1500 47.0 1.0 Included 54 19 Apr. 2016 Lethbridge Chinook NW POD 1260 0 30.0 Included 55 Energize d Oct. 2014 Fortis Spring Coulee Upgrade 1338 0 2.0 Included 55 57 Feb. 2017 BowArk Energy Drywood Power Gas Plant 1522 18.6 1.0 Excluded * Per the AESO Connection Queue posted in December 2015. Provide any other relevant information for each project, such as whether it has already been approved by the Alberta Utilities Commission (AUC). 3.6. Facility Ratings and Shunt Elements Include tables that show the facility ratings for key existing and proposed equipment rated XX kV and above and any other relevant equipment ratings. Show only the most important equipment. Below is an example of the write up: R[x] Project and System Access Studies (PSAS) Group 19 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. [The Transmission Facility Owner (TFO) provided the ratings of the existing transmission lines (Error! Not a valid bookmark self-reference.) and the existing transformers (Error! Reference source not found.) in the Study Area.] Table 3.6-1: Summary of Transmission Line Ratings in the Study Area (MVA on 138 kV Bases) Line ID Line Description Nominal Rating (MVA) Short-term7 Rating (MVA) Voltage Class (kV) Summer Winter Summer Winter 7L84 Flyingshot 749S – Crystal 722S 138 142.8 142.8 180 181 7L03 Flyingshot 749S – Elmworth 731S 138 109.3 139 123.6 150.5 7L68 Clairmont Lake 811S – Rycroft 730S 138 94.9 CT8 94.9 CT 94.9 CT 94.9 CT Table 3.6-2: Summary of Transformer Ratings in the Study Area Substation Name and Number Transformer ID Transformer Voltages (kV) MVA Rating Battle River 757S 912T 240/144 224 Battle River 757S 701T 144/72 75 Nevis 766S 901T 240/144 100 H-M: 33.3 Nevis 766S 701T 144/72/25 X-M: 33.3 Y-M: 16.6 List the shunt elements in the Study area, including shunt element size and status. Use a table. Present all assumptions made regarding the shunt elements, such as whether they will be switched on or off in the studies. Below is an example of the write up: [The details of shunt elements in the Study Area are given in Table 3.6-3.] 7 When line loading in post Category B contingency is observed to exceed nominal rating and is less than the Short-term (emergency) rating, it is assumed that AESO and TFO operating practices can manage the constraint within the time requirements of TFO Short-term (emergency) rating. 8 The limitation factor for the line rating is due to a current transformer. R[x] Project and System Access Studies (PSAS) Group 20 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Table 3.6-3: Summary of Shunt Elements in the Study Area Capacitors Substation Name and Number Voltage Class (kV) Number of Switched Shunt Blocks Status in Study (on or off) Total at Nominal Voltage (MVAr) 138 2017 WP (MVAr) (MVAr) 71.9 27 (on) 27 (on) - 27.17 (off) (off) 45 45 (both on) 45 (both on) 1 x 44.9 MVAr Tucuman 478S 138 Hill 751S 138 1 x 27.17 MVAr Number of Switched Shunt Blocks 2017S P 1 x 27 MVAr Hardisty 377S Reactors 1 x 20 MVAr 1 x 25 MVAr Total at Nominal Voltage (MVAr) Status in Study (on or off) 2017 SP 2017 WP (MVAr) (MVAr) - - - - - - - - - - - Protection Fault Clearing Times 3.7. List the fault clearing times used for the transient stability analysis. Use a table. When providing near-end and far-end fault clearing times, include different directions with the clearing times only when the clearing times are not the same for faults at each end. Indicate if the fault clearing time assumptions have been verified by the Transmission Facility Owner (TFO). Below is an example of the write up: [Fault clearing times for existing facilities are provided by TFO and are listed in Table 3.7-1.] Table 3.7-1: Summary of Protection Fault Clearing Times Terminal Location Line Nominal Bus Voltage (kV) 9Lxx 240 3.8. Terminal 1 SUB 1S Terminal 2 SUB 2S Total Clearing Time Terminal 3 SUB 3S Faulted Location State if it is calculated (specific) or estimated (generic) Faulted Location Terminal 1 Terminal 2 Terminal 3 SUB 1S 6 7 8 calculated SUB 2S 6 7 8 calculated SUB 3S 6 7 9 calculated Voltage Profile Assumption Please keep the following description unless any change is required. The AESO Voltage Control Practice ID # 2010-007RS is used to establish normal system (i.e., pre-contingency) voltage profiles for key area busses prior to commencing any studies. Table 2- R[x] Project and System Access Studies (PSAS) Group 21 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 1 of the Reliability Criteria applies for all the busses not included in the ID 2010-007RS. These voltages will be utilized to set the voltage profile for the study base cases prior to load flow analysis. 