Facilities Improvements and
Bond Construction Update
Facilities Advisory Committee
Long Beach Community College District
February 3, 2009
EDUCATE  ENGAGE  EMPOWER
1
Agenda





Completed Construction Projects
 PCC Learning Resource Center
 LAC Central Plant
 PCC Central Plant
Current & Upcoming Construction Projects
 LAC South Quad Complex
 LAC Learning Resource Center
 LAC Building A, Student Services Retrofit
 LAC Math Technology Building
 LAC Parking Structure
 LAC Alteon Buildings
 LAC Infrastructure Improvements – Phase 3
 LAC Bldg. Q & R Roof Replacement
 LAC Bldg. P Faculty Restroom Upgrades
 PCC Industrial Tech Phase 1
 PCC MDAB (Multi-Disciplinary Academic Building)
 PCC Building C Retrofit
 District Wide - Master Landscape Plan
 District Wide - Marquee Signage Plan
 Los Coyotes Property
 Upcoming Projects
Recently Completed Facilities Improvements
Planned Phasing of Future Projects
Q&A
2
Completed Construction Projects
PCC Learning Resource Center – Measure E 2002






Construction Complete
Modern Facility with Computer Lab
and Multimedia
Stand alone Data Center. Provides
District IT redundancy
Bridge to building E
Design elements move towards
energy efficiencies
Ribbon cutting held 9/17/08
3
Completed Construction Projects
LAC Central Plant – Measure E 2002
 Construction Complete
 Central Plant equipment, Public
Safety, & Field House for
Athletics
 Public Safety relocated to facility
 Plant startup has commenced
4
Completed Construction Projects
PCC Central Plant – Measure E 2002



Construction Complete
Houses Central Plant
equipment and
Maintenance and
Operations facility
Currently provides
chilled water to the PCC
LRC
5
Current and Upcoming
Construction Projects
South Quad Complex – Measure E 2002


Construction approx. 89%
Complete
Space includes







Approx. 68,000 ASF
32 modern classrooms and labs
38 faculty offices
Executive office suites
Multipurpose room
State of the art Board Room
Substantial completion
anticipated May 2009
6
Current and Upcoming
Construction Projects
LAC/Learning Resource Center – Measure E 2002



Construction 97% Complete
Adds 10,000 ASF to existing
building
Substantial Completion
Anticipated February 2009
7
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008




Design Development phase completed
Adds 4,000 ASF to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
Estimated start of construction end of Summer 2009
8
Current and Upcoming
Construction Projects
LAC Math Technology Building – Measure E 2008
 Completed Schematic Design (June 2008)
 Will house Math and Culinary Arts instructional
program as well as Reprographics
 Estimated start of construction 2011
9
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008






Planning initiated for
approximately 900 Vehicles
To be procured under “Design
Build Delivery” method
Final Design Criteria completed
To be located Southeast corner of
Lot J adjacent to the Verizon
building
Photovoltaic Electrical Generation
Array on top level of structure
Anticipated start of construction
2009
Proposed Math
Technology
Bldg.
Lot J
Proposed Parking
Structure Loc.
Verizon Bldg.
10
Current and Upcoming
Construction Projects
LAC Alteon Buildings – Measure E 2008






Property acquired December
2008
Two structures totaling
75,000 square feet
Potential occupants to be
ACIT, District Warehouse
Facility, ERD, and Foundation
Office
Future occupants and space
use to be determined
Warehouse to be temporarily
located in building 2 (March
2009)
Foundation Offices under
Design Development
11
Current and Upcoming
Construction Projects
LAC Infrastructure Improvement Projects
Measure E 2008





Planning underway with engineers
Completes chilled water lines to
North side of campus
Includes other major utility
upgrades; Reclaimed Water,
Domestic Water, Data, etc.
Existing building HVAC systems to
be upgraded in synch with
infrastructure improvements
Coordinated with modernization,
quick start projects, and Master
Landscape Project
12
Current and Upcoming
Construction Projects
Building “Q” and “R” Roof Replacement
Measure E 2008


Replace existing roof with
modified bitumen roof system.
Existing skylights will be
removed and new skylights will
be installed. Any broken tiles
will be replaced on all perimeter
edging of both buildings.
13
Current and Upcoming
Construction Projects
Building “P” Faculty Restroom Upgrade
Measure E 2008



The scope of this project shall be to
provide two new ADA compliant
restrooms in lieu of the existing staff
restrooms.
Installation of new wall and framing,
redesign layout, finishes, fixtures and
doors.
New fixtures and restroom accessories
will be installed throughout. Finishes
shall match existing building décor.
14
Current and Upcoming
Construction Projects
PCC Industrial Technology Center Phase 1
Measure E 2002





Modern facility houses Welding
Department and other trade
programs
Construction is 51% complete
Replaces existing antiquated
structures
New Northern face of the
campus
Completion anticipated late
summer 2009
15
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) Measure E 2002




