Odd Fellows Road Interchange and Roadway Improvements Pardon Our Dust Meeting

advertisement
Odd Fellows Road Interchange
and Roadway Improvements
Pardon Our Dust Meeting
January 12, 2016
Objectives
 Project Overview
 Status
 Schedule
 Maintenance of Traffic
 Contract Information
Project Overview
Odd Fellows
Segment A
US 460
Top Ridge Roundabout
Design Features: New interchange with US 29/460 and Odd Fellows Road Extension
New roundabout at Top Ridge Road
Project Overview
Segment B1
Design Features: Roadway improvements along Odd Fellows Road
New roundabout at Mayflower Drive
Project Status
1. Final plans for Segment A have been submitted to
VDOT for final approval
2. Right of way acquisition is underway for Segment A
3. Right of way plans are being finalized for Segment
B1; right of way acquisition will follow
4. Environmental permits are being obtained from state
and federal agencies
5. Utility relocation plans are being finalized
6. Wagman has set up construction trailers on site
Project Schedule
Project Awarded: January 15, 2015
Notice to Proceed: February 18, 2015 (Design Start Date)
Construction Start: January 2016
Early Completion Date: December 21, 2017
Contract Completion Date: August 3, 2018
Construction Timeline
Maintenance of Traffic
for Route 29/460
Key Points
•
Speed limit reduced to 45 mph when work is adjacent to mainline
•
Vehicles entering and exiting Route 460, caution urged
•
Temporary lane restrictions used when necessary (predominately
in 2017)
Maintenance of Traffic
for Odd Fellows Road
Key Points
• Phase 1 – Construct east
side of Odd Fellows Rd
• Phase 2 – Construct west
side of Odd Fellows Rd
• Maintain access to all
parcels at all times
• One-lane, one-way traffic
(southbound) between
Mayflower Dr and Bradley
Dr (24 hours a day)
• One-lane with flaggers
south of Bradley in offpeak hours; two-lanes
during peak hours
• Speed limit reduced to 25
mph
Detour for Mayflower Drive
Roundabout Construction
Key Points
• Odd Fellows Road/Mayflower Dr intersection closed for 90 days
– Summer of 2017
Contract Information
Contractor: Wagman Heavy Civil
Designer:
David Lyle
Design-Build Project Manager
Paul Phillips
Design-Build Construction Manager
Johnson, Mirmiran & Thompson, Inc.
Rodney Hayzlett, P.E
VDOT Project Manager:
Raina Rosado, P.E.
Contract Price: $29,846,350
Design Manager
Please Join Us at the Displays
For More Information
Download