June 2008 Finance and Budget Presentation President Nancy L. Zimpher Monica Rimai, Senior VP, Administration and Finance June 24, 2008 1 Presentation Agenda • FY 2008 Close • Operating • Capital • FY 2009 Budget • Operating • Capital • Status on 3-5 Year Plan 2 FY 2008 Year End Projection University of Cincinnati Uptown Campus General Funds FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 477,760,429 2008 YTD Actuals 466,805,150 Uncommitted Budget Balance 10,955,279 477,760,429 Expenses 429,055,100 371,775,885 57,279,215 429,055,100 Transfers 48,705,329 47,739,357 965,971 48,705,329 0 47,289,907 Net Change 3 (47,289,907) Projected Year End 0 FY 2008 Year End Projection University of Cincinnati Raymond Walters General Funds FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 28,685,391 2008 YTD Actuals 28,119,928 Expenses 27,885,892 23,929,128 Transfers Net Change 799,499 787,606 0 3,403,194 4 Uncommitted Projected Year Budget End Balance 565,463 28,685,391 3,956,764 27,885,892 11,893 799,499 (3,403,194) 0 FY 2008 Year End Projection University of Cincinnati Clermont College General Funds FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 17,904,367 2008 YTD Actuals 17,475,229 Expenses 17,843,871 13,925,318 Transfers Net Change Uncommitted Projected Year Budget End Balance 429,138 17,904,367 3,918,553 60,496 232,590 (172,093) 0 3,317,321 (3,317,321) 5 17,843,871 60,496 0 FY 2008 Year End Projection University of Cincinnati Campus Services Auxiliary FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 48,733,000 2008 YTD Actuals 58,905,321 Expenses 31,774,000 36,651,564 Net Transfer 20,017,000 20,365,808 Change in Fund Balance (3,058,000) 1,887,949 6 Uncommitted Projected Year Budget End Balance 3,767,000 62,672,321 5,083,949 41,735,513 0 20,365,808 (1,316,949) 571,000 FY 2008 Year End Projection University of Cincinnati Parking Auxiliary FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 16,376,993 2008 YTD Actuals 13,330,868 Expenses 7,998,299 5,179,927 Net Transfer Change in Fund Balance Uncommitted Projected Year Budget End Balance 3,046,125 16,376,993 2,818,372 6,640,561 9,736,431 9,736,431 9,546,646 189,786 (1,357,738) (1,395,705) 37,967 7 0 FY 2008 Year End Projection University of Cincinnati Athletics FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 22,758,161 2008 YTD Actuals 14,097,205 Expenses 30,793,276 29,288,495 Net Transfer (5,372,182) (5,281,148) Change in Fund Balance (2,662,933) (9,910,142) 8 Uncommitted Projected Year Budget End Balance 8,660,956 20,777,900 1,504,781 (91,035) 7,247,210 28,277,582 (4,816,283) (2,683,399) FY 2008 Year End Projection University of Cincinnati Designated funds FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 97,371,346 2008 YTD Actuals 100,711,922 Expenses 142,464,092 99,316,526 43,147,566 119,117,000 Net Transfer (11,923,290) (55,135,175) 43,211,885 (55,135,175) Change in Fund Balance (33,169,456) 56,530,571 (89,700,027) 48,263,175 9 Uncommitted Projected Year Budget End Balance (3,340,576) 112,245,000 FY 2008 Year End Projection University of Cincinnati Restricted Funds FY 2008 Year End Projection For Period Ending May 31, 2008 Revenue 2008 Current Budget 308,270,114 2008 YTD Actuals 296,250,298 Uncommitted Budget Balance 12,019,816 326,719,108 Expenses 349,680,533 285,125,341 64,555,192 314,160,000 8,146,194 11,512,515 (3,366,322) 12,559,108 (49,169,054) 0 Net Transfer Change in Fund Balance (49,556,612) (387,559) 10 Projected Year End FY 2008 Major Capital Projects 11 Major Projects in Design and Construction During FY 2008 Project Name Phase Board Approval FY Capital Budget Approved FY 2008 Expenditures Total Expenditures to Date Education and General Projects Kettering Preclinical Science Lab Renovation Construction $ 2,760,000 2007 $ 653,344 $ 756,956 Langsam Library Roof Replacement Construction $ 2,700,000 2008 560,783 560,783 McMicken Perimeter Heating System Construction $ 2,200,000 2007 1,109,743 1,246,336 MSB Rehabilitation Ph 1, CARE, & Eden Quad Construction $ 214,245,000 1999-2008 37,607,358 183,675,415 MSB Rehabilitation Ph 2 - 5 Design $ 204,000,000 2005 & 2008 3,276,254 9,307,355 Teachers College/Dyer Renovation Phase 2 Construction $ 18,900,000 2002, 2003, & 2005 9,157,882 12,101,915 Zimmer Rehabilitation Construction Closeout $ 3,100,000 1999 2,605,831 3,130,231 Construction $ 6,000,000 2007 2,041,312 2,392,910 Auxiliary Project Clifton Court Garage Total $ 453,905,000 12 $ 57,012,507 $ 213,171,901 Kettering Preclinical Science Lab Renovation Description: Renovation of space for research