Agenda Board of Regents Facilities and Land Management Committee Thursday, September 18, 2008; *1:00 p.m. – 4:30 p.m. 106 Lee Gorsuch Commons University of Alaska Anchorage Anchorage, Alaska *Times for meetings are subject to modifications within the September 17-19, 2008 timeframe. Committee Members: Michael Snowden, Committee Chair Timothy Brady, Committee Vice Chair Fuller Cowell I. Call to Order II. Adoption of Agenda Robert Martin Kirk Wickersham Mary Hughes, Board Chair MOTION "The Facilities and Land Management Committee adopts the agenda as presented. I. II. III. IV. V. VI. VII. Call to Order Adoption of Agenda Full Board Consent Agenda A. Formal Project Approval for the Anderson Building Remodel and Pedestrian Crossing at the University of Alaska Southeast B. Schematic Design Approval for the TVCC Revitalization Phase 3 Exterior Envelope at the University of Alaska Fairbanks New Business A. Formal Project Approval for the Northwest Campus Deferred Renewal at the Northwest Campus in Nome, Alaska Ongoing Issues A. Status Report on University Investments in Capital Facilities, Construction in Progress, and Other Projects B. Update on IT Issues C. Update on University of Alaska Fairbanks Master Plan Future Agenda Items Adjourn This motion is effective September 18, 2008." Facilities & Land Management Committee Agenda: Page 1 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska III. Full Board Consent Agenda A. Formal Project Approval for the Anderson Building Remodel and Pedestrian Crossing at the University of Alaska Southeast The President recommends that: MOTION "As required by Regents’ Policy 05.12.04, the Facilities and Land Management Committee recommends that the Board of Regents approve the formal Project Approval request for the University of Alaska Southeast Anderson Building Remodel and Pedestrian Crossing Improvements as presented, and authorize the university administration to proceed through schematic design not to exceed a Total Project Cost of $10,700,000. This motion is effective September 18, 2008." POLICY CITATION In accordance with Regents’ Policy 05.12.04, Formal Project Approval (FPA) represents approval of the Project including the program justification and need, scope, the Total Project Cost (TPC), and funding plan for the project. It also represents authorization to complete the development of the project through the schematic design, targeting the approved scope and budget, unless otherwise designated by the approval authority. A FPA is required for all projects with an estimated TPC in excess of $2.5 million in order for that project’s inclusion of construction funding to be included in the university’s capital budget request, unless otherwise approved by the Board. The level of approval required shall be based upon TPC as follows: TPC > $4 million will require approval by the Board based on recommendations from the Facilities and Land Management Committee (F&LMC). TPC > $2 million but ≤ $4 million will require approval by the F&LMC. TPC > $1 million but ≤ $2 million will require approval by the Chairperson of the F&LMC. TPC ≤ $1 million will require approval by the university’s Chief Finance Officer (CFO) or designee. Facilities & Land Management Committee Agenda: Page 2 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska RATIONALE/RECOMMENDATION 1. Background The programs that constitute Arts and Sciences at UAS have a significant leadership position and set of responsibilities in the UAS mission as a teaching and learning-led institution. This mission focuses institutional energies and strategy on the development and provision of excellent learning environments and communities for our students and faculty. Within that general focus, science programs occupy a special place in the identity of the University and the challenge of its mission, particularly given the unique marine location that is Juneau. In addition, the existing running seawater system in the building, fed directly from Auke Bay, is a unique asset to marine science programs. The program for the remodeled building should make the most of this capability. Based on its unique setting, science programs at UAS offer important opportunities to build enriching undergraduate research and project-based learning experiences directly linked to the goal of academic excellence in a teaching and learning-led institution. Within this context, all majors can benefit from the strength of the science curriculum. The remodeling of the Anderson Building into a modernized science facility presents an essential opportunity for UAS to further its strengths and core values around the mission of building a teaching and learning-led institution that, as a result, uniquely and effectively serves the higher education imperatives of the southeast region and state of Alaska. These considerations lead to the following operational priorities for the remodel proposal: 1st priority: the remodeled building is to provide facilities that enhance the quality of the science teaching programs and classrooms, and; 2nd priority: to provide space