Q4 STAKEHOLDS MEETING PRESENTATION Updated:2015-12-15 15:52 CS

advertisement
4th Quarter
Stakeholder Transmission Planning Meeting
December 14, 2015
Unisource Energy Headquarters
88 E. Broadway
Tucson, AZ
9:00 a.m. – 11:00 p.m.
December 14, 2015
TEP & SWTC 2nd Quarter
Stakeholder Meeting
1
1)
2)
3)
4)
5)
6)
7)
8)
Welcome, Introductions, and Meeting Overview
Review of action Items from 2015 2nd Quarter
Meeting
SWAT and WestConnect Overview
SWTC 2015 Study Update
TEP/UNSE 2015 Study Update
WECC Update
Stakeholder Questions/Comments
Review of 2015 4th Quarter Meeting Action Items
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
2

Welcome

Introductions

Meeting Overview
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
3

To provide for stakeholder input into the
transmission planning process by:
◦ Facilitating open, transparent, and coordinated
transmission planning with all affected
stakeholders as required by FERC (OATT
Attachment K)
◦ Describing the 10 Year transmission planning
process
◦ Presenting 10 Year Transmission Plans
◦ Supporting and coordinating stakeholder
participation in Regional Planning Efforts (SWAT,
WestConnect, and WECC)
◦ Accommodating Economic Study Requests
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
4


For example, joint planning sessions with
Pima County jurisdictions
Today, time is needed to meet FERC
requirements to involve Stakeholders in the
regional transmission planning process
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
5

There were no action items.
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
6




Planning Groups in Western Interconnection
SWAT Footprint
Website information
WestConnect Update
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
7




The Southwest Area Transmission (SWAT) is a subregional planning group within the Western
Interconnection
It is comprised of transmission
regulators/government entities, transmission
users, transmission owners, transmission operators
and environmental entities
The goal of SWAT is to promote regional planning
in the Desert Southwest. It includes transmission
planning subcommittees, which are overseen by
the SWAT Oversight Committee
SWAT is governed by a Charter
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
8



WestConnect is composed of utility companies
providing transmission of electricity in the United
States
Its members work collaboratively to assess
stakeholder and market needs and to develop costeffective market enhancements to the western
wholesale electricity market
WestConnect is committed to coordinating its work
with other regional industry efforts to achieve as
much consistency as possible in the Western
Interconnection
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
9
WECC
(PCC & TEPPC)
WGA &
CREPC
NWPP Area
NTAC
Col.Grid
CCPG
NTTG
SSPG
SWAT
CTPG
CAISO
LADWP
RETI
December 14, 2015
WestConnect
Others
TEP & SWTC 4th Quarter
Stakeholder Meeting
NM
RETA
10
WestConnect Footprint
with Sub-Regional
Planning Groups
SSPG
CCPG
Sierra Subregional
Planning Group
Colorado
Coordinated
Planning
Group
SWAT – http://www.westconnect.com/planning_swat.php
SSPG – http://www.westconnect.com/planning_sierra.php
CCPG – http://www.westconnect.com/planning_ccpg.php
Southwest
Area
Transmission
WestConnect – http://www.westconnect.com
December 14, 2015
SWAT
TEP & SWTC 4th Quarter
Stakeholder Meeting
11
SWAT FOOTPRINT
Utah
Colorado
Nevada
Shiprock
Crystal
Market
Place
Mead
Navajo
Glen
Canyon
Ojo
Arizona
Four
Corners
Cholla
Moenkopi
California
San Juan
Norton
BA
McKinley
McCullough
Blackwater
Coronado
West Mesa
Springerville
Perkins
Palo
Verde
Hub
Devers
WW
Rudd
Liberty Browning
Saguaro
North Gila
South
Sandia
New
Mexico
Pinnacle
Peak
Kyrene
Silver King
Vail
Artesia
Amrad
Greenlee
Winchester
Tortolita
Luna
Afton
Arroyo
Hidalgo
Diablo
SWAT
Taos
Web Sites
WestConnect: http://www.westconnect.com/
SWAT: http://www.westconnect.com/planning_swat.php
Newman
Caliente
500kV
345kV
5/30/2014070670-1
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
12
SWAT Subcommittee Footprints
SWAT
Colorado
Utah
Nevada
Shiprock
Crystal
Market
Place
Glen
Canyon
Ojo
McCullough
Four
Corners
Cholla
Moenkopi
Arizona
Coronado
Norton
BA
McKinley
Blackwater
West Mesa
Springerville
Perkins
Palo
Verde
Hub
Devers
Taos
Mead
EVSG
California
San Juan
Navajo
WW
New
Mexico
Pinnacle
Peak
Rudd
Liberty
Browning
Kyrene
Saguaro
North Gila
Sandia
Silver
King
Greenlee
Winchester
Tortolita
Amrad
Hidalgo
Luna
Afton
Artesia
Arroyo
South
Vail
Diablo
SWAT
SWAT-AZ
NM
EVSG
Southwest Area Transmission
Arizona Transmission Subcommittee
New Mexico Transmission
Eldorado Valley Study Group
Newman
Caliente
NM
500kV
345kV
Footprint wide committees: Short Circuit, Transmission Corridor,
Web Sites
WestConnect: http://www.westconnect.com/
SWAT: http://www.westconnect.com/planning_swat.php
5/30/2014070670-2
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
13

