A N A LY S I S A N D D E S I G N O F C O N C R E T E B U I L D I N G T H E W E S T I N G H O U S E E L E C T R I C C O M PA N Y C O R P O R AT E H E A D Q U A R T E R S C R A N B E R R Y, P A JESSICA L. LAURITO STRUCTURAL OPTION AE SENIOR THESIS APRIL 14, 2009 PENN STATE UNIVERSITY TOPIC OUTLINE Background Information Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations T H E W E S T I N G H O U S E E L E C T R I C C O M PA N Y C O R P O R AT E H E A D Q U A R T E R S •Building Background Information •Existing Building Conditions •Project Goals •Design Process •Design Implications and RAM Model •Lateral Loads and Considerations •Schedule Comparison •Cost Analysis Study •Sustainable Architecture Study •Recommendations •Acknowledgements Acknowledgements •Questions Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION B A C K G R O U N D I N F O R M AT I O N Background Information Existing Conditions T H E W E S T I N G H O U S E E L E C T R I C C O M PA N Y C O R P O R AT E H E A D Q U A R T E R S Project Goals Function: Corporate Headquarters and Office Space Design Process Project Size: 434,800 sq. ft. Stories: 5 above grade, 1 below grade Total Cost: $55,878,000 Construction: February 2008 – May 2009 Design Implications Lateral Loads Schedule Comparison Building Location: Cranberry, Pennsylvania Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION EXISTING CONDITIONS Background Information Existing Conditions Project Goals Design Process Design Implications EXISTING STRUCTURAL STEEL FRAMING S t e e l f r a m i n g C o m p o s i t e m e t a l d e c k L W C t o p p i n g T y p i c a l f l o o r h e i g h t 1 4 ’ F o u n d a t i o n : S p r e a d f o o t i n g s a n d c a i s s o n s M o m e n t c o n n e c t i o n s a t e v e r y c o l u m n T y p i c a l b a y s i z e i s 4 5 ’ x 2 4 ’ Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION EXISTING CONDITIONS Background Information Existing Conditions Project Goals Design Process Design Implications 4 3 4 , 8 0 0 S F B U I L D I N G O N E B U I L D I N G S T W O A N D T H R E E O N E A C H S I D E T O S T A R T THE CAMPUS T H E B U I L D I N G I S E Q U I P P E D W I T H A M E N I T I E S S U C H A S : C A F E T E R I A G Y M L O C K E R R O O M S O F F I C E S E X E C U T I V E C O N F E R E N C E R O O M S L E E D C E R T I F I E D B U I L D I N G G O A L Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION EXISTING CONDITIONS Background Information Existing Conditions 8 3 A C R E S I T E I N B U T L E R C O U N T Y E A S I L Y A C C E S S I B L E F R O M I - 7 9 , I - 7 6 , AND PA - 2 2 8 Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO Site Map From www.google.com T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION EXISTING CONDITIONS Background Information Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION EXISTING CONDITIONS Background Information Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION P R O B L E M S TAT E M E N T Background Information Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Structural Depth The building has been shown to be effective with the existing system. However, the wind moment connections at every column could be more efficient. The typical bay size fits into the L1/L2>2 requirement, making it ideal for a one-way slab. Construction Management Breadth Before a final decision can be made on the effectiveness of the new building structure, the systems must be compared for cost and construction time. Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO Sustainable Architecture Breadth As a corporate headquarters, the building should make a statement. LEED certification is a requirement to the owner. A campus of this magnitude needs to be integrated into the environment. T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION PROJECT GOALS Background Information Existing Conditions Project Goals Structural Depth Goals Redesign the structural system using reinforced cast-in-place concrete and a one-way slab with beams floor system Implement the code effectively and efficiently Design a practical building Design Process Design Implications Lateral Loads Schedule Comparison Construction Management Breadth Study Goals Calculate a cost estimate for redesigned building Generate a schedule for redesigned building Effectively compare the new cost and schedule with Turner Construction Company’s actual cost and schedule Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO Sustainable Architecture Breadth Study Goals Incorporate the building into the environment Successfully implement a green roof Detail, specify plants and materials, size drainage system pipes Determine number of LEED points possible for new design T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION DESIGN PROCESS Design Codes Used: Background Information IBC 2006 Existing Conditions ACI 318-08 Project Goals Design Process Design Implications Lateral Loads Schedule Comparison ASCE 7-05 Design Basis AISC Steel Construction Manual 13th Ed. Dead load= weight of concrete + superimposed loads Live load= 70 PSF (50 Office and 20 Partition) Same building as the steel, only concrete No beams, just girders and slab Cost Analysis Additional load for green roof =100 PSF dead and patio live load= 100 PSF Sustainable Architecture Hand design checked in RAM Structural System and rechecked with lateral by hand Recommendations Acknowledgements Foundations resized for new building Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Concrete Design Considerations Existing Conditions One-way slab L1/L2>2 Project Goals Transverse reinforcement for shrinkage and temperature Design Process Moment transfer in concrete is different than in steel Design Implications Foundation impact on spread footings and caissons Resized for new dead load Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Design Process Determine superimposed loads from drawings and ASCE 7-05 Perform a preliminary design of slabs, beams, and columns Determine location of CMRF’s Create a RAM Structural System Model Compare the preliminary sizes to the RAM generated model sizes Hand calculation of lateral loads Update beam and column sizes for lateral loads in RAM model Spot check column sizes with PCA Column Spot check lateral beam by hand Update RAM model Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Existing Conditions Project Goals Design Process Design Implications Design Assumptions The ideal condition for the gravity members was assumed to be a simply supported beam The lateral members were assumed to be the ideal fixed-fixed connection to the columns Lateral Loads The column connection to the foundation was assumed to be pinned Schedule Comparison The seismic response coefficient was assumed to be R=3.0 Cost Analysis Model has ordinary moment frames in RAM Structural System Sustainable Architecture Recommendations Green roof and inclusive loads are present (separate analysis without performed for breadth) Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Design Process Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Existing Conditions Design Process Concrete Moment Resisting Frame Detail Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Existing Conditions RAM STRUCTURAL SYSTEM MODEL Whole building framing Project Goals Design Process Design Implications Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Existing Conditions RAM STRUCTURAL SYSTEM MODEL Whole building framing beams Project Goals Design Process Design Implications Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO Beam