ADDENDUM #3
Date :
To :
Project :
May 29, 2015
Bidders of Record
B id Package Cross Street Sidewalk Replacement Between Fountain Avenue And
Pine Street
Annual Major Maintenance FY 16
SPECIAL NOTE: Addendum #1 information shall supersede the information contained in the
Contract Documents
This Addendum forms a part of the Contract Documents and modifies the original Bidding
Documents dated December 20, 2014, 5/22/2015 and May 2015 and related addenda and clarifications. Acknowledge receipt of this Addendum in the space provided on the Bid Form.
Failure to do so may subject the Bidder to disqualification.
Bid / Construction Schedule
Bids due: June 1, 2015 @ 2:00PM
Selection of successful bidders: June 2, 2015
Construction Start Date: June 3, 2015
Project Completion Date: August 14, 2015 http://www.wesleyan.edu/construction/majormaint/FY_16/FY_16.html
Housing Opens/Students Arrive on campus: August 14, 2015
Decorative light pole base shall be DB9. Eliminate reference to DB8.
The DB9 decorative light pole base has a 3 bolt pattern. Cut sheet attached and link provided. http://www.aal.net/content/products/specs/specs_files/aal_db9_spec.pdf
.
A total of 6 pole bases are required.
All pole bases need to have an 8’ ground rod.
Five (5) shall have 3 conduit and one (1) shall have 4 conduit.
The pole base with 4 conduit shall be located closest to 109 Cross Street.
Coordinate with Electrical Contractor.
Please provide the proper light pole base.
A combination electrical/USB receptacle shall be placed on the pole base at 107 Cross Street,
109 Cross Street and 113 Cross Street light fixture locations.
Major Maintenance FY16
Project Number 2016000026 ADDENDUM #21
Pre-Bid Conference -Page 1
5/28/15