4th Quarter Stakeholder Transmission Planning Meeting December 14, 2015 Unisource Energy Headquarters 88 E. Broadway Tucson, AZ 9:00 a.m. – 11:00 p.m. December 14, 2015 TEP & SWTC 2nd Quarter Stakeholder Meeting 1 1) 2) 3) 4) 5) 6) 7) 8) Welcome, Introductions, and Meeting Overview Review of action Items from 2015 2nd Quarter Meeting SWAT and WestConnect Overview SWTC 2015 Study Update TEP/UNSE 2015 Study Update WECC Update Stakeholder Questions/Comments Review of 2015 4th Quarter Meeting Action Items December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 2 Welcome Introductions Meeting Overview December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 3 To provide for stakeholder input into the transmission planning process by: ◦ Facilitating open, transparent, and coordinated transmission planning with all affected stakeholders as required by FERC (OATT Attachment K) ◦ Describing the 10 Year transmission planning process ◦ Presenting 10 Year Transmission Plans ◦ Supporting and coordinating stakeholder participation in Regional Planning Efforts (SWAT, WestConnect, and WECC) ◦ Accommodating Economic Study Requests December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 4 For example, joint planning sessions with Pima County jurisdictions Today, time is needed to meet FERC requirements to involve Stakeholders in the regional transmission planning process December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 5 There were no action items. December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 6 Planning Groups in Western Interconnection SWAT Footprint Website information WestConnect Update December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 7 The Southwest Area Transmission (SWAT) is a subregional planning group within the Western Interconnection It is comprised of transmission regulators/government entities, transmission users, transmission owners, transmission operators and environmental entities The goal of SWAT is to promote regional planning in the Desert Southwest. It includes transmission planning subcommittees, which are overseen by the SWAT Oversight Committee SWAT is governed by a Charter December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 8 WestConnect is composed of utility companies providing transmission of electricity in the United States Its members work collaboratively to assess stakeholder and market needs and to develop costeffective market enhancements to the western wholesale electricity market WestConnect is committed to coordinating its work with other regional industry efforts to achieve as much consistency as possible in the Western Interconnection December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 9 WECC (PCC & TEPPC) WGA & CREPC NWPP Area NTAC Col.Grid CCPG NTTG SSPG SWAT CTPG CAISO LADWP RETI December 14, 2015 WestConnect Others TEP & SWTC 4th Quarter Stakeholder Meeting NM RETA 10 WestConnect Footprint with Sub-Regional Planning Groups SSPG CCPG Sierra Subregional Planning Group Colorado Coordinated Planning Group SWAT – http://www.westconnect.com/planning_swat.php SSPG – http://www.westconnect.com/planning_sierra.php CCPG – http://www.westconnect.com/planning_ccpg.php Southwest Area Transmission WestConnect – http://www.westconnect.com December 14, 2015 SWAT TEP & SWTC 4th Quarter Stakeholder Meeting 11 SWAT FOOTPRINT Utah Colorado Nevada Shiprock Crystal Market Place Mead Navajo Glen Canyon Ojo Arizona Four Corners Cholla Moenkopi California San Juan Norton BA McKinley McCullough Blackwater Coronado West Mesa Springerville Perkins Palo Verde Hub Devers WW Rudd Liberty Browning Saguaro North Gila South Sandia New Mexico Pinnacle Peak Kyrene Silver King Vail Artesia Amrad Greenlee Winchester Tortolita Luna Afton Arroyo Hidalgo Diablo SWAT Taos Web Sites WestConnect: http://www.westconnect.com/ SWAT: http://www.westconnect.com/planning_swat.php Newman Caliente 500kV 345kV 5/30/2014070670-1 December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 12 SWAT Subcommittee Footprints SWAT Colorado Utah Nevada Shiprock Crystal Market Place Glen Canyon