Coppin State University Health and Human Services Building Baltimore, Maryland Corinne Ambler Penn State AE Senior Thesis Construction Management Presentation Outline Project Overview Construction Cost Escalation Analysis Solar Shading Analysis Overhead Pedestrian Bridge Illumination Summary and Conclusions Questions Corinne Ambler Penn State AE Senior Thesis Construction Management Project Overview Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Size: Construction Cost: Construction Dates: Delivery Method: Corinne Ambler Five Stories, 150,000 sf $48.6 Million January 2006 – August 2008 CM at Risk with GMP Penn State AE Senior Thesis Construction Management Project Team Presentation Outline Owner Client Project Overview Construction Cost Escalation Solar Shading Analysis University of Maryland, Baltimore Coppin State University Architect Construction Manager Bridge Illumination Analysis Acknowledgements Design Collective, Inc. Barton Malow Company Structural Engineer MEP Engineer Hope Furrer Associates RMF Engineering, Inc. Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management Project Features Presentation Outline Academic Facility Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler – – – – – – – – – Early Childhood Demonstration Center Lecture Halls Meeting Rooms Offices Outpatient Health Clinic Research Labs Moot Courtroom Forensic Lab Overhead Pedestrian Bridge Penn State AE Senior Thesis Construction Management Building Envelope Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Façade Materials – – – – – Glazed Aluminum Curtain Wall Glazed Storefront Face-Brick Veneer with Masonry Cavity Cast Stone Panels Insulated Metal Panels Bridge Illumination Analysis Acknowledgements Questions & Comments Roof Materials – Metal Screen – EPDM Single Ply Membrane – Hot Fluid Applied Roof Corinne Ambler Penn State AE Senior Thesis Construction Management Structural System Presentation Outline Framing – ASTM A992 Structural Steel Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Foundation – 4000 psi Cast-in-Place Caissons, Grade Beams & Foundation Walls Decking – Composite Metal Deck – 3” 3500 psi Reinforced Lightweight Concrete Corinne Ambler Penn State AE Senior Thesis Construction Management Mechanical & Electrical Systems Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Mechanical System – 6 Rooftop Air Handling Units – (2) 400 Ton Chillers – (2) 200 HP Boilers Electrical System – 480Y/277 Volt Service – 400kW Emergency Back-Up Generator Corinne Ambler Penn State AE Senior Thesis Construction Management Site Conditions Presentation Outline Project Overview – Located in Baltimore, Maryland on a College Campus – 8 miles Northwest of Inner Harbor – 3 Site Entrances Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management Volatility of Escalating Construction Costs Corinne Ambler Penn State AE Senior Thesis Construction Management Construction Cost Escalation Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Coppin State University - Health and Human Services Building Conditions - Project Bid to Contractors in Three Phases - Hurricane Katrina Hit During Bidding Process - Materials Escalated Unprecedented High Trades in Each Bid Phase Phase I Excavation and Grading Demolition Deep Foundations Concrete Structural Steel Elevators Phase II Fireproofing Glass Systems Fire Protection Mechanical Electrical Acknowledgements Questions & Comments Phase III Final Sitework Landscaping Masonry Misc. Metals Carpentry & Woodwork Metal Panels Roofing Doors, Frames and Hardware Partitions and Ceilings Ceramic Tile Painting and Coating Lab Casework *Steel & Glazing Bid Accounted for Most Over Estimated Budget Overage - Owner Forced to Alter Budget or Building - Considered Removing Early Childhood Demonstration Center - Asked State of Maryland for $5 Million More X Corinne Ambler 5 Story Main Building Penn State AE Senior Thesis Construction Management Construction Cost Escalation Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Problem: Managing the risk of maintaining a Budget in the Current Market - Volatility of Material Costs - Escalation of Labor Wages Bridge Illumination Analysis Acknowledgements Questions & Comments Solution: Alter the Contractors Bidding and Payment Process - Require Contractor Bids to Reflect Current Market Prices - Owner Compensate for Escalation Quarterly Corinne Ambler Penn State AE Senior Thesis Construction Management Current Market Conditions Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Escalation of Material Costs - Inflation/Escalation Free Era from 2001-2003 - Volatile Escalation of Material Prices from 2004-2006 - Material Costs have Decreased in Recent Months - Material Costs Expected to Rise 6-8% by end of 2007 Causes of Material Escalation: Increased Fuel Prices - Anything Being Shipped or Hauled - Raw Materials and Finished Products Acknowledgements Questions & Comments - Petroleum Products – PVC, Roofing/Waterproofing, PVC Pipe & Asphalt Increase In Global Economy (India and China) - Longer Lead Time for Materials Materials