labs on Level 200 Justification: To meet the need for additional research space for the Department of Environmental Health Funding: Debt Total Project: $2.76 million 13 Langsam Library Roof Description: Roof replacements Justification: Complete replacement of roofs required to protect library Funding: Debt Total Project: $2.7 million 14 McMicken Perimeter Heating Description: Heating system upgrades Justification: Only half of this 1948 building’s heating systems have been replaced - the south portion in 2007 Funding: State Total Project: $2.2 million 15 MSB Rehabilitation Ph 1, Center for Academic Research Excellence (CARE), and Eden Quad Description: Renovation of 171,000 sq ft for the medical library and student service space and 240,000 of new academic & research and swing space Justification: To address research space needs and upgrades to existing MSB systems. Funding: State, Debt, Federal Grants, Gifts, Local Total Project: $204.8 million 16 MSB Rehabilitation Phases 2-5 Description: Renovation of mechanical and building systems for the 940,000 gross sq ft Medical Sciences Building Justification: The existing systems are extensive, deteriorated, and at the end of their useful life. Lab air requirements have changed Funding: State, Debt, Federal Grants, Gifts, Local Total Project: $204.0 million 17 Teachers College/Dyer Renovation - Phase 2 Description: Major renovation of approximately 1/3rd of the total complex of three buildings originally built between the 1930’s and 1950’s Justification: Major renovation needed to address deteriorated systems, windows, and building envelope; and to respond to current teaching needs and standards Funding: State, Debt, Gifts, Local Total Project: $18.9 million 18 Zimmer Rehabilitation – Phase 1 Description: Renovation of the large lecture hall, and supporting HVAC, life-safety, and audio-visual systems Justification: Furniture, finishes, audio visual, and systems dated to original construction in the 1970’s. Fire suppression of the large auditorium necessary Funding: State & Debt Total Project: $3.1 million 19 Clifton Court Garage Renovation Description: Replace top deck, replace concrete & structural steel, upgrade electric and ventilation systems Justification: Major structural repairs needed for this 1960’s-era garage Funding: State & Debt Total Project: $4.6 million 20 FY 2009 Budget 21 FY 2009 University Current Funds Budget Plan Summary of Budgeted Resources Total University Resources by Source Auxiliary Enterprises 7% Net Tuition, Fees & Other Student Charges 29% Other Resources 19% Govt. & Private Grants & Contracts 24% 22 State Appropriations 21% FY 2009 University Current Funds Budget Plan Summary of Budgeted Expenditures Total University Expenditures by Function Auxiliary Enterprises 7% Nonmandatory Transfers 4% Instructional & General 31% Mandatory Transfers 8% Scholarships & Fellow ships 4% Operation & Maintenance of Plant 5% Institutional Support 7% Student Services 4% Academic Support 9% Public23 Service 6% Separately Budgeted Research 15% FY 2009 Budget Process • Transparency • President’s Budget Advisory Committee (PBAC) • Fiscal Coordinating Committee (FCC) • Academic Operations Committee (AOC) • Faculty Senate • Cabinet • Executive Committee • Board of Trustees (BOT) 24 FY 2009 Income Assumptions • State Appropriation Increase of 9.8% $14.9M State Share of Instruction Uptown Campus 170,000,000 167,299,921 160,000,000 152,367,382 150,000,000 144,219,588 145,115,081 144,188,235 140,000,000 140,384,295 140,076,481 130,000,000 FY03 FY04 FY05 25 FY06 FY07 FY08 Projected FY09 Projected FY 2009 Income Assumptions • Tuition & Fees • Resident Undergraduate – frozen – State Mandate • Non-Resident Undergraduate – no increase – University Decision • Gross Tuition Inflation $2.3M – All Graduate Programs – increase 2% – Professional Schools – increase 2% • College of Medicine – increase additional 2% • FY08 Core Tuition Adjustment • Enrollment Increase per IEP Goals Total 26 600K 3.9M $6.8M FY 2009 New Expenditure Allocation Highlights • Achieving Academic & Research Excellence • Academic Priorities $ 1.1M • Supporting Enrollment Growth 500K • UC|21 – 21st Century Learning 1.4M • Academic Salaries 7.2M* • Funding the Research Initiative 3.0M • Library Acquisition 267K • Academic Building & Lab Integrity 1.6M • Revenue Generating Programs 3.5M *This figure represents the permanent AAUP salary increase for both FY 2008 and FY 2009 27 FY 2009 New Expenditure Allocation Highlights • Other University Expenditure Highlights • 2% Salary Increase – unrepresented staff $ 2.0M • Union Contract Salary Increase – non-faculty 650K • Performance-Based Budgeting 258K • University Diversity Initiative 350K • University-Wide Roof Repair 500K 28 FY 2009 Summary FY 09 - FY 11 Incremental Revenue & Expense Recommendation & Projections INCLUDING REVENUE GENERATING ADDITIONS Revenue: FY 09 1 Gross Tuition Inflation FY 08 Core Tuition Adjustment Enrollment Increase per IEP Goals Less Revenue Generating Increases Revenue Generating Increases (Increase)/Decrease in Graduate Scholarships (UGS) Less Undergraduate Scholarships Total Net Tuition 2,328,000 600,000 400,000 3,512,395 1,629,000 8,469,395 State Investment in Instruction2 Challenges Reduction Total Revenue 14,951,098 (37,000) 23,383,493 Expenses and Transfers: Expenses and Transfers Academic Priorities & Salaries Revenue Generating Expenses Unrepresented Staff Increases & UC|21 Initiatives Other Priorities Total Expenditures 12,619,231 3,512,395 8,222,377 0 24,354,003 FY Surplus/(Deficit) after Expenses and Transfers BUDGET REALLOCATION (970,510) 970,510 Assumptions: 1 Tuition increase of 2% for Graduate and Professional Students in FY 09. Tuition increase of 3% for all students in FY 10 and FY 11. 2 SSI increased by 2% in FY 10 and FY 11. Note: SII and tuition projections for FY 10 and FY 11 are unpredictable at this point due to a total revamp of the funding 29 formula at the state level and legislative tuition setting policies. 30 FY 2009 Capital Budget 31 Criteria for Projects • • • • • Academic Priorities STEMM Highest and Best Use of Existing Space Renovations of Existing Academic Space Sustainability 32 State Capital Appropriations 2009-2010 Biennium • Uptown Campus – Medical Science Building Rehabilitation – $26.4M – Basic Renovations - $10.7M ◦ The Procter Hall Façade Replacement project has been allocated $4.0M ◦ The remaining $6.7M has been allocated to small renovation projects below the threshold for Board approval – Instructional Equipment - $1.7M • Clermont College – Capital Allocation – $751K – Basic Renovations - $326K – Instructional Equipment - $87K • Raymond Walters College – Capital Allocation – $1.6M – Basic Renovations - $501K – Instructional Equipment - $130K 33 Projects for Budget Approval Funding Sources Project Name Approval Request Project Amount State Debt Education and General Projects Energy Savings Projects (Ongoing) Part 2 $10,000,000 $10,000,000 Kettering North Demolition/Site Preparation Initial 3,000,000 3,000,000 Procter Hall Façade Replacement Initial 4,000,000 Rieveschl 500 Level Teaching Labs Renovation Initial 6,000,000 6,000,000 Teachers College / Dyer Renovation Phase 2A Initial 2,500,000 2,500,000 Initial 10,000,000 10,000,000 $4,000,000 Auxiliary Project Morgens & Scioto Residence Hall Upgrades Total $35,500,000 34 $4,000,000 $31,500,000 Projects for Budget Approval Energy Savings Projects (Ongoing) Description: Projects to improve plant efficiencies, improve existing systems’ efficiencies and operations, and to provide major upgrades to facilities Justification: To reduce energy use, to comply with the mandates of HB 251, and to meet the commitments of the American College and University Presidents’ Climate Commitment Funding: Debt proceeds Total Project: $10.0 million 35 Projects for Budget Approval Kettering North Wing Demolition/Site Preparation Description: Demolition of North Wing Lab building Justification: Unused facility is not structurally sound and does not provide appropriate space for future research Funding: Debt Total Project: $3.0 million DRC Comments: • Agreement with building assessment • Recommend demolition approval 36 Projects for Budget Approval Procter Hall Façade Replacement Description: Replacement of existing panels with new sun control façade Justification: Existing panels contain asbestos and bird-droppings Funding: State Basic Renovation funds Total Project: $4.0 million 37 Projects for Budget Approval Rieveschl 500 Level Teaching Labs Renovation Description: Renovation of approximately 5,000 sq ft of existing chemistry teaching labs Justification: Labs have not been upgraded since original construction in 1970’s - systems, equipment, and finishes outdated and deteriorated, current teaching needs and standards need to be met Funding: Debt proceeds Total Project: $6.0 million 38 Projects for Budget Approval Teachers College/Dyer Renovation Phase 2A Description: Departmental and faculty office renovations, teaching lab renovations, consolidation of College operations in Edwards, and restoration of site and