JW Marriott OUTLINE Greg Kochalski Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System Lateral System Architectural Redesign Cost Analysis Conclusions/Recommendations Introduction Project Information •24 story Marriott signature series Hotel •Located along the Grand River in downtown Grand Rapids, MI •340 Rooms •376,000 sq. ft. •Amenities include restaurant, lounge, business center, fitness center, and spa •Stylistic architecture with reflective glass cladding •Open Air Atrium •Heated Helipad JW Marriott Greg Kochalski Introduction Site Plan Downtown Grand Rapids JW Marriott Greg Kochalski JW Marriott Introduction Greg Kochalski Project Team owner- Alticor inc. Architect- Goettsch Partners and Beta Design Group Structural- Thornton Tomasetti Engineers Contractor- Pepper Construction and Rockford Construction MEP- Cosentini Associates JW Marriott OUTLINE Greg Kochalski Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System Lateral System Architectural Redesign Cost Analysis Conclusions/Recommendations Existing Structure JW Marriott Greg Kochalski Foundation •200 ton micro piles •Pile caps located along the perimeter and beneath the core •4-7 micro piles per group Existing Structure JW Marriott Greg Kochalski Floor System •Flat Plate R.C. •Short spans- 17 ft. •One way action •Typical bay approx 17x35 ft •7.5 in. Slab • f’c = 5700 psi •Blade-Columns located along perimeter •Transfer girders at levels 3-5 Eccentric loading requires heavy torsional reinforcing in beam Existing Structure JW Marriott Greg Kochalski Blade-Columns •Reduce spans •Limit slab thickness •Maximize patron views •Fit within interior partitions •Boundary confinement at edges Typical Floor with Radial Columns Confinement Typical bay Existing Structure JW Marriott Greg Kochalski Lateral System •Two pairs of shear walls •F’c varies from 10 ksi to 6ksi •Boundary elements for increased inertia in east-west •12 in. thick in both directions Heavy confinement in boundary elements JW Marriott OUTLINE Greg Kochalski Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System Lateral System Architectural Redesign Cost Analysis Conclusions/Recommendations JW Marriott Structural Redesign Greg Kochalski Proposal Summary Design Goals •Relocation to Monterey, CA •Achieve desired non-linear response •New lateral system •New Post tension floor system •Use updated building code Building Codes Grand Rapids Monterey •MBC 3003 (IBC 2003) •IBC 2006 •ACI318 2002 •ACI318 2002 •ASCE7 2002 •ASCE7 2005 •Avoid pitfalls of peer review •Limit vertical walls to <3.0% of floor area JW Marriott Post Tension System Greg Kochalski Characteristics •Typical span = 35 ft. •9.5 in. PT flat plate (l/45) •Class U system •Balance 85% dead load •½ in. 270 ksi strands •F’c = 4000 psi PT Floor Loads Labeling Scheme Design Loads (psf) ASCE 7 (psf) Dead 20 20 Live 40 40 Post Tension System JW Marriott Greg Kochalski JW Marriott Post Tension System Large banded tendons Greg Kochalski Small banded tendons JW Marriott Post Tension System Greg Kochalski Average Stresses F Mn A S Mn F 225 psi , 442 psi ,79 psi A S f 217 6 f 'c f 667 0.3 f 'c 79 2 f 'c 529 Slab Deflections Span Deflection (in) Deflection Equivalent AB 0.268 L/1150 CD 0.361 L/1150 *9.5 in. PT flat slab works* JW Marriott Lateral System Greg Kochalski Nonlinear Response •Force dissipation mechanism ensures integrity •Plastic hinging in beams, walls approach yielding •Detailed for proper ductility •Even deformations over height Peer Review •256 ft exceeds 240 ft height limit •Requires “code equivalent performance”… •Inherent uncertainties when interpreting code JW Marriott Lateral System Greg Kochalski Analysis Methods •Equivalent lateral force method •Manual calculations •Etabs •Modal response (dynamic) analysis •Etabs Spectral Response Parameters •Sds=0.97 •O.C.