Kelvin Droegemeier: Future of Project CRAFT: Technical Options, Costs, Scenarios

advertisement
The Collaborative
Radar Acquisition
Field Test (CRAFT):
Next Steps
Kelvin K. Droegemeier
University of Oklahoma
2nd Level II Stakeholders Workshop
26-27 September 2002
Norman, Oklahoma
NCDC
The Issues Before Us



Grant funding for CRAFT communication links and
personnel is nearly exhausted (data will stop flowing
from CAPS sometime in November)
The private and academic sectors are finding value in
real time Level II data
A real time Level II NWS collection system
– is likely more than 1 year away
– may not provide the latencies and reliability needed by the
private sector for the short term
– may be perfectly suited for meeting all needs in the longer
term


What options exist?
How can we maximize the benefits to all stakeholders:
Government, industry, academia?
Options

A wide range of potential options exists, all of which
require Government approval
– Shut CRAFT down and wait for the NWS system





Timeline not yet defined
Not clear the NWS system will meet non-Government user needs
We likely won’t know until the system is in place
If it does meet all user needs, we’re set
If it does not, no alternative will exist (might take months to create)
– Continue the present collaborative system (58 radars) or expand
to all 120 NWS radars (lots of sub-options)
– Create a stand-alone system that includes all 120 NWS WSR-88D
radars, serves as a back-up to whatever the NWS implements, and
has 7x24 support, improved reliability, etc


Must consider administration of system (later in talk)
The ideal perhaps is a partnership among all groups, with
“partnership” defined many ways
Suppose the NWS Deploys
and Manages its Own Level II
Distribution System
(a very sensible approach)
CRAFT as a Scalable System:
The Current Concept
Expanded for “Operational”
Deployment
Logical Network Topology
LDM Server
Logical Network Topology
LDM Server
OU
At the moment, OU
is the only server –
Single points of failure
(server and line from
each radar)
Logical Network Topology
LDM Server
Universities
NOAA Laboratories
NOAA Joint Institutes
NCAR/UCAR
MIT/Lincoln Lab
NWS Regional HQ,
NCEP Centers, RFCs
Logical Network Topology
LDM Server
Universities
NOAA Laboratories
NOAA Joint Institutes
NCAR/UCAR
MIT/Lincoln Lab
NWS Regional HQ,
NCEP Centers, RFCs
These already exist!!
Logical Network Topology
via phone lines
or commodity
Internet
Commodity Internet
LDM Server
Abilene Backbone
(no commercial traffic)
LDM Server
LDM Server
LDM Server
LDM Server
LDM Server
LDM Server
LDM Server
LDM Server
LDM Server
Abilene Network
LDM Server
LDM Server
LDM Server
Each LDM “Hub Site” Carries all 88D
data on Abilene “bus”-- redundancy
LDM Server
LDM Server
LDM Server
Abilene Network
LDM Server
LDM Server
LDM Server
HUB
HUB
HUB
HUB
HUB
HUB
HUB
LDM Server
LDM Server
LDM Server
Abilene Network
LDM Server
LDM Server
LDM Server
LDM Server
Commodity Internet
LDM Server
Commodity Internet
LDM Server
Abilene Network
LDM Server
Commodity Internet
LDM Server
LDM Server
Commodity Internet
Commodity Internet
Commodity Internet
LDM Server
Commodity Internet
LDM Server
Commodity Internet
LDM Server
Abilene Network
LDM Server
Commodity Internet
LDM Server
LDM Server
Commodity Internet
Commodity Internet
Commodity Internet
LDM Server
Commodity Internet
LDM Server
Commodity Internet
LDM Server
Abilene Network
LDM Server
Commodity Internet
LDM Server
LDM Server
Commodity Internet
Commodity Internet
Commodity Internet
LDM Server
Commodity Internet
LDM Server
Commodity Internet
LDM Server
Abilene Network
LDM Server
Commodity Internet
LDM Server
LDM Server
Commodity Internet
Commodity Internet
Commodity Internet
Commodity Internet
Commodity Internet
LDM Server
Commodity Internet
LDM Server
LDM Server
Abilene Network
LDM Server
LDM Server
Commodity Internet
Customers
LDM Server
LDM Server
Commodity Internet
Commodity Internet
Private
Company
LDM Server
LDM Server
LDM Server
Abilene Network
LDM Server
LDM Server
LDM Server
Features of this Concept


