10. Lean Operations: Process Synchronization and Improvement Chapter 10 1 Lean Operations: Process Synchronization and Improvement 10. Lean Operations: Process Synchronization and Improvement Introduction 2 Lean Operations: – Perfected by Japanese automaker - Toyota – A more efficient process – Adopted in USA by the aerospace industry in 1990’s – Some turnaround times were lowered by 30-50% – Maintenance productivity improved by 25-50% 10. Lean Operations: Process Synchronization and Improvement Introduction 3 Overall: – Many industries have adopted lean operations Why?? Improved performance including: Cost Quality Response time $ 10. Lean Operations: Process Synchronization and Improvement Introduction 4 Quick review: Responsiveness A B Operations Frontier C High Low Price 10. Lean Operations: Process Synchronization and Improvement 10.1 Processing Networks 5 Processing Networks: consists of information and material flows of multiple products through a sequence of interconnected processes. Process 2 Process 4 Product A Process 6 Process 1 Product B Process 3 Process 5 10. Lean Operations: Process Synchronization and Improvement 10.1 Processing Networks 6 Plants & Supply Chains— – Two different levels: Plants: any singly owned, independently managed and operated facility (i.e., manufacturing site, service unit, storage warehouse) Supply Chain: a network of interconnected facilities Diverse ownership Flows of information and materials between the facilities (i.e., raw materials suppliers, finished goods producers, wholesalers, distributors, retailers) 10. Lean Operations: Process Synchronization and Improvement 10.2 The Process Ideal: Synchronization & Efficiency 7 What is an “Ideal Process”? A process that achieves synchronization at the lowest possible cost Process Synchronization The ability of the process to meet customer demand in terms of their quantity, time, quality and location requirements. Process Efficiency Measured in terms of the total processing costs. Less cost, more efficient!!. 10. Lean Operations: Process Synchronization and Improvement 10.2 The Process Ideal: Synchronization & Efficiency 8 Perfectly Synchronized Process that is LEAN will develop, produce and deliver these ONLY on demand: – Exactly what is needed (not wrong or defective products) – Exactly how much is needed (neither more or less) – Exactly when it is needed (not before or after) – Exactly where it is needed (not somewhere else) 10. Lean Operations: Process Synchronization and Improvement 10.2 The Process ideal: Synchronization & Efficiency 9 Just-In-Time (JIT) – When the four “just rights” come together— – Action is taken only when it becomes necessary!!! – In Manufacturing - production of only necessary flow units in necessary quantities at necessary times!!! 10. Lean Operations: Process Synchronization and Improvement 10.2 The Process ideal: Synchronization & Efficiency 10 Synchronized Networks: – Outflow of one process is the inflow to another process!!!! – REQUIRES PRECISE MATCHING OF SUPPLY & DEMAND – All stages are required to be tightly linked with flow of information and product – Ideally – the processing stages are achieved for lowest possible cost!!!! 10. Lean Operations: Process Synchronization and Improvement 10.3 Waste and Its Sources 11 ANYTHING LESS THAN IDEAL PERFORMANCE IS AN OPPORTUNITY FOR IMPROVEMENT!!! Low Efficiency = High Processing Costs Lack of Synchronization Defective products, high inventories, delays, stock outs 10. Lean Operations: Process Synchronization and Improvement 10.3 Waste and Its Sources 12 Waste: producing inefficiently, producing wrong or defective products, producing in quantities that are too small/large, delivering early/late Sources of Waste: – Producing defective products – Producing too much product – Carrying inventory – Waiting due to unbalanced workloads – Unnecessary processing – Unnecessary worker movement – Transporting materials 10. Lean Operations: Process Synchronization and Improvement 10.3 Waste and Its Sources 13 Waste Elimination: – Short term strategies include: Cycle & Safety inventories Safety capacity Non-Value adding activities (transportation, inspection, rework, process control) 10. Lean Operations: Process Synchronization and Improvement 10.3 Waste and Its Sources 14 Waste Elimination (cont’d): – Long-Term Strategy – Improve the overall processes – Build in flexibility, predictability, stability to eliminate temporary fixes. i.e.