Software Engineering: A Practitioner’s Approach Chapter 25 Process and Project Metrics copyright © 1996, 2001, 2005 R.S. Pressman & Associates, Inc. For University Use Only May be reproduced ONLY for student use at the university level when used in conjunction with Software Engineering: A Practitioner's Approach. Any other reproduction or use is expressly prohibited. 1 Until you can measure something and express it in numbers, you have only the beginning of understanding. - Lord Kelvin 2 Until you can measure something and express it in numbers, you have only the beginning of understanding. - Lord Kelvin Non-software metrics you use everyday: - Gas tank scale - Speedometer - Thermostat in your house - Battery monitor in your laptop What would happen if instead these were not numeric? What other examples do you have? Gas Tank ☐A Lot ☐Some A little 3 Until you can measure something and express it in numbers, you have only the beginning of understanding. - Lord Kelvin The problem is non-numeric measurements are subjective… they mean different things to different people. Numbers are objective… they mean the same thing to everyone! When your friend says “oh yeah, John/Jane Doe is super attractive, you should go out with him/her”… that is a subjective measurement… so, you ask “Send me a photo”. Why? Because the subjective term “super attractive” has vastly different meanings for different people! 4 Coming up: Metrics for software Metrics for software When asked to measure something, always try to determine an objective measurement. If not possible, try to get as close as you can! 5 Coming up: A Good Manager Measures A Good Manager Measures process process metrics project metrics measurement product metrics product What do we use as a basis? • size? • function? 6 Coming up: We need a basis to say 20 defects per X lines of code. Why is this important? We need a basis to say 20 defects per X lines of code. Why is this important? A Because lines of code equals cost B We want our metrics to be valid across projects of many sizes C Because you just caused me to die in God of War III… stop asking these questions! D Because this helps up understand how big our program is 7 Coming up: Why Do We Measure? Why Do We Measure? assess the status of an ongoing project track potential risks uncover problem areas before they go “critical,” adjust work flow or tasks, evaluate the project team’s ability to control quality of software work products. 8 Coming up: Process versus Project Metrics Process versus Project Metrics Process Metrics - Measure the process to help update and change the process as needed across many projects Project Metrics - Measure specific aspects of a single project to improve the decisions made on that project Frequently the same measurements can be used for both purposes 9 Coming up: Process Measurement Process Measurement We measure the efficacy of a software process indirectly. That is, we derive a set of metrics based on the outcomes of the process Outcomes include measures of errors uncovered before release of the software defects delivered to and reported by end-users work products delivered (productivity) human effort expended calendar time expended schedule conformance many others… We also derive process metrics by measuring the characteristics of specific software engineering tasks. 10 Coming up: Process Metrics Guidelines Process Metrics Guidelines Use common sense and organizational sensitivity when interpreting metrics data. Provide regular feedback to the individuals and teams who collect measures and metrics. Don’t use metrics to appraise individuals. Work with practitioners and teams to set clear goals and metrics that will be used to achieve them. Never use metrics to threaten individuals or teams. Metrics data that indicate a problem area should not be considered “negative.” These data are merely an indicator for process improvement. Don’t obsess on a single metric to the exclusion of other important metrics. 11 Coming up: If I calculate the number of defects per developer and rank them, then using that rank assign salary raises based on that. If I calculate the number of defects per developer and rank them, then using that rank assign salary raises based on that. A. This is good B. This is bad 12 Coming up: Software Process Improvement Software Process Improvement Process model Process improvement recommendations Improvement goals Process metrics SPI Make your metrics actionable! 13 Coming up: Typical Process Metrics Typical Process Metrics Quality-related focus on quality of work products and deliverables Productivity-related •Correctness Production of work-products related to effort expended •Maintainability Statistical SQA data•Integrity •Earned Value Analysis •Usability error categorization & analysis Defect removal efficiency propagation of errors from found process activity to activity Defects this (1-5) stage •Severity of in errors Reuse data --------------------------------------•MTTF (Mean time to failure) This Stage + Next Stage The number of components produced andtotheir degree of reusability •MTTR (Mean time repair) Within a single project this can also be a “project metric”. Across projects this is a “process metric”. Coming up: Can you calculate a metric that records the number of ‘e’ that appear in a program? A. Yes B. No 14 Can you calculate a metric that records the number of ‘e’ that appear in a program? A. Yes B. No Should you calculate the number of ‘e’ in a program? A. Yes