SWAT Oversight Committee Meeting Held 11/18/15
◦ SWAT/SWAT-AZ Recent Efforts:
 Started the process of putting together the study plan for the upcoming
Biennial Transmission Assessment (BTA). Types of studies that will be in the
plan are:
◦
◦
◦
◦
◦
◦
◦




Extreme Contingency Study
Snapshot Study
RMR Studies
EE/DG Study
Presentation on CAISO 2015-2016 Study work
Presentation on North Gila to Imperial Valley #2
Presentation on Ten West Project, Delaney to Colorado River
Presentation on SunZia
Presentation on Southline
Presentation on Arizona Renewable Energy Build-Out Study
NERC/WECC Standards Update
 TPL-001-WECC-CRT-3 draft out for comment
 TPL-007 spreadsheet being created to collect data needed for GMD Study
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
14

Information on SWAT can be found at the
WestConnect website:
◦ www.westconnect.com/planning.php



WestConnect Site contains information
about sub-regional planning groups
within SWAT, planning calendars, and
documents
Chair: Patrick Harwood, Western
Vice Chair: Chris Fecke-Stoudt, APS
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
15

WestConnect Regional Planning Process:
◦
◦
◦
◦
◦
◦
◦


Develop Study Plan
Model Development
Indentify Regional Needs
Define Regional Alternatives
Evaluate and Select Alternatives
Identify Benficiaries and Allocate Costs
Issue Regional Transmission Plan
The 2015 Regional Transmission Needs Assessment did not identify any
regional needs. A draft of the report was distributed on 11/20/15 and
posted on the WestConnect website http://www.westconnect.com/
Stakeholder Comments were accepted until by 12/4/15.
WestConnect will move to a full 2-year planning cycle. Upcoming Cycle
will be for 2016/2017
◦ Base Power Flow Models for 2026 Heavy Summer and 2026 Light Spring are being
created in addition to a 2026 Cost Allocation Model
◦ A draft Scenario Submittal form is available to submit scenarios for the 2016/2017
cycle
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
16

WestConnect Planning Management Committee (PMC):
◦ Since the last meeting, Energy Strategies has been selected as the Planning
Consultant to PMC.
 Ron Belval is the Chair of the PMC
 Bob Smith is the Vice-Chair of the PMC
◦ PMC has held numerous meetings to begin regional and interregional
compliance efforts as mandated by FERC Order 1000.
◦ PMC began interregional coordination with the other Regions on February
26,2015.
◦ PMC Committees:
 Planning Subcommittee:
 Tom Green, Chair
 Gary Trent, Vice-Chair
 Cost Allocation Subcommittee:
 Jeff Hein, Chair
 Legal Subcommittee:
 Jennifer Spina, Chair
 Contract & Compliance Subcommittee (CCS):
 Stephanie Copeland, Chair
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
17

Planning Subcommittee (PS):

Cost Allocation Subcommittee (CAS) Meetings:

◦ Met frequently in 2015 to receive updates on and review
the studies conducted for the 2015 abbreviated planning
cycle study.
◦ Currently developing Study Plan for the 2016/2017 study
cycle
◦ Scenario submittal window is open until December 31,
2015.
◦ Met periodically during 2015
◦ Developed plan for determining cost allocation
◦ No cost allocation was necessary in 2015 since no regional
needs were identified
Contract and Compliance Subcommittee is working on a
charter.
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
18






