ISAC Target Reliability from
Design to Implementation to
Long Term Service
Violeta Toma
WAO 2012
Accelerating Science for Canada
Un accélérateur de la démarche scientifique canadienne
Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada
Propriété d’un consortium d’universités canadiennes, géré en co-entreprise à partir d’une contribution administrée par le Conseil national de recherches Canada
Overview
• Introduction to ISAC
• Past: Phase I – on-line testing
• one target module
• more target modules
• Present: Phase II – off line testing
• ISAC target life cycle
• Future: Phase III – remote connect &
disconnect
August 2012
Violeta Toma
WAO 2012
2
ISAC
ISAC =
Isotope
Separation
and
Acceleration
August 2012
Violeta Toma
WAO 2012
3
Phase one
•Two target stations
•One target module
August 2012
Violeta Toma
WAO 2012
4
ISAC Target Life Cycle
Machine shop
6 -12 months
August 2012
Violeta Toma
WAO 2012
5
ISAC Target Life Cycle
Machine shop
6 -12 months
August 2012
Target (material)
1 – 8 weeks
Violeta Toma\
WAO 2012
6
ISAC Target
Target and target tube
August 2012
Violeta Toma
WAO 2012
7
ISAC Target Life Cycle
Machine shop
6 – 12 months
August 2012
Target material
1-8 weeks
Target assembly
and baking
5 days
Violeta Toma
WAOP 2012
8
ISAC Target
•
In house made target
1 -8 weeks
•
Target assembly
&baking
5 days
August 2012
Violeta Toma
WAO 2012
9
ISAC Target Life Cycle
Machine shop
6 -12 months
Target material
1 – 8 weeks
Target assembly
and baking
5 days
Test stand
1 week
August 2012
Violeta Toma
WAO 2012
10
ISAC Target
August 2012
Violeta Toma
WAO 2012
11
ISAC Target Life Cycle
August 2012
Violeta Toma
WAO 2012
12
Test stand
Target assembly goes to the
Test stand.
August 2012
Violeta Toma
WAO 2012
13
ISAC Target Life Cycle
Machine shop
6 -12 months
Target material
1 – 8 weeks
Test stand
1 week
Target installed in
Target Module
2 days
August 2012
Target assembly
and baking
5 days
Violeta Toma
WAO 2012
14
ISAC Target
Hot Cell (HC) – Target remote
installation into the Target
Module (TM)
August 2012
Violeta Toma
WAO 2012
15
ISAC Target Module
August 2012
Violeta Toma
WAO 2012
16
ISAC Target Life Cycle
Machine shop
6 -12 months
Target material
1 – 8 weeks
Target assembly
and baking
5 days
Test stand
1 week
Target installed in
Target Module
2 days
Conditioning
Station
2 days
August 2012
Violeta Toma
WAO 2012
17
Conditioning station
August 2012
Violeta Toma
WAO 2012
18
ISAC Target Life Cycle
Machine shop
6 -12 months
Target material
1 – 8 weeks
Target assembly
and baking
5 days
Test stand
1 week
Target installed in
Target Module
2 days
Conditioning
Station
2 days
Target preparations
for production
2 days
Beam Delivery
2-4 weeks
August 2012
Post mortem
analysis and storage
Violeta Toma
WAO 2012
19
Beam on Target
Target tube
Ionizer tube
Proton beam
August 2012
Violeta Toma
WAO 2012
20
Phase I & II
Machine shop
6 -12 months
Target material
1 – 8 weeks
Target assembly
and baking
5 days
Test stand
1 week
Target installed in
Target Module
2 days
Conditioning
Station
2 days
Target preparations
for production
2 days
Beam Delivery
2-4 weeks
August 2012
Post mortem
analysis and storage
Violeta Toma
WAO 2012
21
Documenting & Improving
• Target travel document
• Learn from failures
• Learn from success
• Standardized parts
• Dedicated target reliability engineer
August 2012
Violeta Toma
WAO 2012
22
Phase III
• Present: manual connect/disconnect
• Cool- down for one week after beam off
• Beam off during manual dis/re-connect
• Personnel dose
• Future: remote connect/disconnect
• No cool-down necessary
• Dis/Re-connect can be done while delivering
beam from the other station
• No dose to personnel
August 2012
Violeta Toma
WAO 2012
23
Manual Target Disconnect/Connect
August 2012
Violeta Toma
WAO 2012
24
Beam Availability
Machine shop
6 -12 months
Target material
1 – 8 weeks
Target assembly
and baking
5 days
Test stand
1 week
TRG installed in
Target Module
2 days
Conditioning
Station
2 days
Target preparations
for production
2 days
Beam Delivery
2-3 weeks
August 2012
Post mortem
analysis and storage
Violeta Toma
WAO 2012
25
ISAC Target
• Problems:
• Manufacturing problems
• During baking:
• Target legs warping
• Target tube warping
• During conditioning
• Electrical short
• Vacuum leaks
• Water leaks
August 2012
Violeta Toma
WAO 2012
26
Summary
• Phase I => II
• Gain: ~ 9 days beam
availability and
improved reliability
• Phase II => III
• Gain: ~11 days
beam availability
and further improved
reliability
August 2012
Violeta Toma
WAO 2012
27
Canada’s national laboratory for particle and nuclear physics
Laboratoire national canadien pour la recherche en physique nucléaire
et en physique des particules
Thank you!
Merci!
Questions?
Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada
Propriété d’un consortium d’universités canadiennes, géré en co-entreprise à partir d’une contribution administrée par le Conseil national de recherches Canada
TRIUMF: Alberta | British Columbia |
Calgary Carleton | Guelph | Manitoba |
McMaster Montréal | Northern British
Columbia | Queen’s Regina | Saint Mary’s |
Simon Fraser | Toronto Victoria | Winnipeg
| York
July 2, 2016
Presentation Title
29