ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-001 (a)-(c) Page 1 of 3 Preamble: IPPSA questions the need for the AESO’s application, or at least an application of the nature filed by the AESO, given the recency and continued applicability of the Board’s Decision 2002-103 and given the MSA Report: TMR Investigation, February 28, 2005 (“MSA Report on TMR”). In IPPSA’s view, only section 23 of the Transmission Regulation is “new” since Decision 2002-103. It does warrant consideration by the Board for possible amendment to Article 24, but does not suggest any change in approach is required or even advisable for the AESO to deal with occasions of its so called “extended duration TMR.” In IPPSA’s view a tariff approach to “extended duration TMR” is contrary to Decision 2002-103, the MSA Report on TMR and the legislators’ intent to not regulate power generation. Request: (a) Please comment on the degree to which the AESO agrees or disagrees with the Preamble and why. (b) Assuming the Board were to agree with IPPSA’s Preamble above, does the AESO agree that a negotiated solution to the remaining issue is achievable? The only outstanding issue, in IPPSA’s view, is: “What methodology should be described in the ISO tariff pursuant to s.23 of the Transmission Regulation?” (c) Please explain how the AESO’s application, if approved, would not result in the AESO setting electricity prices for “extended duration TMR”, or result in the Board regulating electricity pricing via the AESO tariff. Response: (a) The AESO fundamentally disagrees with IPPSA’s position that the present application is not needed. The AESO has filed its application to achieve two objectives. The first is to ensure that the AESO’s tariff remains at all times just and reasonable and properly addresses all circumstances for which the tariff applies. The second objective is to ensure that the AESO’s tariff includes a compensation methodology for transmission must run services that comports with the requirements of section 23 of the Transmission Regulation and that this methodology receives final approval by the EUB. IPPSA’s Preamble refers to Decision 2002-103. The AESO notes that the present application arises due to circumstances that have been encountered following the issuance of this Decision. Recent circumstances have caused the Page 2 of 3 AESO to conscript transmission must run services for extended durations. While Decision 2002-103 suggests that it would not likely be necessary for the AESO’s then predecessor to conscript for extended periods of time1, the AESO’s actual experience has differed from this expectation. This has been due to the inability of parties to reach agreement over the terms that should govern the provision of this service in the future. Further, regardless of short or long term duration issues, in circumstances where limited options exist in obtaining the required services, Article 24 can create perverse incentives. In non-competitive procurement processes, Article 24 has operated to provide a compensation benchmark by which future services are determined regardless of changes in market conditions. The inappropriate benchmark established by Article 24 must now be remedied through the appliedfor amendments so as to ensure the AESO’s tariff remains just and reasonable. New government policy has also been issued since Decision 2002-103 and which discusses, among other matters, principles that should govern how compensation for conscripted transmission must run services should be determined. The Framework Paper presented by the Alberta Department of Energy, in June 6, 2005 and subsequent to Decision 2002-103 discusses these principles. Those principles refer to how conscripted transmission must run payments should be fair and based upon cost of service principles, should be simple and transparent, and should minimize interference in the energy market. In the AESO’s view, the proposed amendments achieve these objectives. The Preamble to this question also refers to a Report provided by the Market Surveillance Administrator as support for the proposition that the applied-for amendments are not needed. With respect, the AESO disagrees. The focus of the MSA’s Report concerns the need for the AESO to establish and follow competitive processes when procuring transmission must run services and minimize conscriptions and the use of tariff-based compensation. The AESO does not interpret the MSA Report to suggest that the compensation methodology found in the existing Article 24 must continue. A tariff approach continues to be needed such that a workable means is available to maintain reliability in non-contestable situations or if competitive processes prove to be unsuccessful. The AESO continues to believe that the potential for noncontestable circumstances remains real, that a regulated approach is therefore required, and that the changes as applied-for to the compensation methodology are required to ensure the tariff remains just and reasonable. The Preamble also seems to imply the AESO’s applied-for changes are intended to prevent the market from operating properly. Quite the opposite is in fact the case. The proposed amendments are requested so as to minimize interference in the energy market and ensure compensation remains fair and just regardless of the duration in which the conscription occurs. With these amendments the AESO anticipates that it will continue to be able to resource its ancillary service requirements through bilateral arrangements and remains committed to, as best possible, obtain its AS requirements through an open and efficient marketplace for such services. However where circumstances do not permit such outcomes, then the applied-for amendments will ensure the 2 Page 3 of 3 AESO can obtain the necessary services and compensate for same on a fair and reasonable basis. That basis, applies both to short and long term duration AS requirements. (b) The AESO cannot agree with the premise to this question, namely that the Board finds there is no merit with the present Application. If that were the case, the AESO would have expected the Board to have summarily dismissed the Application long before now, particularly given the previous submissions made by ATCO and IPPSA in respect of this position. With respect to the need for a negotiated solution, the AESO agrees that negotiated solutions are preferable to litigated outcomes. In this case however, the AESO and others have attempted as best possible to resolve differences through a variety of negotiated options but to no avail. Given the passage of time since the original application was filed, the AESO believes that the most efficient process ahead is to pursue a litigated course following the existing hearing schedule. During this time the AESO will continue to consult with stakeholders on the merits of the Application and hopefully address outstanding concerns as best possible. In this way, the AESO is hopeful that need for an extensive hearing proceeding will be limited. (c) The AESO application would result in a regulated tariff as an option for extended duration TMR services. The tariff would only be used if competitive processes and negotiations were unsuccessful and conscription of services was required to maintain reliability of the transmission network. 3 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-002 Reference: August 4, 2005 Revised Application, pp. 3-4 Preamble: The Application states: Page 1 of 1 … This application is based on the assumption that the contract documents will be completed satisfactorily and therefore some issues raised in previous applications no longer need to be addressed by the Board. There has been a significant amount of information filed on the AS Article during the above mentioned process. In order to better assist parties, this filing provides a consolidated view of all relevant information filed by the AESO since the August 16 Application, including amendments of some of the proposed changes included in the August 16 Application. Accordingly, this filing includes restatements of material previously filed, new material not previously placed on the record, and appendices, which include complete documents as previously filed. (Emphases added) Request: Please confirm that this amended re-filing supersedes and replaces all information provided in previous episodes of this application, with the effect that such prior information has been retracted or withdrawn? If not, please clarify what specific information from previous applications the AESO has retracted or withdrawn, if any, and what information parties and the Board should regard as still the AESO’s evidence. Response: Please refer to BR.AESO-001. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-003 (a)-(c) Reference: Page 1 of 1 August 4, 2005 Revised Application, p. 6 Preamble: The Application states: Outcomes of previous EUB proceedings have established the current Ancillary Services Article (AS Article) of the AESO’s Terms and Conditions of Service and allowed the AESO, and its predecessor the Transmission Administrator (TA), to carry out its responsibilities with respect to AS in the context of circumstances that existed at the time. These proceedings form a unique history and are summarized by the EUB in Decision 2002-103. [emphasis added] Request: (a) (b) (c) What new circumstances exist that the AESO believes were not contemplated by the Board during the process culminating in Decision 2002-103? Does the AESO consider any aspects of Decision 2002-103 no longer appropriate for current circumstances? If so, please explain fully. To the extent not covered by responses to (a) and (b) above, please identify any “circumstances” which are now irrelevant or superseded by new “circumstances”. Please identify the new “circumstances”. Response: (a) & (b) Please refer to IPPSA.AESO-001(a). (c) Given the policy directions for Alberta contained in the regulation and papers noted in (a) above, reliance on the AESO’s experience in negotiating contracts as the basis for structuring an AS Article has diminished as a consideration. That experience was considered in development of Option 2 or the Going Forward Cost option presented in the 2004 Application. Also, the relevance of the FERC directions on TMR have diminished as a consideration. The Going Forward Cost Option was also in line with the FERC direction. As such the Going Forward Cost option is now not the recommended option. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-004 (a)-(g) Reference: August 4, 2005 Revised Application, p. 6 Preamble: The Application states: Page 1 of 2 In its experience with the current AS Article, the AESO has generally been able to manage situations of short-term emergency service. The current AS Article was not, however, intended to address situations of foreseeable longduration services, and more specifically extended-duration transmission mustrun (TMR) services. Instances of extended-duration TMR services have occurred. AESO and the supplier have recently agreed to compensation for the specific circumstance. Compensation for such long-duration service remains a concern. The AESO therefore proposes that the current AS Article be amended to address concerns related to long-duration services, especially TMR, as well as refinements to support these provisions and to remove elements that potentially inhibit energy market efficiency. (emphases added) Request: (a) Please describe what the AESO means by “situations of short-term emergency service”. Is the AESO speaking exclusively of non-contracted situations? Please explain and provide a list of such circumstances. (b) Please describe what the AESO means by “foreseeable long-duration services” and explain the characteristics that distinguish a long-duration service from a short-term service. Is the AESO speaking exclusively of non-contracted situations? Please explain. (c) Please describe all instances of extended-duration TMR services that have occurred since January 2002. (d) Please explain in what way compensation for extended-duration service remains a concern. Does this concern extend to all instances of services under contract, including IBOC contracts, LBC SO contracts and the Calgary Area TMR RFP (awarded March 24, 2005) contracts. Please explain. (e) Why does the AESO believe that managing “extended-duration TMR services” by the processes outlined in the MSA’s Report on TMR is insufficient? (f) Please describe when the proposed Article 11 would be used for extended duration TMR and when it would not be used. Explain the extent to which the proposed Article 11 would influence whether the AESO bypasses some or all of the processes in the MSA Report. Page 2 of 2 (g) Does the AESO see any merit in having two distinct schemes in Article 11, one for pricing shorter duration TMR and the other for pricing extended duration TMR? Response: (a) Short-term emergency service would normally be situations where services are required from a generator to maintain system reliability for a period of hours, days or possibly weeks and the required services have not been contracted for. Please see FIRM.AESO-020 for a listing of Ancillary Services. Other aspects of emergency circumstances may include loss of transmission elements, unexpected load patterns or unexpected generation patterns. (b) Foreseeable long-duration services differ from short-term in that such services may cover a few upcoming months or years. Such situations would be expected to require addition or replacement of a new transmission element with an extended time before the element would be operational. The needed services would be uncontracted. Conscription of uncontracted generators would be foreseeable. (c) Please refer to FIRM.AESO-037. (d) AESO is committed to avoid extended term conscriptions as much as possible but due to long-lead times for transmission projects and continued load growth it is realistic to expect extended term conscriptions will be required and therefore addressed in the AESO’s tariff. The concern does not extend to services under contracts. One situation where requirements materialize is if transmission facilities are not completed prior to expiration of contracts. (e) Please refer to IPPSA.AESO-001(a). (f) The conditions under which Article 11 would be used are described in Article 11.1. Processes described BR.AESO-003(b) would be followed. The proposed Article 11 is not a means to bypass contestable processes. The proposed Article 11 will provide a known and certain backstop for non-contestable situations. (g) No. The structure of Article 11 in Option 3 is appropriate for short and extended duration conscriptions. Separate schemes would add complexity compared to a single approach, and are not considered to be necessary. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-005 Page 1 of 1 Reference: August 4, 2005 Revised Application, p. 6 Preamble: The Application states: The ADOE issued the findings of its wholesale market review in a policy paper titled “Alberta’s Electricity Policy Framework: Competitive – Reliable – Sustainable”, on June 6, 2005. Section 4.4.2 of the policy paper addressed TMR services and included overarching principles for the TMR process as well as requiring the AESO to create processes, practices, and rules to address several aspects of TMR services. Request: Please file a copy of the ADOE’s Electricity Policy Framework document. Response: Please refer to BR.AESO-002 (a). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-006 (a)-(b) Reference: August 4, 2005 Revised Application, p. 8 Preamble: The Application recites the ADOE principle: Page 1 of 1 Principle 7. The ISO must act as a rational buyer of TMR services with the Market Surveillance Administrator’s (MSA) oversight regarding competitive procurement. [emphasis added] Request: (a) (b) Response: (a) (b) Please file a copy of the AESO’s Ancillary Services Procurement Process, Version 1, June 17, 2005 and any subsequent version. Please explain the reason for this document(s). Please provide the AESO’s definition and understanding of a “rational buyer”. Please refer to BR.AESO-003(a). A rational buyer is someone who procures needed products or services at reasonable prices using appropriate procurement processes. AESO has a duty to procure Ancillary Services at costs which are reasonable and prudent. AESO’s intent is to develop and follow open, competitive procurement processes, where possible, which treat all competitors equally and fairly. Use of such processes would be in line with Principle 7 and achieve competitive prices for compensation. It is not possible to use competitive processes in all cases. In some cases it is necessary to conscript services to meet reliability requirements. In such cases, AESO has proposed a reasonable compensation proposal based on pro-rating costs among joint uses. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-007 Reference: August 4, 2005 Revised Application, p. 8 Preamble: The Application states: Page 1 of 1 Principle 9. Fidelity of Pool price is important and TMR rules and practices should preserve price fidelity and minimize any undue interference in the energy market. and The ADOE’s principles relating to TMR compensation as listed first above include and elaborate on the principles which the AESO included in the August 16 Application. … Minimizing market interference (principle 9) was discussed in paragraphs 9 and 14, specifically in the context of avoiding extra TMR compensation which could incent generators to submit high prices or withdraw supplies from the energy market. Request: If the AESO was concerned that a candidate for conscription was changing its offers in order to gain unwarranted TMR compensation, explain why submitting the concern to the MSA for investigation and adjudication is insufficient. Response: The current application remedies the issue by removing the incentive. The application also addresses other concerns as discussed in pages 11 and 12 of the Amendment Application. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-008 (a)-(d) Reference: August 4, 2005 Revised Application, p. 8 Preamble: The Application states: Page 1 of 2 The remaining principles (2, 3, 4, and 7) relate to processes for acquiring TMR services, as follows: 2. The need for TMR services should be identified as early as possible and defined as broadly as possible to maximize available alternatives. 3. Competitive processes should be used to the extent possible (and practical) and processes should be designed to maximize available alternatives. 4. In non-contestable situations, the process and next steps for acquiring TMR must be transparent. 