PRELIMINARY TEST REPORT
March 23, 1998
Covers Tests:
InterfaceView Unit Test, TP-11
ExerciseInterfaceView Unit Test, TP-38
ExerciseListner Unit Test, TP-39
TextAreaListner Unit Test, TP-40
GetSourceListner Unit Test, TP-41
Test Conductor: ______________________________________
Prepared for:
University of Massachusetts Boston, Harbor Campus
100 Morrissey Boulevard
Boston, MA 02125-3393
Professors Henry Batterman & William Campbell
Laboratory in Software Engineering I, II (CS 611, CS 613)
Prepared by:
Language Teacher (LT) Project Team
Satit Phanichyakarn, Project Lead
Contributors: James R. Hill, William Perry, Malisetti Sagar
PRELIMINARY TEST REPORT
DESCRIPTION
This test report covers tests accomplished on March 21, 1998. It was
accomplished as part of our regular Saturday meeting. Listings that formed the
basis of the code walkthrough were printed as part of the actual test and were
printed from our code baseline located on the UMB CS UNIX Lab. Network.
All of the tests were conducted without difficulty and all units testing during this
session passed; however some comments were made. The comments are
written on the source code listing (attached) and the comments were “carried
over to the test data sheet as well. Other side benefits from the code
walkthroughs are a better understanding of the LT architecture of all project
participants and formal code listings are generated and delivered as part of this
test report.
The formal status of our test program is shown on the chart on the next page.
The chart relates the requirement to the test type and test method with the test
procedure and its current status. No entry signifies that the test is yet to be
conducted.
ATTACHMENTS
A. TEST PROCEDURE (COPY)
B. TEST DATA SHEETS
C. BUG REPORTS
Test Status Report