Ojo McCullough Four Corners Cholla Moenkopi Arizona Coronado Norton BA McKinley Blackwater West Mesa Springerville Perkins Palo Verde Hub Devers Taos Mead EVSG California San Juan Navajo WW New Mexico Pinnacle Peak Rudd Liberty Browning Kyrene Saguaro North Gila Sandia Silver King Greenlee Winchester Tortolita Amrad Hidalgo Luna Afton Artesia Arroyo South Vail Diablo SWAT SWAT-AZ NM EVSG Southwest Area Transmission Arizona Transmission Subcommittee New Mexico Transmission Eldorado Valley Study Group Newman Caliente NM 500kV 345kV Footprint wide committees: Short Circuit, Transmission Corridor, Web Sites WestConnect: http://www.westconnect.com/ SWAT: http://www.westconnect.com/planning_swat.php 5/30/2014070670-2 December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 13 SWAT Oversight Committee Meeting Held 11/18/15 ◦ SWAT/SWAT-AZ Recent Efforts: Started the process of putting together the study plan for the upcoming Biennial Transmission Assessment (BTA). Types of studies that will be in the plan are: ◦ ◦ ◦ ◦ ◦ ◦ ◦ Extreme Contingency Study Snapshot Study RMR Studies EE/DG Study Presentation on CAISO 2015-2016 Study work Presentation on North Gila to Imperial Valley #2 Presentation on Ten West Project, Delaney to Colorado River Presentation on SunZia Presentation on Southline Presentation on Arizona Renewable Energy Build-Out Study NERC/WECC Standards Update TPL-001-WECC-CRT-3 draft out for comment TPL-007 spreadsheet being created to collect data needed for GMD Study December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 14 Information on SWAT can be found at the WestConnect website: ◦ www.westconnect.com/planning.php WestConnect Site contains information about sub-regional planning groups within SWAT, planning calendars, and documents Chair: Patrick Harwood, Western Vice Chair: Chris Fecke-Stoudt, APS December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 15 WestConnect Regional Planning Process: ◦ ◦ ◦ ◦ ◦ ◦ ◦ Develop Study Plan Model Development Indentify Regional Needs Define Regional Alternatives Evaluate and Select Alternatives Identify Benficiaries and Allocate Costs Issue Regional Transmission Plan The 2015 Regional Transmission Needs Assessment did not identify any regional needs. A draft of the report was distributed on 11/20/15 and posted on the WestConnect website http://www.westconnect.com/ Stakeholder Comments were accepted until by 12/4/15. WestConnect will move to a full 2-year planning cycle. Upcoming Cycle will be for 2016/2017 ◦ Base Power Flow Models for 2026 Heavy Summer and 2026 Light Spring are being created in addition to a 2026 Cost Allocation Model ◦ A draft Scenario Submittal form is available to submit scenarios for the 2016/2017 cycle December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 16 WestConnect Planning Management Committee (PMC): ◦ Since the last meeting, Energy Strategies has been selected as the Planning Consultant to PMC. Ron Belval is the Chair of the PMC Bob Smith is the Vice-Chair of the PMC ◦ PMC has held numerous meetings to begin regional and interregional compliance efforts as mandated by FERC Order 1000. ◦ PMC began interregional coordination with the other Regions on February 26,2015. ◦ PMC Committees: Planning Subcommittee: Tom Green, Chair Gary Trent, Vice-Chair Cost Allocation Subcommittee: Jeff Hein, Chair Legal Subcommittee: Jennifer Spina, Chair Contract & Compliance Subcommittee (CCS): Stephanie Copeland, Chair December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 17 Planning Subcommittee (PS): Cost Allocation Subcommittee (CAS) Meetings: ◦ Met frequently in 2015 to receive updates on and review the studies conducted for the 2015 abbreviated planning cycle study. ◦ Currently developing Study Plan for the 2016/2017 study cycle ◦ Scenario submittal window is open until December 31, 2015. ◦ Met periodically during 2015 ◦ Developed plan for determining cost allocation ◦ No cost allocation was necessary in 2015 since no regional needs were identified Contract and Compliance Subcommittee is working on a charter. December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 