3.9. Motor Starting Assumptions The section is to evaluate the potential impacts of motor starting operation on the surrounding system. The customer must provide details of study assumptions (including how frequent the motor starts and then find the voltage dip percentage for different voltage levels), motor model, and software used to perform the studies. Also the type of motor starting equipment and/or starting methodology that would be implemented must be specified. Motor starting analysis is no longer required and removes the subsection – The example below assumes that VFD will be installed with across the line staring capability as backup. If the Market Participant confirms that the motors in the Project will not start motors across the line, Motor starting analysis is no longer required. Below is an example of the write up for motor starting assumption portion: [The following assumptions were used in conducting motor starting analysis: 4. The transient voltage dip at the 138 kV transmission bus should not exceed 5% when starting a single motor. The motors will not start simultaneously. Only one motor will be allowed to start in VFD bypass mode while the other motors are running at full load.] Study Methodology 4.1. Connection Studies Carried Out The studies to be carried out for this connection study are identified in Table 4.1-1: Please delete the rows that are not applicable to the Project. Table 4.1-1: Summary of Studies Performed Scenario and Condition 9 Project 1234 System Conditions Load Flow9 Voltage Stability9 Transient Stability9 Motor Starting9 The critical generator identified for this study will be [Name N-G unit, e.g., the H.R. Milner unit]. R[x] Project and System Access Studies (PSAS) Group 22 Public R3-2016-01-01 Shortcircuit Connection Engineering Study Report for AUC Application: Error! Reference source not found. Load (MW) Generation (MW) 10 1 2016 SP Pre-project 0 0 Category A and Category B X 2 2016 WP Pre-Project 0 0 Category A and Category B X 3 2016 SP Post-Project 20 0 Category A and Category B X 4 2016 WP Post-Project 20 0 Category A and Category B X 4.2. X X X X Load Flow Analysis Each project has different load flow analysis methodology based on Study Area characteristics and study assumptions. Please describe the methodology used in the load flow analysis in this section. If any abnormal thermal loadings (above 100% thermal loading) are observed, perform Category B load flow analysis on the identified contingencies by stepping Transformer tap adjustment. The identified abnormal thermal loadings are still observed, it should be addressed in the load flow results. Below is an example of the write up: [Load flow analysis will be completed for all study scenarios to identify any thermal or transmission voltage violations as per the Reliability Criteria. Transformers taps and switched shunt reactive compensation devices such as shunt capacitors and reactors will be locked and continuous shunt devices will be enabled when performing Category B load flow analysis. POD low voltage bus deviations will also be assessed by first locking all tap changers and area capacitors to identify any post-transient voltage deviations above 10%. Tap changers will then be allowed to adjust, while shunt reactive compensating devices remained locked; to determine if any voltage deviations above 7% would occur in the area. Once all taps and shunt reactive compensating devices have been adjusted, voltage deviations above 5% will be reported, for both the pre-Project and post-Project networks.] 4.2.1. Contingencies Studied Load flow analysis will be performed for the Category A condition and all Category B contingencies in [the Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios. 4.3. Voltage Stability (PV) Analysis If this analysis is not required, please remove the subsection. The objective of the Power-Voltage (PV) curve is to determine the ability of the network to maintain voltage stability at all the busses in the system under normal and abnormal system conditions. The PV curve is a representation of voltage change as a result of increased power 10 Only Category A with all generators in the study area on. R[x] Project and System Access Studies (PSAS) Group 23 Public R3-2016-01-01 X Connection Engineering Study Report for AUC Application: Error! Reference source not found. transfer between two systems. The reported incremental transfers will be to the collapse point. As per the AESO requirements, no assessment based upon other criteria such as minimum voltage will be made at the PV minimum transfer. Voltage stability analysis for post-connection scenarios will be performed. For load connection projects, the load level