The Schoharie Bridge Collapse Group 18 Introduction Constructed in early 1950’s 165m span comprising of 5 simple spans Two Piers on shallow footings in Schoharie Creek Two Piers on creek banks Collapsed in 1987 Pier Section 112.5' 27.75' 57' 27.75' Symmetrical about C L Deck Stringer at 8'-6" o.c. Floor Beam at approx. 20' o.c. Knee Brace Main Girder Cantilever Floor Beam Ends Bearing 7'-0" sq Column 5'-0" wide X10'-0" deep Tie Beam Column Plinth Reinforcement Plinth Footing Figure 1 - Pier Section ( after "Collapse," 1987 ) Plan of Bridge Sloped Embankment NORTH Riprap Sloped Embankment East Abutment West Abutment Flow PIER 1 100' SPAN1 PIER 2 110' SPAN2 PIER 4 PIER 3 120' SPAN3 110' SPAN4 100' SPAN5 Figure 2 - Schematic plan of bridge ( after "Collapse," 1987 ) Summary of Events 1954: Construction completed 1955: Bridge survived 100 year flood Vertical cracks began to appear in Pier Plinths 1957: Plinth reinforcement added and other minor problems corrected 1987: Bridge Collapsed The Collapse The Bridge collapsed on April 5 1987 during an estimated 50 year flood Pier 3 was the first to fail This caused the collapse of span 3 and span 4 Sloped Embankment NORTH Riprap Sloped Embankment East Abutment West Abutment Flow PIER 1 100' SPAN1 PIER 2 110' SPAN2 PIER 4 PIER 3 120' SPAN3 110' SPAN4 100' SPAN5 Figure 2 - Schematic plan of bridge ( after "Collapse," 1987 ) The Collapse Pier 2 and Span 2 fell ninety minutes after Span 3 had dropped 10 people were killed Sloped Embankment NORTH Riprap Sloped Embankment East Abutment West Abutment Flow PIER 1 100' SPAN1 PIER 2 110' SPAN2 PIER 4 PIER 3 120' SPAN3 110' SPAN4 100' SPAN5 Figure 2 - Schematic plan of bridge ( after "Collapse," 1987 ) The Collapse Collapse of Span 2 Cause of Collapse Shallow footings were not deep enough to resist scour Pier 3 was bearing on erodable soil Riprap (Broken stones for protection of Piers) had not been adequately maintained Area around footing had been backfilled with erodable soil, not Riprap Original Riprap layer is thought to have been moved during the 100 year storm of 1955 Cofferdams used for pier construction had been removed, contrary to designers’ specifications Plinths were initially under reinforced and the additional reinforcement added wasn’t adequately anchored and contributed to sudden, brittle failure Human Factors Contributing to Disaster Design Documents did not clearly state that cofferdams were to be left in place Under reinforcement of plinths An inexpert state employee deleted all reference to new Riprap in a maintenance contract in 1980 Lessons Learnt Piles could have been used for footings in order to resist scour Cofferdams should have been left in place The use of a continuous span rather than 5 simple spans would have provided redundancy once pier 3 failed Critical features that could have led to collapse such as pier footings should have been identified, inspected regularly and maintained