ELEMENTARY SCHOOL ONE TOWN, MARYLAND Jonathan Cann Mechanical Option BAE/MAE Integrated Program www.nps.gov/nr/ Advisor: Dr. Treado Spring 2015 www.janneyschool.org Presentation Outline Building Statistics Project Background Existing Conditions Proposal Mechanical Depth Existing Building: Built 1925 National Register of Historic Places Gross Square Feet : 84,400 Overall Project Budget: $25 Million Completion Date: August 2011 3 stories above grade, 1 below Function: Educational Acoustical Breadth Conclusion maps.google.com Jonathan Cann Elementary School One Mechanical Option Presentation Outline Project Background Existing Conditions Location and Weather Town, Maryland Relative Humidity – 50% Summer Winter Designed Dry Bulb (°F) 91 13 Designed Wet Bulb (°F) 77 - Indoor Air Temperature (°F) 75 72 Proposal Mechanical Depth Acoustical Breadth Conclusion Weather data based on Baltimore, Maryland www.ashrae.org Jonathan Cann Elementary School One Mechanical Option Presentation Outline First Floor Mechanical Layout Project Background Blue: RTU-1 & 2 Cafeteria Existing Conditions Orange: RTU-3 &4 (DOAS) and VRF Proposal Purple: RTU- 5 (DOAS) and VRF Mechanical Depth Green: RTU-6 & 7 Multipurpose Red: AHU-1 Administrative Offices Acoustical Breadth Basement Second Floor Third Floor Conclusion Jonathan Cann Elementary School One Mechanical Option Presentation Outline Mechanical Schedule Project Background Existing Conditions Proposal Mechanical Depth Acoustical Breadth Conclusion Rooftop Unit Schedule Unit No. Area Served Supply CFM Total Load (MBH) RTU-1 Cafeteria 7500 227 RTU-2 Cafeteria 7500 227 RTU-3 Exist. Bldg. 8300 350 RTU-4 Exist. Bldg. 5600 236.9 RTU-5 Addition 10650 538 RTU-6 Multi-purpose 7500 235 RTU-7 Multi-purpose 7500 235 Air Cooled Condensing Units Schedules (VRF System) Unit No. Cooling (MBH) Heating (MBH) Condenser CFM CU-VRF-1 439 494 20100 CU-VRF-2 343 386 20100 CU-VRF-3 305 343 13400 www.daikin.com Jonathan Cann Elementary School One Mechanical Option Mechanical Schematics Presentation Outline Project Background Existing Conditions Proposal Mechanical Depth Acoustical Breadth Conclusion Jonathan Cann RTU- 1, 2, 6 & 7 RTU- 3, 4, & 5 DOAS Elementary School One VRF System Mechanical Option Presentation Outline Energy Use & Emissions Project Background % of Total Building Energy Total Building Energy (kBtu/yr) 21.56% 30.80% 0.51% 47.13% 100% 894,258 1,277,511 21,069 1,954,985 4,147,823 Heating Cooling Receptacles Lighting Total Existing Conditions Proposal Mechanical Depth Acoustical Breadth Building Emissions CO2 (lbm/year) SO2 (gm/year) NOx (gm/year) 1,626,597.0 14,638.5 2,801.8 Conclusion Jonathan Cann Elementary School One Mechanical Option Presentation Outline Project Background Proposal Goals Depth: Implement a geothermal system to improve the buildings energy use. Existing Conditions Proposal Breadth: The impact of a geothermal system on the construction management of the project. Mechanical Depth Acoustical Breadth Conclusion Jonathan Cann Breadth: Perform acoustical analysis to insure the comfort of the spaces www.nps.gov/nr/ Elementary School One Mechanical Option Proposed System Presentation Outline Project Background Water-cooled VRF units coupled with closed loop ground coupled heat pump Existing Conditions Proposal Mechanical Depth Acoustical Breadth • • • • • • • More efficient than air-cooled condensers Constant thermal properties Reduces noise pollution Minimal site area loss High initial cost (long term owners) Renewable energy source (earth) Low maintenance Conclusion Jonathan Cann Ball State University Elementary School One Mechanical Option Presentation Outline Site & Well Properties Soil Properties Dry Density Conductivity (k) Diffusivity (α) Project Background Existing Conditions Proposal Annual Average Ground Temperature - 55ºF Mechanical Depth