to enhance the undergraduate research experience and opportunities for project-based learning with faculty. The current project builds on work accomplished in the past five years that identified a goal to advance and achieve further recognition for excellence of the UAS programs in biology, marine biology, and environmental sciences. There is an important need to refine program offerings at UAS, including its science programs, to ensure that they contribute to the imperatives of program quality and growth in a teaching and learning-led institution. Given the Juneau setting and the strength of its faculty, the biological and Facilities & Land Management Committee Agenda: Page 3 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska environmental science programs provide important opportunities for recruiting students not only within the region and state, but also to attract students from outside of the southeast region as well as outside of the state to UAS These twin imperatives of quality and growth are clearly articulated in strategic documents and planning activities at UAS, particularly, “The Study for an Expanded Science Facility (August 2002)” and “UAS: The Next Decade: Strategic Plan for the University of Alaska Southeast 20002010”. UAS Strategic Goals In “Strategic Plan for the UAS 2000-2010,” a set of key strategic goals were developed by the University community and approved by the Board of Regents to provide a roadmap for the continuing success and growth of the University. Several of these goals directly relate to the development of the facilities and are encompassed in the current Anderson Building project including: Goal One: Student Success “The University will provide the learning environment, support systems, academic programs, facilities, technology, and faculty to enhance the learning opportunities for students, who have diverse needs, interests, capabilities, and ambitions.“ Goal Two: Faculty & Staff Strength “The University will recruit, develop and retain a culturally diverse faculty and staff who bring excellence to our teaching, research, and service through innovative and mission-focused academic programs and services.” To accomplish this goal, the University supports “faculty to grow in their discipline through research and scholarship, and professional engagement”. The university also seeks to “assist faculty in integrating technology into instruction that leads to enhanced learning.” Facilities & Land Management Committee Agenda: Page 4 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska Goal Three: Educational Quality “In an effort to increase retention and attract new students, bachelor degree programs have expanded and now include liberal arts, English, social science, mathematics, biology, marine biology, and environmental science. Each program emphasizes experiential learning and mentoring relationships with faculty to take advantage of favorable student to faculty ratio and the campus’ unique location. “The UAS will offer the highest quality programs, from non-degree training to graduate degrees. Our campuses will provide the highest possible quality programs and services within their respective missions. UAS recognizes that the traditional liberal arts education is more important now than ever as it provides students with the critical thinking skills and the foundation necessary to be prepared to meet rapid changing work, cultural, and social environments. The liberal arts education at UAS helps students develop skills in self-examination, imagination, and citizenship.” Existing Facilities The majority of UAS Juneau Campus specialized science teaching space is located in the Anderson Building on Auke Bay. The Anderson Building occupies a lovely and unique site on Auke Bay. The building has a saltwater supply system that is currently one of only two such systems in Southeast Alaska. The Anderson Building was constructed in two phases. The first two floors were constructed in 1976 and the third floor was added in 1980. The total gross square feet of the building is 15,608. The Anderson Building has been occupied until recently by both the UAS Science Department and the UAF School of Fisheries & Ocean Sciences (SFOS). The SFOS is moving to a new location with the completion of their new facilities at Lena Point. Because of the age of the Anderson Building, and the fact that SFOS is moving out the building in 2008, the University has an opportunity to make major programmatic and technical improvements to the Anderson Building at this time. UAS currently offers Bachelor degrees in Biology, Environmental Science and Marine Biology. The 2001 UAS Campus Master Plan anticipates that science enrollment (headcount) will approximately double between 2005 and 2012. Facilities & Land Management Committee Agenda: Page 5 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska During the planning process for the Anderson Building Remodel all of the University’s science education program delivery spaces were examined to determine the best mix of those spaces to be located in the Anderson Building. 