PREPARATION OF THE ANNUAL PROGRESS REPORTS FOR 8TH AND 9TH TRANCHE DEVELOPMENT ACCOUNT PROJECTS Project managers are strongly encouraged to follow this outline when preparing annual progress reports on Development Account projects. Progress reports for 8th and 9th tranche projects must be submitted to the DA-PMT by January 31st 2015 and are required for all 8th and 9th tranche projects that have been allotted prior to 1 July 2014. Main uses of annual progress reports include the following: For Implementing Entities Support good management by providing regular, timely and relevant information on the project’s achievements; Provide a tool for DA Focal Points and the senior management of implementing entities to review and assess progress made in the project’s implementation and provide guidance in case of risks and/or challenges encountered; For the Development Account Programme Management Team (DA-PMT) Support the DA Programme Manager in reporting to Member States on the progress made in the implementation of the projects; Provide a tool for the DA-PMT to liaise with implementing entities on the review and assessment of progress made on ongoing projects. Project title Project DA code Executing entity Reporting period mm/yy - mm/yy Please use the percentage calculated on page 5 Implementation rate 1. SUMMARY OF ACHIEVEMENTS TO DATE This section should be no longer than three paragraphs and should provide a concise and effective narrative of the key accomplishments of the project to date. It should not repeat information already provided (for instance, information presented in the project document) but should highlight results, potential impact and any relevant achievement related to the project’s implementation (including unexpected results, both positive and negative). This section will be used for the DA website (http://www.un.org/esa/devaccount/), hence project managers are encouraged to include links to websites that may represent useful references. For projects in initial stages, it is understood that only limited results might have been achieved at the time of reporting. 1 2. REVIEW OF PERFORMANCE INDICATORS AND ACTIVITIES The purpose of this section is to understand how the project is actually performing against its intended accomplishments. This should be done through the verification of the indicators of achievement that were developed in the project document, both quantitative and qualitative, as well as through an assessment of the implemented activities (see tables below). Project managers are encouraged to make sure that this review includes all Expected Accomplishments (EAs) and activities, as per the approved project document, and state whether the activities have been completed or are still being implemented. Table 1 – Review of Performance Indicators Expected Accomplishment EA1 Indicator of achievement at the start of the project (T0) Indicator of achievement at the time period when the project is being reviewed (T1) Please provide the baseline, or value of the indicator at the start of the project, if available Please provide an estimate or actual value of the indicator for the time period considered Comments Please elaborate on the progress made on achieving the EA so far EA2 Table 2 – Review of Completed Activities Activities Please list the completed activities as per project document Comment Please briefly assess the implementation of each activity, i.e. the extent to which the activity has been implemented 2 3. CHALLENGES/PROBLEMS ENCOUNTERED SO FAR Project managers are kindly asked to elaborate on possible problems faced by the project (e.g. change in country situation, administrative processes, collaboration with partners, internal issues, etc.). For each issue identified, one short paragraph should be provided, as well as any action taken to address the issue, as per the table below. Table 3 – Challenges and actions Action(s) taken to solve the issue, if any Description of challenge 4. SUPPLEMENTARY FUNDING This section should be able to help access DA projects’ ability to raise additional funds for the set of activities undertaken. The purpose is to highlight any form of additional funding (financial or in-kind) that has been leveraged to further the implementation of the project through partnerships and/or donors (e.g. additional participants at workshops, paying for venues/additional activities etc; it does not refer to funds leveraged for projects other than the one being reviewed). If additional funds were received, project managers are asked to specify the origin, the purpose and the amount leveraged, as per the table below. Table 4 – Financial Leveraging Donor Purpose Amount raised Cash (USD) In-Kind 5. REVISIONS In this section project managers are kindly requested to report on whether any change to planned activities and/or the budget has occurred. Whether the revisions have been submitted to the Programme Manager (PM) or Programme Planning and Budget Division (PPBD) for approval should also be clarified. If changes to the distribution of funds between objective classes/budget lines have taken place, they must be clearly indicated in the financial information table on page 5 (columns F and G). 3 6. WORK PLAN FOR REMAINING ACTIVITES Project managers are kindly requested to list the activities that still require completion and, for each one, specify the planned start and end date, as per the table below. Table 5 – Remaining activities Remaining Activities Start date Date of completion 7. ADDITIONAL INFORMATION In this section project managers are kindly asked to include any relevant publication, media coverage or meeting report linked to the project. 4 8. FINANCIAL INFORMATION Object Class Description 602 General Temporary Assistance 604 Consultants and Expert Groups 608 Travel of staff 612 Contractual services 616 Operating expenses 618 Supplies, Materials etc. 621 A. Budget/Allotment B. Actual disbursements C. Commitments outstanding D. Total Expenditure E. Balance Remaining F. Revisions to allotments (if any) G. Explanations to revisions Fellowships, grants and contributions Total Implementation rate (%) = Total expenditure (D)/Total budget (A) 5 January 2015 6