Steve Shectman/Pat McCarthy

advertisement
Giant Magellan Telescope Project
Science with Giant Telescopes - June 2008
1
GMT Partners
Astronomy Australia Limited
Australian National University
Carnegie Institution of Washington
Harvard University
Smithsonian Institution
Texas A&M University
U. of Arizona
U. of Texas at Austin
Joining:
Korea Astronomy & Space Science
Institute
Science with Giant Telescopes - June 2008
2
GMT Project
Governing & operating bodies
• GMT Board of Directors
overall policy & governance
• Science Working Group
scientific priorities, instruments, site selection, operations
• Project Scientists’ Working Group
technical guidance, telescope and instrument design teams
• Project Office
project management, engineering, contracting, construction
Science with Giant Telescopes - June 2008
3
Topics
•
Telescope and related systems
•
•
•
Adaptive optics
Instrument concepts
Site selection and characterization
Pat McCarthy:
• Science priorities and capabilities
• Operations model
• Public participation
•
Status and schedule
Science with Giant Telescopes - June 2008
4
Telescope Concept
Seven x 1.1m
segmented secondary
mirror (3.2 m Φ)
Alt-az mount
Seven x 8.4 m segmented
borosilicate primary mirror
Laser house
Pier
Science with Giant Telescopes - June 2008
Telescope stats
Height: 38.7 meters
1,125 metric tons
Lowest Mode: 4.5 Hz
(4.3 Hz with pier)
5
Operating modes
• Natural seeing operation
• 20´ “Wide-Field” mode
• Multiple AO modes
• Laser Tomography AO
(LTAO)
• Ground layer AO (GLAO)
• High contrast AO (ExAO)
• Future MCAO, MOAO
Science with Giant Telescopes - June 2008
6
How Big Is It?
Full Diameter: 25.4 m
Diffraction limit equivalent 24.5 m
Circular aperture 22 m
Science with Giant Telescopes - June 2008
7
8.4 m Primary Mirror Segments
Off-axis, highly aspheric require the development of new
casting/generating/polishing techniques
Metrology challenge
Provide multiple independent surface figure verification tests
Each mirror takes ~3.5 years
Production pipeline to produce a mirror every 10-12 months
Pacing item for GMT completion
Prototype off-axis segment to retire technical & schedule risk
Science with Giant Telescopes - June 2008
8
GMT1 casting
May 2005
Science with Giant Telescopes - JuneJul
20082005
Jun 2005
Nov 2005
9
Processing stages
Pipeline processing
1. Casting
2. Clean-out
3. Rear surface processing
a. Generating
b. Grind & polish
c. Loadspreader attachment
4. Front surface processing
a. Generating
b. Grind & polish
c. Final figuring
Science with Giant Telescopes - June 2008
Mar 2006
10
SOML Polishing Lab
Test
tower
LOG
LPM
Stressed
lap
Science with Giant Telescopes - June 2008
11
Optical Testing
Metrology is the greatest challenge
•
High degree of aspheric departure ~14 mm
•
Requirement that segments match to high accuracy
•
•
ΔRc < 0.3 mm (0.0006%)
•
Repeatability over 10 years of production
Use compensators to relax tolerances
Principal test – full aperture, nulling interferometer
•
In-process testing during polishing
Verification Tests:
1. Laser tracker Plus test- pre-polish generation & independent loworder figure verification
2.
Scanning pentaprism- final low-order figure verification
3.
Shear test- high frequency errors
Science with Giant Telescopes - June 2008
12
New Test Tower
23.5 m
vertex to vertex
Science with Giant Telescopes - June 2008
13
M1 Fold sphere & GMT1
GMT1 Completion April 2009
GMT1
3.8 m Fold sphere
Science with Giant Telescopes - June 2008
Jan 2008
14
Segmented Gregorian Secondary Mirrors
Fast-steering secondary (FSM):
Seven 1.06 m segments aligned with
primary mirror segments
Tip-tilt & translation actuators
Adaptive secondary (ASM):
Technology developed for MMT,
LBT and VLT
View from
below
~672 actuators per segment
~4700 actuators total
Capacitive position sensors.