2. Project Scope The Anderson Building Remodel project will require the rehabilitation of most of the existing 15,608 GSF building. Since November 2007, ECI/Hyer Inc. has been meeting with UAS administration, faculty, students and staff to prepare a program of all UAS science space as envisioned for the year 2015. The resulting program document establishes space use priorities for rehabilitation of the Anderson Building and lists pertinent attributes of each space, including: area in net square feet, all finish materials, environmental criteria, building systems, equipment and furnishings. Facilities & Land Management Committee Agenda: Page 6 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska Final Concept Program – Stacking Diagram Facilities & Land Management Committee Agenda: Page 7 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska Additional Life Cycle Replacement and Energy Conservation Considerations Because of the building’s age, virtually all of the Anderson Building’s systems are nearing the end of their anticipated lifespan, and are due to require replacement in the near term. So it is appropriate, and advantageous that maintenance and operational improvements will be made to the Anderson Building as a part of the project. These improvements will address issues related to sustainability, energy use and efficiency, fire safety, life cycle costs, accessibility, and hazardous materials. Work items that will be analyzed as part of the initial design phases include: Improve parking lot and site circulation Replace roof Upgrade windows Upgrade elevator Renovate heating & ventilating systems Upgrade saltwater system Replace reverse osmosis system Provide new electrical panel and main distribution system Replace Gen set/transfer switch Provide cable tray system for data/communications Replace fire alarm system Pedestrian Crossing Improvements Alaska DOT&PF prepared a reconnaissance study in 2004 (ABCOR) that included this segment of the Glacier Highway and recommended that increased pedestrian amenities be provided. Improving student access to the Anderson Building is a major component of the project. Parking is limited at the Anderson Building. Many building users park on campus and walk to the building. To get to the building pedestrians must cross Glacier Highway where traffic moves at speeds of 40 to 50 MPH and sight lines are short due to the curvature of the highway. This project proposes improvements that provide for safe pedestrian access to the Anderson Building. A pedestrian overpass or underpass, and improved on grade crossings and sidewalks are being considered. This project considers three alternate improvements that would provide for safe pedestrian access to the Anderson Building. A pedestrian overpass or underpass, and improved on grade crossings and sidewalks are being considered. On Grade Crossing: DOT&PF’s preliminary analysis of improvements considered for the Glacier Highway incorporate a realignment of the curve Facilities & Land Management Committee Agenda: Page 8 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska moving the roadway closer to the main campus. DOT&PF analysis also suggests creating roundabouts at the intersection of the Glacier Highway with Fritz Cove Road and DeHarts. The introduction of roundabouts gains the support of DOT&PF to incorporate on-grade crossing of the highway. This support is due to reduced travel speeds associated with a roundabout, reduced distance to cross single lanes of traffic, and the creation of a safe zone in the center of the roundabout for the pedestrian to time their crossing. Reliance on the roundabout solution to access the Anderson Building would require the addition of sidewalk along the highway between the roundabout and the Anderson Building. The availability of right-of-way combined with step shoulder gradient along the highway increase the costs associated with this crossing option. A project that incorporated the roadway realignment at the same time the roundabouts were built would most likely provide the needed right-of way for the necessary sidewalk. Elevated Crossing: Provide a bridge that crosses the Glacier Highway in the vicinity of the Anderson Building. The transition from the main campus to the Anderson Building offers a grade differential that might eliminate stairs or an elevator to access the crossing on the main campus side. Overhead utility lines exist on the Anderson Building side of the highway that may require relocation to facilitate the bridge structure. The ultimate solution would be to extend the bridge walkway to the Anderson Building and utilize the elevator access in the building to transition to grade level. The issues of building security and use by other than the university population may limit this function. Depressed Crossing: Construct a tunnel under the Glacier Highway. This option would avoid interference with overhead utility lines but may result in longer walkway distances to reach grade levels at each terminus. DOT&PF’s most recent position has been that the construction of