=II •Sd1=0.53 •R=5.0 •S.D.C.= D •Cd=4.5 •S.C. = C JW Marriott Lateral System Etabs Cases & Combinations •Static analysis (accidental torsion) •EXZ1- ecc in x, cw moment •EXZ2- ecc. In –x, ccw moment •EYZ1 •EYZ2 •Dynamic analysis (member forces) •XSPECF •YSPECF •Dynamic analysis (Displacements) •XSPECD •YSPECD Greg Kochalski Scale Factors JW Marriott Lateral System Greg Kochalski Pier and Spandrel Labeling JW Marriott Lateral System Greg Kochalski Coupling Beams Interpreting the output Influence… 3 •Period Period (s), V (normalized) 2.5 •Shear (in walls) •displacements Cracked section Ieffective Period 1.5 Vnormalized 1 0.5 0.2 Igross 2 1 3h / ln 2 Ultimate shear Vu 8.0 f ' c bd 0 0.00 0.20 0.40 0.60 0.80 Ie Ie 0.10 0.16 0.5 0.75 Varying Ieff Vmax Vnorm Period 189 232 317 340 2.76 2.425 1.99 1.90 0.814655 1 1.366379 1.465517 JW Marriott Lateral System Ultimate Shear Determined Group, and will be the Maximum of •0.8Vmax •Vaverage Detailing Reinforcing must ensure •Proper Ductility •Failure in moment, not shear Greg Kochalski Level Roof 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 Mezz 2 Coupling Beam Ultimate Shear Shears Design Group Shears Shear 0.8 Vmax Vaverage 0.8 Vmax Vaverage (K) (K) (K) (K) (K) 90 111 113 122 122 122 122 121 131 142 152 162 171 179 161 161 182 182 187 194 201 208 214 220 186 221 225 229 232 186 213 231 228 220 186 205 205 181 163 Lateral System JW Marriott Greg Kochalski JW Marriott Lateral System Greg Kochalski Displacement <2.0% Height (code) <1.0% Height (imposed) 0.01H = 30 in. Max Displacement 16.6 in. (x) 21.4 in. (y) y x X direction Y direction JW Marriott Lateral System Greg Kochalski Displacement Roof Max Displacement Story 23 Story 21 16.6 in. (x) Story 19 21.4 in. (y) Story 17 Level Story 15 delta y Story 13 delta x Interpreting output Story 11 •Beam action in Y Story 9 •Frame action in X Story 7 Story 5 Story 3 y 2nd 0.00 5.00 10.00 15.00 Inches 20.00 25.00 x JW Marriott Lateral System Greg Kochalski Shear Walls Design Criteria Direct Shear Flexure •Distributes by area •Distributes by inertia •Limit shear to: •Reinforce to resist tension Vu 4.0 f 'c t l JW Marriott Lateral System Greg Kochalski Direct Shear Vu 4.0 f 'c t l Pier 3 : 1100 k 3 . 59 Pier 4 & 5 : 343 k 2 . 24 f ' c Av , where Av 4 / 5 18 . 67 ft 2 Pier 6 : 876 k 4 . 11 f ' c Av , where Av 6 26 . 0 ft 2 Pier 7 & 8 : 350 k 3 . 78 f ' c Av , where Av 7 / 8 * 19 . 5 ft 2 f ' c Av , where Av 3 37 . 33 ft 2 * Av 7 / 8 9 . 77 ft 2 cos( 33 ) 12 . 2 ft 2 cos( 22 ) JW Marriott Lateral System Greg Kochalski Interpreting the Output Av shown in blue Theoretical Av (ft2) 26 Kv 0.7 DFv 0.21 37.3 1.0 0.29 Etabs Output (YSPECF) VOP 876 1100 DFOP 0.22 0.28 37.3 1.0 0.29 26 0.7 0.21 1100 0.28 876 0.22 JW Marriott Lateral System Greg Kochalski Flexure Reinforce Tension Areas where E v 0.2 S DS D , S DS 0.97 , and L 0 •PCA column ASCE7 then becomes : •Load cases derived from ASCE7 My ASCE7 : 0.9 D 0.5 L 1.0 E 1.0 E v Mx 1 0.7 D 1.0 E x 0.3E y 2 0.7 D 1.0 E x 0.3E y 3 0.7 D 1.0 E x 0.3E y 4 0.7 D 1.0 E x 0.3E y 5 0.7 D 0.3E x 1.0 E y 6 0.7 D 0.3E x 1.0 E y 7 0.7 D 0.3E x 1.0 E y 8 0.7 D 0.3E x 1.0 E y Where E x M x due to Earthquake in Y E y M y due to Earthquake in X D PSELF W T PGRAVITY Moment sign convention JW Marriott Lateral System Greg Kochalski Reinforcing Trends: •Heavy reinforcing in outer areas of