Facilities Improvements and
Bond Construction Update
Facilities Advisory Committee
Long Beach Community College District
December 2, 2008
EDUCATE ENGAGE EMPOWER
1
Agenda
Completed Construction Projects
PCC Learning Resource Center
LAC Central Plant
Current & Upcoming Construction Projects
LAC South Quad Complex
LAC Learning Resource Center
LAC Building A, Student Services Retrofit
LAC Math Technology Building
LAC Parking Structure
LAC Infrastructure Improvements – Phase 3
PCC Central Plant
PCC Industrial Tech Phase 1
PCC MDAB (Multi-Disciplinary Academic Building)
PCC Building C Retrofit
District Wide Building Needs Assessment Projects
Toilet Improvement Projects
Quick-Start Projects
ADA Projects
Lighting Projects
Classroom Improvement Projects
Recently Completed Facilities Improvements
Important Ongoing Initiatives
Planned Phasing of Future Projects
Q&A
2
Completed Construction Projects
PCC Learning Resource Center – Measure E 2002
Construction Complete
Modern Facility with Computer Lab
and Multimedia
Stand alone Data Center. Provides
District IT redundancy
Bridge to building E
Design elements move towards
energy efficiencies
Ribbon cutting held 9/17/08
3
Completed Construction Projects
LAC Central Plant – Measure E 2002
Central Plant equipment, Public
Safety, & Field House for Athletics
Final FF&E installation underway
Plant ready for operation and
awaiting completion of LRC & SQC
Construction Complete
Anticipated startup 12/05/08
4
Current and Upcoming
Construction Projects
South Quad Complex – Measure E 2002
Construction approx. 89%
Complete
Space includes
Approx. 68,000 ASF
32 modern classrooms and labs
38 faculty offices
Executive office
Multipurpose room
State of the art Board Room
Substantial completion
anticipated 1/09
5
Current and Upcoming
Construction Projects
LAC/Learning Resource Center – Measure E 2002
Construction 91% Complete
Adds 10,000 ASF to existing
building
Substantial Completion
Anticipated January 2009
6
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008
Design Development to be submitted this month
Adds 4,000 ASF to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
Estimated start of construction 7/09
7
Current and Upcoming
Construction Projects
LAC Math Technology Building – Measure E 2008
Completed Schematic Design (June 2008)
Currently in Design Development phase
Will house Math and Culinary Arts instructional
program as well as Reprographics
Estimated start of construction 2011
8
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008
Planning initiated for
approximately 900 Vehicles
To be procured under “Design
Build Delivery” method
To be located Southeast corner
of Lot J adjacent to the Verizon
building
Photovoltaic Electrical Generation
Array on top level of structure
Anticipated start of construction
2009
Proposed Math
Technology
Bldg.
Lot J
Proposed Parking
Structure Loc.
Verizon Bldg.
9
Current and Upcoming
Construction Projects
LAC Infrastructure Improvements – Phase 3
Measure E 2008
Planning underway with engineers
Completes chilled water lines to
North side of campus
Includes other major utility
upgrades; Reclaimed Water,
Domestic Water, Data, etc.
Existing building HVAC systems to
be upgraded in synch with
infrastructure improvements
Coordinated with modernization
and quick start projects
10
Current and Upcoming
Construction Projects
PCC Central Plant – Measure E 2002
Houses Central Plant
equipment and
Maintenance and
Operations facility
Construction
Approximately 99%
Complete
Currently provides
chilled water to the PCC
LRC
11
Current and Upcoming
Construction Projects
PCC Industrial Technology Center Phase 1
Measure E 2002
Modern facility houses
Welding Department and
other trade programs
Construction is 45%
complete
Replaces existing
antiquated structures
New Northern face of the
campus
Completion anticipated
summer 2009
12
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) Measure E 2002
90% construction documents submitted
Swing space planning completed 9/2008, construction of swing space starts
Spring 2009
Anticipated start of MDAB construction Summer 2009
To be completed in two phases
13
Current and Upcoming
Construction Projects
PCC Building C Retrofit - Measure E 2008
To be designed by Hill Partnership Architects
Houses the Fitness Center, Gymnasium, Weight
Room, and Faculty and Staff Offices
Swing space to be located on PCC Campus (TBD)
To be completed concurrently with MDAB project
Anticipated start of construction Spring 2010
14
Current and Upcoming
Construction Projects
District Wide Building Needs Assessment Project
Measure E 2008
Toilet Improvement
Projects
Quick-Start Projects
ADA Projects
15
Current and Upcoming
Construction Projects
District Wide Building Needs Assessment Projects
Measure E 2008
Lighting Projects
Classroom Improvement Projects
16
Recently Completed
Facilities Improvements
Building “B” and “E” Boiler Replacement
Replaced existing boilers, pumps,
expansion tanks and common
flue with new equipment via
helicopter lift.