18 SWTC Planning Calendar & Methodology 2016-2025 Ten-Year Plan Review Interconnection Requests and Transmission Service Requests Economic Study Requests of SWTC Stakeholder comments/questions on study plan Stakeholder submittal of requests for additional transmission studies December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 19 Planning Calendar for Ten-Year Planning Cycle SWTC Transmission Planning 10 Year Plan Jan. Arizona Utilities coordinated seed cases Development – from WECC Base cases Mar. Develop 10 Yr. base cases From AZ seed cases May Jun. Jul. Aug. Sep. SWTC Load Forecast for Class A Members 10 Yr. study plan effort Determination of projects, timings, and scope 10 Yr. Plan final development for submittal to ACC and WestConnect Dec. December 14, 2015 1. Class A Operating Committee (CAOC) Meetings between SWTC and Class A Members – currently 3 times per year 2. WestConnect Meetings 2 nd Quarter Stakeholder Meeting – Stakeholder Input on studies, request study alternatives, updates on current projects a. Steering Committee b. PMC c. PS Subcommittee 3. SWAT Meetings July 31 st – Network Transmission Customers Loads & Resources Forecast a. Oversight Committee b. SWAT-AZ c. Short-circuit Working Group 4. ACC Jan 31, 2015 – Timeframe to submit TEPPC Economic Study Requests Oct. Nov. Activities related to: 1. Development of SWTC Construction Work Plans and Long Range Plans 2. Demonstration of compliance with NERC Standards 3. WECC Planning Model Development and Reports 4. Regulatory Submittals Activities Throughout the Year: 10 Yr. Plans filed By others 10 Yr. Plan – Filed with the ACC by Jan. 31 st. Feb. Apr. Stakeholder Input Other Regional Coordination a. BTA b. Others 4th Quarter Stakeholder Meeting – Review draft Of current 10 Yr. plan, discussion on Economic Study requests, receive Stakeholder input TEP & SWTC 4th Quarter Stakeholder Meeting 20 NERC Planning Standards WECC System Performance Regional Business Practices Internal planning criteria ◦ SWTC Planning Guidelines are posted on the SWTC OASIS at http://www.oasis.oati.com/swtc/ December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 21 The 2016-2025 Ten Year Plan will be submitted to the ACC by the end of January 2016. It contains minor changes from last year’s plan: ◦ SWTC is currently involved in discussions with various entities on projects that may be advanced for consideration in future Ten Year Plans. These are discussed in the Ten Year Plan. On-going discussions throughout the year at the Class A Operating Committee (CAOC) Meetings will necessitate minor changes to this plan in the future. As changes are approved by the SWTC Board, they will be incorporated into the next filing at WestConnect and the ACC. December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 22 FIGURE 1 SWTC NORTHERN AREA SYSTEM TO SPRINGERVILLE SWTC GREENLEE MORENCI HACKBERRY TO HAYDEN TEP GREENLEE TEP 345 kV TO DUNCAN SWTC 69 kV TALLEY THATCHER SWTC 230 kV CORK SAN MANUEL NEW THATCHER GCEC 69 kV GCEC 69 kV FREEMAN SAN JOSE SAFFORD GCEC 69 kV SWIFT TRAIL TO DUNCAN CACTUS GCEC 69 kV GCEC 69 kV DOS CONDADOS Ten Year Plan Projects in Northern Area: ROMNEY HOOKER SWTC 230 kV SWTC 115 kV SSVEC 69 kV None GCEC 69 kV BONITA MORTENSON BOWIE SAN SIMON STEWART REDTAIL SSVEC 69 kV SWTC 230 kV WILLCOX WINCHESTER TO VAIL APACHE COCHISE TO ADAMS TAP KANSAS SETTLEMENT SSVEC 69 kV SSVEC 69 kV TO BUTTERFIELD TO CHIRICAHUA 69 kV LINES 115 kV LINES 138 kV LINES 230 kV LINES 345 kV LINES 500 kV LINES FUTURE SUBSTATION SWTC SUBSTATION OTHER SUBSTATION December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting AEPCO GENERATION 23 FIGURE 2 SWTC SOUTHERN AREA SYSTEM TO WINCHESTER TO REDTAIL APACHE SWTC 230 kV TO NOGALES TAP BUTTERFIELD COCHISE (2016) WESTERN 115 kV TO BICKNELL MESCAL PANTANO ADAMS TAP COTTONWOOD SSVEC 69 kV SSVEC 69 kV SSVEC 69 kV TO VAIL KANSAS SETTLEMENT SSVEC 69 kV BENSON ST. DAVID SWTC 230 kV Capacitor Bank Additions planned at: CHIRICAHUA TOMBSTONE JUNCTION SSVEC 69 kV SWTC 115 kV Ten Year Plan Projects in Southern Area: BOOTHILL WEBB