Size Total Length (ft) Density (PCF) 24x34 32000.00 145 30x34 96 145 34x34 28x34 32x34 Weight (#) Volume (ft3) 26293333 181333.33 98600 Volume (yd3) 6716.05 680 25.19 223.87 145 260594.78 1797.2054 66.56 71.01 102.88 145 145 68067.78 469.43296 112711 777.32 17.39 28.79 185057.3 6854.0 Total Beam volume T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S Background Information Existing Conditions RAM STRUCTURAL SYSTEM MODEL Whole building framing columns Project Goals Design Process Design Implications Design Implications Lateral Loads Schedule Comparison Cost Analysis 24x24 8141.5 145 4722070 Volume (ft3) 32566 28x28 622 145 360760 2488 92.15 Recommendations 30x30 32x32 986.5 72 145 145 572170 41760 3946 288 146.15 10.67 Acknowledgements 34x34 18 145 10440 72 2.67 36x36 182 145 105560 728 26.96 48x48 220 145 127600 880 32.59 40968 1517.33 Column Size Sustainable Architecture Questions JESSICA L. LAURITO Total Length (ft) Density (PCF) Weight (#) Total Column Volume T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS Volume (yd3) 1206.15 STRUCTURAL OPTION D E S I G N I M P L I C AT I ON S F O U N D AT I O N I M P L I C AT I O N S Background Information Old and New Foundation Sizes for spot checked columns Existing Conditions Project Goals Design Process Size Column Design Implications Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements 28 24 24 24 28 24 30 28 24 28 24 48 24 24 28 0.7-C 1-B 1-C 1-D 2-D 4-B 1-E 6-B 7.9-C 8-B 8-C 13-A 14-A.4 15-B.7 16-E Type of Foundation spread footing spread footing spread footing spread footing spread footing spread footing caisson #48 spread footing spread footing spread footing spread footing spread footing spread footing spread footing caisson #53 New Final RAM RAM Size Height Capacity Required Required Required New Capacity Height Size Height (ft) (in) (k) (k) Size Height (in) Size (ft) (k) (in) (ft) (in) 5 9.5 12 11 12 10 5.5 10 13 11 13 8 8 12 4 18 200 28 722 36 1152 34 968 36 1152 32 800 146 712.749 32 800 40 1352 34 968 40 1352 32 512 32 512 36 1152 306 376.991 384.844 978.696 1471.816 1606.032 2179.108 1417.268 957.832 1454.464 1342.364 922.328 1330.536 570.728 418.416 1782.08 1316.164 6.936 11.061 13.564 14.169 16.504 13.310 13.484 12.954 10.737 12.896 8.446 7.232 14.925 18.273 39.397 49.499 51.518 56.044 47.480 146 42.858 45.460 33.426 45.460 14.111 25.211 53.536 306 7 392 11.5 1058 14 1568 14.5 1682 17 2312 13.5 1458 7.00 1084.30 13.5 1458 13 1352 11 968 13 1352 9 648 8 512 15 1800 8.25 1399.22 22 44 54 56 60 52 150 48 50 38 50 18 30 58 310 8 11 13 14 16 13 24 36 42 42 48 42 13 12 11 12 9 7 14 36 36 30 36 24 18 48 Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION L AT E R A L L O A D S Background Information Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO SEISMIC DESIGN LOADS Floor wx (k) hx (ft) k hx (ft) k wxhx Cvx Story Force Story Shear Moment at Fx (k) Vx (k) Floor (ft-k) Penthouse 6481.1 92.5 1115.41 7229044 0.179 293.33 0 27133.348 Roof 5 4 18245.1 14162.0 13922.9 74.5 60 46 797.56 570.24 377.75 14551503 8075727 5259370 0.361 0.200 0.130 590.46 327.69 213.41 293.33 43989.083 883.79 19661.364 1211.48 9816.8534 3 16960.3 32 215.24 3650482 0.091 148.13 1424.89 4740.0283 2 17785.3 18 88.23 1569200 0.039 63.67 1573.02 1146.1239 1 Sum 19178.2 106734.9 92.5 3164.42 40335326 1.000 1636.69 1636.69 1636.69 106486.8 The seismic load for the redesigned concrete building is considerably larger than for the as-built steel building, which is to be expected since the new building is more massive. Floor Penthouse Roof 5 4 3 2 1 Sum hxk (ft) wxhxk Cvx Story Force Story Shear Moment at Fx (k) Vx (k) Floor (ft-k) wx (k) hx (ft) 4213 4240.5 4713.6 4726.5 4724.0 4653.4 5444.4 28502.4 92.5 74.5 60 46 32 18 1678.33 1176.85 825.15 533.66 294.28 114.53 7070795 4990465 