Westar Formula Rate and your bill 10/22/2010 1 What we will be going over • Transferring the results from the Westar Formula Rate to the SPP tariff. • The SPP Tariff – – – – Basic Cost Recovery Cash flow through the SPP tariff Base Plan Funding (BPF) What goes into a Customer’s bill • Results from the 2010 projection • Customer bills 10/22/2010 2 Overview Westar ATRR TO 2 ATRR Each Transmission Owner in the SPP reports its authorized Annual Transmission Revenue Requirement (ATRR) 10/22/2010 TO 2 ATRR SPP Tariff TO 17 ATRR SPP bills its customers based upon these ATRRs and its FERC approved Tariff 3 Westar Formula Rate • Annual Transmission Revenue Requirement Based on a fully projected 2010 Rate Year – – – – Projection based on 13 month average rate base for 2010 Beginning balance: 2008 Form 1 adjusted for projected 2009 Ending Balance: Beginning balance plus 2010 projections Add in any “True-up” balance (plus interest) from 2008 True-up based on actual 2008 cost vs Projected 2008 ATRR for the period from June 1 to December 31 • Most Projections based on internal formulas – Projected O&M is based upon the change in Net Plant – Other factors held at 2008 levels • New Capital based on 2010 Construction Budget – Based on Projects required by SPP 10/22/2010 4 The SPP Tariff - Rates • SPP is broken up into 17 different Pricing Zones – The Transmission Rates for each Zone are calculated by SPP – Annual Transmission Revenue Requirements (ATRR) from each Transmission Owner are used – Cost of Transmission Service for each Zone are based on the sum of all the ATRR allocated to that Zone (ZATRR) – Network Customers pay a Load Ratio share of the allocated ATRR The Load Ratio shares are calculated in January each year based on the previous Calendar year period (Customer 12 mo. Avg.. Peak / Zonal 12 mo Avg. Peak) – PTP rates are shown in Attachment T of the SPP Tariff Total Allocated ATRR / Zonal 12 mo Avg. Peak from formula = Annual Rate. 10/22/2010 5 SPP Tariff – Cost Recovery • Zonal charges Transmission Plant in existence prior to Jan. 1, 2006 Reliability Upgrades needed to meet local area criteria Costs of new transmission projects assigned to the Zone by SPP • Regional charges ATRR of each project is allocated to all Zones on a load ratio share basis – 12 mo. Zonal Avg. Load / (Σ 12 mo. Zonal Avg. Load for all zones) – Based on previous calendar year load values • Direct Assigned Costs Costs assigned to specific transmission customers or Transmission Project Sponsors 10/22/2010 6 SPP Tariff – Cost Recovery • Certain Transmission Projects can also qualify for Base Plan Funding (BPF) – Costs of BPF projects are recovered: 33% Regionally; 67% Zonally – Zonal costs are primarily allocated to the zone where the upgrade is built Zonal Costs may be allocated to other Zones based upon benefit 10/22/2010 7 SPP Tariff – Cost Recovery of New Transmission Upgrades • Reliability Projects – Normally BPF – If needed to meet local area reliability criteria that are more strict that SPP criteria, then its costs are assigned to the specific Zone • Upgrades related to requests for Transmission Service – Costs may qualify for Base Plan Funding – Otherwise, costs direct assigned to Customer • Economic Balanced Portfolio Upgrades – Regional • Sponsored Upgrades – Costs direct assigned to Sponsor • Generation Interconnection Service – Upgrades assigned to Generator, with credits from Attachment Z 10/22/2010 8 Revenue Requirements from Transmission Owners to SPP Pricing Zones Westar’s Total ATRR Westar Zonal ATRR SPP Tariff Westar Zone Regional Charge BPF ATRR BPF Projects OGE’s Total ATRR BPF ATRR 33% of Total BPF Zonal Charges 67% OGE Zone OGE Zonal ATRR All Other SPP TO’s Total ATRR BPF ATRR Zonal ATRR 10/22/2010 All Other SPP Price Zones 9 Example of BPF Cost Allocation BPF Projects $16 BPF ATRR=$12 Project 1 Regional Rate Rev. Req. Allocated By Load Ratio Share $4 $4.80 (30%) 33% Regional 67% Zonal Allocation $8 BPF ATRR=$36 $12 Project 2 Zonal Rate Rev. Req. Allocated By Zonal Benefit (This is Done by Project) $24 Zonal Rate Rev. Req. Allocated By Zonal Benefit (This is Done by Project) Total BPF ATRR for all Projects = $48.00 10/22/2010 $4.80 (20%) SPP Pricing Zone 2 LRS=30% $8.00 (50%) 33% Regional 67% Zonal Allocation Total BPF Allocated Costs $3.20 $3.20 (20%) $8.00 Westar Pricing $8.00 (100%) $1.20 Zone LRS=20% ------$1.20 $12.40 (5%) $18.00 (75%) SPP Pricing Zone 3 LRS=50% $4.80 $4.80 ------$9.60 $8.00 $18.00 ------$26.00 Sum of Allocated BPF ATRR = $48.00 10 Customer Bill Make up Ancillaries Supplied by SPP SPP pays suppliers for Ancillaries 2 & 4 SPP keeps Admin fees to support the RTO (Anc. 1A) SPP Admin Charge (Schedule 1A) Ancillary 2 - RV SPP Ancillary 4 - EIS Customer 1 Ancillaries 3, 5 & 6 Supplied on behalf of SPP by Westar as necessary Westar’s Share of BPF Westar Generation Ancillary Services Ancillary 1 - SC Schedule 11 BPF ATRR Allocated To Westar Zone 10/22/2010 Total Westar Zonal ATRR Westar Retail = Acct. 566.0011 Other Whsle. bus. = Acct. 565. Schedule 9 Westar Transmission Cost Recovery Other Transmission Owners in SPP Other TO’s Share of BPF 11 Looking at 2010 . . . 10/22/2010 12 Comparison between 2010 and 2009 Comparison of Transmission Formula Rate Results 10/22/2010 2009(Proj) 2010(Proj) 516,089,141 $ 640,910,500 Change from 2009 to 2010 24.19% Rate Base $ O&M Dep. Expense Taxes Other than Inc. Income Taxes Return Incentive Return Gross Rev. Req. $ $ $ $ $ $ $ 35,776,626 25,511,853 13,463,304 18,574,132 42,355,852 488,817 136,170,584 Rev. Credits True-up Adj(3) Net Rev. Req. $ $ $ 15,227,764 $ 17,939,732 (3,034,975) $ (1,120,609) 117,907,845 $ 131,957,167 17.81% -63.08% 11.92% BPF Rev. Req. BPF True up Zonal Rev. Req. $ $ $ 10,932,138 $ 19,256,992 (122,136) $ (2,803,356) 107,097,843 $ 115,503,531 76.15% 2195.27% 7.85% $ 36,577,947 $ 25,969,421 $ 12,959,043 $ 22,551,336 $ 52,428,290 $ 531,471 $ 151,017,508 2.24% 1.79% -3.75% 21.41% 23.78% 8.73% 10.90% Notes: (1) Current collected ATRR from TFR posted Feb. 17, 2009 (2) 2010 ATRR posted October 15, 2009. (3) Total True up value is : Adjustment Interest Zonal $ 1,594,109 $ 88,638 BPF $ (2,550,745) $ (252,611) Total $ (956,636) $ (163,973) Total True up value is only for the months of June 2008 through December 2008. Total True-up $ 1,682,747 $ (2,803,356) $ (1,120,609) 13 BPF