Manoa Elementary School Amanda Cronauer Faculty Advisor: Dr. William Bahnfleth 14 April 2010 Presentation Overview Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Spring 2010 Project Background Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Project Information: Project Size: Location: Cost: Stories: Construction Dates: Delivery Method: 85,355 sf Havertown, PA $21.2 million Classroom [3], Administration [1] May 2007-November 2008 Design-Bid-Build Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Project Team: Owner: Architect: General Contractor: Structural Engineer: MEP Engineer: Haverford School District McKissick Associates Architects John S. McManus, Inc. Baker Ingram & Associates, Inc. H.F. Lenz Company Spring 2010 Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Building Layout Spring 2010 Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Building Layout Spring 2010 Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Building Layout Spring 2010 Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Building Layout Spring 2010 Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Building Layout Spring 2010 Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Building Layout Spring 2010 Project Background Existing Mechanical System Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Classroom Wing: [2] Rooftop Variable Air Volume Units Direct Expansion Cooling Hot Water Perimeter Heating Energy Recovery Ventilators [2] Air Cooled Condensing Units AHU-3 Final Recommendations Administration Wing: AHU-2 AHU-1 Third Floor Second Floor Amanda Cronauer │ Mechanical Option AHU-5 AHU-4 Air Source Heat Pumps System Comparison Spring 2010 First Floor Rooftop VAV Unit with Energy Recovery Ventilator [AHU-3] [2] Rooftop Constant Volume Units Direct Expansion Cooling Hot Water Heating [3] Air Cooled Condensing Units Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Design Objectives Improve System Performance Energy Consumption Emissions Total System Cost Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Comparison of Proposed System Performance Spring 2010 Project Background Existing Mechanical Summary Alternatives Spring 2010 Ground Source Heat Pumps: Air Source Heat Pumps: Air Source Heat Pumps [+] Decentralized System [+] Higher System Efficiencies [+] Lower Greenhouse Gas Emissions [-] Increased Construction Costs [-] Impact of Loop on Ecosystem [+] Decentralized System [+] Higher System Efficiencies [+] Lower Greenhouse Gas Emissions [+] No Extensive Excavation [-] Utilizes Electricity System Comparison Dedicated Outdoor Air: Final Recommendations [+] Reduce Load on Heat Pumps [+] Smaller Design Objectives Alternative Descriptions Ground Source Heat Pumps Amanda Cronauer │ Mechanical Option [-] Utilizes Electricity Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Vertical Loop Analysis Systems to be Replaced: Series Fan Powered Boxes Heat Pump Rooftop Air Handling Units Dedicated Outdoor Air Unit Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Vertical Loop Analysis Project Background Existing Mechanical Summary Design Objectives Assumptions: Zoning Alternative Descriptions Ground Source Heat Pumps Heat Pumps Air Source Heat Pumps DOAS Units System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Vertical Loop Analysis Spring 2010 Loop Sizing: Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Vertical Loop Analysis Project Background Existing Mechanical Summary Loop Sizing: Design Objectives Alternative Descriptions Ground Source Heat Pumps Spring 2010 Cooling Design Information Entering Water Temperature (°F) 75 Leaving Water Temperature (°F) 85 Cooling Load (MBH) 1,434 Total Borehole Length (feet) 23,959 Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Heating Design Information Entering Water Temperature (°F) 45 Leaving Water Temperature (°F) 35 Heating Load (MBH) 1,153 Total Borehole Length (feet) 25,052 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Vertical Loop Analysis Existing Mechanical Summary Spring 2010 Loop Sizing: Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Heating Design Information Entering Water Temperature (°F) 45 Leaving Water Temperature (°F) 35 Heating Load (MBH) 1,153 Total Borehole Length (feet) 25,052 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Vertical Loop Analysis Existing Mechanical Summary Design