In-telescope calibration source.
Science with Giant Telescopes - June 2008
15
Gregorian Instrument Mounting
Intermediate size & AO instruments always “hot” - above
Large survey instruments mount below
Science with Giant Telescopes - June 2008
16
AO Relay
Science with Giant Telescopes - June 2008
17
AO System on Instrument Platform
LGS
WFS
Science with Giant Telescopes - June 2008
18
Instrument Concepts
Instrument
Function
l range
Resolution
FOV
(microns)
GMACS
Optical Multi-Object
Spectrometer
0.35-1.0
250-4000
36-144
arcmin^2
NIRMOS
Near-IR Multi-Object
Spectrometer
1.0-2.5
Up to ~4000
49
arcmin^2
QSpec
Optical High Resolution
Spectrometer
0.3-1.05
30K
1” slit
3” + fibre mode
SHARPS
(G-CLEF)
Optical High Resolution
(Doppler) Spectrometer
0.4-0.7
150K
7 x 1” fibers
GMTNIRS
Near-IR High-Resolution
Spectrometer
1.2- 5.0
25K-100K
Single object
MIISE
Mid-IR Imaging
Spectrometer
3.0-25.0
1500
30”
HRCam
Near-IR AO Imager
0.9-5.0
5-5000
30”
GMTIFS
NIR AO-fed IFU
0.9-2.5
3000-5000
3”
Science with Giant Telescopes - June 2008
19
“Telecentric” Corrector/ADC (20’ FOV)
BK7
ADC
Telecentrator
Exit pupil
1.53 m dia
Focal plane
BK7 & LLF6
Fused Silica
RMS polychromatic image diameter at r = 10′
uncorrected
corrected
= 0.62 arcsec
= 0.07 arcsec
Science with Giant Telescopes - June 2008
Residual dispersion @ ZD = 50º:
No ADC correction: 1.97
With ADC: 0.17
20
Wide-field Corrector/ADC
Corrector
removed
M1 cell #7
ADC
Instrument Platform
Telecentrator
Science with Giant Telescopes - June 2008
21
GMACS
• Multi-object, multi-slit spectrograph
• 4x spectrographs, each with
red and blue arms, VPH gratings
• Field of view: 8 x 18 arcmin
• Wavelength range 0.36 – 1.02 μm
• Collimated beam diameter: 300 mm
Science with Giant Telescopes - June 2008
• Resolving power w/ 0.7 arcsec slit:
R ~ 1400 in blue
R ~ 2700 in red
(for accurate sky subtraction)
cross-over at 6500 Å
• Separate 8 x 9 arcmin imaging
channel
22
GMACS – Optical Layout x4
Science with Giant Telescopes - June 2008
23
NIRMOS
• Wavelength range: 0.85 – 2.5 μm
• Imaging Mode:
• 7 x 7 arcmin field of view
• 0.067 arcsec/pixel
• 6kx6k detector
• Spectroscopy Mode:
• Multi-slits: 140 x 3 arcsec long,
full wavelength coverage
• 5 x 7 arcmin field of view
• R ~ 3000 with 0.5 arcsec slits
• Augmented by GLAO
Science with Giant Telescopes - June 2008
24
Gregorian Instrument Rotator
Instrument
platform (IP)
Hydrostatic
bearings (6)
C-rings &
K-bracing
Oil
trough
Science with Giant Telescopes - June 2008
Lift platform
(not shown)
25
GMACS, NIRMOS & MIISE
Science with Giant Telescopes - June 2008
26
QSpec
• Four beam instrument
• 450 mm beam diameter
• R4 echelle gratings (x2):
200 x 1600 mm
• Rφ = 30,000 arcsecs
• λλ = 300 nm to 1.07 µm
(in four channels)
• 2-pix resolution: R=125,000
• Pupil anamorphism
• White pupil design
• VPH grating cross-dispersion
• Four catadioptric cameras
• 4k x 6.5k to 6k x 8k CCDs
(15 µm pixels)
Science with Giant Telescopes - June 2008
Red: 536 to 734
nm
NIR: 723 to 1072
nm
1m
UV: 299 to 389
nm
Blue: 383 to
545 nm
27
SHARPS
• Planet Doppler spectroscopy
• Fiber-fed: 7x(obj,sky,cal) x 1.0” 
• Resolving power ~ 150,000
• Wavelength: > 4400 – 6700 Å
• White pupil spectrograph design
Science with Giant Telescopes - June 2008
• CCD mosaic detector
• Deep depletion CCDs for red orders
