New Regional Medical Center East Norriton, PA Advisor: Dr. Robert Leicht

advertisement
New Regional Medical Center
East Norriton, PA
Brian J. Nahas [Construction Management Option]
Advisor: Dr. Robert Leicht
New Regional Medical Center
East Norriton, PA
implement virtual design and
construction processes to identify
options & trends in design,
construction, and facility
management
Brian J. Nahas [Construction Management Option]
Advisor: Dr. Robert Leicht
New Regional Medical Center
East Norriton, PA
Project Background
Design
Preconstruction
Construction
Turnover
• Atrium Curtain Wall
• Pour Strip System
• 3D Quantity Takeoff
& Estimating
• Steel Trending
• Crane Logistics
• Industry Research
• FM Dashboard
• FM Interact
Recommendations
New Regional Medical Center
Project Background
Owner’s Goals
• service to the community
• hosting excellence in clinical care
• fulfill the void in healthcare in Montgomery County
East Norriton, PA
Location
Project Team Members
Presentation Outline
• East Norriton, PA
• 84-acre former golf course
• access to major highways and state roads
• Norristown Farm Park
• Goal to preserve 1/3 of the campus as green space
“From its soaring atrium to its advanced imaging services, the center's
architectural elegance is matched by top tier patient care capabilities.”
Barry Freedman, President & CEO
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
Hospital
Campus
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
Center City
Philadelphia
Brian J. Nahas [Construction Management Option]
IV. Acknowledgements
New Regional Medical Center
Project Background
Building Program
• 146 beds
• medical/surgical
• intensive care
• neo-natal
• emergency care
• trauma center (pending)
• LEED certification (pending)
East Norriton, PA
Architecture
Systems & Engineering
• cast-in-place spread footings & foundation walls
• structural steel system [30’ x 30’ grid]
• W12 & W14 columns| 1st & 3rd floor splices
• composite decking
• composite curtain wall façade
•
•
•
•
•
precast panels
glazing units
curtain wall glazing
metal panel
Split-faced masonry block
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Brian J. Nahas [Construction Management Option]
Project Background
New Regional Medical Center
East Norriton, PA
Construction Program & Logistics
$147 million | CM at Risk contract
Construction Schedule: July 6, 2010 – August 31, 2012
Staff Training: August 8 – October 15, 2012
Opening Day: September 29, 2012
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Brian J. Nahas [Construction Management Option]
Design
New Regional Medical Center
East Norriton, PA
Architectural Breadth Analysis
Presentation Outline
• improve curtain wall constructability
• addition of public space
• modularization of glazing panels
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
System
Floor System
Structural Steel
Cost
$8,450
$24,338
GWB
$3,280
Finishes
Redesign Total
$87,387
$123,455
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Brian J. Nahas [Construction Management Option]
Design
Structural Breadth Analysis
Pour Strip Assembly*
Foundation System
$59,512
Structural Columns
$61,217
Structural Beams
$101,826
Slab on Grade
$684
Slab on Metal Deck
$9,230
Reinforcing
$7,303
Total:
$239,772
Existing System:
• 2 pour stops per floor
• 125 foot offset from east &
west end wall
• requires building enclosure &
temperature regulation
New Regional Medical Center
East Norriton, PA
IT IS UNDERSTOOD THAT THIS DESIGN DECISION
MAY CREATE CONSTRUCTION ISSUES, AND
AREAS FOR DELAY. ALTHOUGH THIS DECISION
DOES NOT SIMPLIFY THE AEC’S PROJECT
APPROACH, IT EASES THE MAINTENANCE AND
LIFECYCLE CONTROL OF THE SPACE… FOCUS
ON COST SAVINGS.
RICHARD MONTALBANO, PROJECT MANAGER, EINSTEIN
HEALTHCARE NETWORK
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
*quantities derived through Revit design alternates
III. Recommendations
IV. Acknowledgements
Brian J. Nahas [Construction Management Option]
New Regional Medical Center
Design
East Norriton, PA
Structural Breadth Analysis
Method:
• calculate design tolerance & joint gap
• size structural steel members
• tributary area
• load calculation
• locate splices
• design member per AISC Table 4-1
• size spread footings per column case
• model redesign
• export quantities for estimate
Expansion Joint Assembly
Outcome:
• 2 expansion joints per floor
• 2” structural gap
• use W12 x 50 & W12 x 40
• 13’ x 13’ x 30”
#7 bars each way 6” oc
• 13.5’ x 13.5’ x 30”
#7 bars each way 6” oc
Diff.
Foundation System
$32,758
-45%
Structural Columns
$60,671
-1%
Structural Beams
$101,826
-
Slab on Grade
$684
-
Slab on Metal Deck
$8,552
+7%
Reinforcing
$8,613
+18%
Expansion Joint Covers
$40,289
+100%
Misc. Steel Angle
$44,177
+100%
Total:
$297,570
+24%
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Brian J. Nahas [Construction Management Option]
New Regional Medical Center
Preconstruction
3D Quantity Takeoff
Method:
• create schedule of materials
• export to excel
• reference cost database
• include non-modeled elements
• produce estimate
East Norriton, PA
Model Estimating
Time Savings
Estimate Accuracy
Presentation Outline
99.5%
98.5%
89.0%
76.0%
89.3%
80.0%
80.0%
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
Outcome:
CIP Concrete: +10.7% from as-built costs
Structural Steel: +0.5% from as-built costs
7.5% improvement on Gilbane’s method
I.
