MIS3535 Progress Report Project Team #: Moustafellos 3 – Doyle 2 Team Members: PM’s: Andrew Tauskey, Andre Messa, Anne Buckley, James Brunetto, and Daniel Vessal. BA’s: Matthew Johnson, Nicholas Robinson, Hyun Woo Lee, Cassandra Borek, and Sean Carpenter. Reporting Period From: October 3rd To: October 10th Overall Project Status: On Track / At Risk Deliverables: 1. 2. 3. 1. 2. 3. 4. Work Completed: Task Name Date Completed Summary Notes Preparation for interviews Scope Review Business Rules 9/10, 10/6 9/20 10/1 Gave more specific questions Combination of all BA’s individual docs Clearer definition of what is needed Work in Progress: Task Name Planned End Date Resources Assigned Completed Scope doc JIM Review Assist Prototyping All PM Deliverables (first draft) 10/10 ongoing ongoing 10/13 Anne and Dan James, Andre All PMs All PMs Work Schedule to begin: Task Name Planned Start Date 1. Scenario 2. Data Schema 3. Prototyping 10/20 10/25 10/13 1 MIS3535 Project Issues Descriptions 1. Meeting Times 2. Communication Actions Coordinating everyone’s schedules Starting Group chat via app GroupMe, set the expectations Project Risks: Description Actions 1. Little experience e-commerce Researching valuable e-commerce solutions 2. Lack of trust We have emphasized that we are there for the BAs Meetings 1. 2. 3. 4. 5. 6. 7. Meeting that have taken place: Description Date / Time Attendees Kickoff Meeting Meeting w/ BA’s PM Meeting PM/BA Meeting PM Meeting PM/BA Meeting PM Meeting 9/10 9/22 9/22 9/29 9/29 10/6 10/6 Andre, Anne, BA’s Andre, James, Dan, Matt, BA’s All PM’s Andre, James, Andrew, Bas All PM’s Andre, James, Andrew, Bas All PM’s Planned Meetings: Description Date / Time Attendees 5:30 All BA’s and selected PM’s 1. Monday Recurring 2