Affected Most - Concrete - Aluminum - Steel - Glass - Copper - Drywall/Gypsum - Lumber Products Affected by Multiple Material Escalation – Cast-in-Place Concrete Corinne Ambler Penn State AE Senior Thesis Construction Management Current Market Conditions Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Escalation of Labor Wages - Construction Industry Produced 1 out of 10 New Jobs - Recent Years Employment Dropped 0.2% - Hourly Wages increased 4.8% in 2006 - Labor Wages Increase 5% by end of 2007 Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Causes of Labor Wage Increase - Labor Shortage - Decline in Residential Construction Increased Number of Higher Paying Jobs - Shortage of Apprentices Coupled with Shortage of Teachers Penn State AE Senior Thesis Construction Management Construction Cost Escalation Presentation Outline Resources Contacts for Cost Escalation Interview Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Brian Barnes John Bechtel Brook Behner Lee Evey Sarah Forrest Scott Franckowiak Hope Furrer Bob Grottenthaler Merton Harris Matt Herbert Telly Koutris Keith Lambert Mike Miller Jorge Scotti Ken Simonson Todd Sody Todd Vochinsky Contractor Owner Contractor Construction Manager Estimator Contractor Designer Construction Manager Designer Designer Contractor Contractor Construction Manager Owner Economist Contractor Estimator Finishes, Inc The Pennsylvania State University Homewood General Contractors, Inc Design Build Institute of America Hensel Phelps Construction Co. MBR Construction Hope Furrer Associates Barton Malow Company RMF Design Collective, Inc David Allen Company Zephyr Aluminum Southland University of Maryland, Baltimore AGC Chief Economist Sody Concrete Barton Malow Company - Engineering News Record (ENR) Database - Associated General Contractors (AGC) Escalation Reports Corinne Ambler Penn State AE Senior Thesis Construction Management Construction Cost Escalation Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Construction Material Cost Escalation is a Risk for: - Contractors - Construction Managers - Designers - Owners - Vendors/Suppliers Current Strategy Incorporate an Inflation/Escalation Percentage Increase and then Pass the Risk to the Next Party Problem with Current Strategy As Risk is Passed a Premium is Paid by the Owner for an Event that May Never Occur Corinne Ambler Penn State AE Senior Thesis Construction Management Construction Cost Escalation Presentation Outline Current Strategy for Managing Risk Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management Construction Cost Escalation Presentation Outline Recommendation Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Make an Effort to Simplify Bid Documents - Require Thorough Constructability Review that Involves a Contractor - Eliminate Future Addendums - Create a More Accurate Material Take-Off Require Contractor to Bid on Current Market Prices - Require that Initial Bid does not include the Cost of Escalation or Inflation - Standardize Bid Review Material Cost Escalation Quarterly - Assess Material Escalation Quarterly using a Material Escalation Index - Increase/Decrease Contract for Escalation of Materials Bought Each Quarter > Performed for 3 Pay Applications Corinne Ambler Penn State AE Senior Thesis Construction Management Construction Cost Escalation Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Conclusion - Increase Mutual Respect between Parties - Allow Owner to Manage the Risk of Cost Escalation and Inflation - Reduce the Amount of Money Spent on Managing Risk Bridge Illumination Analysis Acknowledgements To Allow the Owner… Questions & Comments ‘To Get More Building For The Buck’ Corinne Ambler Penn State AE Senior Thesis Construction Management Solar Shading Analysis Corinne Ambler Penn State AE Senior Thesis Construction Management Solar Shading Analysis Presentation Outline Existing Sunshade runs along the 5th Floor Perimeter Serves as a Capital to Complete an Aesthetic Look Project Overview Construction Cost Escalation Problem – Sunshade does not Minimize Solar Heat Gain Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Sunshade is 4’-1 ¾ “ Above Head of Window Existing Redesign Solution – Minimize Solar Heat Gain by Extending and Lowering Sunshade – Minimize Initial and Operating Cost Corinne Ambler Penn State AE Senior Thesis Construction Management Solar Shading Analysis Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Existing Conditions - Located at 39.18°N Latitude and 76.67°W Longitude - 5th Floor Exposure Aligned with North/South Axis - 4’ Tapered Outrigger with 4” Airfoil - Sunshade Mounting Tab Welded to Girder Existing Sunshade Connection Bridge Illumination Analysis Acknowledgements Questions & Comments 5th Floor Exposure 4’ Tapered Outrigger Corinne Ambler 4” Airfoil Penn State AE Senior Thesis Construction Management Mechanical Impacts January January Presentation Shadow Length (ft) Shaded (SF) Solar Heat Gain Factor (Btu/h-ft2) Solar Heat Gain (Btu) Shadow Length (ft) Percent Shaded Solar Heat Gain Factor muthPercent Solar