improvements recommended in their reconnaissance report are not in their current short term funding plan. However DOT&PF received a general fund appropriation in FY09 for project design of the general corridor improvements. In addition there is a $5 million allocation of construction funding included in a statewide transportation bond issuance for the Mendenhall Loop Road intersection. Facilities & Land Management Committee Agenda: Page 9 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska 3. Proposed Cost and Funding Source(s) An allocation of $500,000 was received in FY08 for planning and $10,000,000 was received in FY09 for design and construction. Facilities & Land Management Committee Agenda: Page 10 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska 4. Estimated Total Project Cost UNIVERSITY OF ALASKA Project Name: Anderson Building Remodel MAU: UAS Building: Anderson Building Date: Campus: Juneau Prepared By: Project Title: Account No.: Total GSF Affected by Project: 15,608 PROJECT BUDGET A. Professional Services Consultant Basic Services 12.0% Construction Phase Services 2.0% Site Survey Plan Review / Permits Professional Services Subtotal B. Construction General Construction Contract(s) Pedestrian improvements Construction Contingency 10.0% Art 0.5% Construction Subtotal Construction Cost per GSF C. Equipment and Furnishings Classroom Equipment Other Furnishings Make Ready/Move In Equipment and Furnishings Subtotal D. Administrative Costs Temporary relocation costs Project Management 6% Administrative Costs Subtotal E. Total Project Cost Total Project Cost per GSF F. Total Appropriation(s) 5/1/2008 Gerken Original $955,000 $159,000 $35,000 $1,149,000 $5,920,000 $2,040,000 $800,000 $40,000 $8,800,000 564 $75,000 $50,000 $10,000 $135,000 $0 $610,000 $610,000 $10,694,000 685 $10,700,000 5. Maintenance and Operating Costs (M&R) Maintenance and operating costs of the building are expected to be reduced as a consequence of this project. Facilities & Land Management Committee Agenda: Page 11 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska 6. Consultants The lead consultant for the design of the project is the Anchorage based architectural firm of ECI/Hyer, Inc. The ECI/Hyer, Inc. design team for this project includes: Lab Programming & Design: Civil Engineering: Structural Engineering: Mechanical Engineering: Electrical Engineering: NBBJ R&M Engineering, Inc. Reid Middleton Murray & Associates, PC Haight & Associates 7. Other Cost of Consideration Occupants of the building will be affected by the remodel. A logistical approach to the implementation of the remodel work will be developed during the later design phases. The construction work is likely to be accomplished in phases with the most disruptive work efforts scheduled during summer and Christmas breaks. 8. Schedule for Completion The anticipated schedule for the building remodel is as follows: Design Period October 1, 2008 – January 8, 2009 SD October 1, 2008 – November 1, 2008 DD November 1, 2008 – November 21, 2008 95% CD December 5, 2008 – December 19, 2008 100% CD December 19, 2008 – January 8, 2009 Bid Period January 8, 2009 – February 5, 2009 Contract Award February 15, 2009 Construction Period May 15, 2009 – August 15, 2010 Beneficial Occupancy August 22, 2010 The schedule for the pedestrian access project will require additional coordination with and commitments from the Alaska Department of Transportation & Public Facilities. 9. Action Requested Approval to develop the project documents through schematic design. 10. Supporting Documents UAS Anderson Building Remodel & Pedestrian Crossing Improvements, ECI/Hyer l NBBJ, August 11, 2008: http://www.uas.alaska.edu/facilities_services/fpc/andremod/andersonfinal. pdf Facilities & Land Management Committee Agenda: Page 12 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska B. Schematic Design Approval for the TVCC Revitalization Phase 3 Exterior Envelope at the University of Alaska Fairbanks Reference 7 The President recommends that: MOTION “As required by Regents’ Policy 05.12.04, the Facilities and Land Management Committee recommends that the Board of Regents approve the Schematic Design Approval for the University of Alaska Fairbanks Tanana Valley Campus Center Revitalization Phase 3 Exterior Envelope for a total project cost not to exceed $7,000,000. This motion is effective September 18, 2008.” POLICY CITATION In accordance with Regents’ Policy 05.12.04, Schematic Design Approval (SDA) represents approval of the location of the facility, its relationship to other facilities, the functional relationship of interior areas, the basic design including construction materials, mechanical, electrical, technology infrastructure, and telecommunications systems, and any other changes to the project since Formal Project Approval. Unless otherwise designated by the approval authority or a Material Change in the project is subsequently identified, SDA also represents approval of the proposed cost of the next phase(s) of the project and authorization to complete the Construction Documents