Parametric Performance Monitoring and Control (PPMC) Presented by: Karen McRitchie Galorath Incorporated 100 North Sepulveda Boulevard Suite 1801 El Segundo, California 90245 KMcRitchie@galorath.com Galorath Incorporated 2004 1 SEER: Project Management Context Estimate & Plan Measure & Analyze Galorath Incorporated 2004 Monitor & Control 2 s Ba ne eli Measure & Analyze Estimate & Plan ate -d als To ctu A Project Planning • Establish Estimates • Develop a Project Plan • Obtain Commitment to the Plan Project Monitoring and Control • Monitor Project Against Plan • Manage Corrective Action to Closure Measurement and Analysis • Align Measurement and Analysis Activities • Provide Measurement Results Kno Expwled erie ge & nce SEER: Process Focus (CMMI) Monitor & Control s) & BaselinAec(tu als Final Galorath Incorporated 2004 3 s Ba ne eli Galorath Incorporated 2004 Measure & Analyze Estimate & Plan ate -d als To ctu A Project Planning • History-Based Sizing • Direct Measure Sizing • Parametric Estimation • 4-D Planning Project Monitoring and Control • 4-D Earned Value Management • Status Indication • Performance-based Forecasting Measurement and Analysis • Estimation Accuracy Assessment and Improvement • Calibration • Knowledge Base Management • Benchmarking Kno Expwled erie ge & nce SEER: Methods Monitor & Control s) & BaselinAec(tu als Final 4 SEER: Tools SEER-SEM Calibration Mode currently in development Galorath Incorporated 2004 ne eli Measure & Analyze Estimate & Plan s Ba Kno Expwled erie ge & nce SEER-SEM te -da als To ctu A Project Planning • SEER-AccuScope • SEER-SEM • Project Miner (SEER-SEM option) • SEER-H • SEER-IC • SEER-DFM • SEER-SEM Client for Microsoft Project Project Monitoring and Control • Parametric Performance Monitoring and Control (SEER-SEM option) Measurement and Analysis • SEER-CommonRepository • SEER-ScatterPlot+ Monitor & Control s) & BaselinAec(tu als Final PPMC 5 What is PPMC? Monitor & Control Parametric Performance Monitoring and Control A set of add-on features to SEER-SEM that enable project monitoring and control of software development projects Features include: • Inputs for actual effort and project progress as well as project metrics • Algorithms to combine parametric and earned value • Reporting to provide information on project status PPMC employs 4D Earned Value Management • Activity Completion • Expenditures • Artifact Completion • Defect Discovery/Removal Galorath Incorporated 2004 6 Why PPMC? Earned Value Management is considered a best practice for monitoring and controlling the progress of a software project EVM has limitations: • A single focus on activity completion as the basis for earning value • Difficulty in providing realistic performance based estimate at completion (EAC) PPMC adds monitoring and control capabilities to SEER-SEM PPMC combines: • Accepted algorithms currently used for cost and schedule estimation during the project planning process • Accepted equations currently used for traditional Earned Value Management Parametric Performance Monitoring and Control Galorath Incorporated 2004 7 The common question Once a project has started, it is only natural to want to enter your project metrics The most common question: • Can I put in my actual effort once the project is underway and will the tool recalibrate my estimate? The right answer is NO - it’s not enough just to give actual hours • Just because you spent 50% of a planned budget doesn’t mean your are 50% done What the project manager needs to know: • How much more money, how long? • How can the project be adjusted to meet objectives? To do this, you need assess the project status in terms of progress, not just expenditures – Earned Value Earned value compares work complete to original estimates. Galorath Incorporated 2004 8 3500 3500 3000 3000 2500 2500 Hours Hours Combining Earned Value and Parametrics 2000 1500 2000 1500 1000 1000 500 500 0 0 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627 Month Month Plan Plan Actual Expenditure Earned Effort Actual Expenditure 3500 3000 Hours 2500 2000 1500 1000 500 0 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627 Month Plan Galorath Incorporated 2004 Actual Expenditure Remaining Effort 9 Traditional EVM – Measures and Metrics