Altitude Azimuth Percent Shaded (SF) Solar Heat Gain Factor (Btu/h-ft2) Solar Heat Gain (Btu) (SF) Shadow Length (ft) Percent Shaded (SF) Solar Heat Gain Factor (Btu/h-ft2) Solar Heat Gain Sunny Days Solar Altitude Shaded (SF) SolarAzimuth HeatPercent Gain Factor (Btu/h-ft2) Solar Heat Gain (Btu) Outline Solar Heat Gain Sunny Days(Btu/h-f Hou South East West South East West South East West North South East West North South East West South East West North South East We est grees) South East West Time (degrees) (degrees) January South East West North South East West North South East West South East West North South East West No Coefficient per Month Time (degrees) (degrees) South East West North South East West North South East West Coefficient per Month Shadow Length (ft) Percent Shaded (SF) Solar Heat Gain Factor (Btu/h-ft2) Solar Heat Gain (Btu) Solar Altitude Azimuth Solar Heat Gain Sunny Days Hourly Btu 5.3 1.00 0.69 0.00 0.15 0.09 0.00 5 75 111 5 3159 11210 139665 8427 8 8.1 55.3 1.00 0.69 0.00 0.15 0.09 0.00 5 75 111 5 00 0.15 0.15 0.0980.09 0.00 0.00 5 75South75 1110.69 5East0.00 11210 0.4 111 per 12 8.1 55.3 1.00 0.15 0.09 0.00 5East West 75 Coefficient 31 East South West3159 North South East West139665 North South 8427 Time (degrees) Month5 12 5 (degrees) 111 West 5 3159 11210 139665 8427 0.4 77 Project Overview 8 8.1 55.3 1.00 0.69 0.00 0.15 0.09 0.00 5 75 111 5 3159 11210 139665 8427 0.4 12 779816 44 0.25 0.25 1.68 1.74 0.00 0.25 44 0.24 0.00 12 7583 160 21403 154 12 21403 16641812154 9 16.8 16.8 1.68 1.74 0.00 0.25 0.24 0.00 12 0.4 160 12 00 0.00 160 12 20225 12 75 44 1.68 1.74 0.00 0.25 0.2412 166418 0.00 214037583 12 160 154 1220225 0.2490.24 0.00 12 12 154 154 12 0.4 9 16.8 44 1601.68 1.74 0.00 0.25 0.247583 0.00 1221403 160 154166418 7583 20225 166418 20225 0.4 12 1035021 103 10 23.8 30.9 2.06 3.44 0.00 0.30 0.47 0.00 16 213 124 16 10110 26612 101517 26967 0.4 12 792987 0.9 2.06 3.44 0.00 0.30 0.47 0.00 16 213 124 16 10110 26612 101517 26967 10 23.8 30.9 2.06 3.44 0.00 0.30 0.47 0.00 16 213 124 16 00 0.30 0.30 0.47 0.0028.4 16 213 16 100.47 0.00 23.8 2.06 3.44 0.000.0010110 0.3024426612 0.4719 101517 0.00 2941426967 16 213 0.4 124 12 16 12 101 16 30.9 124 124 16 10110 0.4 11 16 2132.25 7.85 0.00 0.33 1.00 1926612 61101517 1200626967 26276 32023 0.4 12 478654 79 Construction Cost 16 0.33 0.33 2.25 7.85 0.00 1.00 0.00 190.0012006 244 61 19 12006 29414 2627612 12 30 00.33 2.31 0.00 0.34 19 0.00 20 25429414 21 21 26276 12638 30280 29042 35394 0.4 244 12 19 515299 120 11 28.4 16 2.25 7.85 0.00 0.33 1.00 0.00 19 0.4 6132023 19 00 0.00 244 617.85 32023 12 111.00 28.4 16 2.25 0.00 0.33 1.00 0.00 19 244 61 1.00 0.00 19 19 2442.25 61 0.00 19 12006 29414 26276 32023 0.4 47 1 28.4 16 0.00 7.85 0.33 0.00 1.00 19 244 19 61 12006 29414 26276 32023 0.4 12 478654 Escalation 0 2.31 0.00 0.00 0.34 0.00 0.00 20 254 21 21 12638 30280 29042 35394 30 20 2.31 0.00 0.00 0.34 0.00 0.00 20 0.4 21 00 0.34 0.34 0.00 210.00 20.0023.8 30.9 0.00 0.30 21 0.00 16 21330280 16 124 29042 10110 2661235394 22127 123722 0.4 254 12 21 12 876341 126 120.00 12 0 2542.060254 2.31 0.000.4712638 0.34 0.00 0.00 20 254 21 0.0030 20 21 3.44 21 12638 30280 29042 35394 0.4 12 51 3 16.8 44 1.68 0.00 1.74 0.25 0.00 0.24 12 160 12 154 7583 21403 16595 202820 0.4 12 1192325 16 0.33 0.33 2.25 0.00 7.85 0.33 0.00 1.00 19 244 19 61 12006 29414 26276 32023 1 28.4 16 2.25 0.00 7.85 0.33 0.00 1.00 19 244 19 61 85 0.00 1.00 19 244 19 61 12006 29414 26276 32023 0.4 12 1 28.4 16 2.25 0.00 7.85 0.33 0.00 1.00 19 244 19 61 120 8.1 0.15 0.00 0.09 529414 75 5 26276 111 3159 32023 11210 6915 170215 0.4 12 919196 47 0.00 1.00 4 19 55.3 2441.00 0.00 19 0.69 61 12006 0.4 12 Total Btu: 123722 7068294 Solar Shading 0.9 2.06 0.00 3.44 0.30 0.00 0.47 16 213 16 124 10110 26612 22127 44 0.30 0.30 0.0020.00 0.47 0.47 23.8 16 21330.9 213 160.00 123722 2 23.8 0.00 3.44 0.30 0.00 0.47 16 0.4 213 16 12 101 12 2.06 3.44 10110 0.30 0.00 0.47 16 213 16 16 30.9 16 2.06 124 124 10110 2661226612 2212722127 123722 0.4 12124 87 Analysis 44 0.25 0.25 1.68 0.00 1.74 0.25 0.00 0.24 12 160 12 154 7583 21403 16595 202820 74 0.00 0.24 12 160 12 154 7583 21403 16595 202820 0.4 12 3 16.8 44 1.68 0.00 1.74 0.25 0.00 0.24 12 160 12 154 75 3 16.8 44 1.68 0.00 1.74 0.25 0.00 0.24 12 160 12 15 0.00 0.24 12 160 12 154 7583 21403 16595 202820 0.4 12 119 5.30.15 0.15 1.00 0.00 0.69 0.00 0.09 111 5 3159 75 11210 5 6915 6915 111 3159 11210 69 0.09 50.15 75 5 0.00 170215 12 31 1.00 0.69 0.15 0.00 0.09 5 75 56915 12111 4 8.1 8.1 0.00 0.69 0.15 0.00 0.09 5 0.4 75 5170215 11 0.0040.00 0.09 5 55.3 7555.3 5 1.00 111 3159 11210 170215 0.4 91 Solar Heat Gain Calculations Bridge Illumination Analysis Acknowledgements Questions & Comments Constants - Reynolds - “Mechanical and Electrical Equipment for Buildings” pg 1638 & 1648 Total Btu: Total Btu: 706 - Altitude - Azimuth - Solar Heat Gain Factor - Viracon Glass VE 1-52 Defines Solar Heat Gain Coefficient - Estimated Number of Sunny days per month Corinne Ambler Penn State AE Senior Thesis Construction Management Mechanical