→ Reduce setup costs to make it more economical to produce small batches. 10. Lean Operations: Process Synchronization and Improvement 10.3 Waste and Its Sources 15 The River Analogy: The boat can sail in shallow water (lean operations) if we are able to find ways to remove the imperfections on the river bottom!!! FM FG WIP Defects Defective Materials Long Lead Times Machine Breakdowns Long Setups Unsuitable Equipment Uneven Schedules Unreliable Suppliers Absenteeism Inefficient Layouts Rigid Work Rules 10. Lean Operations: Process Synchronization and Improvement 10.4 Improving Flows in a Plant: Basic Principles of Lean Operations 16 Many buzz-words for managing and achieving efficiency within a plant: – Lean operations – Just-in-time production – Zero inventory program – Synchronous manufacturing – Agile manufacturing – Toyota Production System (TPS) 10. Lean Operations: Process Synchronization and Improvement 10.4 Improving Flows in a Plant: Basic Principles of Lean Operations 17 LEAN OPERATIONS HAS FOUR OBJECTIVES: 1. To improve process flows Efficient plant layout and fast/accurate flow of materials and information 2. To increase process flexibility Reducing equipment changeover times & cross-functional training 3. To decrease process variability Flow rates, processing times, and quality 4. To minimize processing costs Eliminate non-value adding activities (transportation, inspection, rework) 10. Lean Operations: Process Synchronization and Improvement 10.4 Improving Flows in a Plant: Basic Principles of Lean Operations 18 WHY????? – First three goals improve Process Synchronization – Last goal improves Cost Efficiency 10. Lean Operations: Process Synchronization and Improvement 10.4 Improving Flows in a Plant: Basic Principles of Lean Operations 19 Classic Example: – Efficiency/Synchronization for mass production: Henry Ford’s Rouge, Michigan plant – Totally integrated with – steel mill, glass factory, machine tools, electrical systems, assembly line, welltrained (well-paid) workers – Minimal low time & cost – Everything in place except product variety! 10. Lean Operations: Process Synchronization and Improvement 10.4 Improving Flows in a Plant: Basic Principles of Lean Operations 20 Efficiency/Synchronization for Mass Production Ford Motor Company 1910 Rouge, Michigan Plant Source: <http://www.shadetreemechanic.com/ford_centennial_in_atlanta.htm > 10. Lean Operations: Process Synchronization and Improvement 10.4.1 Improving Process Architecture: Cellular Layouts 21 Process Architecture: the network of activities and resources One method: FUNCTIONAL LAYOUTS Different product types follow different routings through the resource pools…enabling each flow unit to be sent to any available station in the pool. 10. Lean Operations: Process Synchronization and Improvement 10.4.1 Review of Process Architectures: Job Shop 22 Functional Layout: Resources that perform the same function are physically pooled together– JOB SHOPS Output Product 1 Input Product 2 A C B D 10. Lean Operations: Process Synchronization and Improvement 10.4.1 Improving Process Architecture: Cellular Layouts 23 Alternate to Process-based Functional Layout: CELLULAR LAYOUT All workstations that perform successive operations on a given product are grouped together to form a “CELL” 10. Lean Operations: Process Synchronization and Improvement 10.4.1 Improving Process Architecture: Cellular Layouts 24 Product 1 Input A B C Output Example: Henry Ford’s Assembly Line for the Model T 10. Lean Operations: Process Synchronization and Improvement 10.4.1 Improving Process Architecture: Cellular Layouts 25 + ADVANTAGES Facilitates synchronous flow of information and materials between processing stations + Improved communication between stations Physical proximity of cells reduce transportation of low units Improves synchronization where each station produces parts only if the next station needs them Moves small batches of flow units quickly Easier to recognize and report problems Encourages teamwork & cross functional skill development Quicker ability to correct defects 10. Lean Operations: Process Synchronization and Improvement 10.4.1 Improving Process Architecture: Cellular Layouts 26 - DISADVANTAGES Resources are dedicated to specific cells Resources cannot be used by other cells Lose advantage of resource