MIS3535 Progress Report Project Team #: Flanagan 2 – Doyle 3 Team Members: PMs: Stephanie Kilroy, Arren Soroko, Sandra Brown, John Illuminati, Evan Bedor, Melissa Aguilar-Ramirez; BAs: Tyler DiBetta, Trang Nguyen, Michael Paszkiewicz Reporting Period From: 10.18.2014 Overall Project Status: To: 10.24.2014 On Track / At Risk Deliverables: Work Completed: Task Name Date Completed Summary Notes 1. Project Schedule 2. Interview #1 Questions 3. Risk Management Plan 09.10.2014 09.11.2014 09.17.2014 4. Communications Plan 09.17.2014 5. Quality Management Plan 09.17.2014 6. 7. 8. 9. 10. 11. 09.17.2014 09.23.2014 09.24.2014 10.06.2014 10.13.2014 10.13.2014 Shows all tasks and resources assigned Questions were very broad Identifies risks and how they will be dealt with Defines communication goals and strategies Documents the information required to effectively manage project quality Tracks any changes made to the project Questions were more specific BAs combined individual scopes Questions were much better Lists all of the stakeholders & their roles Diagram showing structure of team and relationships & links between members Shows who is Responsible, Accountable, Consulted, and/or Informed for tasks An updated version of the budget; still needs to be implemented into Project Change Management Plan Interview #2 Questions Scope Document Interview Questions #3 List of Stakeholders Organization Chart 12. RACI Chart 10.13.2014 13. Revised Budget 10.22.2014 1 MIS3535 1. 2. 3. 4. Work in Progress: Task Name Planned End Date Resources Assigned Project Charter Scope Revision Schema Prototype #1 10.08.2014 10.08.2014 10.29.2014 10.29.2014 Stephanie All PMs All BAs All BAs Work Schedule to begin: Task Name Planned Start Date 1. Project Issues Descriptions Actions 1. BAs struggling with Justinmind Provide assistance on extra credit assignments and prototypes 2. Lack of MS Project experience Spend time to learn the program and utilize it in our project Project Risks: Description 1. Lack of urgency 2. Staying on schedule Actions Resolved by weekly meetings & discussion expectations Assist the BAs in fully understanding Justinmind and make sure the prototype satisfies business requirements Meetings Meetings that have taken place: Description Date / Time 1. 2. 3. 4. 5. 6. Kickoff Meeting #1 Kickoff Meeting #2 Weekly Meeting Weekly Meeting Weekly Meeting Weekly Meeting 10.24.2014 @ 4pm Sandi, Melissa, Mike, & Trang Arren, John, Melissa, Mike, & Tyler All PMs and BAs All PMs and BAs All PMs and BAs PMs: Arren, Evan, John, Stephanie; BAs: all All PMs and BAs Planned Meetings: Description Date / Time Attendees Weekly Meeting Weekly Meeting Weekly Meeting Weekly Meeting Weekly Meeting Weekly Meeting 10.31.2014 @ 4pm 11.07.2014 @ 4pm 11.14.2014 @ 4pm 11.21.2014 @ 4pm 11.28.2014 @ 4pm 12.05.2014 @ 4pm All PMs and BAs All PMs and BAs All PMs and BAs All PMs and BAs All PMs and BAs All PMs and BAs 7. Weekly Meeting 1. 2. 3. 4. 5. 6. 09.09.2014 @ 4pm 09.10.2014 @ 11am 09.26.2014 @ 4pm 10.03.2014 @ 4pm 10.10.2014 @ 4pm 10.20.2014 @ 4pm Attendees 2