HUACHUCA TOMBSTONE San Rafael (2016) SSVEC 69 kV APS 115 kV SWTC 230 kV SSVEC 69 kV Butterfield (2016) MURAL KARTCHNER DON LUIS SIERRA V ISTA SSVEC 69 kV BEL LA VISTA PUEBL O APS 69 kV SAN RAFAEL KEA TING (2016) HAWES APS 69 kV FT. HUACHUCA SUB PAL OMINAS RAMSEY S SV EC 69 k V HEREFORD APS 69 kV TO SOUTH McNEAL SAN PEDRO APS 69 kV 46 & 69 kV LINES 115 kV LINES 138 kV LINES 230 kV LINES 345 kV LINES 500 kV LINES FUTURE SUBSTATION SWTC SUBSTATION OTHER SUBSTATION December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting AEPCO GENERATION 24 TO HAYDEN FIGURE 3 SWTC WESTERN AREA SYSTEM APS 115 kV ORACLE SAGUARO SAN MANUEL APS 115 kV SADDLEBROOKE RANCH TORTOLITA THORNYDALE RATTLESNAKE MARANA SWTC 115 kV) Capacitor Bank additions planned at: Three Points (2015 – In-Service) NORTH LOOP TWIN PEAKS TO GREENLEE/ SPRINGERVILLE CAP SANDARIO AVRA VALLEY SWTC 115 kV Bicknell (2016) SWTC 115 kV Ten Year Plan Projects in Western Area: TE P 46 kV MARANA TAP Sahuarita (2015 – In-service) SANDARIO TUCSON BRAWLEY SWTC 115 kV WINCHESTER BLACK MOUNTAIN VALENCIA THREE POINTS SWTC 115 kV CAP SOUTH DEL BAC NOGALES TAP APACHE SWTC 345 kV SWTC 345 kV BICKNELL (2016) TEP 345 kV SWTC/TEP 345 kV (2015) SWTC/TEP 345 kV TO REDTAIL VAIL CAP 115 kV CAP SAN XAVIER WESTERN 115 kV SWTC 115 kV TO PINAL WEST SAHUARITA (2015) NEW TUCSON BUTTERFIELD (2016) WESTERN 115 kV PANTANO ADAMS TAP 69 kV LINES 115 kV LINES 138 kV LINES 230 kV LINES 345 kV LINES 500 kV LINES FUTURE SUBSTATION SWTC SUBSTATION OTHER SUBSTATION December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting AEPCO GENERATION 25 SWTC currently has several projects under consideration, and these are included in the 2016-2025 Ten Year Plan Filing These include: ◦ ◦ ◦ ◦ ◦ ◦ ◦ Apache/Hayden to San Manual 115 kV Line Saguaro to Thornydale 115 kV Line Thornydale to Twin Peaks 115 kV Line CAP 115 kV Line Tap to SWTC Sandario Sub Valencia to CAP Black Mountain 115 kV Line Tombstone Junction Project Move one of the 50MVAr Capacitor Banks from Morenci to Dos Condados December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 26 Generation interconnection requests: Transmission interconnection requests Currently involved in transmission study work with the following entities: ◦ None ◦ None ◦ Tucson Electric Power Company ◦ Arizona Public Service Company ◦ Western Area Power Administration December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 27 Currently no Economic Study Requests have been received by SWTC December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 28 December 14, 2015 Any Questions? TEP & SWTC 4th Quarter Stakeholder Meeting 29 Open Discussion ◦ Stakeholder submittal of requests for additional transmission studies: Requests can be made at any time to: swtctransmission@swtransco.coop December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 30 TEP/UNSE Planning Calendar & Methodology 2014-2023 Ten Year Plan Review Interconnection Requests and Transmission Service Requests Economic Study Requests of TEP Stakeholder comments/questions on study plan Stakeholder submittal of requests for additional transmission studies December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 31 December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 32 NERC Planning Standards WECC System Performance Regional Business Practices Internal planning criteria ◦ TEP Planning Guidelines are posted on the TEP OASIS at http://www.oasis.oati.com/tepc/ December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 33 2015-2024 Ten Year Plan was submitted to the ACC on January 31, 2014 Proposed 2015-2024 Ten Year Plan was submitted to WestConnect in December 2014 December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 34 Sigurd Glen Canyon Shiprock Navajo Four Corners San Juan LEGEND 500 kV 345 kV 230 kV Facilities Proposed by TEP Moenkopi Jointly Proposed Facilities McKinley Ya-Ta-Hey PNM Facilities Proposed by Others Cholla Coronado Springerville TBD Westwing Pinnacle Peak Palo Verde / Hassayampa Hassayampa – Pinal West 500kV Line Loop-in to Jojoba Switchyard (2017) Silver King Browning Liberty