3889471 2522321 1390147 532940 0.347 0.245 0.191 0.124 0.068 0.026 136.16 96.10 74.90 48.57 26.77 10.26 74.5 2944.46 20396140 1.000 392.75 T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS 0 136.16 232.25 307.15 355.72 382.49 392.75 392.75 12594.449 7159.2331 4493.7722 2234.2278 856.60376 184.72265 14928.56 STRUCTURAL OPTION L AT E R A L L O A D S Background Information WIND LOAD FOR THE REDESIGNED CONCRETE BUILDING Existing Conditions Level Project Goals Design Process Design Implications Lateral Loads Load (kips) N-S E-W Wind Design Shear (kips) N-S E-W Moment (ft-k) N-S E-W Pent Roof 5 4 3 2 193.4 151.5 144.8 138.0 132.6 140.2 38.8 30.2 29.3 28.1 27.4 31.0 0 193.4 344.9 489.7 627.7 760.3 0 38.8 69.0 98.3 126.4 153.9 3481.3 2196.7 2026.7 1932.5 1856.3 2523.7 698.2 437.6 410.7 393.8 384.1 557.2 Total 900.5 184.8 900.5 184.8 10535.9 2183.4 Note: Total Base Shear includes load from Windward and Leeward pressures Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO W I N D L O A D F O R T H E A S - B U I LT S T E E L B U I L D I N G Level Load (kips) N-S E-W Wind Design Shear (kips) N-S E-W Moment (ft-k) N-S E-W Pent Roof 5 4 3 2 196.5 152.9 146.0 139.1 133.5 140.9 39.6 30.5 29.7 28.4 27.7 31.2 0 196.5 349.4 495.4 634.6 768.1 0 39.6 70.1 99.7 128.1 155.8 3536.7 2217.2 2044.3 1948.0 1869.4 2536.6 712.1 442.4 415.2 397.7 387.5 562.0 Total 909.0 187.0 909.0 187.0 14152.2 2916.9 T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION S C H E D U L E C O M PA R I S O N Background Information T U R N E R C O N S T R U C T I O N C O M PA N Y Existing Conditions Project Goals Design- Bid-Build Design Process Started foundations March 3rd, 2008 Design Implications Lateral Loads Finished construction October 17th, 2008 Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION S C H E D U L E C O M PA R I S O N REDESIGNED BUILDING SCHEDULE Background Information Existing Conditions Project Goals Start foundations on March 3rd, 2008 Finish structure on December 9th, 2008 Lead time for steel is insignificant -steel will be on site when foundations are finished Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Time difference because of sequencing, could potentially be sequenced differently if more crews were on site Questions JESSICA L. LAURITO Turner pushed ahead with the schedule finishing before their estimated date effectively T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION C O S T A N A LY S I S S T U D Y R E D E S I G N E D B U I L D I N G E S T I M AT E Background Information Detailed Cost Analysis of the Structure-No Green Roof Existing Conditions Project Goals Design Process Design Implications Level Reinforcement Cast in Place Concrete Location Factor: 98.9% Description Foundation Columns Beam/Slabs SUB-TOTAL Foundations Amount 58 Ton 156Ton 504 Ton 719 6100 CY Material Price $935.00 $935.00 $935.00 $935.00 $109.00 Material Cost $54,230 $147,263 $470,642 $672,134 $664,900 Labor Price $430.00 $430.00 $430.00 $430.00 $14.90 Labor Cost $24,940 $430.00 $216,445 $241,815 $90,890 Equipment Price $30.35 $30.35 $30.35 $30.35 $5.55 Equipment Cost $1,760 $4,780 $15,277 $21,817 $33,855 Total Cost $80,930 $152,473 $702,363 $935,766 $789,645 Columns Slabs 1443 CY 14192 CY $109.00 $109.00 $157,189 $1,546,928 $34.00 $18.20 $49,031 $258,294 $16.95 $9.15 $24,444 $129,857 $230,664 $1,935,079 Beams 6477 CY $109.00 $706,026 $26.50 $171,648 $1,320.00 $8,550,036 $9,427,710 SUB-TOTAL 28211 $109.00 $3,075,043 $20.20 $569,864 $1,352 $8,738,191 $12,383,098 Total Structure Estimate: $13,173,000 Total Labor Cost: $812,000 Total Material Cost: $3,748,000 Total Equipment Cost: $8,761,000 Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements T U R N E R C O N S T R U C T I O N C O M PA N Y Turner Construction Company Budgets Deep