IV. Turnover
I. FM Documentation
II. FM Interact
20.0%
III. Recommendations
IV. Acknowledgements
[2009] Interior
Partition
[2010] Curtain Wall
[2012] CIP
Concrete
[2012] Structural
Steel
Brian J. Nahas [Construction Management Option]
Construction
New Regional Medical Center
East Norriton, PA
Steel Trending
Presentation Outline
AT EACH EXCHANGE POINT A THOROUGH UNDERSTANDING IS
NEEDED OF WHO IS INVOLVED, WHAT SOFTWARE IS INVOLVED,
AND WHAT DATA NEEDS TO BE EXCHANGED (OR CAN BE
EXCHANGED) AND WHAT THE DATA WILL BE USED FOR.”
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
LUKE FAULKNER, AISC DIRECTOR OF INFORMATION TECHNOLOGY INITIATIVES
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Brian J. Nahas [Construction Management Option]
New Regional Medical Center
Construction
East Norriton, PA
Critical Pick Workflow Trending By Elevation
Steel Trending
Column Splice [Lift 1]
• Revit data to Excel Pivot Table & Chart
Column Splice [Lift 2]
Tonnage of Critical Steel Member
17.5
17.5
Column Splice [Lift 3]
Presentation Outline
11.4
10.9
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
8.3
7.3
III. Construction
I. Steel Trending
II. Crane Logistics
5.4
04'0'
14'-8"
31'- 36'-8"
4"
44'-0"
3.6
51'-1"
3.1
3.8 3.5
58'-8"
70'-10"
Brian J. Nahas [Construction Management Option]
Sector B
Sector A
Sector A
Sector A
Sector B
0.2
Sector A
Sector B
Sector A
0.5
Sector B
Sector A
Sector B
Sector A
Sector B
Sector A
Sector A
Sector D
Sector C
Sector B
29'-4"
2.9
0.5
0.5
Sector A
Sector D
Sector C
Sector B
Sector A
Sector D
Sector D
Sector C
00'-0"
3.5
Sector A
1.3
1.1 1.1
2.9
2.3 2.3
0.1
Sector B
Sector A
3.5
Sector B
2.2 2.5
1.7
0.4
3.0
Preconstruction
I. 3D QTO & Estimating
73'-4" 77'- 90'- 91'-2"
0" 0
3/8"
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
New Regional Medical Center
Construction
East Norriton, PA
Critical Pick Workflow Trending By Sector
Steel Trending
Presentation Outline
• Revit data to Excel Pivot Table & Chart
Tonnage of Critical Steel Member
17.5
17.5
11.4
10.9
7.3
2.5 2.3
0.2 0.1
Sector B
Brian J. Nahas [Construction Management Option]
2.3
1.1 1.1 1.3
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
Preconstruction
I. 3D QTO & Estimating
IV. Turnover
I. FM Documentation
II. FM Interact
Sector C
Sector D
29'-4"
14'-8"
04'-0'
29'-4"
14'-8"
III. Recommendations
00'-0"
0.5
58'-8"
44'-0"
36'-8"
29'-4"
14'-8"
00'-0"
91'-2"
90'-0 3/8"
77'-0"
73'-4"
70'-10"
58'-8"
51'-1"
36'-8"
31'-4"
44'-0"
Sector A
51'-1"
0.5
0.5
0.4
3.1
2.9
00'-0"
2.2
2.9
91'-2"
1.7
3.0
73'-4"
3.8 3.5
3.6
3.5
70'-10"
3.5
29'-4"
II.
III. Construction
I. Steel Trending
II. Crane Logistics
5.4
14'-8"
Project Background
II.
8.3
00'-0"
I.
IV. Acknowledgements
Construction
New Regional Medical Center
East Norriton, PA
Crane Logistics
300 Ton Lattice Crane
Mobilization & Demobilization Costs: $9,000 x 2 = $18,000
Rental Costs: $20,000 x 18 weeks = $360,000
TOTAL: $378,000
Presentation Outline
110 Ton
Mobile Crane
300 Ton Lattice Crane & 110 Ton Mobile Crane
Mobilization & Demobilization Costs: $9,000 x 2 + $3,400 x 2 = $24,800
Rental Costs: $20,000 x 15 weeks + $5,840 x 3 weeks = $317,520
TOTAL: $342,320
Results:
2 week schedule reduction: $280,047 [general conditions]
Crane rental: $35,680
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
300 Ton
Lattice Crane
Total Project Savings: $315,727
Brian J. Nahas [Construction Management Option]
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
New Regional Medical Center
Turnover
Industry Research
Specialty/Subcontractor
Academic Research
Hardware Developer/Vendor
Software Developer/Vendor
Technology Consultant
Current Information Technology Use
9.8
01 | BIM
2.6
2
02 | iPads
04 | Online Project
Documents
6
05 | 3D CAD
03 | Collaboration
Environment
06 | Mobile Tools &
Devices
5.2
General Contractor/CM Firm
Engineer/Architect
East Norriton, PA
Desired Information Technology
32.2
8.6
Engineer
25.3
Contractor/Engineer
22.1
Architect/Engineer
10.9
Architect
10.6
01 | Cheaper, Better
Software
04 | Mobile Hardware
02 | Data Integrations
(BIM)
05 | Cloud Storage &
Tools
03 | Online
Collaboration
06 | Linked & Live
Project Controls
Respondent Type (%)
Owner Interview
Current Use
• Paper Plan Room
• Outdated As-Built information
• Desired Use
• Room Data Log
• As-Built Drawings
• Submittal Log
“THE WORDS THAT CAME UP MOST OFTEN
WERE ‘CHEAPER,’ ‘SIMPLER,’ STREAMLINED,’
‘USER-FRIENDLY,’ ‘INTEROPERABLE,’ AND
‘INTEGRATED’.”