B. No 15 Coming up: Effective Metrics (ch 16) Effective Metrics (ch 16) Simple and computable Empirically and intuitively persuasive Consistent and objective Consistent in use of units and dimensions Programming language independent Should be actionable 16 Coming up: Effective Metrics- Baseball On Base Percentage Effective Metrics- Baseball On Base Percentage Simple and computable Empirically and intuitively persuasive Consistent and objective Consistent in use of units and dimensions Programming language independent Should be actionable 17 Coming up: Effective Metrics- Baseball Runs Batted In Effective Metrics- Baseball Runs Batted In Count of times when the outcome of player’s at-bat results in a run being scored Simple and computable Empirically and intuitively persuasive Consistent and objective Consistent in use of units and dimensions Programming language independent Should be actionable 18 Coming up: Actionable Metrics Actionable Metrics Actionable metrics (or information in general) are metrics that guide change or decisions about something Actionable: Measure the amount of human effort versus use cases completed. Too high: more training, more design, etc… Very low: maybe we can shorten the schedule Not-Actionable: Measure the number of times the letter “e” appears in code Think before you measure. Don’t waste people’s time! Coming up: Project Metrics 19 Project Metrics used to minimize the development schedule by making the adjustments necessary to avoid delays and mitigate potential problems and risks used to assess product quality on an ongoing basis and, when necessary, modify the technical approach to improve quality. every project should measure: Inputs —measures of the resources (e.g., people, tools) required to do the work. Outputs —measures of the deliverables or work products created during the software engineering process. Results —measures that indicate the effectiveness of the deliverables. 20 Coming up: Typical Project Metrics Typical Project Metrics Effort/time per software engineering task Errors uncovered per review hour Scheduled vs. actual milestone dates Changes (number) and their characteristics Distribution of effort on software engineering tasks Actionable: What do you do if it’s too high/low? 21 Coming up: Metrics Guidelines Metrics Guidelines Use common sense and organizational sensitivity when interpreting metrics data. Provide regular feedback to the individuals and teams who have worked to collect measures and metrics. Don’t use metrics to appraise individuals. Work with practitioners and teams to set clear goals and metrics that will be used to achieve them. Never use metrics to threaten individuals or teams. Metrics data that indicate a problem area should not be considered “negative.” These data are merely an indicator for process improvement. Don’t obsess on a single metric to the exclusion of other important metrics. Same as process metrics guidelines Coming up: Typical Size-Oriented Metrics 22 Typical Size-Oriented Metrics errors per KLOC (thousand lines of code) defects per KLOC $ per LOC pages of documentation per KLOC errors per person-month Errors per review hour LOC per person-month $ per page of documentation 23 Coming up: Typical Function-Oriented Metrics Typical Function-Oriented Metrics errors per Function Point (FP) defects per FP $ per FP pages of documentation per FP FP per person-month 24 Coming up: But.. What is a Function Point? But.. What is a Function Point? See Book section 23.2.1 for more detail Function points (FP) are a unit measure for software size developed at IBM in 1979 by Richard Albrecht To determine your number of FPs, you classify a system’s features into five classes: Transactions - External Inputs, External Outputs, External Inquires Data storage - Internal Logical Files and External Interface Files Each class is then weighted by complexity as low/average/high Multiplied by a value adjustment factor (determined by asking questions based on 14 system characteristics Coming up: But.. What is a Function Point? 25 But.. What is a Function Point? Count Low Average High External Input x3 x4 x6 External Output x4 x5 x7 External Inquiries x3 x4 x6 Internal Logic Files x7 x10 x15 External Interface Files x5 x7 x10 Total Unadjusted Total: Value Adjustment Factor: Total Adjusted Value: Coming up: Function Point Categories 26 Function Point Categories External Inputs (EI) - Info coming into the system External Outputs (EO) - provides derived info out of a system (use ILF and EIF to create information) External Inquiries - provides non-derived information out of the system (echoes back EI) Internal Logical Files (ILF) - Think structures in RAM, datafiles ONLY updated based on EI External Files - Think database, datafile updated by this code, but also other systems 27 Coming up: Function Point Example Function Point Example http://www.his.sunderland.ac.uk/~cs0mel/Alb_Example.doc 28 Coming up: Comparing LOC and FP Comparing LOC and FP Programming Language Ada Assembler C C++ COBOL Java JavaScript Perl PL/1 Powerbuilder SAS Smalltalk SQL Visual Basic LOC per Function point avg. median low high 154 337 162 66 315 109 53 104 91 33 29 205 694 704 178 77 63 58 60 78 32 40 26 40 47 77 53 63 67 31 41 19 37 42 14 77 42 22 11 33 10 7 16 400 75 263 105 49 55 110 158 Representative values developed by QSM Coming up: At IBM in the 70s or 80s (I don’t remember) they paid people per line-of-code they wrote 29 At IBM in the 70s or 80s (I don’t remember) they paid people