foundations (caissons) Concrete (Spread ftgs, slabs) Structural Steel Total Structure Whole Building $215,000 $5,199,000 $7,892,000 $13,306,000 $55,878,000 $30.60/SF vs. $30.90/SF R.S. Means is not as accurate as real estimates Turner had contractors actually bid Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION S U S TA I N A B L E A R C H I T E C T U R E S T U D Y T H E W E S T I N G H O U S E E L E C T R I C C O M PA N Y C O R P O R AT E H E A D Q U A R T E R S Background Information Existing Conditions Functions and benefits Project Goals Design Process Patio Meeting area Lunch area Design Implications Lateral Loads Storm water collector Reduces heat island effect www.deq.state.mi.us/documents/deq-ess-p2-p2week-greenroofresources.doc Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION S U S TA I N A B L E A R C H I T E C T U R E S T U D Y Background Information Plant Layout on accessible roof on 3rd floor Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION S U S TA I N A B L E A R C H I T E C T U R E S T U D Y Background Information Existing Conditions No green roof structure costs $13,173,000 or $30.60/SF With green roof, structure costs $1,159,000 or $2.68/SF more Beam and columns needed to be resized, the slab was checked and found to be adequate Project Goals Green roof adds 100 PSF dead and100 PSF live load to the accessible portion Design Process Detailed Cost Analysis of the Structure Level Design Implications Reinforcement Lateral Loads Schedule Comparison Cost Analysis Cast in Place Concrete Location Factor: 98.9% Description Foundation Columns Beam/Slabs SUB-TOTAL Foundations Amount 58 Ton 175 Ton 572 Ton 805 6100 CY Material Price $935.00 $935.00 $935.00 $935.00 $109.00 Material Cost $54,230 $163,625 $534,820 $752,675 $664,900 Labor Price $430.00 $430.00 $430.00 $430.00 $14.90 Labor Cost $24,940 $430.00 $245,960 $346,150.00 $90,890 Equipment Price $30.35 $30.35 $30.35 $30.35 $5.55 Equipment Cost $1,760 $5,311 $17,360 $24,432 $33,855 Total Cost $80,930 $169,366 $798,140 $1,123,257 $789,645 Columns Slabs 1518 CY 14192 CY $109.00 $109.00 $165,462 $1,546,928 $34.00 $18.20 $51,612 $258,294 $16.95 $9.15 $25,730 $129,857 $242,804 $1,935,079 Beams 7197 CY $109.00 $784,473 $26.50 $190,721 $1,320.00 $9,500,040 $10,475,234 SUB-TOTAL 29007 $109.00 $3,161,763 $23.40 $271,330 $1,352 $9,689,482 $13,122,575 Total Structure Estimate: $14,332,000 Total Labor Cost: $863,000 Total Material Cost: $3,915,000 Total Equipment Cost: $9,714,000 Sustainable Architecture Recommendations An additional week is needed to erect the green roof building than without it Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION R E C O M M E N D AT I ON S Background Information Existing Conditions Recommendations The building was successfully redesigned and the code was correctly implemented Project Goals It is possible to have a reinforced concrete building Design Process Based on cost and schedule, this system is not recommended Design Implications $30.90/SF vs. $30.60/SF March-October vs. March-December Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture The addition of a green roof however, is recommended. If the building were in concrete the green roof structural cost would be $2.68/SF of building or $20.24/SF of green roof One additional week construction for the additional structure Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION A CKNOWLEDGEMENTS Background Information Existing Conditions Project Goals I would like to thank: Turner Construction Company Bob Hennessey Design Process LLI Engineering Design Implications Westinghouse Electric Company Lateral Loads Wells Real Estate Funds Schedule Comparison Penn State University Cost Analysis Sustainable Architecture Dr. Hanagan Prof. Parfitt Prof Holland Recommendations Acknowledgements And the rest of the AE faculty and staff Family and friends Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION QUESTIONS Background Information Existing Conditions Q UESTIONS Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations ? Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION FLOOR PLANS Background Information THIRD FLOOR EAST Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION FLOOR PLANS Background Information THIRD FLOOR CENTER Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION FLOOR PLANS Background Information ROOF EAST Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION FLOOR PLANS Background Information ROOF CENTER Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION EXISTING CONDITIONS Background Information Existing Conditions Project Goals Design Process Design Implications Whole Building Steel Lateral Loads Schedule Comparison Cost Analysis East Building Steel Sustainable Architecture Recommendations West Building Steel Acknowledgements Questions Pictures taken by Jessica L. Laurito on 8/19/2008 JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE Background Information P O R TA L M E T H O D A N A LY S I S F O R R E D E S I G N E D Existing Conditions Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE Background Information Existing Conditions H A N D C A L C U L AT E D B E A M Preliminary Beam Design Project Goals Design Process Design Implications Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO Based on this preliminary design and interior gravity beam can be 24”x34” T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE Background Information PCA C OLUMN CHECK Column D-7.9 Fourth Floor Existing Conditions Project Goals Design Process Design Implications Design Implications Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE Background Information Wind Frame 19 TORSION Existing Conditions Project Goals Design Process Wind Frame 22 Design Implications Lateral Loads Schedule Comparison Cost Analysis Seismic Frame 19 Sustainable Architecture Recommendations Seismic Frame 22 Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE Background Information DRIFT FOR REDESIGNED BUILDING Existing Conditions Project Goals Design Process Design Implications Lateral Loads Controlling Controlling Seismic Wind Story Pent Roof 5 4 3 2 Allowable (in) Total TotalDrift Drift Ratio Allowable Total Drift (in) Story Story Drift StoryAllowable AcutalStory DriftDrift Story DWind=H/400 height (ft) (in)height (ft) DWind = H/400dxe/hsx=0.02*1.0/3 Ratio (in) 92.5 Pent 0.087 92.5 < 0.54 0.0004 Acceptable < 0.39369 0.006667 < 2.775 Acceptable 74.5 Roof 0.035 74.5 < 0.4350.0005 Acceptable < 0.30695 0.006667 < 2.235 Acceptable 60.05 0.044 60.0 < 0.42 0.0008 Acceptable < 0.27184 0.006667 < 1.8 Acceptable 46.04 0.093 46.0 < 0.42 0.0009 Acceptable < 0.22799 0.006667 < 1.38 Acceptable 32.03 0.049 32.0 < 0.42 0.001 Acceptable < 0.1345 0.006667 < 0.96 Acceptable 18.02 0.085 18.0 < 0.54 0.0009 Acceptable < 0.08531 0.006667 < 0.54 Acceptable Schedule Comparison Cost Analysis Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO D R I F T F O R T H E A S - B U I LT S T E E L B U I L D I N G Story Roof Controlling Wind Controlling Seismic Drift (in) Total Allowable Total Drift (in) Story Story Drift TotalDrift DriftRatio Story Allowable Acutal Story Drift Allowable Story DWind=H/400 height (ft) (in) DRatio dxe/hsx=0.02*1.0/3 (in) height (ft) Wind= H/400 0.127 74.5 < 0.435 Acceptable 0.0011 < 0.187 60.0 < 0.420.0013 Acceptable < 1.02425 < 0.006667 0.89767 < 0.006667 2.235 Acceptable 5 74.5 Roof 60.0 5 1.8 Acceptable 4 3 2 46.0 4 32.0 3 18.0 2 0.247 46.0 < 0.420.0014 Acceptable < 0.257 32.0 < 0.420.0012 Acceptable < 0.207 18.0 < 0.540.0006 Acceptable < 0.71044 < 0.006667 0.46336 < 