NOAA runs its own operational ingest system but
allows connections to the BDDS of each NWS radar
The CRAFT configuration
– Is completely scalable to more nodes or radars
– Is highly redundant (each major hub server contains all of
the data)
– Is highly reliable (loss of a major hub has minimal impact)
– Leverages existing infrastructure
– Links easily to other networks (e.g., AWIPS)
– Has significant capacity for future growth (dual-pol, phased
array)
– Could have dual communication lines from each radar
– Could serve as a backup system for the NWS
Features of this Concept




Many variants exist
May require enhancements to LDM, e.g., multi-cast
Must consider support of LDM to the commercial
sector
Key point is to create a national hierarchical
distribution system along the lines of the current
Unidata IDD
Primary Ingest Node
Source
LDM
LDM
LDM
Source
Source
LDM
LDM
LDM
Internet
LDM
LDM
LDM
Source
LDM
LDM
LDM
Source
Source
LDM
LDM
LDM
Internet
LDM
LDM
LDM
Relay Node
Leaf Nodes
Source
LDM
LDM
LDM
Source
Source
LDM
LDM
LDM
Internet
LDM
LDM
LDM
8 Scenarios (6 Detailed)
and
Provisional Costs
Possible Scenarios

Scenario #1: Maintain the current system of 58
radars with OU as the single ingest node
– Assumptions

Line charges paid by same groups as now, at the same rates
Possible Scenarios

Scenario #1: Maintain the current system of 58
radars with OU as the single ingest node
– Assumptions

Line charges paid by same groups as now, at the same rates
–
–
–
–
–
–

6 Sea Grant sites:
$31K/year
6 SRP sites
$72K/year
21 MIT sites
$200K/year
4 Florida sites
$5K/year
10 OU sites
$80K/year
11 other sites FSL, NASA, GTRI, SLC, RAP, SEA (no cost
estimates available)
Total leveraging is ~ $450,000 per year
Possible Scenarios

Scenario #1: Maintain the current system of 58
radars with OU as the single ingest node
– Assumptions






Line charges paid by same groups as now, at the same rates
No significant s/w development or 7x24 QOS
Maintain current OU staff levels (C. Sinclair at 1.0 FTE and
S. Hill at 0.5 FTE)
$20K for h/w replacement, $10K for travel (per year)
$1K for supplies (per year)
KD, DJ, DE at 1 month each (1.0 FTE) (per year)
– Yearly cost: $355,000 (could be reduced by
shifting some existing lines to cheaper alternatives)
– Advantages


No additional h/w costs (above replacement)
Continue using a proven reliable infrastructure
Possible Scenarios
– Disadvantages








Not all radars are included
Continue with heterogeneous communications
infrastructure, latency problems
Relies on existing groups to continue paying their
local costs
Little increase in QOS (i.e., no 7x24)
56K lines will continue to fall behind in weather
Single ingest system at OU provides no redundancy
Reliance upon university for private sector missioncritical needs
No clear path to deal with data volume increase;
however, this may not be critical if NWS system is
available relatively soon
Possible Scenarios

Scenario #2: Same as Scenario #1, but add
the remaining 64 NWS radars
– Additional assumptions







New CAPS technical staff member ($40K/year) for QOS and
other work
$100K in one-time costs for PCs
$200K for one-time line installation costs and routers
$50K in travel
$5K for supplies
$50K in h/w replacement costs and hot spares
30 new lines cost average of current OU lines; rest cost
$50/month based on DSL/cable modem
– Year-1 cost: $1.3M (could be reduced by shifting
some existing lines to cheaper alternatives)
– Beyond Year-1: Estimate $900,000/year
Possible Scenarios
– Advantages




