573 version 4 Page 1 of 4 Construct, energize, and test permanent electric fences Level 3 Credits 10 Purpose People credited with this unit standard are able to, for a permanent electric fence: install end assemblies and primary posts; select, run out, and set line wires; pre-tension, tension, and terminate line wires in a permanent electric fence; install electric fence components; and connect and test an electric fence. Subfield Agriculture Domain Fencing Status Registered Status date 22 August 2008 Date version published 22 August 2008 Planned review date 31 December 2012 Entry information Open. Accreditation Evaluation of documentation and visit by NZQA, industry and teaching professional in the same field from another provider. Standard setting body (SSB) Primary Industry Training Organisation Accreditation and Moderation Action Plan (AMAP) reference 0052 This AMAP can be accessed at http://www.nzqa.govt.nz/framework/search/index.do. Special notes 1 Product use manuals are available from manufacturers and should be consulted in all training situations. 2 Legislation relevant to this unit standard includes but is not limited to the Health and Safety in Employment Act 1992, and its subsequent amendments. New Zealand Qualifications Authority 2016 573 version 4 Page 2 of 4 3 References Fencing the Proven Way, Fletcher Building Holdings Limited, 2006, available at http://www.wiremark.co.nz, or 0800 PACWIRE. Gallagher PowerFenceTM Manual, Gallagher Animal Management Systems, 2007, available at http://www.gallagher.co.nz. 4 Personal protection equipment appropriate to the task is selected and used in accordance with manufacturer’s specifications and the Health and Safety in Employment Act 1992. Elements and performance criteria Element 1 Install end assemblies and primary posts for a permanent electric fence. Performance criteria 1.1 End assemblies are installed to within + or – 10mm of fence design height, plumb on wire side, plumb to 20mm maximum layback at final loading. 1.2 The breast plate length and thickness are suitable for soil structure, are tight fitting, centred on the strainer square to wire line, have full bearing surface with the soil and with depth sufficient to ensure a solid bearing surface. 1.3 Primary and intermediate post positions are identified in relation to terrain and fence design. 1.4 Primary posts are installed plumb, in line, and to fence design and must bisect contour angle. 1.5 Rise posts are installed up to 25mm above fence design height, bisecting contour angle. 1.6 Footed posts are footed according to soil type and final fence loading, and installed up to 25mm below fence design height, bisecting contour angle. 1.7 All posts are installed to fence design height, rammed firmly in line with minimal wire clearance, bisecting contour angle. Element 2 Select, run out, and set line wires for a permanent electric fence. Performance criteria 2.1 Wire size and type are selected according to fence design. 2.2 Wires are drawn from wire dispenser along entire fence without kinking or damage to galvanising. 2.3 Wire is positioned and attached to primary posts according to fence design. New Zealand Qualifications Authority 2016 573 version 4 Page 3 of 4 Element 3 Pre-tension, tension, and terminate line wires in a permanent electric fence. Performance criteria 3.1 Wire is pre-tensioned on face side of fence and without damaging wire in accordance with industry procedures. 3.2 Wire is joined or tied off according to wire manufacturer’s specifications. 3.3 Wire tension is uniformly set according to wire manufacturer’s specifications. 3.4 Wires are tensioned and terminated according to wire manufacturer’s specifications. 3.5 Tension is retained according to industry procedures. Element 4 Install insulators in a permanent electric fence. Performance criteria 4.1 End insulators are installed in accordance with manufacturer’s specifications. 4.2 Post insulators are installed in accordance with manufacturer’s specifications. 4.3 The working site is tidied after installation by removing all waste materials. Element 5 Install electric fence components. Range cut-off switches, line clamps, under-gate cable, electric gate. Performance criteria 5.1 Components are installed in accordance with manufacturer's guidelines. 5.2 Components are installed without damage to components. 5.3 Components are installed with consideration for the health, safety, and welfare of people and animals. New Zealand Qualifications Authority 2016 573 version 4 Page 4 of 4 Element 6 Connect and test an electric fence. Performance criteria 6.1 Connections are firmly fixed in accordance with manufacturer’s specifications. 6.2 Volt meter is used in accordance with manufacturer’s guidelines to obtain a true reading. 6.3 Volt meter reading is interpreted in terms of stock control and energizer output. Please note Providers must be accredited by NZQA, or an inter-institutional body with delegated authority for quality assurance, before they can report credits from assessment against unit standards or deliver courses of study leading to that assessment. Industry Training Organisations must be accredited by NZQA before they can register credits from assessment against unit standards. Accredited providers and Industry Training Organisations assessing against unit standards must engage with the moderation system that applies to those standards. Accreditation requirements and an outline of the moderation system that applies to this standard are outlined in the Accreditation and Moderation Action Plan (AMAP). The AMAP also includes useful information about special requirements for organisations wishing to develop education and training programmes, such as minimum qualifications for tutors and assessors, and special resource requirements. Comments on this unit standard Please contact the Primary Industry Training Organisation standards@primaryito.ac.nz if you wish to suggest changes to the content of this unit standard. New Zealand Qualifications Authority 2016