Acoustical Breadth Conclusion Well Design Details Radius of bore SDR 11 Rpipe Rgrout Rbore Wet dense sand 120 lb/ft^3 1.63 Btu/h*ft*°F 0.91 ft^2/day 0.42 1.00 0.10 0.05 0.15 ft in ft*hr*°F/Btu ft*hr*°F/Btu ft*hr*°F/Btu Geothermal Heat Pump Design Manual by McQuay Air Conditioning Jonathan Cann Elementary School One Mechanical Option Presentation Outline Project Background Geothermal Calculations Required Bore Length for Cooling (ft) Existing Conditions Proposal Required Bore Length for Heating (ft) Mechanical Depth Acoustical Breadth Conclusion Jonathan Cann Equations from ASHRAE Handbook Elementary School One Net annual average heat transfer to the ground Building design cooling block load (or heating) Power input at design cooling load (or heating) Effective thermal resistance of ground annual pulse Effective thermal resistance of ground monthly pulse Effective thermal resistance of ground daily pulse Thermal resistance of bore Short circuit heat loss factor Part load factor during design month Undisturbed ground temperature Liquid temperature at heat pump inlet Liquid temperature at heat pump outlet Temperature penalty Symbol Qa Qlc (or Qlh) Wc (or Wh) Rga Rgm Rgd Rb Fsc PLFm tg twi two tp Cooling 251,250 2,010,000 130,000 0.2438 0.223 0.131 0.15 1.04 1.00 55 74 83 2.00 Heating 150,000 1,200,000 130,000 0.2438 0.223 0.131 0.15 1.04 1.00 55 44 36 2.00 Units Btu/h Btu/h W ft*hr*°F/Btu ft*hr*°F/Btu ft*hr*°F/Btu ft*hr*°F/Btu Length # of wells 33,689 84.2 32,454 81.1 ft °F °F °F °F Mechanical Option Well Layout Presentation Outline 85 wells Project Background 400 ft deep wells Existing Conditions 1 15 ft well spacing Proposal Area used 19,125 sq. ft. Mechanical Depth 2,3 Pump located in East Mechanical Room Acoustical Breadth maps.google.com Direct return piping Conclusion Jonathan Cann Elementary School One Mechanical Option Pipe & Flow Design Presentation Outline 480 GPM Project Background 2.9 GPM/ton design Existing Conditions 6” header pipe Proposal 2” row pipe Mechanical Depth 1” well U-tube Acoustical Breadth Conclusion Jonathan Cann 5” bore diameter www.kochergeowelldrilling.com Elementary School One Mechanical Option Well Pump Selection Presentation Outline Project Background Table 22- Head Loss Friction Loss 6.8 ft Fixture Loss 109 ft Velocity Loss 0.4 ft Total head loss 116.2 ft Existing Conditions Proposal Mechanical Depth www.goulds.com Acoustical Breadth Conclusion Jonathan Cann Size 4x4x7 Head 116.2 ft Flow Rate 480 gpm RPM 3500 HP 20 Manufacturer Goulds Model AC-135.3F www.goulds.com Elementary School One Mechanical Option Presentation Outline Water-Cooled VRF Unit Selection Unified heat pump and heat recovery Project Background Units in series to reach needed capacity Existing Conditions Daikin Unit Capacity Cooling (Btu/h) EER Capacity Acoustical Breadth Heating Conclusion CU-VRF-1 (3)x 21 ton + 12 ton CU-VRF-2 (2)x 21 ton + 7 ton CU-VRF-3 21 ton + 18 ton + 6 ton Self heat recovery between modules Proposal Mechanical Depth Units (Btu/h) COP VRV-WIII Series 21 ton 18 ton 12 ton 7 ton 6 ton 252,000 216,000 144,000 84,000 72,000 15.0 15.3 15.3 15.0 15.3 283,500 243,000 162,000 94,000 81,000 4.7 5.3 5.3 4.7 5.3 www.daikin.com Jonathan Cann Elementary School One Mechanical Option Presentation Outline Heat Exchanger Details Ground Temperature 55ºF Project Background Existing Conditions Ground Coupled Side Proposal • 20% glycol / 80% water Mechanical Depth Jonathan Cann • R140a www.dreamstime.com Acoustical Breadth Conclusion VRF Side Cooling Heating Water Tin Tout 74°F 83°F 44°F 36°F GPM 480 480 Refrigerant Tin Tout GPM 76°F 50°F 280 105°F 89°F 280 Elementary School One Indoor Units Air Supply Return 53-55°F 78-80°F 78-81°F 68-70°F EA Credit 6 Refrigerant Q (tons) R-410a 324 Refrigerant Impact per ton 95.7 Credit (<100) Yes Mechanical Option Presentation Outline Alternative