Photolithography Area Status Friday ,July 06 , 2012 General Information / Lab Activities Mahnaz Out LOA 5-31?? Gary Is out Today 07/06/2012 Good morning All. Here is the morning Litho status report. Please check back in Coral for latest tool updates and current equipment status. Thanks... The Litho Team Old Issues- Ongoing ASML Stepper-Problem: Process restriction- Do not expose any wafers with thick resist, 3.0um and above(220-3 and 220-7 resists) until further notice. The purge/extraction hood has been removed for repair by ASML. YES Oven- Intermittent pumpdown problem. Fails to achieve setpoint. Replaced valve stem/seat for N2 purge. Replace pump on 7/2. Monitoring system Zygo- Problem: User "mcherry" reports that the CD drawer is not opening. Installed a replacement drive but software does not recognize. Need to look at system setup Exposure Tools Status Comments ASML Stepper DOWN ASML Work In Progress EVAlign Problem Intermitent Joystick Issues EVAlign2 UP EVG-Imprint Problem Karl Suss 1 UP Karl Suss 2 UP Manual Coaters Status EVGSpraycoat Up Headway Up Laurel UP Coaters Process Status Tool Idle Til Needed Priority 4 SVGCoat SVGCoat2 3612 Process Up 3617 Process Up 220-7 Process Up 3612 Process Up 955-0.7 Process Up 220-3 Process Up Developers Status SVGDEV UP SVGDEV2 UP Ovens / Hotplates Status BLUEM UP Blue M 90 C. UP Blue M 110 C UP Blue M 150 C UP Fusion UP UV-Cure UP White-Oven UP YES Vapor Prime Problem Hotplates- Laurel-left UP Laurel- right UP Headway UP Wenesco - left UP 90 Deg C UP 115 Deg C UP Wenesco - Right UP Metrology/Inspection Status AFM UP Alpha-Step 500 UP Nanospec 2-Litho UP Nanospec 1-Etch UP P2 Profiler UP Microscpoes- #1 Leica/Analytical UP #2 Ergolux/Drytek2 UP Intermitent Vacuum Problem 1 #3 Olympus/Litho UP #4 Nikon Optiphot/Litho UP #5 Nikon/Litho UP #6 Leitz/Bosch UP #7 Leitz/Diffusion UP #8 Olympus/Litho UP #9 Olympus/Litho UP Miscellaneous Status EVBond Problem KSBonder UP Flags Are Stiff 2 DOWN KSCoat Litho SRD Robot Vacuum UP DOWN Zygo CD Drawer Not Recognized 3