7. The ISO must act as a rational buyer of TMR services with the Market Surveillance Administrator’s (MSA) oversight regarding competitive procurement. AESO is proceeding with establishing processes aligned with the latter principles. [emphasis added] Request: (a) Is the AESO in full agreement with the above noted principles? If not, explain why and specifically how the AESO intends to, or may have to, deviate from the principles. (b) Please describe precisely what the AESO has done to date to implement the process in the MSA Report, what it plans to do and when in respect of each of the above noted principles. (c) Subsequent to the August 16, 2004 application the MSA released the MSA Report on TMR. As part of the report, Charles River provided an assessment of TMR procurement in Alberta. Please explain the extent to which the MSA Report or the Charles River Study influenced the August 4, 2005 revised filing. (d) Please file a copy of the MSA Report, including the Charles River Study. Response: (a) (b) Yes. Please refer to BR.AESO-003 (a). Page 2 of 2 (c) The MSA recommendations with respect to the AESO focused mainly on procurement processes, internal processes, and TMR need identification. Please refer to BR.AESO-003 (a) for more information. Since none of the AESO-related recommendations focused on compensation for conscripted services, the report had limited influence on the 2005 Amendment Application. (d) The MSA report and the Charles River study are available from the MSA website www.albertamsa.ca under the reports section. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-009 (a)-(b) Reference: August 4, 2005 Revised Application, p. 9 Preamble: The Application states: Page 1 of 1 Discussions with stakeholders together with the AESO’s experience with the current AS Article have confirmed the appropriateness of the five TMR compensation principles provided in the ADOE’s Electricity Policy Framework paper. As well, discussions have supported interpreting “fair compensation” to include avoiding overpayment for TMR services. Request: (a) (b) Please describe which stakeholders and which stakeholder discussions confirmed the appropriateness of the five TMR compensation principles, especially the principle to recover a prorated portion of fixed costs. On what basis did stakeholders determine that “fair compensation” should be assessed? On what basis does the AESO consider that “fair compensation” should be assessed? Response: (a) Specific stakeholder comments during discussions were not recorded. (b) The AESO’s considerations have been identified in the application. There was a lack of consensus among stakeholders on a compensation method. The current proceeding provides stakeholders an opportunity to put forward and argue their positions. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-010 (a)-(c) Page 1 of 2 Reference: August 4, 2005 Revised Application, p. 9 Preamble: The Application states: Out-of-merit costs should be compensated under a separate category of costs so that the compensation is transparent and it is clear that such costs are always covered. Some forms of compensation do not clearly cover such out-of-merit costs. For example, in some situations under the current AS Article 24.3(b), a generator is paid another form of compensation (in this case a 10% premium on pool price) but the generator must absorb out-of-merit losses. Such a “netting” formula results in the out-of-merit losses reducing total AS compensation, in some cases to near zero. Separately identifying compensation for out-of-merit costs will ensure such costs are covered and will not create unfair situations where a generator receives little compensation when providing TMR service. Request: (a) Please provide a numerical scenario demonstrating how AS compensation is reduced to near zero amounts under Article 24.3(b), as discussed in the above noted paragraph. (b) For the given scenario in question (a), calculate the AS compensation under each of the remaining pricing options under Article 24.3. Given the “higher of” provision explain why the supplier would not receive at least its “out-of-merit” costs under the current Article 24.3. (c) Is the AESO saying that in order for a compensation scheme to be acceptable it cannot be in a form other than that of a two-part calculation; first addressing compensation when operating costs are less than pool revenue, and second, addressing payment for fixed costs? Please explain your response. Response: (a) Please refer to IPPSA.AESO-017 (a). (b) Please refer to BR.AESO-004 (a) for compensation under other options and similar circumstances. See also IPPSA.AESO-017 (a). (c) The ADOE’s Electricity Policy Framework paper establishes principles. The paper does not dictate a structure for the AS Article. A two-part calculation, where out-of-merit compensation is one of the parts, minimizes interference in the energy market. Minimization of interference in the energy market is a principle articulated in the ADOE’s Electricity Policy Framework paper (principle 9). Such a structure appropriately compensates a generator for the periods when the generator is not expected to participate in the energy market. The structure also does not skew the market signal and market Page 2 of 2 compensation for periods when it appears a unit could economically operate in the energy market. The two-part calculation satisfies the principle of minimizing market interference. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-011 Reference: August 4, 2005 Revised Application, p. 9 Preamble: The Application states: Page 1 of 1 Principle 8 also requires recovery of a portion of fixed costs. Fixed costs are to be prorated according to joint use of the generating unit (such as for providing conscripted TMR service and operating in the energy market). In contrast, the August 16 Amendment proposed a focus on “Going Forward Costs” which would be incurred for operation and maintenance of the generating unit over the next 12 months. Request: Explain why the existing Article 24 does not already comply with principle 8. Response: The existing Article 24 provides for recovery of a proportion of fixed costs and partially complies with principle 8, as stated at page 11, line 42 of the 2005 Amendment Application. The non-compliance of the existing Article 24 is discussed on page 9 of the 2005 Amendment Application. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-012 Reference: August 4, 2005 Revised Application, p. 9 Preamble: The Application states: Page 1 of 1 For a generating unit that is predominantly in-merit and economic in the energy market, a joint use formula would allocate most fixed costs to operations in the energy market. On the other hand, for a unit that is predominantly out-of-merit and conscripted for TMR service, a joint use formula would allocate most fixed costs to the TMR service. A smooth transition between the largely in-merit case and the largely out-of-merit case is desirable to avoid poor incentives associated with sharp or lumpy transitions. [emphasis added] Request: Please explain why the existing Article 24 does not satisfy this requirement. Response: The question is taken as referring only to a requirement for a joint-use formula due to the emphasis added. Please see the response to IPPSA.AESO-011. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-013 Page 1 of 1 Reference: August 4, 2005 Revised Application, p. 10 Preamble: The Application states: Further minimization of distortions preserves energy market signals as much as possible. For in-merit generators, the energy market provides signals for operation in the market. Appropriate AS Article compensation which is clearly additional to and separate from energy market revenues is desirable in that the in-merit generator will continue to receive the energy market signal and revenues as well as supplemental AS compensation. AS Article options that call for inmerit energy market revenues to be substituted or forfeited as part of the AS compensation have the effect of reducing or completely cancelling the energy market signals. Such interruption of or interference with energy market signals represents an undesirable distortion. [emphasis added] Request: Please explain how and in what situations the existing Article 24 compensation options lead to the “substitution or forfeiting” of energy market revenue and fully explain how this has the effect of reducing or completely cancelling the energy market signals? Provide a numerical and graphical example. Response: Please refer to IPPSA.AESO-017 (a). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-014 Reference: August 4, 2005 Revised Application, p. 10 Preamble: The Application states: Page 1 of 1 In Decision 2002-103, the EUB focused on short-term emergency situations and the need to direct service and compensate service providers in such situations, and approved the current AS Article. Since that time the AESO experienced a requirement to procure an ancillary service over the medium to longer term, on a conscripted basis. The service was required in the northwest region of Alberta to ensure voltage stability and reliable electrical service for an extended period. AESO foresees other situations may arise. In addressing the longer-term requirement the AESO generally reviewed experience with the AS Article and other relevant events since Decision 2002-103. [emphasis added] Request: Please explain the “other situations” that may arise (when, where, duration) and explain why the AESO believes it is necessary to rely on a combination of conscription and tariff-based compensation. Explain why the AESO believes that it could not conduct an RFP process or enter bi-lateral negotiations and successfully negotiate a contract for services in these potential situations. Response: Please refer to IPPSA.AESO-001(a), 4(a), (b) and (d). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-015 (a)-(c) Reference: August 4, 2005 Revised Application, p. 10 Preamble: The Application states: Page 1 of 2 Although the AESO is actively assessing the shortage of transmission in the northwest region, it is the case that an expected transmission solution will take three to five years to complete and, therefore, long duration TMR services must be procured in the interim. There is no immediate alternative to negotiating to procure TMR services from existing local generators, such as by initiating a competitive process, as the existing transmission infrastructure is unable to accommodate new generation. Information on the competitiveness of the NW area was provided in the AESO’s January 10, 2005, additional evidence and is included as Appendix D in this Application. [emphasis added] Request: (a) Is the AESO recommending that in instances when it must deal exclusively with a single supplier for TMR services, the terms of compensation should automatically default to a predefined formula as contained in the tariff? Please explain your response. Please explain the timing and role, if any, the AESO envisions for bilateral negotiations, private arbitration or Board adjudication to determine compensation. (b) How frequently will the AESO publish a statement regarding the need for TMR servicesacross the Alberta grid? When will the AESO publish the next such statement? (c) If the AESO publishes a statement of need indicating that from time to time it will be required to direct a supplier for reliability purposes, please: (i) explain whether the AESO will provide compensation from the date that need is identified or only from the date that a direction of real or reactive power occurs and then only as these occur in the future; and (ii) explain when and how a supplier will know that it is a candidate for compensation. For each, please provide a full description in the case of contestable and noncontestable situations. Response: (a) AESO is recommending the AS Article, as proposed, provides a reasonable compensation level in non-contestable circumstances. As such it forms a suitable basis in non-contestable situations, or starting point for negotiated contracts. AESO would also consider reasonable alternative proposals to deal with unique circumstances, including any case where a supplier can demonstrate hardship. Page 2 of 2 Timing and other aspects of negotiations and disputes would be addressed on a case by case basis. Disputes under the AS Article would follow the process outlined in Article 19 of AESO’s Terms and Conditions of Service. (b) The AESO will identify the need for TMR services in the context of 10 year and 20 year plans with the frequency required by the Transmission Regulation. Where other instances of TMR need can be forecast (i.e. transmission maintenance, construction), the AESO will conduct transparent and competitive processes when possible. (c) The AESO will provide compensation from the date that conscription occurs. As noted above, where TMR need can be forecast, the AESO will conduct transparent and competitive processes when possible. During abnormal conditions, TMR services may be conscripted and it may not be possible to provide any significant advance notice to suppliers. The posting of need should not be affected by whether the situation is contestable or non-contestable. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-016 (a)-(c) Reference: August 4, 2005 Revised Application, p. 11 Preamble: The Application states: Page 1 of 2 Undercompensation concerns arise when conditions result in compensation near the transition point between AS Articles 24.3(b) and 24.3(c) when compared to compensation under conditions which are not near the transition point. The current AS Article compensates using the greater of a 10% premium on pool price (in Article 24.3(b)) or 110% of direct costs, including a proportion of fixed costs prorated according to directed hours and service hours, less pool revenues (in Article 24.3(c)). When pool prices are high Article 24.3(b) provides significant compensation compared to the energy market alone, and when pool prices are low Article 24.3(c) provides significantly more compensation than the energy market. However, when pool prices are moderate, both Articles provide relatively lower levels of compensation compared to higher or lower pool prices. Such a result is not considered fair, and is further illustrated in Appendix C. [emphasis added] Request: (a) Please confirm that the “significant compensation compared to the energy market alone” in respect of Article 24.3(b) is equal to 10% of pool price for the period in which conscription occurs. If not, please explain. (b) Please confirm that the “significant compensation compared to the energy market alone” in respect of Article 24.3(c) is equal to the net cost-of-service including sufficient funds to cover out-of-merit expenses (if any) and a prorated share of fixed costs. If not, please explain. (c) Please explain the economic principles that dictate that TMR compensation should be relatively constant compared to pool prices or pool revenue. Response: (a) Confirmed for periods when pool prices are relatively high. (b) Confirmed for periods when pool prices are relatively low and with the clarification that such net compensation is further increased by 10%. (c) The quoted paragraph is included under a discussion of a “fairness” principle, which is the largest concern. Any structure which does not provide for a relatively smooth transition to a supplier as conditions change will have fairness concerns. Similarly structures which do not provide for relatively smooth compensation differences among suppliers will have fairness concerns. The graph in Appendix C of the 2005 Amendment Application illustrates the issue. If three generators Page 2 of 2 were conscripted, one of which was out-of-merit for 25%, one at 30% and the other out-of-merit for 35% of the time, one would expect the extra TMR compensation to be relatively consistent. Yet under Article 24.3, the generator which was out-of-merit for 30% would receive significantly less TMR compensation than both of the other generators and would question the fairness of such an outcome. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-017 (a)-(b) Reference: Request: (a) (b) Response: (a) Page 1 of 1 August 4, 2005 Revised Application, Appendix C Please describe all assumptions and calculations used in developing Appendix C. Provide a summary of all instances of conscription for TMR since January 2002 to the present. Include in each instance the date and length of the conscription, the amount of capacity conscripted and the reason for the conscription. Please see Attachment IPPSA.AESO-017, a worksheet which contains assumptions and calculations. At row 71 in scenario C, the out-of-merit loss is $182,000. The TMR revenue of $203,000 barely covers the loss with little contribution to fixed costs. The TMR revenue although sufficient to cover the OOM costs appears to be unfair in relation to significantly larger coverage for either greater or lesser out-of-merit operation. (b) Please refer to FIRM.AESO-037. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-018 (a)-(c) Page 1 of 2 Reference: August 4, 2005 Revised Application, p. 11 Preamble: The Application states: Under other circumstances the current AS Article may overcompensate a generator providing AS services. Specifically, Article 24.3(c) prescribes 10% to be added to compensation for fixed and variable costs. This premium results in an overpayment above costs. Article 24.3(b) prescribes 10% to be added to pool price and may sometimes also result in an overpayment since the premium is not related to either fixed or variable costs. Request: (a) Provide a numerical example illustrating the AESO’s concern with Article 24.3(c). (b) Please discuss the necessary conditions to arrive at a situation in which Article 24.3(c) compensation will be 10% above the (i) monthly fixed and variable costs and (ii) the annual fixed and variable costs. (c) Explain why section 23 of the Transmission Regulation is not sufficient to address the AESO’s concerns. Does section 23 not cap compensation to protect against any “over compensation”? Response: (a) A simple numerical example of Article 24.3 amounts follows (all values are in $/MWh): Case A 35 3.5 3.5 Case B 150 15 15 Case C 10 1 1 Fixed and variable costs Fixed and variable costs less pool price 24.3(c) (Fixed and variable costs less pool price) plus 10% Article 24.3(c) amount 60 25 27.5 60 negative 0 60 50 55 Article 24.3 Compensation - Greater of (b) or (c) above 27.5 15 55 35 150 10 Total compensation (Pool and Art 24.3) 62.5 165 65 Concern: Compensation above cost Concern: Compensation above Energy Market 2.5 Pool Price 24.3(b) 10% of Pool Price Article 24.3(b) amount Energy Market Compensation (Pool Revenue) 5 15 Page 2 of 2 Cases A and C illustrate the concern regarding payments above costs ($2.5/MWh and $5/MWh) under Article 24.3(c). Case B illustrates the second concern as the $15 extra payment under Article 24.3(b) is not related to costs. (b) The 10% adder contained in Article 24.3(c) means that in most conditions the compensation will exceed fixed and variable costs. A 10% increase to fixed and variable costs occurs under very low pool prices similar to that shown in case C above. (c) Section 23 of the Transmission Regulation does partially address the overcompensation concern by establishing a ceiling. The ceiling as proposed has not been set at a level which would be considered reasonable for most conscription situations. Reliance only on the ceiling with no further changes would also not address other concerns noted at pages 11 and 12 of the 2005 Amendment Application. Please also see the response to IPPSA.AESO-015 (a). 