System Energy Use Project Background Table 25- Alternative Yearly Energy Consumption Existing Conditions Heating Cooling Lighting Receptacle Total Cost Proposal Mechanical Depth Acoustical Breadth Building kWh 185,431 192,269 572,805 6,173 956,678 $131,064.90 Building kBtu/yr 632,320 656,215 1,954,985 21,069 3,264,589 Source kBtu/yr 1,896,960 1,968,843 5,865,541 63,213 9,794,557 Conclusion Jonathan Cann Elementary School One Mechanical Option Presentation Outline Project Background Existing Conditions Proposal Mechanical Depth Acoustical Breadth Energy & Emissions Comparison Table 26- Yearly Energy Breakdown Original System Alternative System Yearly Savings Building (kWh) 1,215,300 956,678 258,622 Building (kBtu/yr) 4,147,823 3,264,589 883,234 Source (kBtu/yr) 12,444,711 9,794,557 2,650,154 Cost $166,496.09 $131,064.90 $35,431.19 Emissions Comparison- 21.3% less Original Design Alternative Design CO2 (lbm/year) 1,626,597.0 1,280,231.0 SO2 (gm/year) 14,638.5 11,521.4 NOx (gm/year) 2,801.8 2,205.2 Conclusion Jonathan Cann Elementary School One Mechanical Option Presentation Outline Payback Period Table 28- Payback Period Project Background Existing Conditions Proposal Mechanical Depth Federal Tax Rebate • 10 % of initial material and labor cost • EER ≥ 14.1 • COP ≥ 3.3 Without rebate Payback Period = 19.53 years Acoustical Breadth Original System Alternative System With 10% Rebate System Difference Yearly Energy Savings Cost $56,348.44 $692,071.26 $622,564.13 $566,215.69 $35,431.19 Payback Period 15.98 Years 191.77 Months Conclusion Jonathan Cann Elementary School One Mechanical Option Presentation Outline Cost Comparison Original Project Background Material Mechanical Cost Existing Conditions Proposal Mechanical Depth Acoustical Breadth Total Construction Cost Original Design $3,461,864 $20,969,617 Alternative Design $4,028,079 $21,535,833 Percent Increase 16.4% 2.7% Labor Alternative Condensers Controls $42,377.00 $823.00 Condensers Controls $11,985.00 $1,163.00 Total Cost Pump Antifreeze Water Material Investigation $56,348.00 Original Building cost is based on 2015 using inflation from 2010. Labor maps.google.com Conclusion Controls Elementary School One $6,786 $14 $1,475 $915 Loop $424,521 Sub-total $452,911 Pump $1,842 Controls $2,952 Investigation $3,993 Loop $230,373 Sub-total $239,160 Total Cost Jonathan Cann $19,200 $692,071 Mechanical Option Presentation Outline Multi-purpose Room Acoustical Treatment After: NC – 39 Project Background Before: NC > 65 Existing Conditions Added Treatment: • 2” duct lining (60 ft each) • One duct silencer each Proposal Mechanical Depth Goal NC-45 Cost Breakdown Duct lining = $11,457 Duct Silencers= $4,700 Acoustical Breadth Total Cost = $16,157 Conclusion Jonathan Cann Elementary School One Mechanical Option Presentation Outline Project Background Existing Conditions Proposal Mechanical Depth Acoustical Breadth Cafeteria Acoustical Treatment Before: NC - 52 Goal NC-45 After: NC – 41 Added Treatment: • One duct silencer each (36”x12”x50”) Cost Breakdown Duct Silencers= $4,000 Total Cost = $4,000 Not recommended extra cost Conclusion Jonathan Cann Elementary School One Mechanical Option Presentation Outline Conclusion Project Background System Initial Cost - $692,071.26 Existing Conditions Monthly Savings - $2952.60 Proposal Payback Period of System – 15.98 years Mechanical Depth EUI Reduction – 21.3% Acoustical Breadth Conclusion Jonathan Cann www.nps.gov/nr/ ww.nbm.org Elementary School One Mechanical Option Acknowledgements Penn State Faculty JVP Engineers Dr. Stephen Treado All my peers that helped during the process All my friends and family for their support www.kumicm.com www.nps.gov/nr/ Jonathan Cann Elementary School One Mechanical Option Questions? www.kumicm.com www.nps.gov/nr/ Jonathan Cann Elementary School One Mechanical Option