Presentation1.ppt

advertisement

L’Ambiance Collapse

Group 15

David Lawlor

Emma Quinn

Daniel O’Sullivan

Cian O’Sullivan

Introduction

Bridgeport, Connecticut

April 23, 1987

Sixteen-story building, Thirteen apartment levels, topping three parking levels

Consisted of two offset rectangular towers

Elevator

Design

Seven inch thick posttensioned, concrete slabs

Steel columns comprised its Structural Frame

Lift-Slab method of construction

Hydraulic lifting apparatus used to put slabs into position

Two shear walls in each tower – Lateral

Resistance (except top two floors)

Collapse

Building little more than halfway completed

First the West Tower, then the East

Took five seconds for entire building to collapse

28 construction workers died in collapse

Unusually prompt legal settlement ended all investigations

Consequently – the exact cause of the collapse has never been established

Number of deficiencies – which was the trigger?

Theory 1

National Bureau of Standards (NBS)

“An overloaded steel angle welded to a shearhead arm channel deformed, causing the jack rod and lifting nut to slip out and the collapse to begin”

Theory 2

Thornton-Tomasetti Engineers

“The instability of the wedges holding the twelfth floor and roof package caused the collapse”

Theory 3

Schupack Suarez Engineers Inc

“The improper design of the posttensioning tendons caused the collapse”

General Layout of Posttensioning

Theory 4

Occupational Safety and Health

Administration (OSHA)

“Questionable weld details and substandard welds could have caused the collapse”

Theory 5

Failure Analysis Associates (FaAA)

“The sensitivity of L’ambiance Plaza to lateral displacement caused its collapse”

Wedged Slab-to-Column Connection

Other factors contributing to disaster

Gross negligence on part on management

Variations in control of lifting operations

Cutting corners to save money (use of broken rock fill under certain footinginstead of direct bearing on rock)

Building regulations not adhered to for innovative “lift-slab” method

Conclusions

Insure lateral stability and safety during construction when using lift-slab method

Responsibility for each aspect of design should be clearly allocated

Ensure a high standard of structural safety during construction by constant monitoring by engineer

Independent Engineers from building authorities to check progress

Download