Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District February 3, 2009 EDUCATE ENGAGE EMPOWER 1 Agenda Completed Construction Projects PCC Learning Resource Center LAC Central Plant PCC Central Plant Current & Upcoming Construction Projects LAC South Quad Complex LAC Learning Resource Center LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Alteon Buildings LAC Infrastructure Improvements – Phase 3 LAC Bldg. Q & R Roof Replacement LAC Bldg. P Faculty Restroom Upgrades PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building C Retrofit District Wide - Master Landscape Plan District Wide - Marquee Signage Plan Los Coyotes Property Upcoming Projects Recently Completed Facilities Improvements Planned Phasing of Future Projects Q&A 2 Completed Construction Projects PCC Learning Resource Center – Measure E 2002 Construction Complete Modern Facility with Computer Lab and Multimedia Stand alone Data Center. Provides District IT redundancy Bridge to building E Design elements move towards energy efficiencies Ribbon cutting held 9/17/08 3 Completed Construction Projects LAC Central Plant – Measure E 2002 Construction Complete Central Plant equipment, Public Safety, & Field House for Athletics Public Safety relocated to facility Plant startup has commenced 4 Completed Construction Projects PCC Central Plant – Measure E 2002 Construction Complete Houses Central Plant equipment and Maintenance and Operations facility Currently provides chilled water to the PCC LRC 5 Current and Upcoming Construction Projects South Quad Complex – Measure E 2002 Construction approx. 89% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office suites Multipurpose room State of the art Board Room Substantial completion anticipated May 2009 6 Current and Upcoming Construction Projects LAC/Learning Resource Center – Measure E 2002 Construction 97% Complete Adds 10,000 ASF to existing building Substantial Completion Anticipated February 2009 7 Current and Upcoming Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 Design Development phase completed Adds 4,000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Summer 2009 8 Current and Upcoming Construction Projects LAC Math Technology Building – Measure E 2008 Completed Schematic Design (June 2008) Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction 2011 9 Current and Upcoming Construction Projects LAC Parking Structure – Measure E 2008 Planning initiated for approximately 900 Vehicles To be procured under “Design Build Delivery” method Final Design Criteria completed To be located Southeast corner of Lot J adjacent to the Verizon building Photovoltaic Electrical Generation Array on top level of structure Anticipated start of construction 2009 Proposed Math Technology Bldg. Lot J Proposed Parking Structure Loc. Verizon Bldg. 10 Current and Upcoming Construction Projects LAC Alteon Buildings – Measure E 2008 Property acquired December 2008 Two structures totaling 75,000 square feet Potential occupants to be ACIT, District Warehouse Facility, ERD, and Foundation Office Future occupants and space use to be determined Warehouse to be temporarily located in building 2 (March 2009) Foundation Offices under Design Development 11 Current and Upcoming Construction Projects LAC Infrastructure Improvement Projects Measure E 2008 Planning underway with engineers Completes chilled water lines to North side of campus Includes other major utility upgrades; Reclaimed Water, Domestic Water, Data, etc. Existing building HVAC systems to be upgraded in synch with infrastructure improvements Coordinated with modernization, quick start projects, and Master Landscape Project 12 Current and Upcoming Construction Projects Building “Q” and “R” Roof Replacement Measure E 2008 Replace existing roof with modified bitumen roof system. Existing skylights will be removed and new skylights will be installed. Any broken tiles will be replaced on all perimeter edging of both buildings. 13 Current and Upcoming Construction Projects Building “P” Faculty Restroom Upgrade Measure E 2008 The scope of this project shall be to provide two new ADA compliant restrooms in lieu of the existing staff restrooms. Installation of new wall and framing, redesign layout, finishes, fixtures and doors. New fixtures and restroom accessories will be installed throughout. Finishes shall match existing building décor. 