Ken Leuderalbert, P.E., PMP FHWA VE Program Manager SAVE International® 2012 Annual Conference Government Value Management Conference June 14, 2012 Overview of FHWA/State DOT Program VE Program Performance Overview of FHWA VE Regulations Future VE Initiatives/Goals 2 2 1784 studies resulting in nearly $10 billion in project cost savings or avoidance over the last five years. 4 On average the VE program has produced the following benefits: VE teams recommend ~ 10% project savings State DOTs implement ~50% of all VE recommendations VE recommendations save ~5% of projects construction costs For every dollar spent on VE analyses, agencies realize a $165:1 return on investment 5 VE Program 2016 Goals: http://www.fhwa.dot.gov/ve/measures.cfm Maximize VE effect of project cost and performance 55% of VE Recommendations Implemented 8% of Project Construction Costs Saved Enhance Quality of State VE Program All States have established VE Program and Policy 50% of all VE studies conducted prior to 30% plans Improve FHWA’s Stewardship of VE Program Division engaged in VE Studies Divisions verifying required VE Studies are Conducted 6 Previous update to VE regulation was 1997 Jun 23, 2011 – NPRM Published Aug 22, 2011 – end of public comment period Mar 15, 2012 Final Rule Published in Federal Register http://www.gpo.gov/fdsys/pkg/FR-2012-03-15/pdf/2012-6244.pdf April 16, 2012 Implementation Date of Final Rule 7 There are now five section to VE Regulation: 627.1 Purpose and Applicability 627.3 Definitions 627.5 Applicable Projects 627.7 Programs 627.9 Conducting a VE Analysis 8 Section 627.1 Purpose and Applicability Prescribes programs, policies and procedures to ingrate VE into project planning and development Establish and sustain policies and procedures to monitor, assess and report on VE program and analyses conducted 9 Section 627.3 Definitions Added definitions for: Bridge Project Project Total Project Costs VE Analysis VE Job Plan VECP 10 VE Job Plan Structure for conducting and documenting results of VE analysis Information Phase Function Analysis Phase Creative Phase Evaluation Phase Development Phase Presentation Phase Resolution Phase 11 Section 627.5 Applicable Projects All FAHP NHS Projects >$25M All FAHP Bridge Projects >$20M All Major Projects on or off the NHS Projects with delayed construction that undergo a scope or design change resulting in meeting threshold Any FAHP projects FHWA determines appropriate 12 Section 627.7 VE Programs State DOTs must establish and sustain a VE program Document Policies and Procedures Identify, Schedule and Conduct VE Analysis Ensure VE analysis follows VE Job Plan Resolve and implement approved recommendations Monitor and Assess VE Program Submit annual report to FHWA 13 Section 627.9 Conducting a VE Analysis Independent, multi-disciplined team Team leader with VE expertise Use of consultants Timing of VE analysis Consider all project objectives/commitments Follow the VE Job Plan 14 Simple, do everything we just talked about. Identify a VE Coordinator Develop a VE Policy/Procedure Develop an Annual List of Projects Identify VE analysis resources for each study Follow VE Job Plan Resolve Recommendations Report on Program Performance 15 Review and Approve VE Policies and Procedures Review of Annual List of VE Projects Ensure VE analysis is conducted on all required projects Monitor and participate in VE analyses Monitor Recommendation Resolution Process Annually Report on VE Program Results 16 Release 2011 VE Performance Report - Spring Update the VE Order (Policy) – Summer/Fall Initiate Development of VE Stewardship & Oversight Tool Box for FHWA Divisions – Summer Enhance consistency of FHWA efforts Provide guidance and resources to assist divisions with carrying out specific VE tasks or functions 17 Share Successful VE Practices: http://www.fhwa.dot.gov/ve/ VE Training: http://www.nhi.fhwa.dot.gov/ Recording of VE Webinar Outreach: http://www.fhwa.dot.gov/ve/ VE regulations and policies: http://www.fhwa.dot.gov/ve/vepolicy.cfm 18 AASHTO VE Technical Committee: http://design.transportation.org/Pages/Value Engineering.aspx AASHTO VE Guide: https://bookstore.transportation.org/collection _detail.aspx?ID=43 19 Questions on VE regulations and policies: Ken Leuderalbert VE Program Manager 317-226-5351 ken.leuderalbert@dot.gov VE Website: http://www.fhwa.dot.gov/ve/ 20