University Ridge at East Stroudsburg University Matthew Carr Spring 2007 Mechanical Option Faculty Advisor: Dr. Freihaut University Ridge at East Stroudsburg University Outline Project Team Building Information Existing Mechanical Conditions Redesign Goals Mechanical Redesign Redesign Analysis Photovoltaic Breadth Recommendations & Conclusions Acknowledgements Questions Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Project Team Building Name: University Ridge at East Stroudsburg Building Owner: University Properties Inc. Building Developer: Capstone Development Corp. Architect: Design Collective Inc. Engineers: Greenman-Pedersen Inc. Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Building Information Location: East Stroudsburg, PA on the East Stroudsburg University Campus Building Statistics: Student Residence – Apartments 541 Beds – 136 Units 3 stories plus an occupied walk in basement 140,000 square feet – 10 Buildings Development Cost: $27,200,000 Construction Cost: $15,750,000 Construction: August 2004 – August 2005 Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Building Information Building Site Plan: Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Existing Mechanical Conditions Heating System: Hot water coil duct furnaces – Dedicated unit for each housing unit Hot water supplied by a dedicated residential hot water heater Electric unit heaters for unoccupied spaces. Cooling System: Chilled water coil duct furnaces – Dedicated unit for each housing unit Chilled water supplied by a dedicated DX condensing unit General: Individual exhaust fans for bathrooms Naturally ventilated living spaces to decrease load Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Goals Combined Heat & Power Goals: Reduce emissions while increasing overall fuel usage for producing power Provide space heating using waste heat from power production Provide chilled water with absorption cooling which utilizes the waste heat from power production Reduce fossil fuel usage Determine feasibility of a payback period Decrease annual operating cost Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign What is Combined Heat and Power? Electricity is generated on site by a prime mover Waste heat is used for the heating and cooling processes CHP typically runs at a lower operating cost but has a higher first cost Load leveling increases operating efficiency Main Components of Combined Heat and Power? Prime Movers (gas turbines, reciprocating engines, etc.) Absorption Chillers Chilled Water Storage Tanks Cooling Towers Pumps and Distribution Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Spark Gap Feasibility Analysis? Determination of difference between natural gas and electricity cost: Natural Gas: $1.33/therm Electricity: $0.0919/kWh $26.94 - $13.30 = $13.64 A spark gap of $12.00 or greater is usually considered a viable solution. Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Determination of Prime Mover Building electric demand load of 366 kW Building heating load of 775 MBH Building cooling load of 177 tons Prime Movers Considered Reciprocating Engines Fuel Cells Natural Gas Turbines Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Natural Gas Micro-turbine & Absorption Chiller Selection Integrated micro-turbine and chiller/heater power system Comes as packaged unit integrated with controls Unit made up of 60 kW micro-turbines Heat exchanger contained within the absorption chiller Good under part load condition as micro-turbines can be selectively turned off or on as needed Fewer moving parts than internal combustion engines Typically reduced emissions over internal combustion engines Integrated inverter optimizes efficiency Integrated system allows for reduced installation cost. Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Integrated Micro-turbine Chiller/Heater System Specs: 4 – 60 kWe Micro-turbines Net Power Output (kWe) Fuel Consumptio n LHV (MBH) Cooling Output (Tons) Heating Output (MBH) Flow Rate (gpm) Net System Efficiency ISO Day (59F) 227 3,000 142 1,282 297 84% Design CoolingDay (95F) 193 2,800 124 - 297 76% Heating Day (32F) 231 2,800 - 1,100 297 68% Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Heat Recovery: Waste heat from turbines recovered in the absorption chiller High temperature generator and evaporator sections used as heat exchanger Production of 140°F water used for hot water heating in the fan coil units. Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Double-effect Absorption Chiller: Waste heat used to regenerate LiBr solution which acts as the condenser which is usually electrically powered Cooling tower needed for heat removal from the condenser Use of LiBr and water eliminates for ozone depleting refrigerants Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Existing Installation Example: Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Mechanical Redesign Chilled Water Storage: Chilled water storage used to level and shift the cooling load to increase efficiency Allows for chiller size reduction Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Analysis Energy Analysis: Energy analysis was done using RETscreen CHP energy analysis program Analysis run using UTC Pure Comfort system, the determined cost data and calculated loads The following table shows the operating capacity of the system Electricity delivered to load Electricity exported to grid Remaining electricity required Heat recovered Remaining heat required Power system fuel Operating profit (loss) Efficiency Operating strategy MWh MWh MWh million Btu million Btu million Btu $ % Full power capacity output 2,102 1 509 7,100 206 27,423 175,052 52.0% Power load following 2,102 0 509 7,095 211 27,413 174,987 52.0% Heating load following 1,030 1 1,581 5,955 1,350 13,442 59,762 70.5% Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Analysis Monthly System Characteristics: Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Analysis Existing Cost: Existing mechanical system cost determined to be $2.1 million dollars as built Estimated First Cost: Equipment Prime Mover Size Installed Cost 240 kW Quantity $2,500 Total 240 $600,000 Cooling Tower 205 (tons) $95.50 (per ton) 2 $39,155 Absorption Chiller 142 (tons) $1197 (per ton) 1 $170,000 - $17,000 - $17,000 Expansion tank 2 - 266 (gal) $3,325 2 $6,650 4" Service pad 2835 s.f. 35 (c.y.) $6,300 Storage Tank $180 (per c.y.) Chilled Water Pumps 1 1/2" 100gpm $3,875 8 $31,000 Cooling Water Pumps 3" 385 gpm $6,175 2 $12,350 - $264,332 Piping - - $1,146,787 Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Analysis System Payback: System payback was also calculated using RETscreen CHP energy analysis program Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Analysis System Payback: Cumulative cash flows graph Year Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Analysis Emissions Analysis: The following tables were generated using manufacturers data and the national grid average for emissions lbm Pollutant /kWh Prime Mover Fuel Particulates SO2/ kWh Nat. Gas. 2.37E-04 n/a lbm Pollutantj /kWh U.S. NOx/kWh CO/kWh 2.15E-04 8.60E-05 Fuel % Mix U.S. Particulates SO2/kWh NOx/kWh CO2/kWh Coal 55.7 6.13E-04 7.12E-03 4.13E-03 1.20E+00 Oil 2.8 3.03E-05 4.24E-04 7.78E-05 5.81E-02 Nat. Gas 9.3 0.00E+00 1.26E-06 2.36E-04 1.25E-01 Nuclear 22.8 0.00E+00 0.00E+00 0.00E+00 0.00E+00 Hydro/Wind 9.4 0.00E+00 0.00E+00 0.00E+00 0.00E+00 Totals 100.0 6.43E-04 7.54E-03 4.44E-03 1.38E+00 Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Redesign Analysis Emissions Analysis: RETscreen CHP energy analysis program was also determined the GHG emissions produced by the proposed system and compared to the base case Combined cooling, heating & power project Years of occurrenc e Base case GHG emission Proposed case GHG emission yr tCO2 tCO2 2,282 2,046 1 to 2 Net annual GHG emission reduction 236 tCO2 GHG credits transactio n fee Net annual GHG emission reduction tCO2 % tCO2 236 is equivalent to Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Gross annual GHG emission reduction 48.0 0% 236 Cars & light trucks not used Matthew Carr Spring 2007 Mechanical Option Photovoltaic Breadth Photovoltaic Basis: Photovoltaic shingles built into sloped roof Able to offset peak power loads during the day reducing the grid dependency of the CHP system Drawbacks: expensive, inefficient, minimal architectural effect Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Photovoltaic Breadth PV Capacity and Cost Analysis: The analysis of the PV cells was done using RETscreen PV PV Cost: $557,476 Energy Delivered: 49 MWh/yr Simple Payback: 12.4 yrs. Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Recommendations & Conclusions Conclusion: Increased total energy and fuel efficiency Lowered operating cost Higher initial cost Lower emissions and greenhouse gases Recommendations: Given the previously determined data and facts, it is recommended that this CHP tri-generation system be implemented as it has a payback timeframe for that of a university and would save money and energy use in the long run Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Acknowledgements Thanks to the Following: Architectural Engineering Faculty and Staff Faculty Advisor: Dr. Freihaut The AE Class of 2007 My Friends The GPI Mechanical Department My Family Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option Questions Penn State Architectural Engineering Thesis University Ridge at East Stroudsburg Matthew Carr Spring 2007 Mechanical Option