14 Current and Upcoming Construction Projects PCC Industrial Technology Center Phase 1 Measure E 2002 Modern facility houses Welding Department and other trade programs Construction is 51% complete Replaces existing antiquated structures New Northern face of the campus Completion anticipated late summer 2009 15 Current and Upcoming Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 90% construction documents submitted Swing space planning completed 9/2008, construction of swing space starts Spring 2009 Anticipated start of MDAB construction Summer 2009 To be completed in two phases 16 Current and Upcoming Construction Projects PCC Building C Retrofit - Measure E 2008 To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. FF) To be completed concurrently with MDAB project Anticipated start of construction Spring 2010 17 Current and Upcoming Construction Projects District Wide – Master Landscape Plan Measure E 2008 Planning completed December 2008 Plan to be implemented concurrently as each Bond construction project finalizes 18 Current and Upcoming Construction Projects District Wide – Marquee Signage Plan Measure E 2008 District Wide Signage Plan complete Currently in construction document phase Final site location to be determined 19 Current and Upcoming Construction Projects Los Coyotes Property - Measure E 2008 Re-design current dirt lot to have 80 parking stalls with new lighting and drainage. (Early Design phase) Re-slurry and re-stripe existing asphalt parking lot. Retrofit hand rails and courtyard entry fencing/gates. Replace elevator controls to bring them up to new current standards. Installation of new automated front door. Building/Monument Signage & Interior Signage upgrade with Tenant/Suite names. Refinish exterior aluminum mullions Building exterior wood/stucco repairs and painting 2nd floor deck repair/resurfacing. Building perimeter landscape upgrade. Replacement of gutters. 20 Current and Upcoming Construction Projects Upcoming Projects LAC Carson Street Median Fence Replacement (Going to bid) Pool boiler upgrade (Going to bid) Replace current heating system with energy efficient boilers. Bldg. F - Conversions of rooms F104 and F106 to new classroom space. Bldg. P – Teachers lounge replace curtains with blinds PCC MM (Design Phase) Exterior renovation (Paint, windows, replacement of all exterior doors) Restroom ADA upgrade Replace dust collector in carpenter Shop Replace ventilation system in Sheet Metal Shop 21 Recently Completed Facilities Improvements Facilities Improvements LAC upgrades: Building P – Theater Room renovation Building E – Existing partial wall repair Add blinds to small classroom Building F – Replaced doors and hardware on Southside PCC upgrades: Building J – Completed boiler replacement project Building BB – Repair wood flooring in room130 District-Wide Energy Efficiency project Phase IIA Lighting upgrades HVAC replacement PCC MM re-roof with Garland cool roof LAC B & E boiler upgrade 22 Planned Phasing of Future Projects Currently Planned Schedule 2008-09 Parking Structure – Design/Build concept Anticipate awarding bid Spring 2009 Moving Warehouse from PCC to Alteon Building at LAC – TBD Moving LAC Building A into Swing Space – Summer 2009 Install portables at PCC for Swing Space – Spring 2009 LAC/PCC Building Needs Assessment Projects Bathroom Improvement Projects Quick-Start Projects Lighting Projects Classroom Improvement Projects Infrastructure Projects Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC Master Landscaping and Signage plans complete Marquee signage anticipated to be installed Summer 2009 23 Planned Phasing of Future Projects Currently Planned Schedule 2009-10 Begin construction of Building A at LAC Anticipating start at end of Summer 2009 Begin construction of Buildings CC, DD, and EE at PCC Anticipating July/August 2009 start Begin Schematic Design for Buildings C and F at LAC Submit plans to DSA no later than March 2010 Begin Master Landscaping and Signage Initiatives Continue District Wide Energy Efficiency Improvements Phase IIA Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc Phase IIB Upcoming advancements include connecting current buildings to Central Plant infrastructure 24 Planned Phasing of Future Projects Currently Planned Schedule 2010-11 Anticipated Construction completion of Building A at LAC – Spring 2011 Submit plans to DSA for Math/Technology Building at LAC Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Spring 2011 Construction completion of Buildings CC, DD and EE at PCC Begin construction of Buildings AA and BB at PCC Anticipating January/February 2011 start 25 Planned Phasing of Future Projects Currently Planned Schedule 2011-12 Begin construction of Math/Technology Building at LAC Submit plans to DSA for M/N Building at LAC 2012-13 Anticipated Construction completion of Buildings C and F at LAC – December 2012 Anticipated Construction completion of Math/Technology Building at LAC – December 2012 Begin construction of Buildings M/N at LAC – January 2013 Anticipated Construction completion of Buildings AA and BB at PCC – June 2013 26 QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER 27