• Vacuum-enclosed spectrograph
• High-stability thermal environment
• Bulky enclosure
28
MIISE – Mid-IR Imaging Spectrometer
3-5 μm detector
8-25 μm
detector
input from
AO feed dichroic
nulling channel
long wavelength
imaging channel
2 micron
phase sensor
Science with Giant Telescopes - June 2008
• Wavelength range: 3 - 25 μm
• Field of view: 30 – 40 arcsec
• Resolving power: R ~ 1500
• Modes:
• Imaging
• Spectroscopy
• Nulling (8-25 μm)
• Coronography (3-5 μm)
• Short wavelength channel: 3-5μ,
0.010 arcsec/pixel
• Long wavelength channel: 8-25μ,
0.030 arcsec/pixel
29
GMTIFS – GMT Integral Field Spectrograph
•
•
•
•
Single-object, AO-corrected, integral-field spectroscopy
Wavelength range: 1.0 – 2.5 μm
Resolving power: 4000 – 5000
Range of spatial sampling and fields of view:
• Galaxy dynamics: 0.05-0.10 arcsec sampling, 2-3 arcsec FOV
• Black hole masses: Diffraction-limited sampling, small FOV
Spaxel size along slit (arcsec)
0.008
0.016
0.032
0.054
Slitlet width (arcsec)
0.020
0.040
0.080
0.135
Field of view (arcsec)
0.80
1.6
3.2
5.4
Tel focus
F-converter
slicer
fold
collimator
detector
grating
Science with Giant Telescopes - June 2008
camera
30
Sites
Science with Giant Telescopes - June 2008
Google
31
Seeing Percentiles- LCO sites
Location
FWHM 25%
arcsecs
FWHM 50%
arcsecs
FWHM 75%
arcsecs
FWHM 90%
arcsecs
Manquis Ridge
0.55
0.68
0.87
1.10
Manqui Peak
(Magellan)
0.51
0.63
0.80
0.99
Alcaino Peak
0.51
0.63
0.80
1.00
Campanas Peak
0.51
0.64
0.81
1.00
Use nights suitable for observing and on which all DIMMS were operating
and operators were on site.
Reporting period: November 12, 2005 through November 19, 2007
covering all seasons.
Total nights/samples: 323/82K
Science with Giant Telescopes - June 2008
32
GMT Facility on Campanas Peak
Enclosure
Control Building
(Below)
Equipment Building
Facility Building
Auxiliary Building
Science with Giant Telescopes - June 2008
Prevailing
winds
33
Science Drivers for the GMT
• Science
Priorities
• Operations Model
• Public Participation
• Status and Schedule
Science with Giant Telescopes - June 2008
34
GMT Science Drivers
Three Approaches:
Discovery Space
Synergy with Current and Future Facilities
Contemporary Science Drivers
Scientific Strengths of the GMT Design:
High angular resolution - 10mas at 1m
Large collecting area - 380 m2 - 10 x Magellan 6.5m
Wide Field - practical paths to seeing-limited survey instruments
Gregorian Adaptive Secondary - GLAO, Great mid-IR performance
Short response time for TOOs
Science with Giant Telescopes - June 2008
35
Discovery Space
100pc z = 1
10
100
KPC
AU
1000
100
10
10
1
0.3
0.5
1.0
2.0 3.0
5.0
10
1
0.1
20
Wavelength (m)
Science with Giant Telescopes - June 2008
36
Discovery Space
3
2
-
mAB
Seeing Limited
1
0
20
Adaptive Optics
22
8m limit
Gain
Spectroscopy
24
26
-1
GMT limit
28
-2
30
-3
0.3
0.5
1.0
2.0
3.0
5.0
10
20
Wavelength (m)
Science with Giant Telescopes - June 2008
37
GMT SCIENCE: CONTEXT & SYNERGY
Broad Synergy Across Wavelength,
Spatial and Time Domains
JWST
Physical Diagnostics
Deep/Wide Surveys
High-resolution imaging
High SNR & Res. Spectroscopy
ALMA
LSST
SKA
Science with Giant Telescopes - June 2008
Magellan
38
Complementarity with JWST
 Pic at 11m
JWST
JWST
GMT
GMT
10 AU
ALMA
GMT has 4 times the spatial resolution….