Transmission Projects • Westar – 41 BPF Projects totaling over $19.3 million (Rev. Req.) $126 million E&C. – Second phase of Wichita-Reno-Summit 345 kV line $101.4 million • AEP – 17 BPF Projects, Total=$12.6 million – Westar’s direct Zonal share, $0 • OGE – 10 BPF Projects, Total = $3.3 million – Westar’s direct Zonal Share, $296,630 • SPS, NPPD – 6 BPF Projects, Total = $2.0 million – Westar’s direct Zonal Share, $0 10/22/2010 14 Estimated Westar Zonal Costs for 2010 Zonal Total BPF Total Westar All Others Total Regional $115,503,530 $19,256,992 2009 Zonal ATRR Regional Westar Zonal 33% * Total LRS % $6,354,807 12% 5,875,701 12% Westar Zone Allocation $762,577 $705,084 $1,467,661 $115,050,240 2010 Zonal ATRR $128,879,788 Westar All Others 10/22/2010 Zonal BPF Cost 67% * Total $12,902,185 Allocated to WR Estimated 12% Increase $11,611,967 $296,630 $11,908,597 15 Wholesale Customer Estimate of Transmission Service Costs based on SPP OATT Line 1 2 3 4 5 Description City Peak Load Average Peak Load (est) Annual Energy (MWH) (Note 6) (12 mo loss comp. avg with trans pk) (Note 5) Average Network Transmission Peak Demand (MW) Load Ratio Share (line 2 / line 4 ) 6 7 7A 8 Transmission charges - SPP OATT Schedule 9 Schedule 11-Zonal Schedule 11 - Regional Total Rev. Req. Calculation SPP OATT-Attachment H SPP OATT-Schedule 11 SPP OATT-Schedule 11 9 10 11 12 13 14 15 16 17 18 19 Estimated Annual Transmission Charges Transmission Charge (Sched. 9 & 11) Schedule 1 - Westar Scheduling [Note 1] Schedule 1A - SPP Scheduling Schedule 2 - Reactive (SPP Billing-est only) Schedule 3 - Regulation [Note 1] Schedule 4 - Imbalance (Based on Market) Schedule 5 - Spinning Reserves [Note 1] Schedule 6 - Supplemental Reserves [Note 5] Schedule 10 - Distribution Facilities Charge Schedule 12 - FERC Fees Total of all Annual Charges Calculation (line 8 * line 5) (line 2 * rate/yr) (line 2 * 730 hrs * rate/MW*12 mos) (Note 2) (line 2 * rate * 1.35%) (varies)(Note 3) (line 2 * rate * 1.67%) (line 2 * rate * 1.65%) (Note 4) (rate per month) (line 3 * rate/MWH) (sum lines 9 to 18) Note 1: Note 2: Note 3: Note 4: Note 5: Note 6: Peak Load (MW) 13.333 10.000 66288 Calculation 3751.667 0.002665482 Revenue Requirements $ 115,503,530 $ 11,908,597 $ 1,467,661 $ 128,879,788 Rates Percentage Annual Costs See Rev Reqm 100.00% $ 343,526.76 $ 752.09 100.00% $ 7,520.90 $ 0.195 100.00% $ 17,082.00 $ 122.63 100.00% $ 1,226.30 $ 53,358.74 1.35% $ 7,203.43 $ 53,358.74 $ 39,134.61 $ 1,000.00 $ 0.054908392 1.67% 1.65% 100.00% 100.00% Pricing comes from the Westar Open Access Transmission Tariff (OATT) Price fluctuates. Cost was estimated by taking about 10% of Westar's OATT price. Charge varies depending on the market and if the supplier takes on the charge from SPP. Distribution facilities charge is based upon the pro-rated costs of any distribution facitlies used by the city to obtain power. Source WEN Form 1 Page 311 Column G (this is only energy sold by WRGS to City, doesn't include any other resources) Peak Load based at Westar Transmission Peak. Loss Compensated based on SPP Transmission Service. $ 8,910.91 $ 6,457.21 $ 12,000.00 $ 3,639.77 $ 407,567.28 10/22/2010 17