Center for Health Research and Rural Advocacy Michael Vergari Construction Management Option Senior Thesis Presentation 2006 Presentation Outline: Project Background Information Thesis & Presentation Goals Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Project Background Information Presentation Outline: Occupant: Geisinger Health System Project Background Information Size: 67,000 sq*ft Thesis & Presentation Goals Cost: $18,400,000 Research Analysis: Schedule: July 2005 – February 2007 Delivery: Design-Bid-Build Function: Facility to promote research efforts for Geisinger Health System locally and nationally with numerous conference spaces, research employee offices, and 300 seat auditorium LEED Rating: Basic certification (26 points) Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Project Background Information Presentation Outline: Architectural Features Project Background Information 13,750 sq*ft aluminum curtain wall Thesis & Presentation Goals 4’ x 9’ architectural pre-cast panels Research Analysis: open office spaces garden roof above auditorium connection to existing weis research center Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Thesis & Presentation Goals Industry Research Presentation Outline: LEED Credit Guide for Envelope Design and Construction Project Background Information Thesis & Presentation Goals Research Analysis: Alternate Construction Methods & Procedures Prefabrication of Aluminum Curtain Wall System Building Envelope Design and LEED Credits VS. Stick-Built Aluminum System Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: Site & Sequencing Issues 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Research Analysis Resources LEED Accredited Professionals Project Background Information Envelope Design & Construction Challenges Thesis & Presentation Goals Interface of all design systems Sustainable aspects LEED-NC Version 2.2 Identifiable feature of project Research Analysis: Building Envelope Design and LEED Credits Analysis: Increasing complexity Lead times Presentation Outline: Prefabrication of Aluminum Curtain Wall System GSA: LEED Cost Study Imported or specialty finishes Analysis: 4D Visualization Model of Façade Construction Version 2.0: Pilot Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy LEED Credits Affect On Envelope Design & Construction Presentation Outline: Project Background Information Thesis & Presentation Goals Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Façade Decision Making Guide Goals Decision timeline Key façade design issues Constructability considerations Participants Potential LEED credits Budget and cost escalation considerations Presentation Outline: Project Background Information Thesis & Presentation Goals Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Prefabrication of Aluminum Curtain Wall System Advantages Complexity of façade components On-site construction schedule Quality Disadvantages Double handling of material Facility & equipment costs Safety Presentation Outline: Project Background Information Thesis & Presentation Goals Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Need for Prefabrication on Center for Health Research and Rural Advocacy Duration Envelope System Total Costs Presentation Outline: Scheduled Durations of Envelope Systems in Days $1,000,000 On critical path Longest scheduled activity Budget Project Background Information 125 Thesis & Presentation Goals 100 Research Analysis: $750,000 Building Envelope Design and LEED Credits $500,000 75 Most expensive envelope component Analysis: $250,000 50 Quality Standards $0 Site Logistics Prefabrication of Aluminum Curtain Wall System Analysis: 25 Aluminum & Glass Curtain Wall: Architectural Pre-cast Concrete Panels: 4D Visualization Model of Façade Construction 0 Metal Panel Walls & Windows: Aluminum & Glass Curtain Wall: Roofing: Architectural Pre-cast Concrete Panels: Metal Panel Walls & Windows: Roofing: Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Typical Prefabricated Units 13’ x 8’ Panels Presentation Outline: Project Background Information Includes triple pane glazing & aluminum frame Thesis & Presentation Goals Watertight connections with silicone Research Analysis: Represents 80 of the 118 panels Revised Durations Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System On-site Install 10 -11 Panels per day (1,040 sq. ft) vs. Stick-built (150 sq. ft) Warehouse – 3 panels per day Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Schedule Impacts On-Site Labor Force Presentation Outline: Project Background Information Original: 10 Skilled Laborers Thesis & Presentation Goals Proposed: 6 Skilled Laborers Research Analysis: Durations Original: 150 SF / Day Proposed: 1,040 SF / Day Overall Curtain Wall Construction Original: 100 Days Proposed: 13 Days Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Cost Impacts Labor Rates Presentation Outline: Project Background Information Original: Pay all laborers equivalent of skilled wages Thesis & Presentation Goals Proposed: On-site workers paid more than fabrication Research Analysis: Fabrication Plant & Equipment Additional facility and equipment rental General Condition Savings Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Mechanical Impacts Additional Resistance to Heat Transfer Presentation Outline: Project Background Information Deletion of Radiant Heaters Thesis & Presentation Goals Create comfortable environment Research Analysis: Double Pane Glass: Heating: Q = (10 – 68) * 13,750 SF / 2 = (398,750) BTU/hr Cooling: Q = (88 – 72) * 13,750 SF / 2 = 110,000 BTU/hr Triple Pane Glass: Heating: Q = (10 - 68) * 13,750 SF / 8 = (88,611) BTU/hr Cooling: Q = (88 – 72) * 13,750 SF / 8 = 24,450 BTU/hr R – Values Insulating Glass r=1 - 4 Triple Pane R= 3 - 8 Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Structural Impacts Presentation Outline: Analysis Conclusion Additional load of triple pane glass Project Background Information Thesis & Presentation Goals dead load Connections Shear, bearing, & Tear - out Structural Columns Compression, buckling, flexure Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy 4D Visualization Model of Façade Construction Building Façade Construction Sequence & Site Analysis Three separate systems Safety issues Controls building enclosure date Proposed Use of 4D Model Coordinate work flow Address hazardous work environments Predict which activities which may delay critical path Presentation Outline: Project Background Information Thesis & Presentation Goals Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy 3D Model Development Presentation Outline: Use CAD systems to create virtual model of CHHRA Project Background Information Adequate level of detail to display construction Thesis & Presentation Goals Included Items Site boundaries Material staging areas Crane locations Temporary facilities Existing Geisinger facilities Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Presentation Outline: Project Background Information Thesis & Presentation Goals Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions July 7, 2006 July 7, 2006 Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Advantages of Using 4D Visualization Model Presentation Outline: Communicate sequence to all contractors Project Background Information Create schedule iterations Thesis & Presentation Goals Conflicts Research Analysis: Hazardous work environments Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Recommendations & Conclusions Industry Research Presentation Outline: LEED Credit Guide for Envelope Design and Construction Project Background Information Thesis & Presentation Goals Research Analysis: Alternate Construction Methods & Procedures Prefabrication of Aluminum Curtain Wall System Building Envelope Design and LEED Credits VS. Stick-Built Aluminum System Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: Site & Sequencing Issues 4D Visualization Model of Façade Construction Recommendations and Conclusions Easy to implement Questions Displays an array of information Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Questions??? Presentation Outline: Project Background Information Thesis & Presentation Goals Research Analysis: Building Envelope Design and LEED Credits Analysis: Prefabrication of Aluminum Curtain Wall System Analysis: 4D Visualization Model of Façade Construction Recommendations and Conclusions Questions Michael W. Vergari Construction Management Option Senior Thesis Presentation 2006 Center for Health Research and Rural Advocacy Special Thanks Geisinger Health System Harmon Inc. AE Faculty Fellow Students Family & Friends