FAC Bond Construction Update 09-02-2008

advertisement
Bond Construction Update
Facilities Advisory Committee
Long Beach Community College District
September 2, 2008
BUILDING  TOMORROW  TODAY
1
Agenda


Completed Construction Projects
Current & Upcoming Construction Projects
 LAC South Quad Complex
 LAC Central Plant
 LAC Learning Resources Center
 LAC Building A, Student Services
 LAC Math Technology Building
 PCC Central Plant
 PCC Learning Resources Center
 PCC Industrial Tech Phase 1
 PCC MDAB (Multi-Disciplinary Academic Building)
 LAC/PCC Building Needs Assessment Project








Toilet Improvement Projects
Quick-Start Projects
ADA Projects
Lighting Projects
Classroom Improvement Projects
Infrastructure Projects
Facilities Improvements
Q&A
2
Current and Upcoming
Construction Projects
LAC Central Plant



Central Plant equipment,
Public Safety, & Field house
for Athletics
Installed (2) 600 ton Chillers
and (1) 300 ton chiller with
room for expansion
Installed 4 cooling towers with
additional expansion space
3
Current and Upcoming
Construction Projects
LAC Central Plant




Plant ready for operation and
awaiting completion of SQC
Construction 99% Complete
Awaiting completion of punch list
Completion Anticipated Summer
2008
4
Current and Upcoming
Construction Projects
LAC/Learning Resources Center



Construction 75%
Complete
Adds 10,000 ASF to
existing building
Substantial Completion
anticipated December
2008
5
Current and Upcoming
Construction Projects
South Quad Complex


Construction Approx. 70%
Complete
Space includes







Approx. 68,000 ASF
32 modern classrooms and labs
38 faculty offices
Executive office suites
Multipurpose room
State of the art Board Room
Substantial Completion
Anticipated December 2008
6
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit





Martinez Architects received Board Approval as the Architect of Record
Programming work began on April 10, 2008
Schematic Design scheduled completion June 30, 2008
Adds 4000 ASF to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
7
Current and Upcoming
Construction Projects
LAC Math Technology Building
 Marlene Imirzian & Associates Architects received
Board Approval as the Architect of Record
 Will house Math and Culinary Arts instructional
program as well as Reprographics
8
Current and Upcoming
Construction Projects
LAC Math Technology Building
 Programming work began in May 2008
 Schematic Design scheduled completion
June 30, 2008
9
Current and Upcoming
Construction Projects
LAC Math Technology Building

Currently completing Design Development Phase
10
Current and Upcoming
Construction Projects
PCC Central Plant






Houses Central
Plant equipment
and Maintenance
and Operations
facility
Installed (3) 300
ton Chillers
Installed 3 cooling
towers
Will support LRC
Construction
Approximately 57%
Complete
Completion
Anticipated late
Summer 2008
11
Current and Upcoming
Construction Projects
PCC Learning Resources Center






Construction 94% Complete
Modern Facility with Computer Lab
and Multimedia
Stand alone Data Center. Provides
District IT redundancy
Bridge to Bldg. EE
Design elements move towards
energy efficiencies
Opened August 2008
12
Current and Upcoming
Construction Projects
PCC Industrial Technology Center Phase 1





Replaces Existing Antiquated
Structures
Construction is 20%
Complete
Modern Facility Houses
Machine Tool and Welding
Departments
New Northern Face of the
Campus
Completion Anticipated
Spring 2009
13
Current and Upcoming
Construction Projects
PCC Multi-Disciplinary Academic Building (MDAB)




Programming is completed and submitted to the State for Approval
Schematic Design and Design Development to be completed by June 2008
Anticipated start of construction Summer 2009
Completed in Two phases
14
Current and Upcoming
Construction Projects
LAC/PCC Building Needs Assessment Project



Restroom Improvement
Projects
Quick-Start Projects
ADA Projects
15
Current and Upcoming
Construction Projects
LAC/PCC Building Needs Assessment Project



Lighting Projects
Classroom Improvement Projects
Infrastructure Projects
16
Recently Completed
Facilities Improvements
Long Beach Community
College District
17
Facilities Improvements
LBCC
Building “P” Exterior Renovation








Complete exterior renovation.
Entire roof replacement with a
Spanish tile design, covering
approximately 21,000 square feet.
Architectural features added to
the new doors.
Windows replaced.
French doors were installed
entering into main meeting areas.
Exterior painted
Added new copper gutters.
Completed 02/2006
18
Facilities Improvements
LBCC
Building “P” Teachers Lounge Renovations





