Facilities Improvements and
Bond Construction Update
Facilities Advisory Committee
Long Beach Community College District
December 2, 2008
EDUCATE  ENGAGE  EMPOWER
1
Agenda






Completed Construction Projects

PCC Learning Resource Center

LAC Central Plant
Current & Upcoming Construction Projects

LAC South Quad Complex

LAC Learning Resource Center

LAC Building A, Student Services Retrofit

LAC Math Technology Building

LAC Parking Structure

LAC Infrastructure Improvements – Phase 3

PCC Central Plant

PCC Industrial Tech Phase 1

PCC MDAB (Multi-Disciplinary Academic Building)

PCC Building C Retrofit

District Wide Building Needs Assessment Projects
 Toilet Improvement Projects
 Quick-Start Projects
 ADA Projects
 Lighting Projects
 Classroom Improvement Projects
Recently Completed Facilities Improvements
Important Ongoing Initiatives
Planned Phasing of Future Projects
Q&A
2
Completed Construction Projects
PCC Learning Resource Center – Measure E 2002






Construction Complete
Modern Facility with Computer Lab
and Multimedia
Stand alone Data Center. Provides
District IT redundancy
Bridge to building E
Design elements move towards
energy efficiencies
Ribbon cutting held 9/17/08
3
Completed Construction Projects
LAC Central Plant – Measure E 2002





Central Plant equipment, Public
Safety, & Field House for Athletics
Final FF&E installation underway
Plant ready for operation and
awaiting completion of LRC & SQC
Construction Complete
Anticipated startup 12/05/08
4
Current and Upcoming
Construction Projects
South Quad Complex – Measure E 2002


Construction approx. 89%
Complete
Space includes







Approx. 68,000 ASF
32 modern classrooms and labs
38 faculty offices
Executive office
Multipurpose room
State of the art Board Room
Substantial completion
anticipated 1/09
5
Current and Upcoming
Construction Projects
LAC/Learning Resource Center – Measure E 2002



Construction 91% Complete
Adds 10,000 ASF to existing
building
Substantial Completion
Anticipated January 2009
6
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008




Design Development to be submitted this month
Adds 4,000 ASF to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
Estimated start of construction 7/09
7
Current and Upcoming
Construction Projects
LAC Math Technology Building – Measure E 2008
 Completed Schematic Design (June 2008)
 Currently in Design Development phase
 Will house Math and Culinary Arts instructional
program as well as Reprographics
 Estimated start of construction 2011
8
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008





Planning initiated for
approximately 900 Vehicles
To be procured under “Design
Build Delivery” method
To be located Southeast corner
of Lot J adjacent to the Verizon
building
Photovoltaic Electrical Generation
Array on top level of structure
Anticipated start of construction
2009
Proposed Math
Technology
Bldg.
Lot J
Proposed Parking
Structure Loc.
Verizon Bldg.
9
Current and Upcoming
Construction Projects
LAC Infrastructure Improvements – Phase 3
Measure E 2008





Planning underway with engineers
Completes chilled water lines to
North side of campus
Includes other major utility
upgrades; Reclaimed Water,
Domestic Water, Data, etc.
Existing building HVAC systems to
be upgraded in synch with
infrastructure improvements
Coordinated with modernization
and quick start projects
10
Current and Upcoming
Construction Projects
PCC Central Plant – Measure E 2002



Houses Central Plant
equipment and
Maintenance and
Operations facility
Construction
Approximately 99%
Complete
Currently provides
chilled water to the PCC
LRC
11
Current and Upcoming
Construction Projects
PCC Industrial Technology Center Phase 1
Measure E 2002





Modern facility houses
Welding Department and
other trade programs
Construction is 45%
complete
Replaces existing
antiquated structures
New Northern face of the
campus
Completion anticipated
summer 2009
12
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) Measure E 2002