Science with Giant Telescopes - June 2008
and up to 100 times the spectral resolution
39
GMT Science Goals
• Planets and Their Formation
• Stellar Populations and Chemical Evolution
• Assembly of Galaxies
• Black Holes in the Universe
• The Accelerating Universe
• First Light and Reionization of the Universe
http://www.gmto.org/sciencecase
Science with Giant Telescopes - June 2008
40
Updates to the GMT Science Case
New Tools:
Quantitative Science Use Cases
Exposure-Time Calculators
Spectral & Imaging Simulation Software
Examples:
• Near- and mid-IR Exoplanet Studies
D4 or faster
• AO Imaging of Resolved Stellar Populations
• Near-IR Spectroscopy of Galaxies at z ~ 2
• Ly Emission at z > 6
Science with Giant Telescopes - June 2008
GLAO &
Seeing-limited
41
Exoplanets in Reflected Light
Exoplanets are faint!…
Jupiter reflects 10-9 Lsun
Earth reflects 10-10 Lsun
…and close in
Jupiter 0.5´´ @ 10pc
Earth 0.1´´ @10pc
Suppression of
diffraction is essential
Coronagraphy, phase modulation, nulling, -lensing, transits, PRV
Science with Giant Telescopes - June 2008
42
GMT PSF
with phase apodization
1.65 m, 5% band. Diffraction only, no
wavefront error
10-6 suppression at 4 l/D, 56 mas
Science with Giant Telescopes - June 2008
10-5 companion
43
Planets and Their Formation
A handful of known exoplanets are detectable in reflection with GMT
Science with Giant Telescopes - June 2008
44
Mid-IR Imaging of Exoplanets
(Phil Hinz - Arizona)
L band detection limit 40x improved with ~3x
larger diameter
1 hour 5 sigma limits
3.8 um: 25 Jy
3 λ/D: 0.48”
10 um: 750 Jy
3 λ/D: 1.0”
Detect 5-10 MJ giant planets
100-300 zody warm debris
disks
3.8 um: 0.6 Jy
3 λ/D: 0.11”
10 um: 18 Jy
3 λ/D: 0.25”
Detect <1 MJ planets
3-10 zody warm debris disks
GMT can undertake comprehensive study of giant
planets in > 3 AU range around stars at 30 pc.
45
Terrestrial Planets - 10 micron imaging
280K habitable planets detectable at 10m around nearby stars.