modelled in postconnection scenarios are the same or higher than in pre-connection scenarios. Therefore, voltage stability analysis for pre-connection scenarios will only be performed if post-Project scenarios show voltage stability criteria violations. Voltage stability (PV) analysis will be performed according to the Western Electricity Coordinating Council (WECC) Voltage Stability Assessment Methodology. The voltage stability criteria states, for load areas, post-transient voltage stability is required for the area modeled at a minimum of 105% of the reference load level for system normal conditions (Category A) and for single contingencies (Category B). For this standard, the reference load level is the maximum established planned load. Typically, voltage stability analysis is carried out assuming the worst case scenarios in terms of loading. The voltage stability analysis was performed by increasing load in [Study Areas, e.g., the Grande Prairie and Grande Cache Areas (AESO planning areas 20 and 22, respectively)], and increasing the corresponding generation in the following AESO Planning Areas: [Source area, e.g., the Wabamun planning area (Area 40)] [Source area] [Source area] As per the voltage stability criteria, post transient techniques (all tap changers, all discrete capacitors locked, but SVCs will be allowed to adjust) will used in applying the criteria and this information is reflected in all tables and graphs. Also for this analysis, no limits will be selected for the generation sources, non-negative active power constant MVA loads will be enforced and the existing power factor for the reference will be maintained. 4.3.1. Contingencies Studied Voltage stability analysis will be performed for the Category A condition and all Category B contingencies in [Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios. 4.4. Transient Stability Analysis If this analysis is not required, please remove the subsection. Transient stability analysis will be performed following the post-Project scenarios using [Study scenarios, e.g., the 2017 SL and 2017 SP scenarios]. Stability plots for [State Monitoring quantities , e.g., bus voltage, machine relative angle and active and reactive power outputs…etc] for all available generation units in [Study Area, e.g., the Cold Lake (Area 28) planning area] are provided. [State reference generator, e.g., Genesee #1] will be used as the system reference. R[x] Project and System Access Studies (PSAS) Group 24 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 4.4.1. Contingencies Studied Transient stability analysis wil be performed for the Category A condition and all Category B contingencies in [Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios. 4.5. Short-Circuit Analysis Short-circuit analysis will be performed for [Study scenarios, e.g., the 2016 WP pre Project scenario and 2016 WP and 2025 WP post-Project scenarios] to determine the short-circuit levels in the vicinity of the Project. The short-circuit analysis includes three phase and single line to ground faults. Fault levels are provided in the form of currents in kilo amperes and per unit positive and zero sequence impedances. 4.6. Motor Starting Analysis [as required] If this analysis is not required, please remove the subsesction. This section is to describe the study methodology of motor starting analysis. Below is an example of the write up: [Motor starting analysis will be performed for the proposed motors under system normal (Category A) conditions and worst case contingencies identified in the voltage stability and power flow analyses. The analysis considered the starting of one motor, with its Variable Frequency Driver (VFD) out of service, while the other motors will be running at full load.] 4.7. Effectiveness Factor Analysis Studies [as required] Effectiveness factor analysis studies are carried out to determine the generator/load effectiveness factors and identify the most effective generator/load(s) to be curtailed in order to mitigate the thermal violations observed following some Category B contingencies in the Study Area. 4.8. Sensitivity Studies [as required] Describe the methodology used for any other studies carried out. Use a separate heading for each study. The headings should match the headings used in section 3.2. Include the intent, the assumptions, and any relevant discussions regarding the study methodology. Use a table. R[x] Project and System Access Studies (PSAS) Group 25 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 4.9. Mitigation Measures If study results indicate transmission constraints associated with or exacerbated by the project addition, modification