Wilmarth-Lakefield 345 kV Line Series Compensation Study Summary Presentation to Northern MAPP Sub-regional Planning Group October 27, 2004 Warren Hess Excel Engineering, Inc. www.exceleng.net Outline Project Background & Goals Conditions Studied & Models employed Technical Considerations Study Results Conclusions & Recommendations Project Background & Goals Wind generation additions in Southwest MN & gas generation in SE South Dakota (Buffalo Ridge area & Anson) have “flowgate problems” on “Ft Cal S” & “Cooper S” interfaces (PTDFs exceed 5%) November 2001 Buffalo Ridge outlet report identified need for flowgate mitigation Recent Midwest ISO Transmission Service Request studies identified a few new constraints on neighboring systems due to other projects -- such as wind development in Iowa. Series compensation of Lakefield 345 kV line was one possible solution Wind in SW MN: problem after addition of Split Rock-Nobles-Lakefield Junction 345 kV line Anson: problem before and after Split RockLakefield Junction 345 kV line Proposed solution: series compensation! Task: determine amount & location of series comp. Conditions Studied & Models employed Year 2006 and 2008 Summer Peak and off-peak load Powerflow cases derived from 2001 Series 2007 model Generation additions represented Buffalo Ridge 425/825 MW Wilmarth 667 MW Lakefield 100 MW Faribault 300 MW Anson 232 + 170 MW Contingencies: NSP, Alliant-W, WAPA, GRE, SMMPA, MEC areas all 115 kV & above n-1 & multiple circuits over 1 mile Monitored: NSP, Alliant-W, WAPA, GRE, SMMPA, MEC areas all 69V & above Technical Considerations PTDFs Line & transformer loadings (system intact & postcontingency) Voltage profiles Arrestor (MOV) energies Fault levels Losses Dynamic Stability Study Results (1) PTDFs: need at least 40% comp to achieve <5% on Ft Cal & Cooper Anson Distribution Factors Year 2008 Summer, Off-Peak Load, 9% 8% Distribution Factor (%) 7% 6% 5% 4% 3% Cooper S (PTDF) Ft Cal S (PTDF) 2% Spencer-Triboji (OTDF) 1% 0% 0 0.1 0.2 0.3 0.4 0.5 Series Comp Level Spencer-Triboji OTDF goes up! 0.6 0.7 0.8 Line & transformer loadings Only “new” overload is Lakefield JunctionLakefield 345 (rating is 574 MVA) Some existing overloads eliminated or alleviated (e.g. Marshall-Lyon Co 115 kV) Wilmarth area 69 kV loadings increase Study Results Voltage profiles not limiting consideration, but midline is best Series comp reduces system losses, increases NSP losses Fault levels increase slightly 13% at Wilmarth 345 kV 5% at Wilmarth 115 1% at Wilmarth 69 8% at Lakefield Junction 345 Dynamic Stability Generally, imperceptible change Slight improvement (0 – 2%) for EI2 & NBZ voltages Lakefield wind farm may trip for Wilmarth area faults Recommended Plan (Preliminary) Series Comp Amount: 60% (20.0 Ohms) Location: mid-line (based on MOV energy, not V profile) Protection: bypass breaker & MOV (approx 42 MJ) Resultant Anson PTDFs, % (2008 off-peak) before after Ft Cal S 8.3 2.5 Cooper S 5.8 2.7 Spencer-Triboji OTDF: Anson to use tripping scheme for outage of Lakefield Junction-Raun 345 kV Next Steps Confirm results on Midwest ISO TSR model (facility study). Investigate cost. Finalize plans and make decision.