Objectives Goals: Meet Mechanical Load Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Spring 2010 Minimize Construction Cost Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Vertical Loop Analysis Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Assumptions: Piping 1” High Density Polyethylene [HDPE] $0.53 per linear foot 40 foot lengths $4.79 per weld $40.25 per day for welding machine Grout Constant Price of $5,937 regardless Miscellaneous Site Costs Specified by Number of Boreholes Borehole Driller Earth Auger Data Bore Length Rent Output (feet) ($/day) (feet/day) < 225 12190 1800 225 ≤ Lbore ≤ 325 14840 1200 > 325 12190 900 Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Vertical Loop Analysis Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Spring 2010 Results: $160,000 $150,000 $140,000 $130,000 Air Source Heat Pumps System Comparison Final Recommendations A $120,000 B C $110,000 $100,000 $90,000 Amanda Cronauer │ Mechanical Option $80,000 25 45 65 85 105 125 145 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Vertical Loop Analysis Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Spring 2010 Results: $160,000 $150,000 $140,000 $130,000 Air Source Heat Pumps System Comparison Final Recommendations A $120,000 B C $110,000 $100,000 $90,000 Amanda Cronauer │ Mechanical Option $80,000 25 45 65 85 105 125 145 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Vertical Loop Analysis Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Spring 2010 Results: [115] Boreholes [218] feet per borehole $86,889 Total Installed Cost Air Source Heat Pumps System Comparison Final Recommendations Drill C: Depths Less than 225 feet Calculated # Length Boreholes 25,052 Amanda Cronauer │ Mechanical Option 115 Length per bore Actual Length Days 218 25,070 14 Drilling Welding Grouting Pipe Cost Miscellaneous Rental Rental Cost Cost Number Cost Cost Weeks Days 3 $36,570 $13,287 627 2 $3,095 $5,937 $28,000 Total Cost $86,889 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Vertical Loop Analysis Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Design Objectives $120,000 Alternative Descriptions $100,000 Electricity $60,000 $40,000 Final Recommendations $91,792 System Comparison Gas $85,923 Air Source Heat Pumps $80,000 $87,273 Ground Source Heat Pumps $20,000 Amanda Cronauer │ Mechanical Option Spring 2010 $2,357 Existing Mechanical Summary $140,000 $26,970 Project Background $37,556 Vertical Loop Analysis $0 AHSRAE Baseline System 1 Designed 2 System Redesigned System 3 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Vertical Loop Analysis Project Background Existing Mechanical Summary 5000 4500 Final Recommendations 2500 Gas 3,319 1500 3,211 Electricity 2000 2,966 System Comparison 3000 MBH Air Source Heat Pumps 3500 61 Alternative Descriptions 1,320 4000 918 Design Objectives Ground Source Heat Pumps 1000 500 0 Amanda Cronauer │ Mechanical Option Spring 2010 ASHRAE Baseline As Designed Proposed Redesign Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Vertical Loop Analysis Project Background Existing Mechanical Summary System Energy Savings Comparison Savings Over Baseline Design Objectives % Alternative Descriptions 25% Reduction = Savings Over Designed $ % As Designed 9.56 11,936 Redesign 24.58 30,680 19.91 Spring 2010 7/19 LEED Points [EA Credit 1] $ 18,744 Ground Source Heat Pumps Air Source Heat Pumps Greenhouse Gas Emission Data System Comparison CO2 NOX (lbm/year) (lbm/year) ASHRAE Baseline 2.02E+04 3.05E+01 1.64E+03 1.56E+04 As Designed 1.59E+04 2.47E+01 1.15E+03 1.08E+04 Redesign 6.15E+03 1.10E+01 1.03E+02 Final Recommendations Amanda Cronauer │ Mechanical Option Total SOX Redesign Savings (lbm/year) (lbm/year) Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Vertical Loop Analysis Existing Mechanical Summary Simple Payback Period: Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Design: [5] Rooftop AHU’s =$280,000 [5] ACCU’s= $12,000 Utility= $112,893 Redesign: •[67] Heat Pumps= $420,050 •[5] DOAS Units= $82,042 •Vertical Loop= $86,889 •Utility=$94,129 Simple Payback Period: 10.76 years Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Vertical Loop Analysis Existing Mechanical Summary Simple Payback Period: Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Design: [5] Rooftop AHU’s =$280,000 [5] ACCU’s= $12,000 Utility= $112,893 