MIS3535 Progress Report Project Team #: Flanagan 2 – Doyle 3 Team Members: PMs: Stephanie Kilroy, Arren Soroko, Sandra Brown, John Illuminati, Evan Bedor, Melissa Aguilar-Ramirez; BAs: Tyler DiBetta, Trang Nguyen, Michael Paszkiewicz Reporting Period From: 11.01.2014 Overall Project Status: To: 11.07.2014 On Track / At Risk Deliverables: Work Completed: Task Name Date Completed Summary Notes 1. Project Schedule 2. Problem Statement 3. Project Charter 09.10.2014 09.10.2014 09.10.2014 4. Work Breakdown Structure 09.10.2014 5. Interview #1 Questions 6. Risk Management Plan 09.11.2014 09.17.2014 7. Communications Plan 09.17.2014 8. Quality Management Plan 09.17.2014 9. 10. 11. 12. 13. 09.17.2014 09.23.2014 09.24.2014 10.06.2014 10.08.2014 Shows all tasks and resources assigned Defines the problem to be solved States that the project exists and has authorization from the PMs to begin work Organizes the team’s work into manageable sections Questions were very broad Identifies risks and how they will be dealt with Defines communication goals and strategies Documents the information required to effectively manage project quality Tracks any changes made to the project Questions were more specific BAs combined individual scopes Questions were much better Statement of scope, objectives, and participants in the project Change Management Plan Interview #2 Questions Scope Document Interview Questions #3 Project Charter 1 MIS3535 14. Scope Revision 10.08.2014 15. List of Stakeholders 16. Organization Chart 10.13.2014 10.13.2014 17. RACI Chart 10.13.2014 18. Revised Budget 10.22.2014 19. Critical Path 10.29.2014 20. Prototype #1 10.29.2014 21. Use Case 10.29.2014 22. Prototype #2 11.05.2014 23. Persona/Story 11.05.2014 24. Revised RM Plan 11.12.2014 25. Business Rules 11.12.2014 26. Prototype #3 11.12.2014 27. Data Schema 11.12.2014 28. Revised Comm. Mgmt. Plan 11.19.2014 29. Revised Change Mgmt. Plan 11.19.2014 30. Prototype #4 11.19.2014 Revised scope based on professor’s comments and critique. Lists all of the stakeholders & their roles Diagram showing structure of team and relationships & links between members Shows who is Responsible, Accountable, Consulted, and/or Informed for tasks An updated version of the budget; still needs to be implemented into Project Integrated project into MS Project, used to determine critical path First draft of the Justinmind; focused on front-end rather than back-end Defines how users can use the prototype Some front-end changes as well as working on making it functional Layout of what the presentation will be like, and a persona to have a character in mind for the presentation The plan is now 1 page and meets all of the requirements Specifies all of the rules that must be followed for the project The prototype’s design looks great. They are still working on the functional aspects and making sure that it meets and professor’s requirements and business rules. States all of the data masters and attributes for each of them within the prototype. Meets the requirements for the document. Will make some revisions based on class critique. Still needs a lot of work to be done on it. Will be further revised based on class critique. The design looks fantastic. Still some functional issues to work on, but that shouldn’t be an issue. 2 MIS3535 Work in Progress: Task Name 1. Prototype #5 2. Presentation 3. Finished Deliverables Work Schedule to begin: Task Name Planned End Date Resources Assigned 12.03.2014 12.03.2014 12.01.2014 All BAs All BAs All PMs Planned Start Date 1. No more future tasks. Project Issues Descriptions Actions 1. None; we are in good shape Project Risks: Description 1. Staying on schedule Actions Specify where the BAs should be at the end of each week. The PMs know how long each task should take. Meetings Meetings that have taken place: Description Date / Time 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Kickoff Meeting #1 Kickoff Meeting #2 Weekly Meeting Weekly Meeting Weekly Meeting Weekly Meeting Weekly Meeting Justinmind Help Weekly Meeting Weekly Meeting Weekly Meeting 12. Weekly Meeting Planned Meetings: Description 1. Weekly Meeting 2. Weekly Meeting 09.09.2014 @ 4pm 09.10.2014 @ 11am 09.26.2014 @ 4pm 10.03.2014 @ 4pm 10.10.2014 @ 4pm 10.20.2014 @ 4pm 10.24.2014 @ 4pm 10.27.2014 @ 11am 10.31.2014 @ 4pm 11.07.2014 @ 4pm 11.14.2014 @ 4pm Attendees 11.21.2014 @ 4pm Sandi, Melissa, Mike, & Trang Arren, John, Melissa, Mike, & Tyler All PMs and BAs All PMs and BAs All PMs and BAs Arren, Evan, John, Stephanie, & all BAs All PMs and BAs John, Arren, & all BAs All PMs and BAs All PMs and BAs, except Tyler PMs: John, Evan, Stephanie, Melissa; BAs: Trang, Michael All PMs and BAs Date / Time Attendees 11.28.2014 @ 4pm 12.05.2014 @ 4pm All PMs and BAs All PMs and BAs 3