Impacts January Presentation Length (ft) Percent Solar Heat FactorHeat (Btu/h-ft2) Solar Heat Gain Solar (Btu) Shadow Length (ft) Shaded (SF) Percent Shaded (SF)Gain Solar Gain Factor (Btu/h-ft2) Altitude Solar Azimuth Altitude Shadow Azimuth Outline South East South West East South West East South West East North West South North East South West East North West SouthNorth East Sou degrees)Time (degrees) (degrees) (degrees) 8.1 8 55.3 8.1 16.8 44 16.8 Project9Overview 23.8 10 30.9 23.8 11 16 28.4 Construction Cost28.4 12 0 30 30 Escalation 1 16 28.4 28.4 2 30.9 23.8 23.8 Solar Shading 3 44 16.8 16.8 4 Analysis 8.1 55.3 8.1 Solar Heat Gain Calculations January 1.00 Solar Time 1.68 8 9 2.06 10 2.25 11 12 2.31 1 2 2.25 3 4 2.06 1.68 1.00 0.69Azimuth1.00 0.00 0.15 55.3 Shadow 0.69 Length (ft) Altitude East West (degrees) (degrees) South 1.74 0.00 0.25 44 1.68 1.74 8.1 55.3 1.00 0.69 0.00 16.83.44 44 2.06 1.68 1.74 0.00 0.00 0.30 30.9 3.44 23.8 30.9 2.06 3.44 0.00 16 7.85 0.00 0.33 28.47.85 16 2.25 2.25 7.85 0.00 30 0 2.31 0.00 0.00 0 2.31 0.00 0.00 0.00 0.34 28.4 16 2.25 0.00 7.85 23.8 30.9 2.06 0.00 3.44 16 2.25 0.00 0.00 7.85 0.33 16.8 44 1.68 0.00 1.74 8.10.00 55.32.06 1.00 0.00 0.69 30.9 0.00 3.44 0.30 44 0.00 1.68 1.74 0.00 0.25 55.30.00 1.00 0.69 0.00 0.15 0.09Shaded0.15 0.00Solar0.09 5 Factor0.00 75 0.00 Percent (SF) Heat Gain (Btu/h-ft2) South East West North South East West 0.24 0.00 12 160 0.00 0.25 0.24 0.00 0.15 0.09 0.00 5 75 111 5 0.250.47 0.24 0.30 0.00 160 12 0.00 12 0.47 16 1540.00 213 0.00 0.30 0.47 0.00 16 213 124 16 0.00 0.00 19 1.00 19 610.00 244 0.331.00 1.00 0.33 0.00 244 19 0.34 0.00 0.00 20 254 21 21 0.00 0.34 0.00 0.00 0.00 0.00 20 254 0.33 0.00 1.00 19 244 19 61 0.30 0.00 0.47 16 213 16 124 7.85 0.33 0.00 1.00 0.00 1.00 19 244 0.25 0.00 0.24 12 160 12 154 0.150.00 0.00 0.30 0.09 111 3.44 0.47 5 0.0075 16 5 0.47 213 1.74 0.24 0.00 0.25 0.24 0.0012 160 0.69 0.09 0.00 0.15 0.09 0.005 75 East 111 5(Btu) 111 3159 11210 5 112 Solar Heat 75 Gain Solar Heat5 Gain Sunny3159 Days 139665 Hourly Btu South East West Coefficient per Month 15411210 12 7583 21403 166418 12 160 154 12 7583 214 139665 8427 0.4 12 779816 21403 166418 20225 0.4 12 1035021 124 16 10110 162661210110 101517 16 213 124 266 26612 101517 26967 0.4 12 792987 19 61 1200626276 61 29414 244 19 32023 12006 0.4192941412 26276 478654294 30280 29042 35394 0.4 12 515299 20 21 1263829042 21 29414 254 21 32023 12638 0.4213028012 26276 478654302 26612 22127 123722 0.4 12 876341 19 19 1200626276 294 19 21403 244 61 202820 12006 0.4612941412 16595 1192325 6915 170215 919196266 16 16 1011022127 16 11210 213 124 10110 0.41242661212 Total Btu: 7068294 12 160 12 12 154 7583 15421403758316595214 111 and55West75 Sides 53159 111112103159 6915112 North 3159 7583 10110 12006 12638 12006 10110 7583 3159 Bridge Illumination Analysis Shadow Length = tan(Altitude) x Acknowledgements South Side Shadow Length = tan(Altitude) x Questions & Comments Shadow Length Height (ft) Length (ft) Area(ft2) North South 7.33 6.83 86.17 25.33 631.89 Length of Overhang cos(Azimuth) Length of Overhang cos(Azimuth) East 7.33 188.58 West 7.33 229.83 173.11 1382.94 1685.44 Percent Shaded = Shadow Length x Length of Glass Total Area of Glass Corinne Ambler Penn State AE Senior Thesis Construction Management Mechanical Impacts Presentation Outline (ft) Percent Shaded Shadow Length (ft) (SF) muth West South South EastEast rees) 0.00 0.15 0.690.09 5.3 1.00 Project Overview 0.00 0.25 1.740.24 44 1.68 0.30 3.440.47 0.90.00 2.06 Construction 160.00 2.25 7.851.00 0.33 Cost 0 0.00 2.31 0.34 0.000.00 Escalation 167.85 2.25 0.33 0.000.00 0.93.44 2.06 0.00 Solar0.30 Shading0.00 441.74 1.68 0.25 0.000.00 Analysis 5.30.69 1.00 0.15 0.000.00 Bridge Illumination Analysis Acknowledgements Questions & Comments Solar Heat Gain Calculations Solar Heat Gain(SF) Factor (Btu/h-ft2) Heat Gain (Btu) Solar Heat Gain Solar(Btu) Heat Gain Sunny Percent Shaded Solar Heat Gain FactorSolar (Btu/h-ft2) SolarDays Heat Gain Sunny Hourly Btu D January West South North East South West East North West South NorthEast South East West Coefficient per Month West West North South East West Coefficient per Mo Shadow Length (ft) Percent Shaded (SF) Solar Heat Gain Factor (Btu/h-ft2) Solar Heat Gain (Btu) Solar Altitude Azimuth Solar Heat Gain Sunny Days Hourly Btu South West 5South East West South East West North East 0.4 West 5 0.09 75 East 5 11210 139665 8427 South 139665 Time0.00 (degrees) per Month 77981612 0.00 0.15(degrees) 0.00111 75 3159 111North 5 3159 11210 8427 Coefficient12 0.4 8 8.1 55.3 1.00 0.69 0.00 0.15 0.09 0.00 5 75 111 5 3159 11210 139665 8427 0.4 12 779816 0.0016.8 160 1.74 12 160 7583 21403 166418 20225 0.420225 0.00 0.25 1244 0.241.68 0.001540.00 120.25 12 2140321403 166418 20225 0.4 12 0.4 12 1035021 9 0.24 0.00154 12 160 1547583 12 7583 166418 1035021 12 10 0.0023.8 30.9 0.47 2.06 0.4710110 0.00124 1626612 213 124 16 10110 101517 792987 12 213 3.44 16 213 101517 26967 0.426967 792987 0.00 0.30 16 0.001240.00 160.30 16 10110 2661226612 101517 26967 0.4 12 0.4 12 