process, to bid and award a contract within the approved budget, and to proceed to completion of project construction. Provided, however, if a Material Change in the project is subsequently identified, such change will be subject to the approval process described below. For the Schematic Design Approval, if there has been no Material Change in the project since the Formal Project Approval, approval levels shall be as follows: TPC > $4 million will require approval by the Facilities and Land Management Committee (F&LMC). TPC > $2 million but ≤ $4 million will require approval by the chair of the F&LMC. TPC ≤ $2 million will require approval by the university’s Chief Finance Officer (CFO) or designee. If there has been a Material Change in the project since the Formal Project Approval, the Schematic Design approval levels shall be the same as the Formal Project Approval. Facilities & Land Management Committee Agenda: Page 13 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska RATIONALE / RECOMMENDATION 1. Narrative Description The UAF Tanana Valley Campus Center at 604 Barnette Street in Fairbanks, Alaska (formerly the Fairbanks Courthouse) was designed and constructed in 1962-63. The building has four stories plus a mechanical penthouse with a total of 78,504 gross square feet. Since taking ownership in 2003, the university has accomplished a series of two state-funded projects and two additional projects funded by the Denali Commission. The second state-funded project, Phase 2 Mechanical and Electrical Upgrades, is in the final stage of completion. The Phase 3 Exterior Envelope project will replace the entire existing exterior building envelope and windows, which have failed. The existing exterior wall system consists of enamel coated aluminum storefront panels with an R-value of no more than 4. The panels enclose asbestos containing materials (ACM) that provide most of the insulating value. Hazardous materials handling methods will be employed for demolition and disposal of the panels. The exterior aluminum windows have deteriorated and are beginning to fall out of the exterior skin. The storefront system also acts as the building’s vapor barrier which is not continuous, and is leaking. The poor wall system and inconsistent vapor barrier have led to some corrosion of the structural systems, access for mold, drafty and uncomfortable spaces, and poor use of energy. The new wall system will be an Exterior Insulation Finish System (EIFS) integrated with a pre-fabricated, lift-in-place panel system. The system is medium priced with many advantages including low maintenance, durability, excellent thermal performance, and site assembly methods that result in minimum exposure of the building interior during construction. The new panel system will connect to the structural connection points of the existing curtain wall system, and will provide an R-21 insulation value and a continuous vapor barrier at the perimeter of the entire facility. The new windows will be fixed double pane, argon filled, low E-coated, high performance (HP) insulated windows with extruded aluminum (thermal break) frames. There are approximately 224 windows and replacement will improve both function and aesthetics. Each window will have a separate window shade. All storefront and insulated hollow metal doors will be replaced as part of this project. Storefront interior and exterior doors, sidelights and transoms will be replaced with insulated, thermal break (HP) systems. The Facilities & Land Management Committee Agenda: Page 14 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska building’s exterior electrical equipment will be replaced with colorcorrected, high pressure sodium lights and new headbolt outlets on control points for energy conservation. The exterior look of the building will take on a 21st century, modernized look utilizing a series of linear and square/rectangular panels. The existing penthouse and building parapets will also be modified to tie into the building design. Window sizes will allow for day lighting deeper into the building spaces including the programmed student lounge areas. An insulated, translucent wall system will be installed on the exterior wall where the main stair is located at the east end of the facility (Barnette Street). Daylight will penetrate into the building through the panels while still maintaining a thermal buffer from the exterior cold. Replacement of the exterior envelope will impact the interior perimeter hydronic heating system and various architectural, mechanical, and electrical aspects of the interior rooms. The impact to these systems and areas will be addressed as needed by this project. 2. Graphic Description See Reference 7. 