Copper Verde Kyrene Jojoba Gila River Gila (Jointly owned) Bend Frisco Abel Duke Pinal Central Pinal West Morenci North Gila Saguaro TBD Dos Condados TBD Tortolita TBD TBD Greenlee Greenlee SWTC PD-Morenci Irvington TBD Winchester Red Tail Vail South TBD Bicknell December 14, 2015 Luna EPE Pantano Butterfield Apache Hidalgo EPE Completed Projects ◦ Pinal Central – Tortolita 500kV Line ◦ Tortolita 500kV Expansion ◦ Springerville – Vail 345kV Line Series Capacitor Replacement at Vail ◦ Winchester – Vail 345kV Line Series Capacitor Replacement at Vail ◦ Springerville – Greenlee 345kV Line Series Capacitor Replacement at Greenlee Planned Projects ◦ South 345kV Substation Conversion (2016) ◦ Greenlee 345kV Substation Conversion (2017) ◦ Hassayampa-Pinal West Loopin to Jojoba (2017) TEP & SWTC 4th Quarter Stakeholder Meeting 35 Sigurd Glen Canyon Shiprock Navajo Four Corners San Juan LEGEND 500 kV 345 kV 230 kV Facilities Proposed by TEP Moenkopi Jointly Proposed Facilities McKinley Ya-Ta-Hey PNM Facilities Proposed by Others Cholla Coronado Springerville TBD Westwing Pinnacle Peak Palo Verde / Hassayampa Hassayampa – Pinal West 500kV Line Loop-in to Jojoba Switchyard (2017) Silver King Browning Liberty Copper Verde Kyrene Jojoba Gila River Gila (Jointly owned) Bend Frisco Abel Duke Hidalgo EPE Pinal Central Pinal West Morenci North Gila Saguaro TBD Dos Condados TBD Tortolita TBD TBD Greenlee Greenlee SWTC PD-Morenci Irvington TBD ◦ Vail to Irvington 345kV ◦ Irvington to South 345kV ◦ Tortolita to Winchester 500kV ◦ Vail to South #2 345kV ◦ Springerville to Greenlee #2 345kV ◦ Tortolita to South 345kV ◦ Westwing to South #2 345kV Winchester Red Tail Vail South TBD Bicknell December 14, 2015 Luna EPE Conceptual Projects (TBD) Pantano Butterfield Apache TEP & SWTC 4th Quarter Stakeholder Meeting 36 138kV Ten Year Plan Map (2016 – 2025) CHOLLA (Yr 2015) PINAL CENTRAL 500 SAGUARO 500 = Existing Substation TORTOLITA 500 Existing EHV / HV Line TORTOLITA 138 = New Substations = New 138kV Line = Reconductored 138kV Line = New EHV Line 2017 Reconfigure: Tortolita-Rancho Vistoso (disconnect) Tortolita-North Loop (connect) North Loop-Rancho Vistoso (connect) (Yr 2022) NORTH LOOP MARANA (Yr 2022) (Yr 2018) RANCHO VISTOSO NARANJA (Yr 2023) r (Y LA CANADA 20 (Yr 2015) ) 15 WEST INA (Yr 2016) ORANGE GROVE ( Yr 20 15 ) DEL CERRO (Yr 2021) CRAYCROFT - BARRIL RILLITO SNYDER (Yr 2020) r2 02 HARRISON (Y 3) (Yr 2015) NORTHEAST DMP ROBERTS EAST LOOP TUCSON (Yr 2020) (Yr 2020) 22ND ST SANTA CRUZ KINO (Yr 2020) SPANISH TRAIL IRVINGTON MIDVALE DREXEL PANTANO CORONA (Yr 2024) LOS REALES RBWILMOT CIENEGA VAIL VAIL2 345 T2 n.o. SOUTH 138 T1 SOUTH 345 T3 VAIL 345 AS&R MISSION Ft. Huachuca TBD Toro HARTT (Yr 2021) CYPRUS SIERRITA GREEN VALLEY TBD Duval CLEAR Switchyard Rosemont CANOA RANCH December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 37 Completed Projects ◦ ◦ ◦ ◦ ◦ ◦ ◦ ◦ ◦ ◦ North Loop 138kV Reconfiguration DMP – Tucson 138kV Line DMP – Northeast 138kV Reconductor North Loop – DMP 138kV Reconductor Northeast – Rillito 138kV Reconductor West Ina – Del Cerro 138kV Reconductor North Loop – Rillito 138kV Reconductor North Loop – West Ina 138kV Reconductor Rillito 138kV Capacitor Bank #1 Upgrade South Loop 138kV Capacitor Bank #1 Upgrade December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 38 Planned Projects (2016) ◦ Toro Switchyard Loop-in of South Loop – Green Valley 138kV ◦ Rosemont 138kV Line ◦ North Loop Capacitor Banks #1 & #2 Upgrades December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 39 Planned Projects (2017) ◦ Tortolita – Rancho Vistoso Reconfiguration Tortolita – North Loop #5 North Loop – Rancho Vistoso ◦ Orange Grove Substation Loop-in of La Canada – Rillito 138kV ◦ Canoa Ranch 138kV Capacitor Bank ◦ Roberts 138kV Capacitor Bank December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 40 Planned Projects (2018-2019) ◦ None December 14, 2015 TEP & SWTC 2nd Quarter Stakeholder Meeting 41 Planned Projects (2020) ◦ Harrison Substation Loop-in of East Loop – Roberts 138kV ◦ Irvington – Tucson 138kV Transmission Line #2 Loop-in