flanges •Light reinforcing in webs Pier 3 4 5 6 7 outer 7 inner 8 outer 8 inner Pier Vertical Reinforcing Schedule Spacing As ρ, per Pier ρ, per section Rebar # Rows (in) (sq. in.) (%) (%) 9 1 16 18 0.26 0.94 9 2 6 38 1.41 9 2 6 38 1.41 9 1 11 15 0.40 3.5 9 3 30 1.13 1.16 9 2 6.5 24 1.70 9 3 30 1.13 3.5 9 2 6.5 24 1.70 Pier 3 4 5 6 7 8 Pier Horizontal Reinforcing Schedule Spacing ρ, per Pier Rebar # Rows As (in2/ft) (in) (%) 4 2 10 0.48 0.25 5 2 10 0.74 0.26 5 2 10 0.74 0.26 4 2 10 0.48 0.25 5 2 0.74 0.26 10 5 2 10 0.74 0.26 Lateral System Verifying the Results JW Marriott Greg Kochalski JW Marriott OUTLINE Greg Kochalski Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System Lateral System Architectural Redesign Cost Analysis Conclusions/Recommendations Architectural Redesign JW Marriott Greg Kochalski Affected Areas •Stairwells •Patron elevators •First floor service corridor and restrooms •Second floor fire corridor Notable IBC codes The atrium is a large focal point of the architecture 1019.1: “exit enclosure shall not be used for other than egress…” 1019.1.2: “no penetrations shall be allowed except those related to exit egress or systems directly related to the function of the exit way…” Typical Floor Ground floor JW Marriott OUTLINE Greg Kochalski Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System Lateral System Architectural Redesign Cost Analysis Conclusions/Recommendations Cost Analysis JW Marriott Greg Kochalski Primary Losses •PT system more skill intensive •Lower daily production •Thicker slab Secondary Losses •Duration increase •Interest earnings Post tension system require longer durations and more expensive labor JW Marriott Cost Analysis Greg Kochalski Direct Loss Comparison Flat Plate Location Grand Rapids Crew C-17B Daily Output (cy) 30.24 Labor Hours (cy) 6.878 Material ($) 242 Labor ($) 253 Equipment ($) 24 Total ($) 519 Post Tension (x2.0) Location Monterey Crew (2) C-17B Daily Output (cy) 20 Labor Hours (cy) 8.2 Material ($) 475 Labor ($) 630 Equipment ($) 31 Total ($) 1136 Post Tension (x3.0) Location Monterey Crew (3) C-17B Daily Output (cy) 30 Labor Hours (cy) 8.2 Material ($) 475 Labor ($) 945 Equipment ($) 31 Total ($) 1451 Concrete (cy) Material ($) Labor ($) Equipment ($) Total ($) Incl. O&P ($) Duration (weeks) Concrete (cy) Material ($) Labor ($) Equipment ($) Total ($) Incl. O&P ($) Duration (weeks) Concrete (cy) Material ($) Labor ($) Equipment ($) Total ($) Incl. O&P ($) Duration (weeks) 5707 1,381,094 1,443,871 136,968 2,961,933 3,909,752 38 7228 3,433,300 4,553,640 224,068 8,211,008 10,427,980 72 *Actual duration of 47 weeks due to weather Secondary Losses •$230/night average room price •60% occupancy expected •$8 million lost in 25 week delay 7228 3,433,300 6,830,460 224,068 10,487,828 13,319,542 48 JW Marriott OUTLINE Greg Kochalski Introduction Existing Structure Floor System Lateral System Structural Redesign Floor System Lateral System Architectural Redesign Cost Analysis Conclusions/Recommendations Conclusions and Recommendations JW Marriott Greg Kochalski Non-linear response •Plastic hinging mechanism in beams •Shear walls well below yield, system deforms evenly Floor System •Post Tension system viable alternative •Costs of PT are staggering, use original flat plate system Architecture •Atrium remains focal point •Original spaces accounted for JW Marriott Greg Kochalski Acknowledgements Bert Crandell Ben Kochalski Pete Jackson Jeff Styles Erika Johnson Dr. Boothby Dr. Lepage All AE Faculty Mom and Dad My Friends And Everyone Else that Made Thesis a Reality Questions?