pooling Worker incentives must be “team” oriented, not individual performance based - REMEDIES: – Use flexible resources that are cross functional – Peer pressure to control productivity of team members 10. Lean Operations: Process Synchronization and Improvement 10.4.2 Improving Information & Material Flow: Demand Pull 27 TWO APPROACHES 1. PUSH: Input availability triggers production where emphasis is on “keeping busy” and maximize resource utilization (as long as there is work) Planning Tool: MRP (Material Requirements Planning) MRP: End-Product demand forecasts are “exploded” backwards to determine parts requirements at each station 10. Lean Operations: Process Synchronization and Improvement 10.4.2 Improving Information & Material Flow: Demand Pull 28 PUSH works well under these conditions if: – All information is accurate – Forecasts of finished goods are correct – There is no variability in processing times If one of these conditions at any stages is not met will DISTURB PLANNED FLOW AND DESTROY SYNCHRONIZATION THROUGHOUT THE PROCESS!! 10. Lean Operations: Process Synchronization and Improvement 10.4.2 Improving Information & Material Flow: Demand Pull 29 2. Demand-Pull: Where demand from a customer station triggers production. Consequences of Demand-Pull -- -- -- Each station produces only on demand from its customer station The demand is actually “downstream” Two requirements to make a pull system work: 1. Must have a well-defined customer with a well-defined supplier process. 2. Must produce the quantity needed only when signaled to do so by its customer 10. Lean Operations: Process Synchronization and Improvement 10.4.2 Improving Information & Material Flow: Demand Pull 30 SUPPLY PUSH: Input availability triggers production Supplier Process Inputs Customer Outputs DEMAND PULL: Output need triggers production Supplier Process Inputs Information Flow: Customer Outputs Material Flow: 10. Lean Operations: Process Synchronization and Improvement 10.4.2 Improving Information & Material Flow: Demand Pull 31 Demand Signaling: Customer needs a way to signal (inform) the supplier of its need. Customer’s demand starts a chain reaction – For withdrawals and replenishments of intermediate parts EOQ-ROP system is a “Pull” system where ROP triggers production at the supplier and EOQ determines the quantity produced 10. Lean Operations: Process Synchronization and Improvement 10.4.2 Improving Information & Material Flow: Demand Pull 32 Synchronized Pull: When the delivery of parts are in sequence [Suppliers must have greater ability and capability to achieve a synchronized pull effectively] 10. Lean Operations: Process Synchronization and Improvement 10.4.3 Improving Process Flexibility: Batch-Size Reduction 33 Each station must know HOW MUCH TO PRODUCE AT A TIME Level Production: where small quantities are produced frequently to mach customer demand [i.e., if demand is 10000 sedans and 5000 SUVs, the production would call for producing 2 sedans and then 1 SUV, and then repeat the sequence] Changeover Costs and Batch Reduction: Goal of level production is reduction of changeover costs (fixed setup or transportation costs of each batch) I.E. In auto production expensive parts like seats are produced in batches of one, wipers in larger batches Study the Changeover process to: use special tools to speed it up, customize some machines, keep some machines already set up. Consider “small-batch” production 10. Lean Operations: Process Synchronization and Improvement 10.4.4 Quality at Source: Defect Prevention & Early Detection 34 Defective flow units increase average flow time and cost!!! WHY? It necessitates inspection and rework!!! Anticipate and then Compensate for the problem: – Hold extra safety inventory in the buffer – This increases avg. flow time and cost Plan and control Quality: 1. Prevent defects for occurring in the first place 2. Detect and correct them as soon as they appear 10. Lean Operations: Process Synchronization and Improvement 10.4.4 Quality at Source: Defect Prevention & Early Detection 35 Defect Prevention – Careful design of both product and process – Simplification & standardization – Mistake-proofing (poka yoke) Parts are designed to halt automatically when defective units are fed into them (parts are designed to minimize chances of incorrect assembly) Defect Visibility – Early detection/corrections