TEMPORARY OPERATING INSTRUCTION
O.O.
MISO
1-09470505
No.
1-05550745
115 kV Prairie Caps (7-12) and,
230 kV Line Prairie-Ramsey
2015-11-30 at 0700 to 2015-12-04 1800 CST
(2015-11-30 at 0800 to 2015-12-04 1900 EST)
15-11853-OO
15-03483-OO
Name of
Outage:
Effective Dates:
Standing Guide
Reference:
Description
of Work:
No.
15-270
File No.
240803
MHEX – USA Special Study as per K. Long 2015-11-02
Prairie Caps – Clearance for wiring in existing 115 kV Bays for TR7 & TR8
Prairie – Ramsey (GRE) – House Move
TRANSFER LIMITS:
MH-USA South (MH Export)
SOL:
Location
USA
TTC
1750
Schedule
Limit
1750
1525
RM
Transfer
(SOL)
CRSG
OM
Firm
NonFirm
Schedule
Limit
0
1750
150
75
1525
0
1525
MH-USA North (MH Import)
IROL
Location
USA
TLR
Triggers
850
SOL:
Schedule
Limit
700
650
TTC
700
RM
Transfer
(SOL)
CRSG
OM
Firm
NonFirm
Schedule
Limit
0
700
0
550
150
500
650
South
TLR 1
South
TLR 3
North
TLR 1
North
TLR 3
1584
1600
651
665
15-270_PrairieCaps(7-12)_and_Prairie_Ramsey_11_30_to_12_04.doc
Page 1 of 3
TEMPORARY OPERATING INSTRUCTION
MISO Webtool
Postings
MISO
Webtool
Postings
MHEX_S
(Export)
MHEX_N
(Import)
Special Notes
to MISO North
RC
TTC
TRM
No.
15-270
Coeff
1750
225
1.000
700
550
0.091
A) During this prior outage condition generation curtailment of the St. Joseph and St.
Leon wind farms concurrent with TLR on MHEX_N may be required when
Manitoba to USA flows are north to prevent post contingent overloads on G37C
following a trip of B10T or M602F.
B) The SOL for MHEX_S and MHEX_ N is the same if the MISO RTCA and MISO
Flowgate Monitoring Tool is unavailable prior to or during this outage.
Special
Instructions to
MHEB
Operator:
A) TOI Extentions - This TOI may be extended until 23:59 by performing the following
steps:
1. Verify system conditions to confirm there are no additional tie line facilities
outages, or new internal MH outages.
2. Review RTCA to confirm there are no new contingencies.
3. Contact MISO to confirm there are no new outages, if there are no new outages
provide notice to MISO that MH is extending the TOI.
4. Extend the outage in COLA.
5. Update TLAP outage table.
6. Provide notice to affected balancing authorities
15-270_PrairieCaps(7-12)_and_Prairie_Ramsey_11_30_to_12_04.doc
Page 2 of 3
TEMPORARY OPERATING INSTRUCTION
Special
Instructions to
MHEB
Operator
(cont):
Prepared By:
No.
15-270
B) When called upon by MISO for the supply of CRSG:
If Real Time Contingency Analysis (RTCA) indicates a post contingent overload
condition on Y51L for the contingent loss of D14S - redispatch MH generation to
maintain CRSG delivery as per:

Start Brandon Gas Generation and run up to 60 MW.
Brandon generation must be re-dispatched from HVDC generation at Dorsey

After 60 MW re-dispatch is complete, should RTCA continues to indicate a post
contingent overload condition on Y51L due to the contingent loss of D14S,
Continue to re-dispatch generation from Brandon gas in 10 MW increments until
post contingent overload on Y51L has been mitigated.

The mitigation must be completed within 30 minutes.
D. Williams
Date:
Copies to:
SOSS, System Control Centre
NSSS, System Control Centre
GSSS, System Control Centre
15-270_PrairieCaps(7-12)_and_Prairie_Ramsey_11_30_to_12_04.doc
2015 11 12
MISO
GSO, System Control Centre
Page 3 of 3