No additional h/w costs (above replacement)
Continue using a proven reliable infrastructure
All 120 NWS radars available
Improved QOS via 2nd OU staff person
Possible Scenarios
– Disadvantages







Not all radars are included
Continue with heterogeneous communications
infrastructure, latency problems
Relies on existing groups to continue paying their
local costs
Little increase in QOS (i.e., no 7x24)
56K lines will continue to fall behind in weather
Single ingest system at OU provides no redundancy
Reliance upon university for private sector missioncritical needs
Possible Scenarios

Scenario #3: Same as Scenario #2, but add
UCAR as a second Abilene ingest node
– Additional assumptions


$100K in computer hardware at UCAR
One new UCAR technical staff member
– Year-1 cost: $1.5M (could be reduced by shifting
some existing lines to cheaper alternatives)
– Beyond Year-1: Estimate $1.2M/year
– Note: Could possibly add MIT/LL as third redundant
node, but this has not been discussed with them
Possible Scenarios
– Advantages





No additional h/w costs (above replacement)
Continue using a proven reliable infrastructure
All 120 NWS radars available
Improved QOS via 2nd OU staff person
Greatly improved redundancy, reliability, latencies
Possible Scenarios
– Disadvantages







Not all radars are included
Continue with heterogeneous communications
infrastructure, latency problems
Relies on existing groups to continue paying their
local costs
Little increase in QOS (i.e., no 7x24)
56K lines will continue to fall behind in weather
Single ingest system at OU provides no redundancy
Reliance upon university for private sector missioncritical needs (not clear that UCAR can provide
needed QOS)
Scenario Summaries (1-3)
No.
Radars
Ingest
Nodes
Communications
Infrastructure
QOS
Yearly Cost
Scenario 1
58
OU
Current
Heterogeneous Mix*
Low
$0.36M
Scenario 2
122
OU
Current
Heterogeneous Mix*
Med
$1.3M (Yr 1)
$0.9M (Yr 2)
Scenario 3
122
OU &
UCAR**
Current
Heterogeneous Mix*
High
$1.5M (Yr 1)
$1.2M (Yr 2)
* Leverages $450K/year paid by other organizations
** Could try and add MIT/LL as third node
Possible Scenarios

Scenario #4: Same as Scenario #3, but with a
national telecommunications carrier providing
uniform delivery service to the additional 64
radars only
– Additional assumptions





AT&T line costs for 2-year contract for 64 additional radars
is $850,000/year.
Mixture of T1, DSL
Note that these costs have not been negotiated and likely
could be reduced substantially (might also be able to
eliminate T1 lines)
Removes need for one-time installation charges and router
costs
Still have the costs of the 64 new LDM PCs
– Yearly cost: $2.1M (hope this could be brought
down to $1.6 or $1.7M with tough negotiation)
Possible Scenarios
– Advantages







No additional h/w costs (above replacement)
Continue using a proven reliable infrastructure
All 120 NWS radars available
Improved QOS via 2nd OU staff person
Greatly improved redundancy, reliability, latencies
Uniform networking for 64 radars
QOS should be much higher (AT&T rapid response)
Possible Scenarios
– Disadvantages







Not all radars are included
PARTLY heterogeneous communications
infrastructure, latency problems
Relies on existing groups to continue paying their
local costs
Little increase in QOS (i.e., no 7x24)
56K lines will continue to fall behind in weather
Single ingest system at OU provides no redundancy
Reliance upon university for private sector missioncritical needs
Scenario Summaries (1-4)
No.
Radars
Ingest
Nodes
Communications
Infrastructure
QOS
Yearly Cost
Scenario 1
58
OU
Current
Heterogeneous Mix*
Low
$0.36M
Scenario 2
122
OU
Current
Heterogeneous Mix*
Med
$1.3M (Yr 1)
$0.9M (Yr 2)
Scenario 3
122
OU &
UCAR**
Current
Heterogeneous Mix*
High
$1.5M (Yr 1)
$1.2M (Yr 2)
Scenario 4
122
OU &
UCAR**
AT&T for New 64
Radars
High
$1.6 to $2.1M
* Leverages $450K/year paid by other organizations
** Could try and add MIT/LL as third node
Possible Scenarios

