Design Issues Jake Mazur Eric Tarkleson Josh Wong Ben Kershner November 19th, 2008 Team 2 – Design Issues The task of this team was to design a solar powered multi-seat computer system for deployment into rural schools. This included researching what technologies are currently available to provide the most efficient and cost effective method of running multiple computer terminals from a solar system. This task itself is a serious engineering challenge and it turns out that sourcing components for such a system in under-developed areas is also a big challenge. Certain considerations must be taken when designing anything that is going to be deployed to a foreign country, especially a developing one. When the rural element and placement inside of a classroom are added to the equation it only compounds the already existing issues. Product Safety Since we are designing a system that will be deployed in a school with no preexisting power, and around people without much experience with electrical equipment we need to take some extra precautions to make sure that the entire system is as safe as possible. There will be solar panels that will either be mounted on poles outside of the building or on the roof so we will have to make sure to protect these cables because they will carry high currents. The battery bank also needs extra safety measures because it will have the potential to unleash huge amounts of current should a short, or other low resistance connection (i.e. body) cross the terminals. The solar panels will be mounted outside. If we mount them on the roof then we need to make sure that the cable runs go into the structure through a watertight seal. Also there will need to be an earth ground installed in case lightning hits the building. The building itself must be structurally sound enough not only for the solar panels but also for several people so that installation and maintenance is safe. If the building is orientated in such a way that the panels can not face the sun while they are on the roof then they will have to be mounted on a pole outside of the school building. In this case extra precaution must be used to insure that a person is unable to access any wire leads because the current can easily kill a person. Also the 2 Team 2 – Design Issues cabling will have to be run underground so the wires will have to be enclosed in the proper type of duct to that they cannot be cut by someone digging in the area. They also must be completely weatherproof to avoid the wire insulation breaking down from the elements. One advantage to this setup is that the structure that the panels hang on can be used as an earth ground for the entire system. Once inside the building all wiring outside of the case should be in ductwork. This prevents a person from easily cutting the wires and also prevents animals from chewing through the insulation. The system case must have a hole that is not sharp so that the wires cannot fray over time. Also cabling should be secured to the case so that it cannot easily be pulled out which could cause short circuits or broken hardware. Any short unintentional short circuits have a large probability of destroying the expensive equipment nearby or causing a fire. The battery bank must be carefully installed so as to minimize any possibility of short circuits. Each battery terminal should have a cover installed so that it is difficult to touch the electrodes accidently. All batteries should also be secured to the casing so that they cannot move if the whole case is tipped or moved. There must be circuit breakers at several key points in the system to insure that if there is a problem the system will cut off power to itself and hopefully save the equipment from being ruined. There will be a circuit breaker between the solar panel array and the Charge Controller and also between the Battery Bank and the Inverter. These will trip if current exceeds expected ratings and will also allow the system to be manually shut down if the need arises. Following these simple precautions should allow the system to be safe from prying fingers, weather, animals and equipment failure. Also in the case of a failure troubleshooting should be easy because if our battery management system is running it will provide feedback about which components are not working. If a breaker is reset then it will also provide clues as to which part of the system failed. 3 Team 2 – Design Issues Product Lifecycle Management The solar powered computer system is designed to be easily assembled, maintained, and recycled. The majority of the components used are commercial off the shelf components. This allows for easy replacement of damaged components and allows using other compatible components with minimal effort. It also allows for the efficient upgrading of obsolete components without requiring a redesign of the entire system. The system is comprised of four major independent systems, the server, the satellite dish, the solar array, and the battery array. Each of these major systems can be replaced by a compatible solution without the replacing or modifying any of the other components. There is one crucial component that is unique to our system, the power monitoring hardware. This hardware and software are custom built, but it interfaces with the server using a simple USB connection, and it is compatible with all UNIX-based operating systems. One of the greatest strengths of the design is the multi-terminal approach taken. Many hardware based multi-terminal approaches exist, but these add many more points of failure. The approach taken here is software based. This allows any server fitting a generic set of specifications to be used. Because of the constantly changing nature of computers, this is a powerful tool in reducing cost as no special hardware like thin clients are needed. Also software does not become obsolete as quickly as hardware and can be easily updated if