Complete renovations were made
to the teacher’s lounge.
Existing floor was removed and a
new wood floor installed.
New track lighting and French
doors were also installed.
Outside the French doors are
exterior drains so no overflow of
water can penetrate into this
room.
Completed 01/2008
19
Facilities Improvements
LBCC
Building “E” Upgrades




Replaced broken tile with new
non-skid tile at the entrance of
the cafeteria to match existing
Completed 01/2008
Structural evaluation and Repair
cracks in ceiling, walls, and
flooring due to earthquake
Completed 07/2008
20
Facilities Improvements
LBCC
Building “D” Planetarium Improvements

With the help of LBCC Foundation,
funds were available to do the
following:







carpet replacement
carpet added to the walls to
ensure light-control for
observational needs.
AC unit independent from the
building HVAC system was added
to serve the server room, for
proper load ventilation.
New observation seats were
installed.
entire room painted
new lighting installed.
Completed 06/2008
21
Facilities Improvements
LBCC
Building “J” Boiler Replacement



Replace existing boilers, pumps,
expansion tanks and common flue
with new equipment.
A newly upgraded design
reflecting a mechanical
engineered system was installed
improving the efficiency of the
boilers. This system is the main
heating source serving the
Auditorium.
Completed 06/2008
22
Facilities Improvements
LBCC
Building “F” Upgrades





New stadium seating installed
New carpet installed.
New vertical blinds installed
throughout building.
Completed 12/2007
Upcoming advancements include
exterior door replacement
23
Facilities Improvements
LBCC
Building “Q” Small Gymnasium Improvements





Refinished wood flooring. A five coat
finish system was applied to the
floor for durability and long term
wear. Additional decal of LBCC
game lines were applied on flooring
Interior walls were repainted and
decals were re-applied with paint
New retractable bleacher system
was installed
Completed 02/2008
Upcoming advancement includes
room Q113 dance floor replacement
24
Facilities Improvements
LBCC
Building “Q” Health Center Office Remodel





Two-new office spaces added
Added an HVAC system
Repainted all interior walls
Installed new carpet
Completed 01/2008
25
Facilities Improvements
LBCC
Building “B”, “C”, and “D” Roof Replacement



Replacement of roofs with a 30year Garland roof materials
Removal of radio tower on Bldg
“B”
Completed 07/2008
26
Facilities Improvements
LBCC
ERD Tenant Improvements and Relocation





Economic Resource Development
Complete build out of two-hard
walled offices, a kitchenette, and
a server room
Relocation of a 4,000sq. ft. office
space into the newly re-designed
3,000sq ft. office space
New modular cubicle work stations
were adapted and installed
Completed 05/2008
27
Facilities Improvements
LBCC
Building “P” Boiler Replacement


Replaced boiler for a more
efficient system
Completed 07/2007
28
Facilities Improvements
LBCC
Building “Q” and “R” Exterior Renovations






Repainting of all exterior walls,
windows, and doors
Re-paint trim and detail work
Replaced all broken windows
Installed front landscape
Completed 8/2008
Upcoming advancements
include complete roof
replacement, sky light
upgrades, and exterior clock
repair
29
Facilities Improvements
LBCC
Recently Completed Advancements



Veteran’s Stadium scoreboard and PA system upgrade
Building K upgrades – Exterior door paint, room 111 floor
refinishing
PCC upgrades:






Building AA – Built wall for information desk, installed carpet, and
power upgrades
Building BB – Carpet and window blind installation
Building CC – Installed fans in gym
Building DD – Carpet and window blind installation
Building EE – Window blind installation
Building MM – Exterior paint, replaced doors and awnings, reglazed windows, and replaced fascia boards
30
Facilities Improvements
LBCC
Important Ongoing Initiatives




Building Needs Assessment Project
Design/Build Parking Structure
Master Landscape Project
District Wide Energy Efficiency Improvements

Phase IIA
 Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover,
Roof replacement, etc

Phase IIB
 Upcoming advancements include connecting current buildings to
Central Plant infrastructure






Design Electronic Marquee Signage
Wayfaring and Building Signage
Facilities Website
Facilities Work Order System
Building P Theatre Room renovations
Building P Faculty Restroom ADA upgrades
31
QUESTIONS &
ANSWERS