Scenario #5: Same as Scenario #4, but with a
national telecommunications carrier providing
uniform delivery service to all radars
– Additional assumptions





AT&T line costs for 2-year contract for all radars is
$1.4M/year.
Mixture of T1, DSL
Note that these costs have not been negotiated and likely
could be reduced substantially (might also be able to
eliminate T1 lines)
Removes need for one-time installation charges and router
costs
Still have the costs of the 64 new LDM PCs
– Yearly cost: $2.8M (hope this could be brought
down to $2.2 or $2.3M with tough negotiation)
Possible Scenarios
– Advantages








No additional h/w costs (above replacement)
Continue using a proven reliable infrastructure
All 120 NWS radars available
Improved QOS via 2nd OU staff person
Greatly improved redundancy, reliability, latencies
Uniform networking for ALL radars
QOS should be much higher (AT&T rapid response)
Increased bandwidth needs (e.g., dual-pol, new VCP,
¼ km by ½ degree resolution) could be handled by
the telecomm carrier “automatically”
Possible Scenarios
– Disadvantages
 Not all radars are included
 PARTLY heterogeneous communications
infrastructure, latency problems
 Relies on existing groups to continue paying their
local costs
 Little increase in QOS (i.e., no 7x24)
 56K lines will continue to fall behind in weather
 Single ingest system at OU provides no redundancy
 Reliance upon university for private sector missioncritical needs
Scenario Summaries (1-5)
No.
Radars
Ingest
Nodes
Communications
Infrastructure
QOS
Yearly Cost
Scenario 1
58
OU
Current
Heterogeneous Mix*
Low
$0.36M
Scenario 2
122
OU
Current
Heterogeneous Mix*
Med
$1.3M (Yr 1)
$0.9M (Yr 2)
Scenario 3
122
OU &
UCAR**
Current
Heterogeneous Mix*
High
$1.5M (Yr 1)
$1.2M (Yr 2)
Scenario 4
122
OU &
UCAR**
AT&T for New 64
Radars
High
$1.6 to $2.1M
Scenario 5
122
OU &
UCAR**
AT&T for ALL Radars
High
$2.2 to $2.8M
* Leverages $450K/year paid by other organizations
** Could try and add MIT/LL as third node
Other Scenarios

Scenario #6: Use NWS River Forecast Centers
as points of aggregation
– May make sense only if the NWS wishes to pursue a
non-AWIPS collection strategy
– The general CRAFT concept still could be applied


Scenario #7: Use the Planned NWS
Distribution System
Scenario #8: Create a System Operated
Entirely by the Private Sector (no university or
UCAR involvement)
Administrative Structure

Points of Reference (for the sake of argument)
– Must be able to ensure 7x24 service (high reliability)
– Latency must be as low as possible
– Government receives data at no cost but could/should cost
share overall expenses in light of benefits to NCDC (direct
ingest for long-term archive), NCEP, FSL, NWS Offices (Level
II recorders)
– Educational institutions receive data at no cost
– Presumably don’t want another “NIDS arrangement”

Options
–
–
–
–
–
For-profit private company
University-based consortium
Not-for-profit 501(c)3
University-based center (e.g., Wisconsin for satellite data)
Others?
Key Items for Discussion


Sustaining the operation of CRAFT beyond November
Establishing private sector requirements
– Reliability
– Latency
– Hardware and software support




Meeting private (and academic) sector needs in the
short, medium and long term
Administrative issues (including data access rules)
Dealing with future data volumes
Further analysis of system capabilities
– Impact of weather on data reliability/latency
– Networking simulation
Download