11 28.4 16 2.25 7.85 0.00 0.33 1.00 0.00 19 244 61 19 12006 29414 26276 32023 0.4 12 478654 0.00 0.33 1.00 0.00 19 244 61 19 12006 29414 26276 32023 0.4 0.00 19 244 61 19 12006 29414 26276 32023 0.4 12 478654 12 30 0 2.31 0.00 0.00 0.34 0.00 0.00 20 254 21 21 12638 30280 29042 35394 0.4 12 515299 12 1 0.0028.4 0.00 7.85 0.33 0.00 1.00 19 244 19 61 12006 29414 26276 32023 0.4 12 478654 12 0.00 0.34 2016 0.002.25 0.00 20 254 21 21 12638 30280 29042 35394 0.4 254 0.00 213.44 0.30 21 0.0012638 30280 29042 3539426612 221270.4123722 12 515299 2 23.8 30.9 2.06 0.47 16 213 16 124 10110 0.4 12 876341 7.85 0.33 0.00 1.00 19 244 19 61 12006 29414 26276 32023 0.4 3 1.0016.8 1.68 0.24 1229414 160 12 154 7583 0.4 12 12 1192325 12 1944 244 0.00 191.74 0.25 61 0.0012006 26276 3202321403 165950.4202820 478654 4 55.3 0.00 0.09 75 5 111 3159 6915 919196 3.44 0.001.00 0.47160.69 160.15 16 526612 124 10110 2661211210 22127 123722 0.4 12 0.4 12 12 0.47 8.10.30 16 213 0.00 124 213 10110 22127 123722 0.4170215 876341 Total Btu: 7068294 1.740.24 0.25 12 0.00160 0.2412 12154 1607583 12 21403 154 7583 21403 16595 202820 0.4 16595 202820 0.4 12 119232512 0.690.09 0.15 5 0.0075 0.09 5 5 111 75 3159 5 11210 111 3159 11210 6915 170215 0.4 6915 170215 0.4 12 91919612 Total B Total Btu: 7068294 Solar Heat GainX (Btu) = (1-ASX)ATXFX + ASX ATXFN When… ASX is the Shaded Area for Side X ATX is the Total Area of Glass for Side X FX is the Solar Heat Gain Factor for Side X FN is the Solar Heat Gain Factor for the North Side Hourly Solar Heat = Gain (Btu) Corinne Ambler Solar Heat x Solar Heat Gain x Sunny Days Gain Coefficient per Month Penn State AE Senior Thesis Construction Management Mechanical Impacts Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Impacts of Lowering the Sunshade Overhang Length of 4’ 4’-1 ¾ “ Above Head of Window Month Month Btu per Month January 9,171,824 February 11,290,921 March 14,263,934 April 16,668,644 May 19,361,664 June 20,657,017 July 22,163,105 August 19,301,728 September 18,547,310 October 15,776,857 November 9,466,098 December 7,491,578 Yearly Total: 184,160,679 Current Btu 184,160,679 Corinne Ambler Overhang Length of 4’ 0“ Above Head of Window Btu per Month January 7,068,294 February 8,293,033 March 10,217,519 April 12,269,298 May 14,496,006 June 15,572,578 July 16,679,511 August 13,533,949 September 13,680,595 October 11,807,527 November 7,278,966 December 5,849,392 Yearly Total: 136,746,668 Re-design Btu 136,746,668 Penn State AE Senior Thesis Change in Btu 47,414,011 Construction Management Solar Shading Analysis Presentation Outline Impacts of Extending the Sunshade Lowered Lowered & Extended Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Sunshade Located at Head of Window Length of Sunshade 5' 6' 7' 8' 9' 10' Corinne Ambler Yearly Btu Savings per Additional Foot 10,430,973 9,307,864 7,867,882 6,476,634 5,656,544 4,877,344 Penn State AE Senior Thesis Construction Management Structural Impacts Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Addition of 156 Steel Plates Around 5th Floor Perimeter - A36 24”x 7”x 3/8” - Welded to Girder Beam at 5’ O.C. Existing Connection Redesigned Connection Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management Cost Impacts Presentation Outline Lowering Sunshade Project Overview Construction Cost Escalation Electrical Supply Savings Current Btu 184,160,679 Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Re-design Btu 136,746,668 Item Change in Btu 47,414,011 Savings $141 Savings Electrical Demand Supply Charge Savings Initial One Time Chiller Savings $17,278 Current Lowest Re-design Difference in Change in Demand Hourly Btu Time Lowest Hourly Plate Hourly Btu Tons Charge Saved Initial One Steel Cost -$6,017 7191 7048 143 4.29 $3,079 Electricity Savings per Year $141 Chiller Reduction Savings Demand Charge Savings per Year $3,079 Amount Saved Number of Square Total Initial Cost ($/SF) ($): Total First Year Savings $14,480 (Tons) Feet per Ton Savings ($) 4.29 450 $17,277.98 Additional Savings per $8.95 Year ($): $3,220 Structural Steel Plate Costs Weight of Steel (lb/ft3) 460 Corinne Ambler Volume of Steel per Plate (ft3) 0.036458333 15% for Labor (ft3) 0.00546875 Penn State AE Senior Thesis Weight per Plate (lb) 19.28645833 Number of Plates 156 Cost ($/lb) $2.00 Cost ($) $6,017.38 Construction Management Cost Impacts Presentation Outline Extending Sunshade Cost per Additional Foot for Material and Labor Project Overview Sunshade Length (ft) Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Sunshade Length (ft) 4' 5' 6' 7' 8' 9' 10' Cost ($) 1 4' 5' 6' 7' 8' 9' 10' Additional Length + Steel $6,017 Initial Cost $40,015 40000 $74,387 20000 $109,133 0 $144,170 2 3 4 5 6 7 8 -20000 $179,581 -40000 $215,366 -60000 Area of Sunshade (SF) Cost ($) 3,188 $0 4,006 $33,998 4,833 $68,370 5,669 $103,116 6,512 $138,152 7,364 $173,563 Initial Savings ($)$209,348 Yearly 8,225 Tonnage Reduction $17,278 $21,628 160,000,000 $25,977 $30,206140,000,000 $34,556120,000,000 9 10 $38,906100,000,000 $43,255 80,000,000 -80000 60,000,000 -100000 