Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 2, 2008 BUILDING TOMORROW TODAY 1 Agenda Completed Construction Projects Current & Upcoming Construction Projects LAC South Quad Complex LAC Central Plant LAC Learning Resources Center LAC Building A, Student Services LAC Math Technology Building PCC Central Plant PCC Learning Resources Center PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) LAC/PCC Building Needs Assessment Project Toilet Improvement Projects Quick-Start Projects ADA Projects Lighting Projects Classroom Improvement Projects Infrastructure Projects Facilities Improvements Q&A 2 Current and Upcoming Construction Projects LAC Central Plant Central Plant equipment, Public Safety, & Field house for Athletics Installed (2) 600 ton Chillers and (1) 300 ton chiller with room for expansion Installed 4 cooling towers with additional expansion space 3 Current and Upcoming Construction Projects LAC Central Plant Plant ready for operation and awaiting completion of SQC Construction 99% Complete Awaiting completion of punch list Completion Anticipated Summer 2008 4 Current and Upcoming Construction Projects LAC/Learning Resources Center Construction 75% Complete Adds 10,000 ASF to existing building Substantial Completion anticipated December 2008 5 Current and Upcoming Construction Projects South Quad Complex Construction Approx. 70% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office suites Multipurpose room State of the art Board Room Substantial Completion Anticipated December 2008 6 Current and Upcoming Construction Projects LAC Building A – Student Services Retrofit Martinez Architects received Board Approval as the Architect of Record Programming work began on April 10, 2008 Schematic Design scheduled completion June 30, 2008 Adds 4000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. 7 Current and Upcoming Construction Projects LAC Math Technology Building Marlene Imirzian & Associates Architects received Board Approval as the Architect of Record Will house Math and Culinary Arts instructional program as well as Reprographics 8 Current and Upcoming Construction Projects LAC Math Technology Building Programming work began in May 2008 Schematic Design scheduled completion June 30, 2008 9 Current and Upcoming Construction Projects LAC Math Technology Building Currently completing Design Development Phase 10 Current and Upcoming Construction Projects PCC Central Plant Houses Central Plant equipment and Maintenance and Operations facility Installed (3) 300 ton Chillers Installed 3 cooling towers Will support LRC Construction Approximately 57% Complete Completion Anticipated late Summer 2008 11 Current and Upcoming Construction Projects PCC Learning Resources Center Construction 94% Complete Modern Facility with Computer Lab and Multimedia Stand alone Data Center. Provides District IT redundancy Bridge to Bldg. EE Design elements move towards energy efficiencies Opened August 2008 12 Current and Upcoming Construction Projects PCC Industrial Technology Center Phase 1 Replaces Existing Antiquated Structures Construction is 20% Complete Modern Facility Houses Machine Tool and Welding Departments New Northern Face of the Campus Completion Anticipated Spring 2009 13 Current and Upcoming Construction Projects PCC Multi-Disciplinary Academic Building (MDAB) Programming is completed and submitted to the State for Approval Schematic Design and Design Development to be completed by June 2008 Anticipated start of construction Summer 2009 Completed in Two phases 14 Current and Upcoming Construction Projects LAC/PCC Building Needs Assessment Project Restroom Improvement Projects Quick-Start Projects ADA Projects 15 Current and Upcoming Construction Projects LAC/PCC Building Needs Assessment Project Lighting Projects Classroom Improvement Projects Infrastructure Projects 16 Recently Completed Facilities Improvements Long Beach Community College District 17 Facilities Improvements LBCC Building “P” Exterior Renovation Complete exterior renovation. Entire roof replacement with a Spanish tile design, covering approximately 21,000 square feet. Architectural features added to the new doors. Windows replaced. French doors were installed entering into main meeting areas. Exterior painted Added new copper gutters. Completed 02/2006 18 Facilities Improvements LBCC Building “P” Teachers Lounge Renovations