per lineof-code they wrote What happened? A. The best programmers got paid the most B. The worst programmers got paid the most C. The sneakiest programmers, got paid the most D. The lawyers got paid the most 30 Coming up: Why opt against LOC? Why opt against LOC? LOC is not programming language independent LOC cannot use readily countable characteristics that are determined early in the software process LOC “penalizes” inventive (short) implementations that use fewer LOC that other more clumsy versions Other metrics makes it easier to measure the impact of reusable components (screen, widgets, etc…) Other options: COCOMO, Planning Poker, SLIM, Story Points (remember Scrum?), many others… 31 Coming up: Object-Oriented Metrics Object-Oriented Metrics Number of scenario scripts (use-cases) Number of support classes (required to implement the system but are not immediately related to the problem domain) Average number of support classes per key class (analysis class) Number of subsystems (an aggregation of classes that support a function that is visible to the end-user of a system) 32 Coming up: WebEngineering Project Metrics WebEngineering Project Metrics Number of static Web pages (the end-user has no control over the content displayed on the page) Number of dynamic Web pages (end-user actions result in customized content displayed on the page) Number of internal page links (internal page links are pointers that provide a hyperlink to some other Web page within the WebApp) Number of persistent data objects Number of external systems interfaced Number of static content objects Number of dynamic content objects Number of executable functions 33 Coming up: Measuring Quality Measuring Quality Correctness — the degree to which a program operates according to specification non-conformance Maintainability—the degree to whichVerified a program is with reqmts ---------------------------------amenable to change MTTC KLOC time tois change: Integrity—the degree to which aMean program impervious time to analyze, design, to outside attack implement and deploy t=threat probability a change Usability—the degree to which a program is of easy to use s=security = likelihood repelling attack Integrity = 1-(threat*(1-security)) Many options. See ch 12 E.g. t=0.25, s=0.95 --> I=0.99 34 Coming up: Defect Removal Efficiency Defect Removal Efficiency DRE = E /(E + D) E is the number of errors found before delivery of the software to the end-user D is the number of defects found after delivery. 35 Coming up: Defect Removal Efficiency Defect Removal Efficiency DRE = E /(E + D) Defects found during phase: 10/ /(10 (10++20) 20)==33% 33% 10 Requirements (10) 20 / (20 50)rest? = 28% Design (20) What are+the Construction 5 / (5 + 50) = 9% Implementation (5) Unit Testing (50) 50 / (50 + 100) = 33% Testing Integration Testing (100) 100 / (100 + 250) = 28% System Testing (250) 250 / (250 + 5) = 98% Acceptance Testing (5) 5 / (5 + 10) = 33% By Customer (10) 36 Coming up: Metrics for Small Organizations Metrics for Small Organizations time (hours or days) elapsed from the time a request is made until evaluation is complete, tqueue. effort (person-hours) to perform the evaluation, Weval. time (hours or days) elapsed from completion of evaluation to assignment of change order to personnel, teval. effort (person-hours) required to make the change, Wchange. time required (hours or days) to make the change, tchange. errors uncovered during work to make change, Echange. defects uncovered after change is released to the customer base, Dchange. 37 Coming up: Establishing a Metrics Program Establishing a Metrics Program Set Goals Determine indicators for goals Identify your business goals. Identify what you want to know or learn. Identify your subgoals. Identify the entities and attributes related to your subgoals. Formalize your measurement goals. Identify quantifiable questions and the related indicators that you will use to help you achieve your measurement goals. Identify the data elements that you will collect to construct the indicators that help answer your questions. Define Measurements Define the measures to be used, and make these definitions operational. Identify the actions that you will take to implement the measures. Prepare a plan for implementing the measures. 38 Coming up: Metrics give you information! Metrics give you information! Metrics about your process help you determine if you need to make changes or if your process is working Metrics about your project do they same thing Metrics about your software can help you understand it better, and see where possible problems may lurk. Let’s see the complexity measurement (after a few questions…) 39 Coming up: Questions Questions What are some reasons NOT to use lines of code to measure size? What do you expect the DRE rate will be for the implementation (or construction) phase of the software lifecycle? What about for testing? Give an example of a usability metric? According to the chart, Smalltalk is much more efficient than Java and C++. Why don’t we use it for everything? 40 Coming up: References Code Metrics Previously we have been discussing product and process metrics. However, code metrics are used to make your code better Complexity - See CyclomaticComplexity slides Dynamic measurements – Profile Jkaboom Memory – garbage collector, object crerations CPU performance Threading 41 Coming up: Questions References http://www.lansing.lib.il.us/images/baseball_player.gif 42 End of presentation