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-019 Reference: August 4, 2005 Revised Application, p. 11 Preamble: The Application states: Page 1 of 1 The current AS Article will not always satisfy the cost recovery principle, either. Where compensation is determined as a 10% premium on pool price, it is not related to either variable or fixed costs and is not aligned with the cost recovery principle. Request: Is it the AESO’s position that the ADOE’s Policy Framework document dictates that the method used to compensate for TMR services can only be in the form of a two-part calculation, separately addressing variable and fixed costs. Please coordinate this response with the response to IPPSA.AESO-010 (c). Response: Please refer to IPPSA.AESO-010 (c). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-020 Reference: August 4, 2005 Revised Application, p. 11 Preamble: The Application states: Page 1 of 1 There is also no compensation for out-of-merit costs paid under current AS Article 24.3(b). The 10% premium on pool price generally prevails when pool prices are relatively high, which indicates that units will have substantial in-merit operation. However, even though pool prices are relatively high, directed out-ofmerit operation is likely. Since there is no out-of-merit compensation under 24.3(b), the generator must net off out-of-merit losses against compensation from the energy market or ancillary services. A more desirable approach is to ensure all out-of-merit costs are compensated so that a generator is always kept whole, at a minimum, when out-of-merit operation is directed. Request: Provide a numerical example where a supplier suffers losses under Article 24.3(b) compensation. Explain why the “higher of” provision of the current Article 24 would not ensure that at least out of merit costs are covered. Response: Please refer to the response provided in IPPSA.AESO-017 (a). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-021 (a)-(e) Reference: Preamble: Page 1 of 2 August 4, 2005 Revised Application, p. 14 The Application states: Fixed cost compensation is based on a pro-rating of fixed costs between the two uses of the unit, namely, in-merit energy market service and the conscripted ancillary service. The portion of fixed costs assigned to energy market service is based on in-merit hours. The portion assigned to directed service is based on out-of-merit directed service hours. By basing the energy market share on in-merit hours, the generator is not discouraged from operating during such in-merit periods to capture and retain as much revenue from the energy market as possible, and the incentive to operate during in-merit periods is common to all generators. If a generator is unable to capture in-merit hours due to limitations of the generating unit (for example, start-up times), the number of in-merit hours will be reasonably adjusted to reflect the physical characteristics of the generating unit and its ability to capture revenues from in-merit hours. Such adjustment would be determined on a case-by-case basis after examining the particular circumstances of each case. (emphases added) Request: (a) Using example A, B and C from Appendix E of the revised application, provide an illustrative numerical example comparing the approach to prorating fixed costs from Option 3 to the existing Article 24. (b) Please describe how “in-merit” and “out-of-merit” hours will be determined in Option 3 and compare this to the manner they are determined under the existing Article 24. (c) Who will be responsible for adjusting in-merit hours associated with compensation under Option 3? (d) Are adjustments of in-merit hours restricted to the physical characteristics of the generator? If not, indicate the other reasons the AESO would agree to adjusting “in-merit hours”. To undertake this adjustment, will the AESO require access to confidential offer strategies of market participants in order to fairly assess the amount of in-merit hours? Please explain. (e) If there is a dispute over the quantum of the AESO’s determination of “in-merit hours”, how will it be resolved? Page 2 of 2 Response: (a) Please refer to BR.AESO-004 (a). The examples do not use the same values as Appendix E but the fixed cost compensation values would simply be increased or decreased linearly for different assumed levels of fixed cost. (b) In Option 3, in-merit and out-of-merit are established by comparing the Benchmark price to the pool price. The existing Article 24 does not contain an inmerit/out-of-merit distinction. The current Article 24 prorates according to service hours which are determined by the customers offer prices. (c) Please refer to FIRM.AESO-024 (i). (d) Adjustments are restricted to those pertaining to physical characteristics of the unit. Access to confidential offer strategies of market participants will not be required. (e) Disputes will be addressed in accordance with Article 19 of AESO’s Terms and Conditions of Service. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-022 Page 1 of 1 Reference: August 4, 2005 Revised Application, p. 13 Preamble: The Application states: This option [Option 3] is designed to encourage participation in the energy market. The generator is not disincented from its expected operation during inmerit periods and receives pool price from the market for such operation. The generator retains all in-merit revenue from in-merit energy production. Request: Given the AESO’s role as the buyer of TMR services, please explain why there is not a conflict of interest in proposing a tariff for medium and long-term application that intends to disqualify the operating decisions determined by the owner, and to include only the operating hours as qualified by the buyer. Response: The AESO does not see a conflict of interest arising regarding its purchases of TMR services. AESO procures or in some cases conscripts required supplies solely for the purpose of meeting reliability requirements. The AESO’s duties regarding reliable operation of the transmission system are mandated [EUA Section 17(h)]. The AESO is not disqualifying the operating decisions of an owner. The AESO only directs operation of capacity required for reliability purposes. The generation owner retains decision making ability for all capacity not directed for reliability purposes. The AESO compensates suppliers according to contracts or provides reasonable compensation to suppliers in the case of conscriptions. The AESO has attempted to consider the interests of various stakeholders in developing the tariff proposed. The AESO, as an independent and not-for-profit entity denies that its proposals are biased towards or away from any particular interest. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-023 Reference: August 4, 2005 Revised Application, p. 14 Preamble: The Application states: Page 1 of 1 This option [Option 3] compensates for fixed costs rather than Going Forward Costs as in Option 2. Such compensation for fixed costs aligns more directly with the type of compensation called for in the Transmission Regulation and in the Electricity Policy Framework paper. The determination of fixed costs will be made following the principles proposed for Maximum TMR Compensation in the AESO’s 2006 GTA and as required by Section 23 of the Transmission Regulation, modified such that the pro-rating will be according to the Directed Out-of-Merit ratio as detailed in Appendix A rather than the joint use formula proposed for Maximum TMR Compensation. [emphasis added] Request: Please confirm that the methods for calculating compensation under Option 3 and the Maximum TMR Compensation are identical except for the formula that allocates fixed costs. If not, explain all the differences. Response: Confirmed. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-024 (a)-(d) Reference: August 4, 2005 Revised Application, p. 15 Preamble: The Application states: Page 1 of 1 Under extended duration conscriptions, a generator’s aggregate compensation from the energy market and TMR appears to be generally comparable under Options 1 and 3. Aggregate compensation under Options 1 and 3 for short-term conscriptions may differ according to the specific short-term circumstances. Request: (a) Provide numerical examples for a high-efficiency thermal generator showing how extended duration (at least 1 year in duration) TMR compensation compares between Option 1 and Option 3. Assume the conscription is for 100% of plant capacity under the following types of situations: (i) a high frequency TMR dispatches, (ii) a medium frequency of TMR dispatch, (iii) a low frequency of TMR dispatch. (Provide results in an Excel spreadsheet with graphical summary.) (b) Please re-answer question (a), assuming instead the conscription is for 50% of the plant capacity. (c) Please re-answer questions (a) and (b), for a low-efficiency thermal generator. If the generator’s compensation under Option 3 is comparable to the compensation associated with the existing Article 24, why is there a need to amend the tariff? (d) Response: (a) – (c) (d) Please refer to BR.AESO-004 (a). Please refer to pages 11 and 12 of the 2005 Amendment Application. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-025 (a)-(d) Reference: August 4, 2005 Revised Application, p. 17 Preamble: The Application states: Page 1 of 2 In the definition of “Maximum TMR Compensation” as filed January 31, 2005, the prorating of item (f) total return costs and item (i) credits for common costs were not included. The prorating of each cost was discussed later in section 6.4. The corrected item (f) and (i) are as follows: (f) a prorated share of total return costs reflecting one-twelfth of the sum of: … where the prorated share is based on the number of hours of TMR service compared to the total of hours of TMR service and a reasonable portion of hours in-merit in the energy market; (i) a prorated share of credits for common costs, if applicable, reflecting revenues or benefits attributable to a service in addition to the TMR service and associated with the generating asset where the prorated share is based on the number of hours of TMR service compared to the total of hours of TMR service and a reasonable portion of hours in-merit in the energy market; and Request: (a) Please explain how the prorate method proposed for the requirements of section 23 of the Transmission Regulation compares with the prorate method used in the existing Article 24. Provide illustrative numerical examples.\ (b) Please explain who will undertake to adjust the portion of “in-merit” hours and for what reasons this adjustment take place. Are the reasons for adjustment different than that used to adjust the proposed Article 24 compensation? If so explain. (c) Please provide a definition of “in-merit hours” as it is proposed to be used for the Maximum TMR Compensation. (d) Please explain why Maximum TMR Compensation is not based on a calculation of annual costs rather than monthly costs, particularly in the context of extendeduse TMR? Response: (a) The prorate method for the TMR Maximum is for the purposes of setting a maximum as a reference to which actual TMR compensation under contracts or conscription can be tested. The intent of a cap or ceiling is to indicate the upper end of a reasonable range. Differing TMR contracts may call for TMR compensation across all periods, including periods where a unit may be in-merit. The Maximum has been proposed to include in-merit hours where TMR service Page 2 of 2 is provided to permit a reasonably wide range of contracting arrangements and TMR payment schemes. The AS Article establishes a reasonable compensation amount to be paid when conscription occurs. The intent is to set a compensation level which is within a reasonable range, not at the top or the bottom. The AS Article prorating determines the use for TMR and the energy market and prorates according to the use. Any in-merit operation is considered to be for the energy market use and therefore the AS Article prorating does not include in-merit hours. For examples, please refer to BR.AESO-004(a). (b) Please refer to FIRM.AESO-024(i). The reasons for any adjustment for purposes of TMR Maximum calculations are the same as for Article 11 conscripted operation calculations. (c) The same definition is proposed as is proposed in Article 11.3 calculations, that being the relationship of the pool price to the benchmark price. (d) Please refer to IPCAA.AESO-002(d). 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-026 (a)-(b) Page 1 of 1 Reference: August 4, 2005 Revised Application, p. 18 Preamble: The Application states: A generator’s in-merit pool revenues would not be considered as compensation for TMR service and therefore would not impact TMR maximum compliance calculations. In other words, revenues received by a generator for in-merit energy production would be retained by the generator, as they would have been if the generator had simply operated in the energy market and not provided any TMR service. [emphasis added] Request: (a) (b) Response: (a) (b) Please define “in-merit pool revenue”. Please confirm that in the AESO’s view pool revenue received by the supplier for producing actual energy – whether as a result of a TMR dispatch or the voluntary discretion of the supplier – is to be excluded from the consideration of compensation for purposes of defining the maximum compensation for TMR. If not, please explain. In-merit pool revenue is equal to the pool price multiplied by energy generated by a unit for an hour where the Pool price is greater than the Benchmark price. Confirmed. Pool in-merit revenue would not be considered as TMR compensation as per the preamble. As stated in the paragraph following the preamble, pool revenue related to out-of-merit TMR service would be considered as part of TMR compensation. During a period where a unit is out-of-merit, a generator would not be expected to participate in the energy market. Therefore the energy generated in an out-ofmerit period in compliance with a TMR directive is considered to be solely for purposes of TMR. The TMR revenue and the pool revenue are therefore both considered as being associated with the TMR purpose and to as compensation to cover costs associated with TMR. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-027 (a)-(c) Reference: August 4, 2005 Revised Application, p. 18 Preamble: The Application states: Page 1 of 1 Pool revenues related to out-of-merit TMR service would be considered as part of TMR compensation. Such out-of-merit pool revenues would be included with other forms of TMR compensation and the aggregate of such compensation would be limited by the maximum TMR compensation level. Pool revenues for out-of-merit TMR service would be included as part of TMR compensation because the unit would not normally be expected to operate when out-of-merit. [emphasis added] Request: (a) Please define “out-of-merit pool revenue”. (b) Please confirm that in the AESO’s view power pool revenue received by the supplier for producing actual energy during “out-of-merit” conditions will be classified as TMR compensation. If not, please explain. (c) Please explain how and why this recommendation is consistent with section 23 of the Transmission Regulation. Response: (a) Out-of-merit pool revenue is equal to the pool price multiplied by energy generated by a unit in compliance with a TMR directive for an hour where the Pool price is less than the Benchmark price. (b) Confirmed. (c) Please refer to IPPSA.AESO-026 (b). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-028 Reference: August 4, 2005 Revised Application, p. 18 Preamble: The Application states: Page 1 of 1 In addition, one extra line has been added to the revised attachment to Information Response BR.AESO-042. The extra line (line 55) represents the Maximum Fixed and Indirect Costs. The amount is referenced for fixed costs in the recommended Option 3 for Article 11 compensation. (emphases added) Request: Please define “Maximum Fixed and Indirect Costs” and explain how these costs are to be calculated. Response: Option 3 compensates for a pro-rated share of Average Monthly Fixed Costs as described in Appendix A of the Amendment Application. Article 11.3(b)II refers to Average Monthly Fixed Costs and on page 2 of Appendix A Average Monthly Fixed Costs are defined. The determination of Average Monthly Fixed Costs (before prorating) is calculated in the same manner as fixed costs are determined for purposes of the TMR Maximum. In Schedule E, the extra line titled Maximum Fixed and Indirect Compensation before Prorating is shown and is the intended reference to be used for Average Monthly Fixed Costs in Article 11.3(b)II. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-029 (a)-(d) Reference: August 4, 2005 Revised Application, Appendix A, p. 1 Preamble: The proposed Article 11.3 (a) states: Page 1 of 2 The product of the MW hour directed and the highest price paid in the hour to Customers providing the same Ancillary Service pursuant to Article 11.2 provided the service was not a TMR service and that the Existing Contract was the result of a competitive process conducted in the prior 12 months; or [emphasis added] Request: (a) Please define “a competitive process” and explain the limitations, if any, to the validity of such a process for the purposes of this proposed Article. (b) Please define the term “conducted” and explain the specific part of a “competitive process” that cannot be more than 12 months in the past – the beginning of the process, the conclusion or the contract execution if this occurs afterwards. Please identify the typical time required to conduct a competitive process from identification of the need to the signing of contracts. (c) Please explain why the Existing Contract which is used for reference purposes must arise from a competitive process “conducted” less than 12 months prior. Are there acceptable methods to adjust competitive prices over periods longer than 12 months? Please explain. (d) Why are TMR Services precluded from availing themselves of compensation on the basis of competitive contracts for the same service. Response: (a) (b) A competitive process is a procedure or method of procuring a service where a reasonable number of suppliers, each of whom is credible and qualified to provide the service, actively vie for the right to supply the service. The process may be invalid if too few credible and qualified suppliers participate or if one supplier has an obvious advantage over all of the others which limits competition. As noted in response to BR.AESO-003 (a), the AESO intends to develop process and criteria for determining if specific circumstances result in a situation that is either contestable or non-contestable. For purposes of the AS Article, the AESO proposes to begin the 12 month time period on the contract execution date. Certain AS competitive processes are conducted daily (operating reserves), other can take as long as 6 months or even more. Page 2 of 2 (c) The 12 month limitation is proposed to avoid reference to and use of “stale” prices which do not reflect current market conditions. No adjustment mechanisms are available. (d) TMR services are location specific and prices in one location are not reflective of prices in other locations. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-030 (a)-(c) Reference: August 4, 2005 Revised Application, Appendix A, p. 1 Preamble: The proposed Article 11.3 (b) states: Page 1 of 1 For thermal units, the sum of the following: Request: (a) I. An out-of-merit payment, when Pool Price is less than the Benchmark Price; (Benchmark Price minus Pool Price) multiplied by the energy generated (MWh) in compliance with the directive; plus II. A capacity payment equal to Average Monthly Fixed costs multiplied by Directed Out-of-Merit Ratio as defined below. [emphasis added] Please define “thermal units”. (b) Please explain how the AESO proposes to compensate non-thermal units that are conscripted for TMR dispatch. (c) Please summarize the method for compensation in algebraic form and contrast it to an algebraic summary of the compensation method in the existing Article 24.3(c). Please explain all assumptions and define all terms as they apply to each method. Response: (a) The term “Thermal unit” in Article 11 refers to any unit using natural gas, coal, diesel or other petroleum as fuel for electricity generation. Hydro or wind units would be excluded. (b) Hydro units are expected to be compensated under Article 11.3(c). Conscription of wind units has not been contemplated. (c) Please refer to BR.AESO-004 (a). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-031 (a)-(b) Reference: August 4, 2005 Revised Application, Appendix A, p. 1 Preamble: The proposed Article 11.3 (c) states: Page 1 of 1 The verifiable net opportunity cost related to foregone electricity sales incurred by the Customer to supply the directed Ancillary Services taking into account all offsetting revenues from any source, such as pool energy receipts. [emphasis added] Request: (a) (b) Response: (a) (b) Please define ”electricity sales”. Please explain why the AESO intends to restrict the nature of opportunity costs and provide examples of the types of opportunity costs the AESO would consider unacceptable. Electricity is defined in the Electric Utilities Act. Electricity sales are exchanges of electricity for an agreed price and would involve delivery of electricity to the Power Pool or to a customer. Please refer to BR.AESO-005 (c) and PWX.AESO-009 (b). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-032 (a)-(d) Page 1 of 1 Reference: August 4, 2005 Revised Application, Appendix A, p. 2 Preamble: The proposed Article 11.3 (c) states: Benchmark Price ($/MWh) equals (Heat Rate multiplied by Fuel Cost) plus Variable STS Charges plus Variable O&M Proxy. Request: (a) Why is a Benchmark Price required? What is its purpose? (b) Why is the Benchmark Price based strictly on variable operating costs (i.e. shortrun marginal costs)? (c) Why is the Benchmark Price not set based on the supplier’s offer price? (d) Please provide the entire basis for setting the Variable O&M to a constant $/MWh amount and the entire basis for setting it specifically to $4/MWh. Response: (a) The benchmark price is used to compensate for variable operating and fuel costs and do so in a way which does not require significant disclosure of operating cost information by a customer and recognizes the market value of the natural gas used as a fuel source. (b) The focus of the Benchmark price is direct operating costs which is typically the variable portion of operating costs. Such costs do not require prorating. Indirect and fixed fuel, operating and maintenance costs require prorating and are therefore included with “Average Monthly Fixed Cost”. (c) The supplier’s offer price may not be based on costs or it may be based on recovery of fixed costs which are compensated for separately. Use of a supplier’s offer price would not be based on a cost of service approach and would not be considered reasonable compensation for conscripted service. (d) The variable O&M amount of $4.00/MWh was based on recent analysis by BowArk and evidence of the ancillary services group (ASG) in the process leading to EUB Decision 2002-103. A report by BowArk was attached to AESO's submission on November 2, 2004 shows a variable cost of $4.41/MWh in the first year. ASG Exhibit 233 submitted on April 2, 2002 included a variable cost of $2.78/MWh. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-033 (a)-(d) Reference: August 4, 2005 Revised Application, Appendix A, p. 2 Preamble: The proposed Article 11.3 (c) states: Page 1 of 2 Average Monthly Fixed Cost is equal to the maximum amount of TMR compensation as defined for purposes of Section 23 of the Transmission Regulation, before prorating for joint use, and less the variable portion of such costs, a portion of all of which may be included in the Benchmark Price. Request: (a) Please summarize the referenced clause in algebraic form, providing full definitions for all variables used and assumptions as necessary. (b) Using the above summary, clarify how the Average Monthly Fixed Costs are adjusted when a plant is dispatched at less than full capacity. (c) Please provide the AESO’s rationale for prorating the Average Monthly Fixed Costs. If the AESO intends to prorate the costs using dispatch levels that are below the minimum operating levels for a given plant, provide the entire basis for this approach. (d) Does the AESO intend to adjust the “variable portion of such costs” to reflect less efficient operation of a plant operating at minimum dispatch levels? Please explain. Response: (a) The line numbers in the following refer to the examples in corrected Schedule E as found in Attachment IPCAA.AESO-012. Firstly, the starting point would be TMR Maximum Compensation before prorating for joint use, before prorating for partial use and including the variable portion of costs or: TMR Monthly Return Costs (line 32a); plus Direct O&M costs (line 35); plus Indirect or Fixed O&M costs (line 36); plus Direct Fuel costs (line 42); plus Indirect or Fixed Fuel costs (line 43); less: Credit for Common costs (line 49. Secondly, Variable costs would be subtracted from the above amount: Less: Direct O&M costs – (line 35); Less: Direct Fuel Costs – (line 42). Thirdly, the partial-use adjustment would be made to each of: Page 2 of 2 TMR Monthly Return Costs (line 32a); Indirect or Fixed O&M costs (line 36); Indirect or Fixed Fuel costs (line 43); and Credit for Common costs (line 49). The adjustment would be made using the partial use ratio shown at lines 33, 39, 46 and 52. The Average Monthly Fixed Cost would therefore equal the sum of: TMR Monthly Return costs after partial use adjustment Indirect of Fixed O&M costs after partial use adjustment Indirect or Fixed Fuel costs after partial use adjustment Less: Credit for Common Costs after partial use adjustment. The amount is shown at line 55. Direct O&M costs and Direct Fuel costs are typically variable costs which are incurred only and entirely for the TMR service. Recovery for such variable costs would be expected to occur through Benchmark Price compensation. (b) The partial use adjustment is illustrated at lines 33 & 34, 39 & 40, 46 & 47 and 52 & 53 of Example C of Attachment IPCAA.AESO-012. In Example C, the average maximum MCR of the unit is 50MW (line 5) the average MW directed for TMR is 30 MW (line 6). The ratio of Average MW directed to the average Maximum MCR is 30/50 or 0.6 or 60%. This ratio is used at lines 33, 39, 46 and 52. The return amounts, fixed or indirect costs and the Credit for common costs are all adjusted by the ratio. (c) The rational for prorating the costs is to reflect the usage of the unit for Ancillary Services. The unit remains available for use by the customer in the energy or other markets. AESO dispatches units to their minimum operating level or greater. (d) The Benchmark price reflects the “actual heat rate of the unit during the period when the unit was complying with the directive”. If a unit is directed to an inefficient operating level, the heat rate at the directed level will already be reflected so further adjustment is unnecessary. 