40,000,000 -120000 Savings ($) Payback Period (Years) Demand + Supply $3,220 Yearly Btu 0 4 9 13 16 19 21 $4,026 $4,829 $5,606 $6,400 $7,192 $7,981 20,000,000 -140000 0 -160000 -180000 Corinne Ambler Penn State AE Senior Thesis 1 2 3 4 5 6 7 4 5 6 7 8 9 10 Construction Management Conclusion & Recommendation Presentation Outline Lower the Sunshade to Head of Window but do not extend the Sunshade Project Overview Construction Cost Escalation Solar Shading Analysis Initial Savings $14,480 Yearly Savings $3,220 No Schedule Impact Bridge Illumination Analysis Acknowledgements Questions & Comments Existing Lowered &Extended Lower Sunshade Lowered Corinne Ambler Penn State AE Senior Thesis Construction Management Overhead Pedestrian Bridge Illumination Analysis Corinne Ambler Penn State AE Senior Thesis Construction Management Bridge Illumination Analysis Presentation Outline The Overhead Pedestrian Bridge connects the New Campus to Old Campus and is a visible symbol of the college for all who drive down W. North Avenue Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Conditions – Connects with Health and Human Services Building on 2nd Floor – Will Connect to a Future Parking Garage – Crosses North Avenue Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management Bridge Illumination Analysis Presentation Outline Project Overview Construction Cost Escalation Community Outreach – Early Childhood Demonstration Center – Outpatient Health Clinic – Community BBQ Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management Bridge Illumination Analysis Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Problem - Ignored Architectural Feature of the Campus - Lighting is Ordinary and Industrial Solution - Create a Prestigious Symbol for Coppin State University - Highlight the Structure and Architectural Features of Bridge - Hide the Light Source - Maintain an Average Horizontal Illuminace Level of 5 footcandles and an Average Vertical Illuminance Level of 3 footcandles according to IESNA Handbook Penn State AE Senior Thesis Construction Management Bridge Illumination Analysis Presentation Outline Existing Conditions - 40 Pendant Ceiling Mounted Fixtures - No Light Focused on Structure - Light Source is Visible Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Interior View Acknowledgements Questions & Comments Exterior Views Corinne Ambler Penn State AE Senior Thesis Construction Management Bridge Illumination Analysis Presentation Outline Redesigned Lighting Scheme - Small Fixtures Blend into Space - Fixtures Painted to Match Truss Color - FF-1 Ceiling Mounted Every 20 feet - FF-2 Wall Mounted Every 10 feet on Alternate Sides Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler FF-1 FF-2 Label Description Diecast Aluminum, FF-1 Ceiling Surface Mounted Downlight Diecast Aluminum, FF-2 Wall Mounted Direct/Indirect NO. Lamp Type Watts Ballast Voltage Type Lamps Fixture Qty. 1 50W MH 50W Electronic 1 277 7 1 50W MH 50W Electronic 1 277 16 Penn State AE Senior Thesis Construction Management Bridge Illumination Analysis Presentation Outline Project Overview Pseudo Color Rendering Existing Conditions Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Redesign Conditions Redesigned Illuminance Levels - Average Illuminance of 6.18 footcandles - Maximum Illuminance 11.6 footcandels Corinne Ambler Penn State AE Senior Thesis Construction Management Bridge Illumination Analysis Presentation Outline Hidden Light Source that Highlights the Structure and Architectural Features with a Sufficient Amount of Light Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Interior View Interior View Exterior Views Corinne Ambler Penn State AE Senior Thesis Construction Management Electrical Impacts Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments ASHRAE Design Criteria of Maximum of 3 Watts/ft2 PANELBOARD SCHEDULE Redesign Power Density 80% Less than Allowable VOLTAGE: 480Y/277V,3PH,4W PANEL TAG: LPN2 MIN. C/B AIC: 10K Existing and Redesigned PANEL System Circuited to Panelboard LPN2 SIZE/TYPE BUS: 150A LOCATION: Room 212 OPTIONS: PROVIDE FEED THROUGH LUGS SIZE/TYPE MAIN: 150A/3P C/B PANEL MOUNTING: SURFACE FOR PANELBOARD 1L1B Circuit 4 Redesigned According to NEC DESCRIPTION Lighting Lighting Lighting Lighting Lighting Spare Spare Spare Spare Spare Spare Spare Spare Spare Spare Spare Spare Spare Spare Spare Spare LOCATION LOAD (WATTS) C/B SIZE POS. NO. Offices 2900 20A/1P Existing Power Density 1 2100 20A/1P 3 500 20A/1P Total5 2900 Watts 20A/1P 7 2900 20A/1P Watts 9 0 20A/1P 11 40 35 1400 0 20A/1P 13 Total Watts: 0 20A/1P 1400 15 0 20A/1P Sqare Feet: 204017 0 20A/1P 19 Power 0 Density: 20A/1P0.686275 21 0 20A/1P 23 0 20A/1P 25 0 20A/1P 27 0 20A/1P 29 0 20A/1P 31 0 20A/1P 33 0 20A/1P 35 0 20A/1P 37 0 20A/1P 39 0 20A/1P 41 Offices Exterior Control Panel Qty Label Control Panel FF-1 A B C POS. NO. * * * * * * * * * * * * * * * 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 C/B SIZE LOAD (WATTS) LOCATION Redesigned Density 20A/1P 1800Power Corridor 20A/1P 20A/1P Label 20A/1P 20A/1P FF-1 