needed. It is anticipated that the system will be completely sourced by Lenovo and then shipped as a single unit to the target deployment areas. Based on experiences dealing with foreign suppliers, it makes sense to have the units made in the US and then shipped to the developing countries. This allows for the highest quality components at the lowest possible cost. Because the primary components are already made, there is no need to take into account most of the production issues other products face. The custom hardware for monitoring power can easily be made using the same facilities that manufacture computers components. As far as distribution of the whole system, there are many options. Because the system is modular, each piece can be shipped individually to the area, or the 4 Team 2 – Design Issues entire system can be shipped at once. The modularity also allows for replacement components to be shipped. The anticipated deployment for a single system is in excess of five years. Over this time various components will reach the end of their specified lifecycles (e.g. the battery array) or even fail completely due to weathering (e.g. the solar panels). These can be fixed easily by drop-in replacements. Because the system is connected to the Internet, it is possible to modify the software at any time. In addition to correcting bugs that are discovered after the system has been deployed, this can also be used to back up user data to more secure data centers. It is also possible to fix many of the problems that the users can encounter remotely. To improve the performance and cost of the next generation of the product, the power monitor hardware is set to gather more data then needed for the typical operation of the system. This additional data will provide insight into usage pattern, actual power consumption versus theoretical power consumption and other important data. This data will help in determining how many solar panels or batteries need to be added or removed. Additional logging of other statistics, such as processor usage in the server and memory usage will allow a more efficient server to be designed. Rapidly Sourcing Components Internationally Getting all of the necessary parts in place stateside is one issue. Custom building the computer system took about a week by the manufacturer and then shipment took most of another working week. Upon arrival of the computer more delays where experienced as the unexpected happened, the motherboard was defective. Such delays cannot be accounted for in the planning stages but must be dealt with anyway. There will always be an unexpected delay. Doing so on another continent is completely different. Sourcing the same computer system in an under-developed area obviously takes even longer as the distribution channels are not there. A company that has a huge presence in North America may only have one employee covering even such a large area as the entire 5 Team 2 – Design Issues African continent. This one employee may have to get in touch with other vendors and distribution channels to make shipment to a remote rural location possible. Anytime more people are involved in the chain there are more delays. Also, when communicating across continents it is often only possible to have one information transaction per day, as there is a large time-zone difference. Remotely finding and contacting a supplier in areas where Internet access is limited is quite difficult. Due to time-zone differences, language barriers and longdistance calling charges the phone is not as useful as one might think. Finding the right supplier is closely tied to the geographical location of deployment areas and transportation of the equipment is an issue. Photovoltaic panels are fragile. The panels need to be handled with utmost care anytime they are moved as a single crack in one cell can render the efficiency of the whole panel useless. This is especially a challenge in rural areas due to the condition of the roads. Just one of the batteries weighs 130 pounds, which is another transportation challenge. Ultimately your system components are limited to what is available in the deployment area. Such a design should begin from the opposite end. Not what optimum components you want to put in the system, but what are the most optimum components from what is available. While the team had a good idea of an optimum system setup relatively quickly, sourcing components while working in a short time frame for distribution in a rural area proved to be a real challenge. Environmental Issues Though most of the components are not inherently toxic, complications could arise given the specific implementation. Though it has not been the practice of this team to include wet-acid type batteries in the design, certain situations could arise where the use of such batteries is unavoidable. Wet-acid type batteries pose a three prong environmental threat. In their transportation, they are marked as a chemical hazard, and as such, more care must be taken when shipping them, raising both the cost and the chance of an incident. 6 Team 2 – Design Issues After installed, aside from the previously listen environmental hazard, they also leak hydrogen gas, creating a health and safety hazard as well. Disposing the batteries, and indeed the entire system presents the greatest challenge. Many of the components used cannot be simply thrown away. Although very few of the developing countries have laws governing the disposal of digital waste, it would be irresponsible to deploy these systems without a proper disposal plan. Because of the materials of the system, the best way to dispose of the system would have to be drafted on a country-by-country basis. The worst-case scenario would be to pack everything up and ship it back to the US for disposal, given that many of the developing countries lack the proper facilities to process digital waste and it will end up in a landfill. 7