to existing procedures and/or Remedial Action Schemes (RAS) or addition of new procedures and/or RAS may be required. The Studies Consultant must identify those anticipated constraints in a timely manner to the AESO as they arise. The AESO Studies Engineer will guide the Studies Consultant to; - List study results in the constraint table in Attachment N of the part of the ESR Template. - If N-0 overloads are observed in the post connection system, develop generation or load effectiveness factor tables based on identified thermal constraints for N-0 system. - Develop generation or load effectiveness factor11 tables based on identified thermal constraints under Category B contingencies. - Identify the components of the AESO system development plan which will alleviate the identified constraint. Propose adjustments to the original preliminary connection alternatives to avoid proposing permanent RAS for Category B contingencies. Study and propose possible modifications to existing RAS to ensure coordination of proposed protection additions with the existing schemes. Study and propose new temporary RAS required to ensure system reliability until such time the planned system reinforcements are in place. Proper study scenarios with the planned system reinforcements will be studied to reflect removal of the identified constraints and the temporary nature of the RAS. - The AESO Studies Engineer will closely work with the Consultant and guide the development and/or modifications of the proposed RAS to ensure system reliability, security and compliance with AESO system access business practices. 11 Effectiveness factor analysis is carried out to determine the generator/load effectiveness factors which are used to estimate the ability of each generator/load to relieve transmission element constraints. A generator/load’s effectiveness factor is defined as the change in power flow over a specific line following a change in the generator’s output power/ the load. As such, the larger the generator/load effectiveness factor the more helpful it can be in alleviating a thermal violation on the transmission line associated to it. R[x] Project and System Access Studies (PSAS) Group 26 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Attachment A Transmission Planning Criteria- Basis and Assumptions (Reliability Criteria) R[x] Project and System Access Studies (PSAS) Group 27 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 1. Introduction This document presents the reliability standards, criteria, and assumptions to be used as the basis for planning the Alberta Transmission System. The criteria, standards and assumptions identified in this document supersede those previously established. 2. Transmission Reliability Standards and Criteria12 The AESO applies the following Alberta Reliability Standards to ensure that the transmission system is planned to meet applicable performance requirements under a defined set of system conditions and contingencies. A brief description of each of these standards is given below: 1. TPL-001-AB-0: System Performance Under Normal Conditions Category A represents a normal system condition with all elements in service (N-0). All equipment must be within its applicable rating, voltages must be within their applicable ratings and the system must be stable with no cascading outages. Under Category A, electric supply to load cannot be interrupted and generating units cannot be removed from service. 2. TPL-002-AB-0: System Performance Following Loss of a Single BES Element Category B events result in the loss of any single element (N-1) under specified fault conditions with normal clearing. The specified elements are a generating unit, a transmission circuit, a transformer or a single pole of a direct current transmission line. The acceptable impact on the system is the same as Category A with the exception that radial customers or some local network customers, including loads or generating units, are allowed to be disconnected from the system if they are connected through the faulted element. The loss of opportunity load or opportunity interchanges is allowed. No cascading can occur. 3. TPL-003-AB-0: System Performance Following Loss of Two or More BES Elements Category C events result in the loss of two or more bulk electric system elements (sequential, N1-1 or concurrent, N-2) under specified fault conditions and include both normal and delayed fault clearing. All of the system limits for Category A and B events apply with the exception that planned and controlled loss of firm load, firm transfers and/or generation is acceptable provided there is no cascading. 