20A/1P 20A/1P FF-2 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 20A/1P 1196 Bridge 1100 CoveTotal Qty 0 Watts 0 Watts 0 7 0 52 364 16 0 52 832 0 Total Watts: 1196 0 2040 0Square Feet: Power Density: 0.586275 0 0 0 0 0 0 0 0 0 0 0 DESCRIPTION Lighting Lighting Lighting Lighting Circuit 4 Redesign -* 20A, Single Pole, 277V * * * Allowable Total Wattage on Circuit 4 * * 16A x 277V x 1(Power Factor) = 4,432 Watts CONNECTED LOAD (KW) - A 7.60 TOTAL DESIGN LOAD (KW) CONNECTED LOAD (KW) - B 6.20 POWER FACTOR CONNECTED LOAD (KW) - C 1.60 1,196 Watts < 4,432 Watts 23.09 1.00 TOTAL DESIGN LOAD (AMPS) All Fixtures on Same Circuit Feeder Requires (3) #10 Wires in ½” EMT Conduit Corinne Ambler Penn State AE Senior Thesis Construction Management 28 Cost Impact Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Redesigned Fixture - Material Increase Cost of $1,000 - Labor Increase of 106 hours for Cost of $5,812 Number of Fixtures - Existing has 40 Fixtures - Redesign has 23 Fixtures Lamp Maintenance Reduction - Existing Lamp is Linear Fluorescent T8 - Redesigned Lamp is Metal Halide - Linear Fluorescent Lamps Lose Efficiency and Lamp Life in Low Temperatures - Metal Halide is Better for Outdoor Application Questions & Comments Metal Halide Corinne Ambler Penn State AE Senior Thesis Linear Fluorescent Construction Management Conclusion & Recommendation Presentation Outline Interior View Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Existing Acknowledgements Questions & Comments Redesign Corinne Ambler Penn State AE Senior Thesis Construction Management Conclusion & Recommendation Presentation Outline Exterior View Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Existing Acknowledgements Questions & Comments Redesign Corinne Ambler Penn State AE Senior Thesis Construction Management Conclusion & Recommendation Presentation Outline Existing Project Overview Exterior View Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Redesign Acknowledgements Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management Conclusion & Recommendation Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Utilize the Redesigned Lighting Scheme - Creates a Prestigious Symbol for the College - Slight Cost Increase Corinne Ambler Penn State AE Senior Thesis Construction Management Acknowledgements Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Architectural Engineering Faculty - Dr. Horman - Dr. Ling - Dr. Messner - Dr. Riley Barton Malow Company - Bob Grottenthaler - Katie Lynahan - Jason McFadden - Allen Turnbaugh - Todd Vochinsky Coppin State University & University of Maryland, Baltimore Design Collective, Inc - Matt Herbert - Eric Wohnsigl Family and Friends Fellow Architectural Engineering Students - Alexis Kreft - Joseph Mugford - Angela Nudy - Tyler Swartzwelder Corinne Ambler Penn State AE Senior Thesis Construction Management Questions and Comments Presentation Outline Project Overview Construction Cost Escalation Questions & Comments Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Allow the Owner ‘To Get More Building For The Buck’ - Owner Manages the Risk of Cost Escalation and Inflation - Reduce the Amount of Money Spent on Managing Risk Lower the Sunshade to Reduce Solar Heat Gain - First Year Savings of $14,480 - Yearly Additional Savings $3,220 - No Schedule Impact Corinne Ambler Utilize Redesigned Lighting Scheme of Bridge - Creates Prestigious Symbol - Highlights Structure and Architecture - Hides Light Source Penn State AE Senior Thesis Construction Management Current Market Conditions Presentation Outline Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler AGC Percentage Changes in Producer Price (PPI) Index Product Concrete products Concrete block and brick Concrete pipe Ready-mixed concrete Precast concrete products Prestressed concrete products Brick and structural clay tile Plastic construction products Gypsum products Insulation materials Lumber and plywood Architectural coatings Steel mill products Hot-rolled bars, plates, & structural shapes Steel pipe and tube Copper and brass mill shapes Aluminum mill shapes Fabricated structural metal Fabricated structural metal for buildings Architectural and ornamental metalwork Fabricated iron & steel pipe, tube, & fittings Fabricated steel plate Prefabricated metal buildings Construction machinery and equipment Past Years 2001 2002 2003 2004 2005 2006 2.5 2.3 4.4 2.5 0.7 5.3 5.3 -2.7 0.4 0.4 -2.9 2.9 -6.1 -4.3 -3.7 -9.5 -2.9 -1.3 -1.5 -0.1 0.6 0.6 0.0 -0.1 Penn State AE Senior Thesis -0.3 1.6 1.7 -1.1 0.3 1.8 1.9 3.1 3.4 -1.5 1.4 0.6 11.1 2.1 9.1 -1.6 -0.9 -2.4 -3.3 3.7 0.1 -1.0 4.0 1.9 1.5 3.2 1.4 2.1 2.5 -0.2 0.7 3.2 2.8 2.0 3.1 3.9 1.7 11.3 3.3 11.6 -0.5 0.1 -0.1 0.7 1.2 0.6 -0.7 1.3 7.6 4.7 5.5 8.7 6.0 8.2 3.0 7.2 20.0 8.6 5.0 5.3 48.8 53.8 66.0 29.6 9.9 24.7 20.0 23.5 32.6 7.6 35.5 6.0 10.1 7.9 8.1 7.0 7.5 3.8 11.3 9.8 6.0 3.9 14.3 4.9 9.4 5.8 21.6 -0.6 18.8 5.4 2.6 4.5 -1.1 -10.8 9.2 6.0 -3.8 11.6 -1.0 6.7 1.2 6.2 31.0 44.3 5.0 12.4 2.8 5.2 3.1 3.4 3.1 2.5 5.5 4.9 0.6 8.6 2.0 6.2 4.9 3.4 1 mo. 0.8 0.2 -0.1 1.0 