TOM SAWYER, ENGINEERING NEWS-RECORD
Brian J. Nahas [Construction Management Option]
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Turnover
FM Dashboard
Room Log
• Direct access to equipment files
• Construction & As-built Photographs
As-Built Drawings
• PDF Digital Set
• Hyperlinked details
New Regional Medical Center
East Norriton, PA
“A FM DOCUMENT INTERFACE SHOULD
NOT CONSIST OF A SERIES OF INTERNET
PAGES BUILT AROUND A SPECIFIC
ATTRIBUTE; IT SHOULD CONSIST OF AN
INTERFACE WHICH READS A DATABASE OF
RELATIVE INFORMATION, DATA, AND
ASSET.”
DR. CRAIG DUBLER, OFFICE OF THE PHYSICAL PLANT [PSU]
Submittal / O&M
• Material Submittal Information
• Equipment & Room Locations
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Brian J. Nahas [Construction Management Option]
New Regional Medical Center
Turnover
East Norriton, PA
Filter Parameter
System
FM Interact
• Microsoft Silverlight – Pivot Viewer
Zoom Format
Link to Original File
Document Name
Campus
Facility Name
Building Sector
Floor Level
Room Number
Date Added to
Database
Model/Drawing
CSI Discipline
Bid Package #
Trade Contractor
Trade Contact
Design Team
Design Contact
Construction Manager
Construction Contact
Asset Management
Brian J. Nahas [Construction Management Option]
Document Data & Relationships
Construction Photos, Submittals, RFI’s,
Contract Drawings, Design Model, AsBuilt Model, Equip. Data Sheet
JPG, TIFF
JPG, PDF, RVT, DWG, NWD, DOC, XLS,
SKP, Hyperlink, Other
Individual Description
East Norriton
New Regional Medical Center
A, B, C, D, Central Utility, Site
Ground Level, 1, 2, 3, 4, Roof
####
YYYY-MM-DD
Yes, No
## - Title
BP ##
Company Name
Contact – linked to email address
Company Name
Contact – linked to email address
Company Name
Contact – linked to email address
Hyperlink to external software/file
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Recommendations
Design
New Regional Medical Center
East Norriton, PA
Construction
Atrium & Pour Strip Redesign
Steel Trending
Benefit to NRMC: NO
Benefit to the Industry: YES
Development: Externally
Benefit to NRMC: YES
Benefit to the Industry: YES
Development: Internally
Preconstruction
Turnover
3D Quantity Takeoff & Estimate
Document Management
Benefit to NRMC: YES
Benefit to the Industry: YES
Development: Internally
Benefit to NRMC: YES
Benefit to the Industry: YES
Development: Internally & Externally
Brian J. Nahas [Construction Management Option]
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
III. Recommendations
IV. Acknowledgements
Acknowledgements
New Regional Medical Center
East Norriton, PA
Industry Acknowledgements
Lessons Learned
Special Thanks
VDC implementation goes beyond the
utilization of models and design software.
Richard Montalbano & the Facility Management Staff at Albert
Einstein Healthcare Network
Additional insight into design data
produces a stronger understanding of
construction and FM usage.
Andrew Packer & Jerry Shaheen at Gilbane Building Company
Gene Hodge, Jason Brown, Nicholas Kantor, & Michal Wojtak at
Mortenson Construction
Presentation Outline
I.
Project Background
II.
VDC Implementation
I. Design
I. Atrium Curtain Wall
II. Pour Strip System
II.
Preconstruction
I. 3D QTO & Estimating
III. Construction
I. Steel Trending
II. Crane Logistics
IV. Turnover
I. FM Documentation
II. FM Interact
Dr. Craig Dubler & the Facility Management Staff at Penn
State’s Office of Physical Plant
III. Recommendations
PACE Industry Members
IV. Acknowledgements
My Family & Friends
Brian J. Nahas [Construction Management Option]
New Regional Medical Center
East Norriton, PA
implement virtual design and
construction processes to identify
options & trends in design,
construction, and facility
management
Brian J. Nahas [Construction Management Option]
Advisor: Dr. Robert Leicht
Related documents
Download