at Kino Substation ◦ Irvington 138kV Substation Conversion December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 42 Planned Projects (2021) ◦ Craycroft-Baril Substation Loop-in of Northeast – Snyder 138kV ◦ Hartt Substation Loop-in of Green Valley – Future Toro December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 43 Planned Projects (2022) ◦ Marana Substation Loop-in of a Tortolita – North Loop 138kV circuit December 14, 2015 TEP & SWTC 2nd Quarter Stakeholder Meeting 44 Planned Projects (2023) ◦ Naranja Substation Loop-in of North Loop – Rancho Vistoso 138kV December 14, 2015 TEP & SWTC 2nd Quarter Stakeholder Meeting 45 Planned Projects (2024) ◦ Corona Substation Loop-in of Irvington – South Loop 138kV December 14, 2015 TEP & SWTC 2nd Quarter Stakeholder Meeting 46 Planned Projects (2025) ◦ None December 14, 2015 TEP & SWTC 2nd Quarter Stakeholder Meeting 47 Conceptual Projects ◦ Irvington – 22nd Street 138kV Line #2 (TBD) December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 48 1) Griffith-North Havasu Transmission Project (TBD) December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 49 Vail To Tucson (WESTERN) 1) No Projects Del Bac To Adams (WESTERN) Nogales 345 kV Existing Facilities Kantor 138 kV 115 kV F Canez Fossil Fuel Generation Sonoita Valencia (4 units) F December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 50 • Activity Since 4th Quarter Stakeholder Meeting New Interconnection Requests – Completed Feasibility Studies Completed System Impacts Studies – Completed Facility Studies – Projects Interconnected – Interconnection Projects Withdrawn – New Long-Term Firm Transmission Service Requests requiring SIS – Long-Term Firm Transmission Service Requests Withdrawn - December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 51 Currently involved in scoping/feasibility study work for the following entities: ◦ Western Area Power Administration - DSW ◦ Salt River Project December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 52 Currently no new Economic Study Requests have been received by TEP December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 53 December 14, 2015 Any Questions? TEP & SWTC 4th Quarter Stakeholder Meeting 54 • • Open Discussion – Stakeholder submittal of requests for additional ◦ transmission studies Requests can be made at any time to: Transcoord@tep.com December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 55 June 24, 2015 Board Meeting (minutes excerpts): ◦ Presentation on WECC activities, priorities and plans ◦ Presentation reviewing compliance process improvements ◦ Presentation on the activities and recommendations of the Member Advisory Committee (MAC) ◦ Presentation on Market Interface Committee (MIC) discussions of the Section 4.9 review work and the activities and concerns of the MIC. ◦ Presentation on Operating Committee (OC) activities and goals and reported that the committee is working to bring its goals into alignment with WECC’s strategic goals ◦ Presentation summarizing the Section 4.9 Review Summit held earlier in the week A complete draft of the WECC board minutes can be found at: https://www.wecc.biz/Administrative/2015-06-24%20Draft%20Board%20Minutes.pdf November 18 2015 Update from Section 4.9 Review Work Group: ◦ Section 4.9 Review Work Group provided a summary of feedback received during the Sept/Oct public comment period on the draft of Section 4.9 Review Report to the WECC Board of Directors. The Work Group reviewed the comments received and modified several recommendations to reflect member input ◦ The full Section 4.9 Work Group report can be found at https://www.wecc.biz/Administrative/Final%204%209%20Report%202015-12-02.pdf December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 56 May 6-7th Quarterly Meeting: ◦ There are currently eight positions on the Scenario Planning Steering Group (SPSG) that require appointments ◦ An update was provided on the WECC Board of Directors’ Section 4.9 Work Groups activities ◦ To more effectively incorporate the Integrated Reliability Assurance Model, the WECC Reliability