0.006667 0.20662 < 0.006667 1.38 0.96 0.54 Acceptable Acceptable Acceptable T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE SEISMIC CALCULATIONS Background Information Redesigned Values Existing Conditions Seismic Design Values, ASCE 7-05 Project Goals Response Modification Coefficient Coefficient R= 3 CU= 1.7 Table 12.2-1 Table 12.8-1 Design Process Fundamental Period Seismic Response Coefficient T= 1.5999 CS= 0.015 Sec. 12.8.2 Eq. 12.8-3 Building Height (above grade) h= 92.5 Design Implications Lateral Loads As-Built Values Schedule Comparison Seismic Design Values, ASCE 7-05 Cost Analysis Response Modification Coefficient Coefficient R= 3 CU= 1.7 R= 3.5 CU= 1.7 Table 12.2-1 Table 12.8-1 Sustainable Architecture Fundamental Period Seismic Response Coefficient T= 1.780 CS= 0.014 T= 1.780 CS= 0.012 Sec. 12.8.2 Eq. 12.8-3 Building Height (above grade) h= 92.5 h= 92.5 Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE SEISMIC CALCULATIONS Background Information Existing Conditions Project Goals Design Process Seismic Design Values, ASCE 7-05 Occupancy Importance Factor Site Class Spectral Response Acceleration, short Design Implications Spectral Response Acceleration, 1 sec Site Coefficient Fa Lateral Loads Site Coefficient FV MCE Spectral Response Acceleration, short Schedule Comparison MCE Spectral Response Acceleration, 1 sec Design Spectral Acceleration, short Cost Analysis Design Spectral Acceleration, 1 sec Seismic Design Category II I= 1 Table 1-1 Table 11.5-1 D SS= 0.12 S1= 0.046 Table 20.3-1 Fa= 1.6 FV= 2.4 Table 11.4-1 Figure 22-1 Figure 22-2 Table 11.4-2 SMS= 0.192 SM1= 0.1104 Eq. 11.4-1 SDS= 0.128 SD1= 0.0736 Eq. 11.4-3 B Eq. 11.4-2 Eq. 11.4-4 Table 11.6-1 Sustainable Architecture Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE SEISMIC CALCULATIONS Background Information Existing Conditions Project Goals Calculated Values SS= 0.12 S1= 0.046 SMS= USGS Website Values SS= 0.125 S1= 0.048 (From Figure 22-1) (From Figure 22-2) Fa*SS = 0.192 FV*S1 = 0.1104 Design Process SM1= Design Implications SDS= 2SMS/3= 0.128 SD1= 2SM1/3= 0.0736 SMS= 0.2 SM1= 0.116 SDS= 0.133 SD1= 0.077 A (Table 11.6-1) B (Table 11.6-2) Lateral Loads Fa Values (Table 11.4-1 ASCE 7-05) Schedule Comparison Cost Analysis D SS=0.5 SS=0.75 SS=1.0 SS≥1.25 1.6 1.4 1.2 1.2 1 FV Values (Table 11.4-2 ASCE 7-05) Sustainable Architecture Recommendations SS≤0.25 D S1≤0.1 S1=0.3 S1=0.3 S1=0.4 S1≥0.5 2.4 2 1.8 1.6 1.5 Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE SEISMIC CALCULATIONS Background Information Redesigned Values Existing Conditions Project Goals CT = 0.016 X = 0.9 Ta= Design Process (From Table 12.8-2) (From Table 12.8-2) x Cthn = 0.9411255 Ts= SD1/SDS = 0.575 0.8Ts= <Ta therefore must use Table 11.6-1,2 0.46 Design Implications TL= 12 (From Fig. 22-15 p. 228 ASCE 7-05) Lateral Loads Schedule Comparison SDS/(R/I) = 0.0427 (12.8-2) SD1/(T*R/I) = 0.0153 (12.8-3) 2 SD1TL/(T R/I) = 0.3324 (12.8-4) ≥ 0.01 (12.8-5) CS= MAX for T>TL Cost Analysis CS= Sustainable Architecture 0.0153 T= CU*Ta = 1.5999134 V= Cs*W 1636.69 Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE WIND CALCULATIONS Background Information Basic Wind Speed (V) mph Exposure Category Importance Factor (I) Wind Directionality Factor (Kd) Topographic Factor (Kzt) Existing Conditions Project Goals 90 B 1 0.85 1 From Table 6-3 Design Process Design Implications Lateral Loads Schedule Comparison From RAM H (ft) Kz qz H (ft) Kz qz 92.5 74.5 60 46 32 18 0 0.9675 0.908 0.85 0.79 0.712 0.59 0.57 14.354 13.471 12.611 11.720 10.563 8.902 8.456 92.5 74.5 60 46 32 18 0 0.966 0.909 0.854 0.792 0.714 0.605 0.575 14.331 13.486 12.670 11.750 10.593 8.976 8.531 Cost Analysis Sustainable Architecture Recommendations Acknowledgements Floor Heights Level 18 Penthouse 14.5 Roof 14 5 