1.2 -0.4 -0.1 -0.3 0 0.3 0.2 4.1 2.3 3.7 -0.1 1.7 0.3 0.4 0.4 0.1 -0.7 5.0 0.4 0.2 2007 3 mo. 1 yr. 2.5 1.7 -0.6 2.8 3.6 1.4 0.6 -1.3 -2.5 -1.1 3.5 4.7 3.5 6.1 -2.0 -7.2 2.7 0.9 0.5 3.1 -5.1 5.0 -0.8 1.4 5.3 4.3 2.6 5.8 5.1 5.6 2.4 -2.6 -4.0 -1.3 -10.2 4.6 13.1 12.5 3.0 25.5 7.7 5.3 2.7 5.6 -0.8 14.1 5.2 2.2 Construction Management Current Market Conditions Presentation Outline Material Cost Escalation Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments CPI-U is the Consumer Price Index for all Urban Consumers -Used to Help Predict Project Cost Changes Corinne Ambler Penn State AE Senior Thesis Construction Management Structural Impacts Presentation Outline Project Overview Construction Cost Escalation Addition of 156 Steel Plates Around 5th Floor Perimeter - A36 24”x 7”x 3/8” - Welded to Girder Beam at 5’ O.C. Existing Connection Redesigned Connection Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Eccentric Weld Tables AISC Steel Manual 13th Edition - Downward Force 2k per connection - Moment of 4’k - Plate Checked for Flexural Yield Corinne Ambler Penn State AE Senior Thesis Construction Management Structural Impacts Presentation Outline Project Overview Construction Cost Escalation Wind Load Self Weight Assumptions - Self Weight: 15 psf - Maximum Wind Load: 50 psf - Maximum Snow Load: 50 psf Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments Corinne Ambler Snow Load Penn State AE Senior Thesis Construction Management Cost Impacts Presentation Outline Project Overview Construction Cost Escalation Electrical Savings Current Btu 184,160,679 Acknowledgements Questions & Comments Change in Btu 47,414,011 Change in Btu Savings $141 x $0.0608/kwh COP of Chiller x 3412 kwh/Btu Solar Shading Analysis Bridge Illumination Analysis Re-design Btu 136,746,668 Demand Supply Charge Savings Current Lowest Hourly Btu 7191 Re-design Lowest Hourly 7048 Difference in Hourly Btu 143 Change in Tons 4.29 Demand Charge Saved $3,079 Hourly Change in Btu x 365 Days x COP of Chiller x $10/ton 12000 Btu/ton Tonnage Reduction Savings Amount Saved Number of Square (Tons) Feet per Ton 4.29 450 Cost ($/SF) $8.95 Total Initial Savings ($) $17,277.98 Tons Saved x 450 SF/ton x $8.95/SF Corinne Ambler Penn State AE Senior Thesis Construction Management Cost Impacts Presentation Outline Project Overview Structural Steel Plate Cost Weight of Steel (lb/ft3) 460 Volume of Steel per Plate (ft3) 0.036458333 15% for Labor (ft3) 0.00546875 Weight per Plate (lb) 19.28645833 Number of Plates 156 Cost ($/lb) $2.00 Cost ($) $6,017.38 Volume per Plate x 1.15 (Labor) x 460 lb/SF x Number of Plates x $2/lb Construction Cost Escalation Additional Cost per Foot Solar Shading Analysis Bridge Illumination Analysis Sunshade Length (ft) Area of Sunshade (SF) Cost ($) 4' 5' 6' 7' 8' 9' 10' 3,188 4,006 4,833 5,669 6,512 7,364 8,225 $0 $33,998 $68,370 $103,116 $138,152 $173,563 $209,348 Acknowledgements $41.56/SF (Includes Labor) x Area of Sunshade Questions & Comments Payback Period of Extension Sunshade Length (ft) 4' 5' 6' 7' 8' 9' 10' Cost ($) Initial Savings ($) Additional Length + Steel $6,017 $40,015 $74,387 $109,133 $144,170 $179,581 $215,366 Tonnage Reduction $17,278 $21,628 $25,977 $30,206 $34,556 $38,906 $43,255 Yearly Savings ($) Payback Period (Years) Demand + Electric $3,220 $4,026 $4,829 $5,606 $6,400 $7,192 $7,981 0 4 9 13 16 19 21 (Yearly Savings + Initial Savings – Initial Costs) Yearly Savings Corinne Ambler Penn State AE Senior Thesis Construction Management Mechanical Impacts Presentation Outline Impacts of Lowering the Sunshade on the 5th Floor North Change South Change East Change in Btu in Btu in Btu Month Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Acknowledgements Questions & Comments January February March April May June July August September October November December Yearly Change: 0 0 0 0 0 0 0 0 0 0 0 0 0 364,788 525,743 601,529 243,556 0 0 0 241,207 709,339 683,433 360,811 286,508 4,016,913 761,486 1,049,002 4,600,052 1,825,055 2,074,564 2,138,146 2,332,903 2,369,945 1,713,417 1,408,382 800,958 591,278 21,665,186 West Change in Btu Total Change in Btu 928,050 1,297,054 1,796,514 2,174,106 2,528,345 2,605,835 2,843,193 2,898,136 2,088,203 1,716,446 976,156 720,612 22,572,651 2,054,324 2,871,799 6,998,095 4,242,716 4,602,909 4,743,981 5,176,096 5,509,288 4,510,959 3,808,260 2,137,926 1,598,398 48,254,750 West Side Total Area of Glazing 1,685 ft2 North Side Total Area of Glazing 173 ft2 North Side Total Area of Glazing 632 ft2 East Side Total Area of Glazing 1,383 ft2 Corinne Ambler Penn State AE Senior Thesis Construction Management Conclusion & Recommendation Presentation Outline Light Loss Factors Project Overview Construction Cost Escalation Solar Shading Analysis Bridge Illumination Analysis Luminaire Maintenance LLD LDD RSDD Label Category FF-1 IV 0.7 0.85 FF-2 III 0.7 0.88 Assume : 24 month cleaning interval and a clean Total LLF 0.98 0.5831 0.98 0.60368 environment. BF Acknowledgements Questions & Comments Corinne Ambler Penn State AE Senior Thesis Construction Management