3. Proposed Cost and Funding Source(s) UAF & TVC SB 221 SLA08 FY09 General Fund Appropriation Facilities & Land Management Committee Agenda: Page 15 of 21 $7,000,000 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska 4. Estimated Total Project Cost UNIVERSITY OF ALASKA Project Name: TVCC Revitalization Phase 3 Exterior Envelope MAU: UAF Building: #655 TVCC Date: August 19, 2008 Campus: UAF TVC Prepared By: M. Schuetz Project #: 2008190 TVEE Account No.: TBD Total GSF Affected by Project: 78504 PROJECT BUDGET Original A. Professional Services Consultant Basic Services $482,000 Consultant Extra Services $0 Site Survey $0 Soils Engineering $0 Testing $8,000 Plan Review / Permits $62,000 Other $0 Professional Services Subtotal $552,000 B. Construction General Contractor $5,185,000 Other Contractors $38,000 Construction Contingency $518,500 Art $0 Other (Interim Space Needs) $0 Construction Subtotal $5,741,500 Construction Cost per GSF $73.14 C. Equipment and Furnishings Equipment $0 Furnishings $0 Make Ready/Move In $0 Equipment and Furnishings Subtotal $0 D. Administrative Costs Advance Planning $0 Misc. Expenses $15,682 Parking/Staging $30,000 Project Management $660,818 Administrative Costs Subtotal $706,500 E. Total Project Cost $7,000,000 Total Project Cost per GSF $89.17 F. Total Appropriation(s) $7,000,000 Facilities & Land Management Committee Agenda: Page 16 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska 5. Variance Report None 6. Schedule for Completion Design Development (65%) Construction Documents (95%) Bid Documents (100%) Bid Period Construction Occupancy October 10, 2008 December 5, 2008 January 5, 2009 January 11 to March 15, 2009 March 15 to October 31, 2009 Continuous Coordinated Occupancy 7. Affirmation The Board of Regents gave Formal Project Approval at the June 2008 meeting. 8. Action Requested Schematic Design Approval by the Facilities and Land Management Committee and Board of Regents. IV. New Business A. Formal Project Approval for the Northwest Campus Deferred Renewal at the Northwest Campus in Nome, Alaska Reference 8 The President recommends that: MOTION “As required by Regents’ Policy 05.12.04, the Facilities and Land Management Committee approves the Formal Project Approval request for the University of Alaska Fairbanks Northwest Campus Deferred Renewal as presented, and authorizes the University administration to proceed through schematic design (SD) not to exceed a Total Project Cost of $3,500,003. This motion is effective September 18, 2008.” POLICY CITATION In accordance with Regents’ Policy 05.12.04, Formal Project Approval (FPA) represents approval of the Project including the program justification and need, scope, the Total Project Cost (TPC), and funding plan for the project. It also represents authorization to complete the development of the project through the schematic design, targeting the approved scope and budget, unless otherwise designated by the approval authority. Facilities & Land Management Committee Agenda: Page 17 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska A FPA is required for all projects with an estimated TPC in excess of $2.5 million in order for that project’s inclusion of construction funding to be included in the university’s capital budget request, unless otherwise approved by the Board. The level of approval required shall be based upon TPC as follows: TPC > $4 million will require approval by the Board based on recommendations from the Facilities and Land Management Committee (F&LMC). TPC > $2 million but ≤ $4 million will require approval by the F&LMC. TPC > $1 million but ≤ $2 million will require approval by the Chairperson of the F&LMC. TPC ≤ $1 million will require approval by the university’s Chief Finance Officer (CFO) or designee. RATIONALE / RECOMMENDATION 1. Background The Emily Brown Library building, NW008, was constructed in 1974 as the original building for the Northwest Campus. The foundation consists of 24 each 6” diameter steel pipes augered 13 feet down and consisting of approximately 7 feet of fins (some underground). In 1981, the Nagozruk building (NW001) was added to campus for additional office and classroom space. The Nagozruk building’s foundation consists of 22 each 12” diameter steel pilings drilled to a depth of 25 feet and contain a gas. The Library building and Nagozruk building are adjacent to the ocean and receive the battering of wind, sand and salt on their siding and pilings. Over the years, the painted coating on the pilings has deteriorated and allowed rust to eat away at the steel. The pilings were recoated in 2000, which helped to prevent further deterioration. Since then, rust has found its way through the coating and is again eroding the pilings. Only one other building on the Northwest Campus has steel pilings: NW016. This building was recently purchased by the university and needs some recoating of its pilings, but they appear to be in good structural shape. Over time, the occupancy of the buildings on campus has changed, with more people in less space with more computers, printers, faxes, etc. The classroom buildings were never envisioned to hold computer labs, which Facilities & Land Management Committee Agenda: Page 18 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska now are essential to learning and job training. Funds remaining after repair of pilings will be used to correct electrical code issues, balance electrical loads within the buildings and modify heating and ventilation system to accommodate changes. 