perimeter access Justification: Allows mission-critical College operations that are split to function in most effective manner until Phase 3 funding can be secured Funding: Debt Total Project: $2.5 million 39 Projects for Budget Approval Morgens & Scioto Residence Hall Upgrades Description: A series of separate projects to upgrade fire alarms, install fire suppression, replace furnishings, and improve apartment interiors Justification: The buildings are not fire-suppressed, alarms need upgrading, and furnishings need replacement Funding: Debt Total Project: $10.0 million 40 Status on 3-5 Year Plan 41 42 Status on 3-5 Year Plan • Guiding Principles • Transparency • Speaking the Truth • Collaboration • Building Capacity 43 Cost Containment and Efficiency •INITIATIVES TO INCREASE REVENUE •INITIATIVES TO IMPROVE ACADEMIC QUALITY •INITIATIVES TO USE OUR LIMITED HUMAN AND FISCAL RESOURCES MORE EFFECTIVELY 44 Status on 3-5 Year Plan • Recovery Factors • Creation of A&F • Cash Policy • University-Wide Approach • Accountability • Financial Policies • Business Reviews • Realistic Budgeting 45 Status on 3-5 Year Plan • Creation of Administration and Finance • Checks and Balances • Internal Audit • General Counsel • Speak the Truth 46 Status on 3-5 Year Plan • Operating Cash Policy • Board approved in November 2006 • Established operating cash balance levels • Disciplined payoffs of existing deficit funds • No new deficit funds permitted without approval 47 Status on 3-5 Year Plan Average 48 Minimum Status on 3-5 Year Plan • University-Wide Approach • Campus Services – ahead of schedule • College of Medicine – paid off Milliennium Plan • Athletics – work in progress • Utilities – ahead of schedule • West Campus Colleges – making headway • Research – good start • Benefits – deferred 49 Recovery Plan Cash Reserve Update • Quasi-Endowment and Designated Funds • Quasi transferred to Cash Reserve in FY 2007 - $38.6M • Funding used in FY 2008 to pay off deficits while adhering to underlying donor restrictions - $18.1M • College of Medicine - $15.7M • College of Engineering - $1.3M • Various other colleges - $1.1M • Current Quasi Cash Reserve balance - $20.5M • 1% of Monthly Operations Cash Balance 50 Restructure of Debt • Restructure of June 2008 and Future Restructure of June 2009 Principle Payments • FY 2008 Cash Reserves increased by $26.7M • FY 2009 Cash Reserves to be increased by $26.7M 51 Status on 3-5 Year Plan • Financial Policies • • • • Eight new policies Approximately 1300 trained to date Easy access; policy question “hotline” Policy on Policies 52 Status on 3-5 Year Plan • Business Reviews • Campus Services • Parking • Utilities • Athletics 53 Campus Services Budget Overview • Consolidated Financial Overview Budgeted Net (loss) Actual Net Surplus/(loss) 2007 ($7,900,000) ($3,600,000) 2008 ($2,953,000) $571,000* Fiscal Year * projected 54 Campus Services Budget Overview • Revenue Enhancements • Housing Occupancy – moved from 93% to 95% yearly average plus rate increases • Food Services – increased sales of independent meal plans, commissions, and profit-sharing • Campus Recreation – increases to non-student membership, program and rental revenue • Retail – improved upon guarantee from operator • Kingsgate – maintained occupancy, improved margin, rate increases • University Conferencing – growth in number of conferences managed • MainStreet – Catskellar and Cinema improvements, food sales growth • Campus Life fee – growth due to enrollment increase 55 Campus Services Budget Overview • Cost Containment and Reduction • Food Service – lowered meal plan costs • Housing – reduced O&M costs by reducing frequencies of cleaning, reducing staff, reducing phones (landlines), reduced cost of resident staff, and other costs • Eliminated travel and staff development expenses • Reduced programming expenses at both MainStreet and Campus Recreation • Overall reduction in positions since end of 2006 – 60 • Utility savings in auxiliary buildings with more hands-on management • Operational savings based on contribution margin analysis 56 Status on 3-5 Year Plan • Realistic Budgeting • All-university process • Tied to academic priorities 57 Status on 3-5 Year Plan • Going Forward • Pay Back on Quasi Draw • Enterprise Risk Management • Enrollment Plan with refined forecasting • 5-10 year Financial Plan with accurate, refined forecasting 58 The Credits… Provost Office Deans AHC EC PBAC FCC BMO FPDC DC CS BCS FM CU UCit 59 Status on 3-5 Year Plan • Vision • Balanced budget based on Academic Priorities will be norm 60