economical more effective & 10. Lean Operations: Process Synchronization and Improvement 10.4.4 Quality at Source: Defect Prevention & Early Detection 36 Defect visibility (cont’d) – Early detection helps tracing to the source – Contribution to better synchronization and lower costs – Early detection requires constant vigilance and monitoring!! Decentralized Control – Employees must be empowered with authority and the means to identify & correct problems at the local level 10. Lean Operations: Process Synchronization and Improvement 10.4.4 Quality at Source: Defect Prevention & Early Detection 37 Decentralized Control (cont’d) – In typical plants, line workers don’t feel the responsibility, motivation or security to point out problems. BEST STRATEGIES OF LEAN OPERATIONS ARE: 1. Preventing problems through better planning 2. Highlighting problems as soon as they occur 3. Delegating problem solving to the local level 10. Lean Operations: Process Synchronization and Improvement 10.4.5 Reducing Processing Variability: Standardization of Work Maintenance, and Safety Capacity 38 Reduce Variability: – Standardize work at each stage and specify it clearly Advantages to Standardization: – Reduces variability from changing personnel – Reduces variability from one production cycle to the next – Makes it easier to identify sources of waste that can be eliminated 10. Lean Operations: Process Synchronization and Improvement 10.4.5 Reducing Processing Variability: Standardization of Work Maintenance, and Safety Capacity 39 Lean Operations try to: – Minimize carrying safety inventory due to increased flow time – Maintain some safety capacity as production against variability These could be extra machines, workers, overtime These forms of safety capacity should be flexible so that it can be used as needed!! 10. Lean Operations: Process Synchronization and Improvement 10.4.6 Visibility of Performance 40 1. A company needs to “see” (measure) process performance from the customer’s perspective – I.E. Time per call 2. Measure Percentage of Customers that had a problem resolved with one call 3. Actual performance (along with expectations) should be visible at each work cell 4. Not for punishment, but to provide quick feedback for corrective action 10. Lean Operations: Process Synchronization and Improvement 10.4.7 Managing Human Resources: Employee Involvement 41 SYNCHRONIZATION WITHIN A PLANT REQUIRES: 1. Cooperation 2. Contribution 3. Commitment Elton Mayo’s “Hawthorne Experiments” at Western Electric showed that: Research has shown that workers involved in the decision-making process are better motivated and productive 10. Lean Operations: Process Synchronization and Improvement 10.4.7 Managing Human Resources: Employee Involvement 42 In Companies with Lean Operations: • Workers are cross-trained to provide the company with flexible workers. • Workers are in work teams in cells and may perform certain managerial duties such as material ordering, hiring, scheduling • Great importance on recruiting and training of workers 10. Lean Operations: Process Synchronization and Improvement 10.4.8 Supplier Management: Partnerships 43 Outsourcing: Provides a flexible alternative to producing in-house BUT- - - purchased materials account for a major portion of product cost and are a major source of quality problems!! Lean approach: – Choose only a few capable suppliers – Cultivate cooperative, long-term relationships 10. Lean Operations: Process Synchronization and Improvement 10.4.8 Supplier Management: Partnerships 44 In Lean Operations: – Suppliers are an extension of the plant – Processing without inventories or quality inspection – Synchronization requires defect-free material – Frequent deliveries, small batches – Supplier’s process be able to produce small quantities on demand 10. Lean Operations: Process Synchronization and Improvement 10.4.8 Supplier Management: Partnerships 45 YOU ARE TREATING THE SUPPLIERS AS PARTNERS 10. Lean Operations: Process Synchronization and Improvement 10.4.1 – 10.4.8 SUMMARY 46 Lean Operations aim to sustain continuous flow processing in an economical manner: 1. Synchronize material and information flows 2. Increase flexibility 3. Reduce variability 4. Decrease processing costs 10. Lean Operations: Process Synchronization and Improvement Chapter 10 47 Lean Operations: Process Synchronization and Improvement Questions??