Ductwork= $319,850 Redesign: •[67] Heat Pumps= $420,050 •[5] DOAS Units= $82,042 •Vertical Loop= $86,889 •Ductwork= $74,531 •Utility= $94,129 Final Recommendations Simple Payback Period: 1.2 years Amanda Cronauer │ Mechanical Option Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Horizontal Loop Analysis Systems to be Replaced: Series Fan Powered Boxes Heat Pump Rooftop Air Handling Units Dedicated Outdoor Air Unit Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Horizontal Loop Analysis Existing Mechanical Summary Design Objectives Assumptions: Zoning Alternative Descriptions Ground Source Heat Pumps Heat Pumps Air Source Heat Pumps DOAS Units System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Horizontal Loop Analysis Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Assumptions: Sizing Method Applicable Horizontal, 6-Pipe Coil Ground Temperature Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Horizontal Loop Analysis Existing Mechanical Summary Design Objectives Results: [150] foot per ton loop recommended Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option [17,925] feet of length required Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results $140,000 Design Objectives $120,000 Alternative Descriptions $100,000 $40,000 Final Recommendations $106,856 System Comparison $60,000 $85,923 Air Source Heat Pumps $80,000 $87,273 Ground Source Heat Pumps $20,000 Amanda Cronauer │ Mechanical Option Spring 2010 $2,908 Existing Mechanical Summary $26,970 Project Background $37,556 Horizontal Loop Analysis $0 1 AHSRAE Baseline 2 System Designed 3 Redesign System Gas Electricity Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Horizontal Loop Analysis Project Background 5000 Existing Mechanical Summary Ground Source Heat Pumps 3000 918 3500 2500 System Comparison 1500 Final Recommendations 1000 3,945 2000 3,211 Gas 2,966 MBH Alternative Descriptions 1,320 4000 80 4500 Design Objectives Air Source Heat Pumps 500 Amanda Cronauer │ Mechanical Option Spring 2010 0 ASHRAE Baseline As Designed Proposed Redesign Electricity Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Horizontal Loop Analysis Project Background Existing Mechanical Summary System Energy Savings Comparison Savings Over Baseline Design Objectives % Alternative Descriptions 12% Reduction = Savings Over Designed $ % As Designed 9.56 11,936 Redesign 12.07 15,065 2.85 Spring 2010 $ 1/19 LEED Point [EA Credit 1] 3,129 Ground Source Heat Pumps Air Source Heat Pumps Greenhouse Gas Emission Data System Comparison CO2 NOX (lbm/year) (lbm/year) ASHRAE Baseline 2.02E+04 3.05E+01 1.64E+03 1.43E+04 As Designed 1.59E+04 2.47E+01 1.15E+03 9.55E+03 Redesign 7.40E+03 1.31E+01 1.31E+02 Final Recommendations Amanda Cronauer │ Mechanical Option Total SOX Redesign Savings (lbm/year) (lbm/year) Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Horizontal Loop Analysis Existing Mechanical Summary Simple Payback Period: Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Design: [5] Rooftop AHU’s =$280,000 [5] ACCU’s= $12,000 Utility= $112,893 Ductwork= $319,850 Redesign: •[67] Heat Pumps= $420,050 •[5] DOAS Units= $82,042 •Horizontal Loop= $76,898 •Ductwork= $74,531 •Utility= $109,764 Final Recommendations Simple Payback Period: 0.95 years Amanda Cronauer │ Mechanical Option Spring 2010 Vertical Loop Analysis Systems to be Replaced Assumptions Loop Sizing Loop Optimization [Construction Management Breadth] Results Horizontal Loop Analysis Systems to be Replaced Assumptions Loop Sizing Results Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Air Source Heat Pumps Systems to be Replaced: Series Fan Powered Boxes Heat Pump Rooftop Air Handling Units Dedicated Outdoor Air Unit Spring 2010 Analysis Systems to be Replaced Assumptions Results Air Source Heat Pumps Project Background Existing Mechanical Summary Design Objectives Assumptions: Zoning Alternative Descriptions Ground Source Heat Pumps Heat Pumps Air Source Heat Pumps DOAS Units System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Spring 2010 Analysis Systems to be Replaced Assumptions Results $140,000 Design Objectives $120,000 Alternative Descriptions $100,000 $40,000 Final Recommendations Electricity $83,442 $60,000 System Comparison $20,000 Amanda Cronauer │ Mechanical Option Analysis Systems to be Replaced Assumptions Results Gas $85,923 Air Source