A newly upgraded design
reflecting a mechanical
engineered system was installed
improving the efficiency of the
boilers.
Completed 10/2008
17
Recently Completed
Facilities Improvements
Additional Facilities Improvements
LAC upgrades:
Veteran’s Stadium scoreboard and PA system upgrade
Building K upgrades – Exterior door paint, room 111 floor
refinishing
PCC upgrades:
Building AA – Built wall for information desk, installed carpet, and
power upgrades
Building BB – Carpet and window blind installation
Building CC – Installed fans in gym
Building DD – Carpet and window blind installation
Building EE – Window blind installation
Building MM – Exterior paint, replaced doors and awnings, reglazed windows, and replaced fascia boards
18
Important Ongoing
Initiatives
LBCCD Coming Advancements
Master Landscape Project
District Wide Energy Efficiency
Improvements
Electronic Marquee Signage
Wayfaring and Building Signage
Campus Lighting Improvements
19
Planned Phasing of Future Projects
Currently Planned Schedule
2008-09
Parking Structure – Design/Build concept
Anticipate awarding bid Spring 2009
Moving Warehouse from PCC to Alteon Building at LAC – TBD
Moving LAC Building A into Swing Space – Spring 2009
Install portables at PCC for Swing Space – Spring 2009
LAC/PCC Building Needs Assessment Projects
Bathroom Improvement Projects
Quick-Start Projects
Lighting Projects
Classroom Improvement Projects
Infrastructure Projects
Submit FPP for M/N Project at LAC and MM Project at PCC and
submit IPP for P Building at LAC
Finalize Master Landscaping and Signage plans
Marquee signage anticipated to be installed March 2009
20
Planned Phasing of Future Projects
Currently Planned Schedule
2009-10
Begin construction of Building A at LAC
Anticipating July 2009 start
Begin construction of Buildings CC, DD, and EE at PCC
Anticipating July/August 2009 start
Begin Schematic Design for Buildings C and F at LAC
Submit plans to DSA no later than March 2010
Begin Master Landscaping and Signage Initiatives
Continue District Wide Energy Efficiency Improvements
Phase IIA
Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool
Cover, Roof replacement, etc
Phase IIB
Upcoming advancements include connecting current buildings
to Central Plant infrastructure
21
Planned Phasing of Future Projects
Currently Planned Schedule
2010-11
Anticipated Construction completion of Building A
at LAC – January 2011
Submit plans to DSA for Math/Technology Building
at LAC
Move Buildings C and F programs into Swing
Space (M/N Building) and begin construction –
Spring 2011
Construction completion of Buildings CC, DD and
EE at PCC
Begin construction of Buildings AA and BB at PCC
Anticipating January/February 2011 start
22
Planned Phasing of Future Projects
Currently Planned Schedule
2011-12
Begin construction of Math/Technology Building at LAC
Submit plans to DSA for M/N Building at LAC
2012-13
Anticipated Construction completion of Buildings C and
F at LAC – December 2012
Anticipated Construction completion of
Math/Technology Building at LAC – December 2012
Begin construction of Buildings M/N at LAC – January
2013
Anticipated Construction completion of Buildings AA
and BB at PCC – June 2013
23
QUESTIONS &
ANSWERS
EDUCATE ENGAGE EMPOWER
24