Public Meeting IH 35 FROM: Denton County Line TO: Red River May 28, 2009 1 Project Development Process Plan We Are Here Design Construct 2 Planning Authorization • • • • Prepare route studies & design layouts. Perform environmental impact studies. Conduct public meetings and hearings. Complete the necessary right of way determination including drafting the right of way map. 3 Design Authorization • Prepare the construction plans. • Acquire the necessary right of way. • The amount of projects in development is constrained to seven years of anticipated funding. • No design or construction funding is currently available or authorized. • Upon planning phase completion, funds may be solicited. 4 Construction Authorization • Complete the construction plans. • Perform the utility adjustments. • Award contract for construction. 5 IH 35 Project Development Current scope of work: • Prepare route studies - design layouts. • Prepare environmental assessment. • Conduct public meetings. 6 Initially Suggested Alternatives Design prepared for Year 2030 traffic • Alternative I – Six-lane (three lanes in each direction) barrier separated roadway with two-lane one-way frontage roads; follows existing IH 35 alignment where possible • Alternative II – Same as Alternative I with the addition of a grassy median for possibility of future inside fourth lane in each direction • Alternative III – Six-lane (three lanes in each direction with a grassy median and room for future expansion) roadway without frontage roads on a new alignment • Multiple alignment alternatives around Valley View 7 Mobility Needs Design accommodates Year 2030 Traffic: • 2005 Existing Traffic – 42,000 ADT • 2030 Forecast Traffic – 80,000+ ADT ADT – Average Daily Traffic Both Directions 8 Existing Freeway 9 Proposed Freeway Alternative I 10 Proposed Freeway Alternative II 11 Proposed Freeway Alternative III 12 13 Preferred Alternative Alternative II 14 Preferred Alternative II Selection Considerations • Public Comment and Preference • Refined based on design considerations • Analyzed in Value Engineering Study • Determined traffic required four lanes in each direction 15 Preferred Alternative Typical Section 16 Preferred Alternative Typical Section in Constrained Areas 17 Environmental • We are looking at the project constraints and building a base for use in the future environmental assessment. 18 19 20 21 22 23 24 25 26 27 28 29 30 31 BNSF Railroad Alternative Alignment 32 Project Website • www.dot.state.tx.us/project_ information/projects/wichita _falls/i35_cooke_county 33 IH 35 Study Team TxDOT – Wichita Falls District Federal Highway Administration Jacobs Engineering Group, Inc. 34 Thank You 35