2. Project Scope The Library and Nagozruk buildings' piling are failing and must be replaced. The Nagozruk building will be moved to provide access to the area under the building for installation of new pilings then replaced on top of the new pilings. A site investigation will be conducted to determine appropriate locations, depth and style of pilings. The new pilings for the Library will be placed near the satellite buildings. This follows the long-range Master Plan for the campus and will provide access to restrooms for the satellite buildings as well as a place for the students to study before and after classes. Then, the structure will be moved and placed on its new foundation. A thorough analysis of the buildings electrical and space usage and needs will be conducted in order to provide an upgraded electrical and HVAC system throughout the campus. 3. Proposed Cost and Funding Source(s) Funding for this project comes from a state Capital Appropriation, with a line item appropriation in the amount of $3,500,003. Facilities & Land Management Committee Agenda: Page 19 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska 4. Estimated Total Project Cost UNIVERSITY OF ALASKA Project Name: MAU: Northwest Campus Deferred Renewal UAF Building: NW001, NW008-NW010 Campus: Northwest Project #: 2009012 NWDR Total GSF Affected by Project: PROJECT BUDGET A. Professional Services Consultant Basic Services Consultant Extra Services Site Survey Soils Engineering Testing Plan Review / Permits Other Professional Services Subtotal B. Construction General Contractor Other Contractors (Voice/Data Installation) Construction Contingency Art Other (Interim Space Needs) Construction Subtotal Construction Cost per GSF C. Equipment and Furnishings Equipment Furnishings Make Ready/Move In Equipment and Furnishings Subtotal D. Administrative Costs Advance Planning Misc. Expenses Parking/Staging Project Management Administrative Costs Subtotal E. Total Project Cost Total Project Cost per GSF F. Total Appropriation(s) Date: Prepared By: Account No.: 8,960 August 14, 2008 C. Ward 571291-50216 (+ for electrical & HVAC overall) Original $125,000 $0 $0 $15,600 $0 $15,980 $0 $156,580 $2,751,000 $0 $247,590 $0 $0 $2,998,590 $334.66 $0 $0 $0 $0 $0 $13,540 $0 $331,293 $344,833 $3,500,003 $390.63 $3,500,003 5. Maintenance and Operating Costs (M&R) This project will address outstanding maintenance issues and resolve on going problems thus reducing maintenance costs. 6. Consultant(s) Bezek-Durst-Seiser, Inc. has been selected as the lead consultant from our pool of Term Consultants because of their familiarity with the campus and its master plan. Shannon & Wilson, Inc. has been selected for the soil testing and assessment. 7. Schedule for Completion Design Bid Period Anticipated construction period Anticipated Beneficial Occupancy Date August 2008-May 2009 June 2009 April 2010 – August 2010 mid-August 2010 Facilities & Land Management Committee Agenda: Page 20 of 21 Agenda Facilities & Land Management Committee September 18, 2008 Anchorage, Alaska V. Ongoing Issues A. Status Report on University Investments in Capital Facilities, Construction in Progress, and Other Projects Reference 9 Joe Trubacz, Chief Finance Officer, and campus facilities representatives will update the committee regarding the ongoing investment in capital facilities and answer questions regarding the status report on active construction projects approved by the Board of Regents, implementation of recommendations by the external consultants, functional use survey, space utilization analysis, and other recent activity of note. This is an information and discussion item; no action is required. B. Update on IT Issues Reference 10 CITO Smith will report on IT issues of importance for the university including an update on the status of online security review and remediation across the system. He will also report on the Higher Education Reauthorization Act in regards to online copyright infringement (peer-to-peer file sharing), the impact to the university, and how the system is preparing for implementation of this portion of the Act. C. Update on University of Alaska Fairbanks Master Plan The University of Alaska Fairbanks (UAF) has been developing plans for the most effective use of capital funding to meet its highest priority facilities and infrastructure needs. In conjunction, UAF is incorporating these plans into a Master Plan update. UAF anticipates requesting approval of the Master Plan update at the December 2008 Board of Regents' meeting. UAF will provide information on its 2002 Master Plan, the current status, and future plans. The future plans will include the proposed Life Sciences Facilities, Engineering Addition, Energy and Power Facility, Student Housing, Fire Station, and West Ridge Chilling along with any parking, roads, utilities, or other infrastructure needs or related services. VI. Future Agenda Items VII. Adjourn Facilities & Land Management Committee Agenda: Page 21 of 21