90% construction documents submitted
Swing space planning completed 9/2008, construction of swing space starts
Spring 2009
Anticipated start of MDAB construction Summer 2009
To be completed in two phases
13
Current and Upcoming
Construction Projects
PCC Building C Retrofit - Measure E 2008
 To be designed by Hill Partnership Architects
 Houses the Fitness Center, Gymnasium, Weight
Room, and Faculty and Staff Offices
 Swing space to be located on PCC Campus (TBD)
 To be completed concurrently with MDAB project
 Anticipated start of construction Spring 2010
14
Current and Upcoming
Construction Projects
District Wide Building Needs Assessment Project
Measure E 2008



Toilet Improvement
Projects
Quick-Start Projects
ADA Projects
15
Current and Upcoming
Construction Projects
District Wide Building Needs Assessment Projects
Measure E 2008


Lighting Projects
Classroom Improvement Projects
16
Recently Completed
Facilities Improvements
Building “B” and “E” Boiler Replacement



Replaced existing boilers, pumps,
expansion tanks and common
flue with new equipment via
helicopter lift.
A newly upgraded design
reflecting a mechanical
engineered system was installed
improving the efficiency of the
boilers.
Completed 10/2008
17
Recently Completed
Facilities Improvements
Additional Facilities Improvements

LAC upgrades:



Veteran’s Stadium scoreboard and PA system upgrade
Building K upgrades – Exterior door paint, room 111 floor
refinishing
PCC upgrades:






Building AA – Built wall for information desk, installed carpet, and
power upgrades
Building BB – Carpet and window blind installation
Building CC – Installed fans in gym
Building DD – Carpet and window blind installation
Building EE – Window blind installation
Building MM – Exterior paint, replaced doors and awnings, reglazed windows, and replaced fascia boards
18
Important Ongoing
Initiatives
LBCCD Coming Advancements
 Master Landscape Project
 District Wide Energy Efficiency
Improvements
 Electronic Marquee Signage
 Wayfaring and Building Signage
 Campus Lighting Improvements
19
Planned Phasing of Future Projects
Currently Planned Schedule

2008-09
 Parking Structure – Design/Build concept
 Anticipate awarding bid Spring 2009
 Moving Warehouse from PCC to Alteon Building at LAC – TBD
 Moving LAC Building A into Swing Space – Spring 2009
 Install portables at PCC for Swing Space – Spring 2009
 LAC/PCC Building Needs Assessment Projects
 Bathroom Improvement Projects
 Quick-Start Projects
 Lighting Projects
 Classroom Improvement Projects
 Infrastructure Projects
 Submit FPP for M/N Project at LAC and MM Project at PCC and
submit IPP for P Building at LAC

Finalize Master Landscaping and Signage plans
 Marquee signage anticipated to be installed March 2009
20
Planned Phasing of Future Projects
Currently Planned Schedule
 2009-10
 Begin construction of Building A at LAC
 Anticipating July 2009 start
 Begin construction of Buildings CC, DD, and EE at PCC
 Anticipating July/August 2009 start
 Begin Schematic Design for Buildings C and F at LAC
 Submit plans to DSA no later than March 2010
 Begin Master Landscaping and Signage Initiatives
 Continue District Wide Energy Efficiency Improvements
 Phase IIA
 Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool
Cover, Roof replacement, etc
 Phase IIB
 Upcoming advancements include connecting current buildings
to Central Plant infrastructure
21
Planned Phasing of Future Projects
Currently Planned Schedule
 2010-11
 Anticipated Construction completion of Building A
at LAC – January 2011
 Submit plans to DSA for Math/Technology Building
at LAC
 Move Buildings C and F programs into Swing
Space (M/N Building) and begin construction –
Spring 2011
 Construction completion of Buildings CC, DD and
EE at PCC
 Begin construction of Buildings AA and BB at PCC
 Anticipating January/February 2011 start
22
Planned Phasing of Future Projects
Currently Planned Schedule
 2011-12
 Begin construction of Math/Technology Building at LAC
 Submit plans to DSA for M/N Building at LAC
 2012-13
 Anticipated Construction completion of Buildings C and
F at LAC – December 2012
 Anticipated Construction completion of
Math/Technology Building at LAC – December 2012
 Begin construction of Buildings M/N at LAC – January
2013
 Anticipated Construction completion of Buildings AA
and BB at PCC – June 2013
23
QUESTIONS &
ANSWERS
EDUCATE  ENGAGE  EMPOWER
24