4. TPL-004-AB-0: System Performance Following Extreme BES Events Category D represents a wide variety of extreme, rare and unpredictable events, which may result in the loss of load and generation in widespread areas. The system may not be able to reach a new stable steady state, which means a blackout is a possible outcome. The AESO needs to evaluate these events, at its discretion, for risks and consequences prior to creating mitigation plans. 5. FAC-014-AB-2: Establishing and Communicating System Operating Limits The AESO is required to establish system operating limits where a contingency is not mitigated through construction of transmission facilities. 2.1 Thermal Loading Criteria 12 A complete description of these standards are given in: AESO. Alberta Reliability Standards. Available from http://www.aeso.ca/rulesprocedures/17004.html R[x] Project and System Access Studies (PSAS) Group 28 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. The AESO Thermal Loading Criteria require that the continuous thermal rating of any transmission element is not exceeded under normal and post-contingency operating conditions. Thermal limits are assumed to be 100% of the respective normal summer and winter ratings. Emergency limits are not considered in the planning evaluations. 2.2 Voltage Range and Voltage Stability Criteria The normal minimum and maximum voltage limits as specified in the following table are used to identify Category A system voltage violations, while the extreme minimum and maximum limits are used to identify Category B and C system violations. Table 2-1 presents the acceptable steady state and contingency state voltage ranges for the AIES. Table 2-2 provides voltage stability criteria used to test the system performance. Table 2-1: Acceptable Range of Steady State Voltage (kV) Nominal Voltage Extreme Minimum Normal Minimum Normal Maximum Extreme Maximum 500 475 500 525 550 240 216 234 252 264 260 (Northeast & Northwest)* 234 247 266 275 144 130 137 151 155 138 124 135 145 150 72 65 68.5 75.5 79 69 62 65.5 72.5 76 Table 2-2: Voltage Stability Criteria Performance Level A B MW Margin (P-V method) (5)(6)(7) MVAr Margin (V-Q method) (6)(7) Any element such as: One Generator One Circuit One Transformer One Reactive Power Source One DC Monopole > 5% Worst Case Scenario(8) Bus Section > 5% 50% of Margin Requirement in Level A Disturbance (1)(2)(3)(4) Initiated by: Fault or No fault DC Disturbance R[x] Project and System Access Studies (PSAS) Group 29 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. Performance Level MW Margin (P-V method) (5)(6)(7) Disturbance (1)(2)(3)(4) Initiated by: Fault or No fault DC Disturbance Any combination elements such as: of MVAr Margin (V-Q method) (6)(7) two A Line and a Generator A Line and a Reactive Power Source C 50% Margin > 2.5% Two Generators Two Circuits of Requirement in Level A Two Transformers Two Reactive Power Sources DC Bipole D Any combination of three or more elements. i.e.: Three or More Circuits on ROW >0 >0 Entire Substation Entire Plant Switchyard Including 2.3 Transient Stability Analysis Assumptions Standard fault clearing times as shown in Table 2-3 are used for the new facilities or when the actual clearing times are not available for the existing facilities. Double line-to-ground faults are applied for the Category C5 events with normal clearing times. Single line-to-ground faults are applied for Category C6 to C9 events with delayed clearing times as depicted in Table 2-4 and Table 2-5. Table 2-3: Fault Clearing Times Nominal Near End Far End kV Cycles Cycles 500 4 5 240 5 6 6 8 144/138 with telecommunications R[x] Project and System Access Studies (PSAS) Group 30 Public R3-2016-01-01 Connection Engineering Study Report for AUC Application: Error! Reference source not found. 144/138 6 without telecommunications 30 Table 2-4: Stuck Breaker Clearing Times for Lines Fault Clearing Time Fault Clearing Time (Cycles) (Cycles) (Cycles) 138/144 kV 240 kV 500 kV 2nd Ckt Near End 15 Fault Clearing Time Far (for C5 Near End and C7 End Only) 24 24 Far End 12 2nd Ckt 2nd Ckt (for C5 Near Far and C7 End End Only) (for C5 and C7 Only) 6 14 9 5 11 Table 2-5: Stuck Breaker Clearing Times for Transformers Fault Clearing Time (Cycles) Fault Clearing Time (Cycles) 240/138 kV Fault on 240 kV Side 240 kV 138 kV 12 6 2nd Ckt 500/240 kV Fault on 138 kV Side 138 kV 240 kV 15 5 2nd Ckt Fault on 500 kV Side 500 kV 240 kV 9 5 2nd Ckt Fault on 240 kV Side 240 kV 500 kV 12 4 2nd Ckt (for (for (for (for Breaker Breaker Breaker Breaker Side Side Side Side Side Side Side Side Fail) Fail) Fail) Fail) 14 24 R[x] Project and System Access Studies (PSAS) Group 31 11 14 Public R3-2016-01-01