Heat Pumps $80,000 $87,273 Ground Source Heat Pumps Spring 2010 $19,942 Existing Mechanical Summary $26,970 Project Background $37,556 Air Source Heat Pumps $0 1 AHSRAE Baseline System 2 System Designed 3 Redesign System Air Source Heat Pumps Project Background 5000 Existing Mechanical Summary Analysis Systems to be Replaced Assumptions Results 4500 706 Ground Source Heat Pumps 3000 918 3500 2500 1500 Final Recommendations 1000 2,440 System Comparison 500 0 Amanda Cronauer │ Mechanical Option Gas Electricity 2000 2,966 MBH Alternative Descriptions 1,320 4000 3,211 Design Objectives Air Source Heat Pumps Spring 2010 ASHRAE Baseline As Designed Proposed Redesign Air Source Heat Pumps Project Background Existing Mechanical Summary System Energy Savings Comparison Savings Over Baseline Design Objectives Alternative Descriptions % Savings Over Designed $ % As Designed 9.56 11,936 Redesign 17.18 21,445 9.20 $ Spring 2010 17% Reduction = 3/19 LEED Points [EA Credit 1] 9,509 Ground Source Heat Pumps Air Source Heat Pumps Greenhouse Gas Emission Data System Comparison CO2 NOX (lbm/year) (lbm/year) ASHRAE Baseline 2.02E+04 3.05E+01 1.64E+03 8.75E+03 As Designed 1.59E+04 2.47E+01 1.15E+03 4.00E+03 Redesign 1.22E+04 1.89E+01 8.82E+02 Final Recommendations Amanda Cronauer │ Mechanical Option Total SOX Redesign Savings (lbm/year) (lbm/year) Analysis Systems to be Replaced Assumptions Results Project Background Air Source Heat Pumps Existing Mechanical Summary Simple Payback Period: Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Design: [5] Rooftop AHU’s =$280,000 [5] ACCU’s= $12,000 Utility= $112,893 Ductwork= $319,850 Redesign: •[67] Heat Pumps= $211,403 •[5] DOAS Units= $83,042 •Ductwork= $74,531 •Utility= $103,384 Final Recommendations Simple Payback Period: 0.65 years Amanda Cronauer │ Mechanical Option Spring 2010 Analysis Systems to be Replaced Assumptions Results System Comparison $40,000 Final Recommendations $20,000 Gas $2,908 $0 Amanda Cronauer │ Mechanical Option Baseline As Designed Vertical Loop Horizontal Loop Spring 2010 $19,942 Air Source Heat Pumps $60,000 $83,442 $80,000 $106,856 Ground Source Heat Pumps $2,357 $100,000 $91,792 Alternative Descriptions $26,970 Design Objectives $120,000 $85,923 Existing Mechanical Summary $140,000 $87,273 Project Background $37,556 System Comparison Air Source Electricity System Comparison 80 61 918 1,320 1500 706 Gas 3,945 3,319 2000 3,211 2500 2,966 $2,908 $20,000 Electricity MBH 3000 Gas Electricity 1000 500 0 $0 Amanda Cronauer │ Mechanical Option 3500 2,440 Final Recommendations $19,942 $40,000 4000 $83,442 System Comparison $106,856 Air Source Heat Pumps $60,000 $2,357 Ground Source Heat Pumps $80,000 $91,792 $100,000 $26,970 Alternative Descriptions 4500 $85,923 Design Objectives $120,000 5000 $37,556 Existing Mechanical Summary $140,000 $87,273 Project Background Spring 2010 Baseline As Designed Vertical Loop Horizontal Loop Air Source ASHRAE Baseline As Designed Vertical Horizontal Air Source System Comparison Project Background Greenhouse Gas Emission Data Existing Mechanical Summary Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Total SOX Emissions (lbm/year) (lbm/year) CO2 NOX (lbm/year) (lbm/year) ASHRAE Baseline 2.02E+04 3.05E+01 1.64E+03 2.18E+04 As Designed 1.59E+04 2.47E+01 1.15E+03 1.71E+04 Vertical Loop 6.15E+03 1.10E+01 1.03E+02 6.26E+03 Horizontal Loop 7.40E+03 1.31E+01 1.31E+02 7.54E+03 Air Source 1.22E+04 1.89E+01 8.82E+02 1.31E+04 Design Objectives Alternative Descriptions Spring 2010 Simple Payback Period: •Vertical Loop GSHP = [1.2] years •Horizontal Loop GSHP = [0.95] years •Air Source Heat Pump= [0.65] years Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Air Source Heat Pumps System Comparison Final Recommendations Amanda Cronauer │ Mechanical Option Final Recommendations Emissions and Fuel Consumption: Vertical Ground Source Heat Pump Lowest First Cost: Air Source Heat Pump Fastest Potential Payback: Air Source Heat Pump LEED Points: Vertical Ground Source Heat Pump Spring 2010 Special Thanks To: •Paul Cronauer, H.F. Lenz Contact •Verne McKissick, McKissick Architects Contact •Dr. Bahnfleth, Faculty Advisor •Penn State Architectural Engineering Mechanical Faculty •Family and Friends for all their support •Fellow AE Students •Jonah, moral support Amanda Cronauer │ Mechanical Option Questions Spring 2010