1 – 5 rE, 0.5 – 5 AU
Star
Alpha Cen A
alpha Cen B
Sirius
eps Eri
Procyon
tau Ceti
Altair
beta Hyi
Fomalhaut
d (pc)
1.35
1.35
2.64
3.22
3.5
3.65
5.14
7.47
7.69
a=280 K (AU) ang. dist. (“)
1.04
0.77
0.65
0.48
6.3
2.39
0.56
0.17
1.72
0.49
0.78
0.21
3.36
0.65
2.1
0.28
4.91
0.64
Brightness limit=25 Jy
Earth flux (uJy)
26.34
26.34
6.89
4.63
3.92
3.6
1.82
0.86
0.81
Blue is within 3 l/D
min. size (R_e)
0.97
0.97
1.91
2.32
2.53
2.63
3.71
5.39
5.55
Rocky Planets at 4 microns
600K hot rocky planets detectable at 4 m
0.1 – 1 AU, 0.14 – 1 rE
Star
Alpha Cen A
alpha Cen B
Sirius
eps Eri
Procyon
tau Ceti
Altair
beta Hyi
Fomalhaut
beta Leo
d (pc)
1.35
1.35
2.64
3.22
3.5
3.65
5.14
7.47
7.69
11.1
a=600 K (AU)
0.23
0.14
1.37
0.12
0.38
0.17
0.73
0.46
1.07
1.07
ang. dist. (“)
0.17
0.1
0.52
0.04
0.11
0.05
0.14
0.06
0.14
0.1
hot Earth (uJy)
109.74
109.74
28.7
19.29
16.33
15.01
7.57
3.58
3.38
1.62
mini. size (R_e)
0.14
0.14
0.26
0.32
0.35
0.37
0.51
0.75
0.77
1.11
Brightness limit=2 Jy
AO Imaging of Resolved Stellar Systems
Globular Cluster around Cen A
HST
3.8Mpc
Gemini
3pc core radius
H-band
GMT
4mas pixels
2
Science with Giant Telescopes - June 2008
48
AO Imaging of Resolved Stellar Systems
Globular Cluster around Cen A
Gemini
3.8Mpc
3pc core radius
H-band
GMT
See Knut Olsen’s chapter in the GSMT book
Science with Giant Telescopes - June 2008
49
Operations Philosophy
Use observing time as efficiently as possible (“Flexible”)
• Provide technical expertise during observations
• Use best conditions most effectively
• Be able to switch programs and instruments quickly
• Enable time-critical observations
Retain benefits of on-site PI’s where practical (“Assisted”)
• Guest observers interact with instrument, data & staff in real time
Science with Giant Telescopes - June 2008
50
Observing Modes
• Semi-Classical PI observing
• Block-scheduled time, PI/team present and may run instrument
• Best for large programs or campaigns
• Remote PI observing
• Block-scheduled time, PI/team remote (video link)
• Queue-scheduled service observing
• Observatory staff execute a queue of observations as appropriate
for the conditions. Preferred mode for TOO & synoptic
Projected Staffing Level
• 120 FTEs split between Chile (86) and the US (34)
Science with Giant Telescopes - June 2008
51
Science & Data Archives
• Baseline operations plan includes only bare-bones
archive - “save the bits”++, NVO compliance etc .
• Pipeline software expected to be part of instrument
contracts, maintained by the observatory.
• Community input sought on issues relating to valueadded features, high-level data products, interfaces.
Issues:
Proprietary period, costs, role of national centers, NVO,
international partners participation
Science with Giant Telescopes - June 2008
52
Public Participation in GMT
How much time could be available through federal participation?
25-30% NSF share ~ 80 - 100 nights
Science with Giant Telescopes - June 2008
53
Public Role in GMT
What role can AURA & the community play in the development of GMT?
• Instrument development and selection
• Conceptual development
• Science teams associated with instruments
• Input into selection priorities
• Operations planning
• Operational models
• Refined cost planning
• Definition of archive and other value-added products
• Participation in planning and execution of large science programs
• Development of PI-level science projects
GMT Public Policy White Paper: www.gmto.org/overview
Science with Giant Telescopes - June 2008
54
Instrument Selection Timescale
Call for new and continuing concept studies
Winter 07/08
Design reviews
Fall 2010
Selection of first generation instruments
Fall 2010
Second generation instruments defined
Mid 2012
First instruments delivered to Chile
Fall 2016
There remains time and opportunity for the community to be engaged in
the instrument development and selection process
GMT is open to considering complementarity with TMT in first & second
generation instrument suites
Science with Giant Telescopes - June 2008
55
Legal Niceties
The GMT Founder’s Agreement:
Defines organizational structure
Determines governance procedures
Specifies how $$
access
Transfers responsibility to the GMTO Corp.
The GMTO Corporation
A not-for-profit company
Will assume responsibility for the project
Science with Giant Telescopes - June 2008
56
Status and Schedule
You are here
Science with Giant Telescopes - June 2008
57
Science with Giant Telescopes - June 2008
58
Download