90% construction documents submitted
Swing space planning completed 9/2008, construction of swing space starts
Spring 2009
Anticipated start of MDAB construction Summer 2009
To be completed in two phases
16
Current and Upcoming
Construction Projects
PCC Building C Retrofit - Measure E 2008





To be designed by Hill Partnership Architects
Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space to be located on PCC Campus (Bldg. FF)
To be completed concurrently with MDAB project
Anticipated start of construction Spring 2010
17
Current and Upcoming
Construction Projects
District Wide – Master Landscape Plan
Measure E 2008
 Planning completed December 2008
 Plan to be implemented concurrently as each
Bond construction project finalizes
18
Current and Upcoming
Construction Projects
District Wide – Marquee Signage Plan
Measure E 2008
 District Wide Signage Plan complete
 Currently in construction document phase
 Final site location to be determined
19
Current and Upcoming
Construction Projects
Los Coyotes Property - Measure E 2008











Re-design current dirt lot to have 80 parking stalls with new
lighting and drainage. (Early Design phase)
Re-slurry and re-stripe existing asphalt parking lot.
Retrofit hand rails and courtyard entry fencing/gates.
Replace elevator controls to bring them up to new current
standards.
Installation of new automated front door.
Building/Monument Signage & Interior Signage upgrade with
Tenant/Suite names.
Refinish exterior aluminum mullions
Building exterior wood/stucco repairs and painting
2nd floor deck repair/resurfacing.
Building perimeter landscape upgrade.
Replacement of gutters.
20
Current and Upcoming
Construction Projects
Upcoming Projects


LAC
 Carson Street Median Fence Replacement (Going to bid)
 Pool boiler upgrade (Going to bid)
 Replace current heating system with energy efficient
boilers.
 Bldg. F - Conversions of rooms F104 and F106 to new
classroom space.
 Bldg. P – Teachers lounge replace curtains with blinds
PCC
 MM (Design Phase)
 Exterior renovation (Paint, windows, replacement of all
exterior doors)
 Restroom ADA upgrade
 Replace dust collector in carpenter Shop
 Replace ventilation system in Sheet Metal Shop
21
Recently Completed
Facilities Improvements
Facilities Improvements

LAC upgrades:


Building P – Theater Room renovation
Building E –
 Existing partial wall repair
 Add blinds to small classroom

Building F –
 Replaced doors and hardware on Southside


PCC upgrades:


Building J – Completed boiler replacement project
Building BB – Repair wood flooring in room130
District-Wide Energy Efficiency project Phase IIA




Lighting upgrades
HVAC replacement
PCC MM re-roof with Garland cool roof
LAC B & E boiler upgrade
22
Planned Phasing of Future Projects
Currently Planned Schedule

2008-09
 Parking Structure – Design/Build concept
 Anticipate awarding bid Spring 2009
 Moving Warehouse from PCC to Alteon Building at LAC – TBD
 Moving LAC Building A into Swing Space – Summer 2009
 Install portables at PCC for Swing Space – Spring 2009
 LAC/PCC Building Needs Assessment Projects
 Bathroom Improvement Projects
 Quick-Start Projects
 Lighting Projects
 Classroom Improvement Projects
 Infrastructure Projects
 Submit FPP for M/N Project at LAC and MM Project at PCC and
submit IPP for P Building at LAC

Master Landscaping and Signage plans complete
 Marquee signage anticipated to be installed Summer 2009
23
Planned Phasing of Future Projects
Currently Planned Schedule
 2009-10
 Begin construction of Building A at LAC
 Anticipating start at end of Summer 2009
 Begin construction of Buildings CC, DD, and EE at PCC
 Anticipating July/August 2009 start
 Begin Schematic Design for Buildings C and F at LAC
 Submit plans to DSA no later than March 2010
 Begin Master Landscaping and Signage Initiatives
 Continue District Wide Energy Efficiency Improvements
 Phase IIA
 Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool
Cover, Roof replacement, etc
 Phase IIB
 Upcoming advancements include connecting current buildings
to Central Plant infrastructure
24
Planned Phasing of Future Projects
Currently Planned Schedule
 2010-11
 Anticipated Construction completion of Building A
at LAC – Spring 2011
 Submit plans to DSA for Math/Technology Building
at LAC
 Move Buildings C and F programs into Swing
Space (M/N Building) and begin construction –
Spring 2011
 Construction completion of Buildings CC, DD and
EE at PCC
 Begin construction of Buildings AA and BB at PCC
 Anticipating January/February 2011 start
25
Planned Phasing of Future Projects
Currently Planned Schedule
 2011-12
 Begin construction of Math/Technology Building at LAC
 Submit plans to DSA for M/N Building at LAC
 2012-13
 Anticipated Construction completion of Buildings C and
F at LAC – December 2012
 Anticipated Construction completion of
Math/Technology Building at LAC – December 2012
 Begin construction of Buildings M/N at LAC – January
2013
 Anticipated Construction completion of Buildings AA
and BB at PCC – June 2013
26
QUESTIONS &
ANSWERS