Complete renovations were made to the teacher’s lounge. Existing floor was removed and a new wood floor installed. New track lighting and French doors were also installed. Outside the French doors are exterior drains so no overflow of water can penetrate into this room. Completed 01/2008 19 Facilities Improvements LBCC Building “E” Upgrades Replaced broken tile with new non-skid tile at the entrance of the cafeteria to match existing Completed 01/2008 Structural evaluation and Repair cracks in ceiling, walls, and flooring due to earthquake Completed 07/2008 20 Facilities Improvements LBCC Building “D” Planetarium Improvements With the help of LBCC Foundation, funds were available to do the following: carpet replacement carpet added to the walls to ensure light-control for observational needs. AC unit independent from the building HVAC system was added to serve the server room, for proper load ventilation. New observation seats were installed. entire room painted new lighting installed. Completed 06/2008 21 Facilities Improvements LBCC Building “J” Boiler Replacement Replace existing boilers, pumps, expansion tanks and common flue with new equipment. A newly upgraded design reflecting a mechanical engineered system was installed improving the efficiency of the boilers. This system is the main heating source serving the Auditorium. Completed 06/2008 22 Facilities Improvements LBCC Building “F” Upgrades New stadium seating installed New carpet installed. New vertical blinds installed throughout building. Completed 12/2007 Upcoming advancements include exterior door replacement 23 Facilities Improvements LBCC Building “Q” Small Gymnasium Improvements Refinished wood flooring. A five coat finish system was applied to the floor for durability and long term wear. Additional decal of LBCC game lines were applied on flooring Interior walls were repainted and decals were re-applied with paint New retractable bleacher system was installed Completed 02/2008 Upcoming advancement includes room Q113 dance floor replacement 24 Facilities Improvements LBCC Building “Q” Health Center Office Remodel Two-new office spaces added Added an HVAC system Repainted all interior walls Installed new carpet Completed 01/2008 25 Facilities Improvements LBCC Building “B”, “C”, and “D” Roof Replacement Replacement of roofs with a 30year Garland roof materials Removal of radio tower on Bldg “B” Completed 07/2008 26 Facilities Improvements LBCC ERD Tenant Improvements and Relocation Economic Resource Development Complete build out of two-hard walled offices, a kitchenette, and a server room Relocation of a 4,000sq. ft. office space into the newly re-designed 3,000sq ft. office space New modular cubicle work stations were adapted and installed Completed 05/2008 27 Facilities Improvements LBCC Building “P” Boiler Replacement Replaced boiler for a more efficient system Completed 07/2007 28 Facilities Improvements LBCC Building “Q” and “R” Exterior Renovations Repainting of all exterior walls, windows, and doors Re-paint trim and detail work Replaced all broken windows Installed front landscape Completed 8/2008 Upcoming advancements include complete roof replacement, sky light upgrades, and exterior clock repair 29 Facilities Improvements LBCC Recently Completed Advancements Veteran’s Stadium scoreboard and PA system upgrade Building K upgrades – Exterior door paint, room 111 floor refinishing PCC upgrades: Building AA – Built wall for information desk, installed carpet, and power upgrades Building BB – Carpet and window blind installation Building CC – Installed fans in gym Building DD – Carpet and window blind installation Building EE – Window blind installation Building MM – Exterior paint, replaced doors and awnings, reglazed windows, and replaced fascia boards 30 Facilities Improvements LBCC Important Ongoing Initiatives Building Needs Assessment Project Design/Build Parking Structure Master Landscape Project District Wide Energy Efficiency Improvements Phase IIA Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc Phase IIB Upcoming advancements include connecting current buildings to Central Plant infrastructure Design Electronic Marquee Signage Wayfaring and Building Signage Facilities Website Facilities Work Order System Building P Theatre Room renovations Building P Faculty Restroom ADA upgrades 31 QUESTIONS & ANSWERS BUILDING TOMORROW TODAY 32