2 ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-034 (a)-(c) Page 1 of 1 Reference: August 4, 2005 Revised Application, Appendix B – Maximum TMR Compensation. Preamble: The AESO has revised Section 6.4 of the 2006 GTA filed January 31, 2005 to reflect the prorating method for total return costs and credits for common costs. Request: (a) Are the revisions to the AESO’s application for maximum TMR compensation limited strictly to the addition of the noted prorating methods? Please identify any other revisions. (b) For continuity, please file all Information Responses from the 2006 GTA that pertain to the Maximum TMR Compensation issue. (c) Please confirm that common costs including general and administrative costs would normally be a charge against a particular plant and should be included in the amounts to be prorated. Response: (a) (b) At the time of filing, the only revision was to the prorating as discussed at page 17 of the Amendment Application. In the response to IPPSA.AESO-036(b) a subsequent revision is proposed to recognize Customer and Unit specific capital structure and financial parameters. The following Information Responses from the 2006 GTA pertain to Maximum TMR Compensation and are attached as Att.IPPSA.AESO-034 – Attachment A: AP.AESO-001 to 006 BR.AESO-042 FIRM.AESO-244 IPPSA.AESO-001 to 016 TCE.AESO-219 and TCE.AESO-245(a). Please note that the spreadsheet attached to BR.AESO-042 in the 2006 GTA has been revised and is attached to IPCAA.AESO-012. (c) Not confirmed. Only fixed costs and operating and maintenance costs associated with the specific generating unit would be included. Please refer to Appendix B page 3, line 41. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-035 Reference: Page 1 of 1 August 4, 2005 Revised Application, Appendix E – Revised Schedule BR.AESO042 from 2006 GTA Preamble: Request: Please confirm that under the proposed Maximum TMR Compensation method, fuel costs are to be based on actual costs. If yes, explain why fuel costs in Appendix E are prorated similar to fixed costs. Response: Yes, fuel costs are to be based on actual costs. Direct fuel costs or those incurred only and entirely for TMR service are not prorated. Indirect or fixed fuel costs will be prorated as such costs are incurred to provide other services as well as TMR services. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-036 (a)-(b) Reference: 2006 GTA Application, Information Response AP-AESO-005 Preamble: In AP-AESO-005 (a), the AESO stated: Page 1 of 1 AESO’s preference would be to use the customer’s capital structure for the specific conscripted generating unit in the cost of service calculation. However information on capital structure for a customer is normally not available for an individual generating unit. Such information is normally reported for a business at a consolidated or aggregated level. The specific generating unit would be a relatively small portion of the business. Absent specific customer information on capital structure, AESO proposes to base the capital structure on a typical IPP as per the ASG evidence. AESO understood the ASG evidence to be based on a typical capital structure for an IPP. Such an approach of using industry reference information is consistent with a cost of service concept where specific unit information is unavailable. Request: (a) (b) For purposes of the Transmission Regulation (section 23) requirements, is the AESO opposed to using the customer specific information for determining the capital structure if it is available? If yes, explain why. If the AESO is not opposed to using customer specific information in (a) above, please provide an amended version of the definition for Maximum TMR compensation in order to accommodate the use of customer specific information, including information on the capital structure. Response: (a) AESO is not opposed to using customer information which is unit specific. To avoid provision of selective information, AESO proposes to use customer specific information only when all required information can be provided. (b) To accommodate the use of customer information, AESO proposes to add a new paragraph (k) under “Maximum TMR Compensation” in Appendix B as follows: “(k) in the event a customer provides actual and verifiable information for the generating unit for all of the parameters required in paragraphs (c), (d) and (e) above (capital structure, rate of return on equity, interest rate on debt, other financing costs and income tax costs) such actual information will be used instead of the deemed values in paragraphs (c), (d) and (e) above.” ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-037 Reference: 2006 GTA Application, Information Response IPPSA-AESO-013 Preamble: In IPPSA.AESO-013 (a), the AESO stated: Page 1 of 1 See TCE.AESO-219(a). If the owner is asked to make all of the reactive capability of the unit available for dynamic VAR production, then no adjustment for partial dispatch would be made. Request: Please provide an amended version of the partial dispatch clause to reflect the response to IPPSA.AESO-013(a). Response: The response noted above was not clear. Under AESO rules, generators are required to make VAR capacity available as a requirement of interconnection. AESO does not provide compensation for use of the required VAR capacity. Compensation of AS under the AS Article, including the partial use adjustment, are not affected by directives for VAR production. As such no amendments to the AS Article are required. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-038 Reference: 2006 GTA Application, Information Response IPPSA-AESO-015 Preamble: The response to IPPSA-AESO-015 states: Page 1 of 1 Costs of the independent third party performing the verification of Customer’s costs will be to the account of the AESO. AESO expects the Customer to cooperate with the third party and provide, at the Customer’s cost, information reasonably required to verify the Customer’s information. Request: Please file an amendment to the proposed Article 11 and the Maximum TMR Compensation calculation method to reflect the response to IPPSA-AESO-015. Response: AESO proposes to add the following as Article 11.5: Information and calculations provided in respect of compensation by the Customer may require review and verification through an independent audit. Costs of the independent third party performing the verification of Customer’s costs will be to the account of the AESO. AESO expects the Customer to cooperate with the third party and provide, at the Customer’s cost, information reasonably required to verify the Customer’s information. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-039 Reference: 2006 GTA Application, Information Response IPPSA-AESO-016 Preamble: The response to IPPSA-AESO-016 states: Page 1 of 1 The AESO expects that Article 24 will be amended so that compensation for conscripted TMR will not approach the TMR cap unless the circumstances are exceptional. Consequently, we do not foresee a significant administrative burden. Request: Please describe the exceptional circumstances the AESO envisions which may lead to Article 24 compensation approaching the maximum TMR compensation limit. Response: At present no circumstances are foreseen where compensation under the proposed AS Article will exceed the TMR maximum. The comment was included to acknowledge the possibility of some unforeseen exceptional circumstances. ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-040 Reference: August 4, 2005 Revised Application, Appendix B – Maximum TMR Compensation, p. 5 Preamble: Appendix B states: Page 1 of 1 For simplicity the AESO proposes that a deemed capital structure is used with 70% debt and 30% common equity. This debt-equity ratio is consistent with the evidence of the Ancillary Services Group dated February 21, 2002, filed in the Board’s proceeding into Decision 2002-103. Request: Is there any independent basis for the 70/30 debt/equity split beyond it being selected from out of a broader suggestion of the Ancillary Services Group in 2002? Response: No studies of the debt/equity split were performed or requested by the AESO. Please see also the response to FIRM.AESO-026(b). ALBERTA ELECTRIC SYSTEM OPERATOR Ancillary Services Article Amendment (1357161) Monday, September 26, 2005 IPPSA.AESO-041 (a)-(b) Reference: August 4, 2005 Revised Application, Appendix B – Maximum TMR Compensation, p. 6 Preamble: Appendix B states: Page 1 of 1 In cases where TMR service is provided by a generating unit at or near the end of its life and the UCI amount is at zero, return will reflect a reasonable minimum return amount. Request: (a) (b) Response: (a) (b) Is there a specific amount the AESO has in mind for the “reasonable minimum return amount”? If so, please provide the reasonable minimum return amount and the rationale for it. If not please explain how the AESO will determine this amount. Does the AESO agree fully depreciated generation units, while they could be retired due to limited value in energy markets, may still retain significant capacity benefits to the transmission system and should be compensated accordingly? Please refer to FIRM.AESO-018 (a). Agreed in part. Compensation would be considered on a case by case basis if an owner advised of a pending unit decommissioning and the capacity was required to maintain the reliability of the transmission system.