Planning and Performance Analysis Department has been reorganized. The new structure consists of five teams within the RPPA division: Performance Analysis, Event Analysis, Situational Awareness, Reliability Planning and Standards Development ◦ An update was provided on the Reliability Planning Department’s proposed work priorities for 2015. ◦ An Update was provided on the 2015 Study Program ◦ An Update was provided on the 2024 Common Case and 10-year Study Cases ◦ WestConnect requested that its current three seats on TEPPC (Colorado Coordinated Planning Group, Southwest Area Transmission and Sierra Subregional Planning Group) be consolidated into a single seat represented by WestConnect December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 57 August 12th-13th Quarterly Meeting ◦ A summary of the Final Clean Power Plan was presented. There are interim compliance targets between 2022 and 2029. Mandatory reductions will now occur in that time frame with a three-step implementation approach ◦ There was a discussion about the future of the Base Case Coordination System (BCCS). It is an online resource for information to produce base cases. The contract for developing the system was awarded to Siemens, and is now three and a half years behind schedule. The System Review Work Group (SRWG) has been fully involved in testing and voted to give BCCS a sixmonth extension. The Technical Studies Subcommittee (TSS), SRWG’s parent committee voted later the same day to recommend terminating the BCCS Information can be found at the following link: www.wecc.biz/TEPPC/Pages/Default.aspx December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 58 August 11th-12th Meeting: ◦ Members recommended adding additional functionality WECC’s Environmental Data Viewer that would allow users to analyze their transmission line against WECC’s Environmental Risk Data. ◦ Members reviewed the Energy-Water-Climate Change Scenario to determine the extent to which potential changes to the climate might pose significant risks to the reliability and efficiency of the electric system in the Western Interconnection Information can be found at the following link: https://www.wecc.biz/teppc/Pages/spsg.aspx December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 59 Vijay Satyal, Senior Energy Policy Analyst, Reliability Planning at WECC, is the staff liaison to the RPCG. He is assisted by Colby Johnson, Associate Staff Engineer, System Adequacy. Chair is Gary DeShazo, CAISO and Vice Chair is Jeff Hein, Excel Energy RPCG meetings happen every other year depending on the needs of WECC members. RPCG is not a “formal standing WECC Committee,” but is a member-driven effort to guide and assist WECC staff in their planning efforts. An RCPG–CCTA Process Meeting was held on April 28, 2015: ◦ ◦ ◦ Purpose of the RPCG is: To solicit input on potential transmission projects with probability of being in-service in the next 10 years. To assist with best-estimates on transmission topology. Be stakeholder driven to reflect diversity of views. Critical for WECC Interconnection-wide planning Criteria-driven process (quantitative & subjective) Stakeholder input before submittal to TAS Valuable for future planning for Regional Planning Groups Valuable for resolving inaccurate data/assumptions on transmission projects; inconsistency in modeling assumptions and potential under/over estimation of transmission utilization/congestion levels. Process results - 2400 miles of regionally significant transmission Project kick-off in April 2015. April – August 2015: Develop and revise CCTA Assumptions September – December 2015: 2026 Common Case Kickoff 2024 CCTA Process: 2026 CCTA Process: The documents can be found at this link: www.wecc.biz/TEPPC/Pages/RPCG.aspx December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 60 Open discussion December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 61 Review of action items A status update of the action items to be provided during 2016 2nd Quarter Stakeholder Planning Meeting December 14, 2015 TEP & SWTC 4th Quarter Stakeholder Meeting 62