Fundamental Measures • Budgeted Cost of Work Scheduled (BCWS) • Budgeted Cost of Work Performed (BCWP) • Actual Cost of Work Performed (ACWP) Variances • Schedule Variance (SV) • Cost Variance (CV) • Time Variance (TV) Performance Indices • Schedule Performance Index (SPI) • Cost Performance Index (CPI) • To-Complete Performance Index (TCPI) Galorath Incorporated 2004 10 Earned Value and PPMC Terminology Galorath Incorporated 2004 Earned Value Terminology What it means BCWS - Budgeted Cost of Work Scheduled The planned costs (baseline plan) SEER-SEM calls this the Baseline Plan ACWP – Actual Cost of Work Performed What you paid SEER-SEM calls this Actual Effort or Actual Cost BCWP – Budgeted Cost of Work Performed The earned value SEER-SEM calls this Schedule Accomplishments EAC – Estimate At Complete The latest estimated cost at completion ETC – Estimate to Complete Funds needed to complete the investment SPI – Schedule Performance Index The percent of the investment that has been completed CPI – Cost Performance Index The ratio of earned to actual cost of work performed TCPI - To Complete Performance Index The latest cost efficiency assumed to complete CV - Cost Variance The difference between earned and actual cost of work performed SV – Cost Variance The difference between actual and planned work TV – Time Variance The variance between the actual and planned schedules 11 The PPMC Approach PPMC extends the use of SEER-SEM to projects underway Galorath Incorporated 2004 12 Tracking a Project Once a project is started, the PPMC process may begin Start with a SEER-SEM estimate Establish a baseline estimate Take project “snapshots” periodically Evaluate earned value metrics Replan as required Galorath Incorporated 2004 13 The Baseline A baseline freezes the current estimate The baseline provides the yardstick against which the project is tracked and evaluated Allows you to do trades with the current estimate while maintaining the planning baseline A baseline can be updated at any time The current estimate may be set back to the baseline at any time Galorath Incorporated 2004 14 The Snapshot Snapshots are a picture of the project’s metrics at any give point in time The snapshot includes two key components: • Work Complete • Actual Effort Work Complete describes the progress in terms of milestone completion Actual Effort includes hours as well as size and defect metrics Snapshots are flexible in terms of interval or frequency • Regular snapshots – e.g. monthly or quarterly • As needed – e.g. before a key review Galorath Incorporated 2004 15 Snapshots Snapshots are entered in matched sets in a dedicated input view Galorath Incorporated 2004 16 Reporting PPMC reports and charts are based on the most recent snapshot entered Work complete metrics are used to evaluate remaining effort and schedule (Estimate To Complete) Estimate At Complete = Actual Effort + ETC Galorath Incorporated 2004 17 PPMC Reporting Options Galorath Incorporated 2004 18 Looking at Progress Over Time See how actual and earned effort measure up to the baseline plan Click on any month to see specific information Galorath Incorporated 2004 See CPI and SPI trends over time CPI = Cost Performance Index; SPI = Schedule Performance Index; The ratio of earned to actual cost of work performed The percent of the investment that has been completed 19 Other Metrics Track defect discovery and removal rates against expected rates Heath and Status Indicator shows status and trends from the previous snapshot Thresholds are user definable Increased defect reporting rate shows a worsening trend Galorath Incorporated 2004 20 s Ba ne eli Measure & Analyze Estimate & Plan ate -d als To ctu A Parametric Performance Monitoring and Control enables powerful evaluation of a project’s progress Utilizes EVM best practices Capitalizes on parametric model’s ability to replan and forecast based on current project assumptions Flexible – doesn’t require regular care and feeding, you can use it only when you need to Completes the project management continuum Kno Expwled erie ge & nce Summary Monitor & Control )& BaselinAec(tsuals Final Galorath Incorporated 2004 21 Thank you! For more information: info@galorath.com www.galorath.com Galorath Incorporated 2004 22