14 4 14 3 18 2 Total Height 92.5 74.5 60 46 32 18 Wind Pressures (psf) KZ qZ N-S Windward 0.9675 0.908 0.85 0.79 0.712 0.59 14.354 13.471 12.611 11.720 10.563 8.902 11.54 10.99 10.46 9.91 9.20 7.90 N-S Leeward -8.21 -8.21 -8.21 -8.21 -8.21 -8.21 N-S Side Wall E-W Windward -10.43 -10.43 -10.43 -10.43 -10.43 -10.43 12.20 11.61 11.43 11.04 10.65 10.45 E-W Leeward E-W Sidewall -4.91 -4.91 -4.91 -4.91 -4.91 -4.91 -10.49 -10.49 -10.49 -10.49 -10.49 -10.49 Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE WIND CALCULATIONS Background Information Existing Conditions Wind Design Project Goals Design Process Design Implications Lateral Loads Schedule Comparison Level Load (kips) Shear (kips) Moment (ft-k) N-S E-W N-S E-W N-S E-W Pent Roof 5 4 3 2 193.4 151.5 144.8 138.0 132.6 140.2 38.8 30.2 29.3 28.1 27.4 31.0 0 193.4 344.9 489.7 627.7 760.3 0 38.8 69.0 98.3 126.4 153.9 3481.3 2196.7 2026.7 1932.5 1856.3 2523.7 698.2 437.6 410.7 393.8 384.1 557.2 Total 900.5 184.8 900.5 184.8 10535.9 2183.4 Cost Analysis Sustainable Architecture Level Recommendations Roof 5 4 3 2 Total Acknowledgements Questions JESSICA L. LAURITO Load (kips) N-S E-W 151.6 144.8 137.9 132.3 139.5 706.1 30.5 29.7 28.4 27.7 31.2 147.5 Wind Design Shear (kips) N-S E-W 0 151.6 296.4 434.3 566.6 706.1 0 30.5 60.2 88.6 116.3 147.5 Moment (ft-k) N-S E-W 2198.6 2026.7 1930.7 1852.1 2511.1 10519.2 442.4 415.2 397.7 387.5 562.0 2204.8 T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE WIND CALCULATIONS Background Information 0.00256 KhKztKdV2I= 14.836 qp = Existing Conditions GCpn= Project Goals Design Process 1.5 -1 Pp = qpGCpn = n1 = 43.5 22.254 -14.836 Basic Wind Speed (V) mph Exposure Category Importance Factor (I) Wind Directionality Factor (Kd) Topographic Factor (Kzt) 1.163 eq (C6-15) n1> 1 90 B 1 0.85 1 therefore Rigid structure 0.9 H Design Implications Lateral Loads Schedule Comparison gQ = gV = G= 0.85 z= 0.6h = zmin = 30' 1/6 Iz = c(33/z) = є Lz = l(z/33) = 3.4 55.5 0.275 380.55 Cost Analysis QN-S= √(1/(1+0.63( B+h/Lz)0.63)) = 0.731 Sustainable Architecture QE-W= √(1/(1+0.63( B+h/Lz)0.63)) = 0.832 Recommendations Acknowledgements Gf N-S= 0.925 [(1+1.7IzgQQ)/(1+1.7gvIz)]= 0.7722744 Gf E-W= 0.925 [(1+1.7IzgQQ)/(1+1.7gvIz)]= 0.8296736 Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE F O U N D AT I O N I M P L I C AT I O N S Background Information Caissons Existing Conditions Uncored Caisson Project Goals Axial capacity = area x allow bearing - weight of caisson Design Process Design Implications Design Implications Uplift capacity NON-EMBEDDED CAISSON = Soli Friction + Weight of Caisson 0 ft Embedment CAISSON Pile D Area Circumf. Weight Tu [ft] [sf] [ft] [kips] Lateral Loads Schedule Comparison Cost Analysis Sustainable Architecture 5.00 5.50 6.00 6.50 7.00 7.50 Uplift Axial [kips] Capacity Capacity w/ SF w/o Core w/o Core [kips] [kips] 19.63 15.71 35.83 12.04 47.87 553.21 23.76 17.28 43.36 13.24 56.60 669.39 28.27 18.85 51.60 14.44 66.04 796.63 33.18 20.42 60.56 15.65 76.21 934.93 38.48 21.99 70.23 16.85 87.08 1084.30 44.18 23.56 80.63 18.05 98.68 1244.73 Length = 12.17 ft Recommendations Acknowledgements Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION REFERENCE SLIDE Background Information F O U N D AT I O N I M P L I C AT I O N S Spread footings Existing Conditions Project Goals soil bearing caisson bearing 8 ksf 30 ksf Design Process qu= Pu/A Design Implications Design Implications Lateral Loads Schedule Comparison d^2(4VC+q)+d(2VC+q)w=q(BL-w) Punching Shear VC≤ f(2+4b C)√(f'c)bOd f4√(f'c)bOd f(asd/bo+2)√(f'c)bod Cost Analysis Sustainable Architecture Recommendations Acknowledgements f= 0.75 b C= 1 f'c= 3000 a= 40 30 20 int edge corner Questions JESSICA L. LAURITO T HE WESTINGHOUSE ELECTRIC COMPANY CORPORATE HEADQUARTERS STRUCTURAL OPTION