Ameren Transmission Rate Stakeholder Presentation Questions at 10/17/2012 Meeting 1. ICC Who will make the 205 filing? Ameren recalls this question in regards to the 205 filing to change the cost allocation methodology for Baseline Reliability Projects. MISO and the MISO Transmission Owners made this filing on October 25, 2012 (Docket No. ER13-186). 2. PPI Concerning the FERC filing, is it going to change the way projects can be bid on? ER13-186 did not address bidding on transmission projects. However, the MISO/MISO Transmission Owners compliance filing for Order 1000 filed on the same day addressed competitive bidding on future transmission projects (Docket No. ER13187) 3. PPI Are the existing facilities in GG? AIC has three completed projects that are include in its Attachment GG revenue requirement. MISO MTEP projects 728, 870 and 2829. Please note that the posted calculation also shows project 2065. After the information was posted, MISO informed Ameren that this was inappropriately labeled as a cost-shared project on their website. The final rates for 2013 will reflect this change. 4. PPI Any specific projects in Schedule 9 or is it the legacy system? Does MISO have a say? Any new projects that would alter the basic characteristics of the transmission system would be submitted to MISO for review in MTEP. This would include the construction of new lines, upgrading facilities or new interconnections. New projects would be reviewed in the subregional planning meetings. MISO would not need to review replacement-in-kind projects or other repairs that maintain the existing system. 5. PPI What is in GG versus the Attachment O? Technically, all projects are in the Attachment O calculation. However, certain projects eligible for cost sharing under Attachment GG and MM are removed before determining the zonal Schedule 9 rate. As noted above, only three AIC projects eligible for cost-sharing have been completed. All other facilities are included in the Net Attachment O revenue requirement (Schedule 9). 6. PPI What is the Big Muddy Project status? Ameren has received FERC approval for rate incentives for the Big Muddy project, contingent on the project being approved in MTEP. The Big Muddy project is listed as three separate projects in MISO MTEP11 report. Baldwin-Grand Tower-NW Cape (#3010) is in Appendix B. The other two projects Grand Tower-EW Frankfurt (#3015) and Grand Tower-Joppa (#3039) are in Appendix C. 7. ICC Why is there less Attachment MM in table of presentation? Ameren may not have captured this question correctly, but believes the question may be asking why Attachment MM revenue requirement is deducted from Attachment O on page 3, line 30a. Attachment O calculates the total transmission revenue requirement for all transmission facilities. Attachment GG and MM allocate a portion of the total revenue requirement to specific projects that are eligible for cost sharing. Therefore, the Attachment GG and MM revenue requirements to be recovered under Schedules 26 and 26-A must be removed from Attachment O before determining the Schedule 9 rate. 8. ICC How is point to point revenue distributed? The Transmission Owners Agreement addresses revenue distribution. Revenue from point to point transactions that go through or out of MISO are distributed to TOs as follows: 50% based on gross book plant of each Transmission Owner and 50% based on load flows from the transaction. Therefore, the revenue distribution must be calculated for each reservation. 9. ICC Question was raised about clarifying dates of June 12 and January 13. On slides 23-26, there are two columns labeled Jun-12 and Jan-13. These columns compare the revenue requirement components for AIC revenue requirement calculation currently in effect as of June 2012 based on historical 2011 FERC Form 1 data; versus the projected 2013 revenue requirement calculation which will become effective January 2013. 10. ICC Rate of Return – is it indicative of debt cost or does it take into account adjustment for Good Will? Slide 25 shows the projected overall rate of return for 2013 is 10.06% compared to the current rate of return of 10.44%. Two primary factors explain the lower overall ROR. First, the average debt cost decreased from 7.84% in 2011 to 7.55% in 2013. Second, the 2013 calculation reflects total equity being reduced by $411 million of goodwill in 2013. This lowered the equity ratio to 53%. 11. ICC Is the large increase in gross plant because of new projects? Is CWIP included? Yes. The gross transmission plant for 2013 has increased due to significant capital expenditures. As of the stakeholder meeting, the Illinois Rivers project was the only Ameren project eligible for CWIP. Therefore, some CWIP is included for ATXI. While we expect AIC to incur some capital expenditures related to Illinois Rivers for modifications to its existing facilities, there are none in 2013. 12. ICC Is the return based on 13 month average? The capital structure is based on 13 month average balances for debt, preferred and common stock. The overall rate of return is applied to the 13 month average rate base. The only exception is that deferred income taxes are a simple average of the beginning and end of year balances. 13. ICC Regarding the new projects being built in 2013; was a filing was made? Any projects subject to cost-sharing under Attachment GG? The 2013 AIC revenue requirement reflects any projects expected to be in service before the end of 2013. While there are currently three new AIC projects already approved by MISO and eligible for cost sharing under Attachment GG, none of the three are expected to be in service by the end of 2013. The three projects are Brokaw-South Bloomington, Latham-Oreana and Fargo-Mapleridge. Since these projects have already been approved under previous MTEPs, they will be cost-shared once completed. 14. PPI What is the forecast for Cap Ex for next year and 2014? Ameren has not publically disclosed its annual forecasted CapEx. 15. ICC How are the mechanics of true-up and carry charge handled? What about overcollecting? The true-up is a two step process. The first true-up is for projected versus actual revenue requirement. The second true-up is for projected load used in calculating the projected rate versus the actual load for the year. The AIC true-up for 2013 will be calculated in 2014 after the 2013 FERC Form 1 is available. The true-up calculation will be shared with customers at the October 2014 stakeholder meeting. If an over-collection occurs, the refund, including 24 months of interest at the FERC interest rate, will be included in the projected 2015 transmission rates. ATXI will have its first true-up for 2012 included in the projected 2014 transmission rates.