SWTC Planning Calendar & Methodology
2016-2025 Ten-Year Plan Review
Interconnection Requests and Transmission
Service Requests
Economic Study Requests of SWTC
Stakeholder comments/questions on study
plan
Stakeholder submittal of requests for
additional transmission studies
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
19
Planning Calendar for Ten-Year Planning Cycle
SWTC Transmission
Planning
10 Year Plan
Jan.
Arizona Utilities
coordinated seed cases
Development – from WECC
Base cases
Mar.
Develop 10 Yr. base cases
From AZ seed cases
May
Jun.
Jul.
Aug.
Sep.
SWTC Load Forecast
for Class A Members
10 Yr. study plan effort Determination of projects,
timings, and scope
10 Yr. Plan final development
for submittal to ACC and
WestConnect
Dec.
December 14, 2015
1. Class A Operating
Committee (CAOC)
Meetings between
SWTC and Class A
Members – currently
3 times per year
2. WestConnect Meetings
2
nd
Quarter Stakeholder Meeting – Stakeholder
Input on studies, request study alternatives,
updates on current projects
a. Steering Committee
b. PMC
c. PS Subcommittee
3. SWAT Meetings
July 31 st – Network Transmission Customers
Loads & Resources Forecast
a. Oversight Committee
b. SWAT-AZ
c. Short-circuit Working
Group
4. ACC
Jan 31, 2015 – Timeframe to submit
TEPPC Economic Study Requests
Oct.
Nov.
Activities related to:
1. Development of
SWTC
Construction
Work Plans and
Long Range
Plans
2. Demonstration of
compliance with
NERC Standards
3. WECC Planning
Model Development and Reports
4. Regulatory Submittals
Activities
Throughout the Year:
10 Yr. Plans filed
By others
10 Yr. Plan – Filed with the ACC by Jan. 31 st.
Feb.
Apr.
Stakeholder
Input
Other
Regional
Coordination
a. BTA
b. Others
4th Quarter Stakeholder Meeting – Review draft
Of current 10 Yr. plan, discussion on Economic
Study requests, receive Stakeholder input
TEP & SWTC 4th Quarter
Stakeholder Meeting
20



NERC Planning Standards
WECC System Performance Regional
Business Practices
Internal planning criteria
◦ SWTC Planning Guidelines are posted on the
SWTC OASIS at http://www.oasis.oati.com/swtc/
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
21

The 2016-2025 Ten Year Plan will be submitted to
the ACC by the end of January 2016. It contains
minor changes from last year’s plan:
◦ SWTC is currently involved in discussions with various
entities on projects that may be advanced for consideration
in future Ten Year Plans. These are discussed in the Ten
Year Plan.


On-going discussions throughout the year at the
Class A Operating Committee (CAOC) Meetings will
necessitate minor changes to this plan in the
future.
As changes are approved by the SWTC Board, they
will be incorporated into the next filing at
WestConnect and the ACC.
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
22
FIGURE 1
SWTC NORTHERN AREA SYSTEM
TO
SPRINGERVILLE
SWTC
GREENLEE
MORENCI
HACKBERRY
TO
HAYDEN
TEP
GREENLEE
TEP 345 kV
TO
DUNCAN
SWTC 69 kV
TALLEY
THATCHER
SWTC 230 kV
CORK
SAN
MANUEL
NEW
THATCHER
GCEC 69 kV
GCEC 69 kV
FREEMAN
SAN JOSE
SAFFORD
GCEC 69 kV
SWIFT TRAIL
TO
DUNCAN
CACTUS
GCEC 69 kV
GCEC 69 kV
DOS CONDADOS
Ten Year Plan Projects in
Northern Area:
ROMNEY
HOOKER
SWTC 230 kV
SWTC 115 kV
SSVEC
69 kV
None
GCEC 69 kV
BONITA
MORTENSON
BOWIE
SAN SIMON
STEWART
REDTAIL
SSVEC 69 kV
SWTC 230 kV
WILLCOX
WINCHESTER
TO
VAIL
APACHE
COCHISE
TO
ADAMS TAP
KANSAS
SETTLEMENT
SSVEC 69 kV
SSVEC 69 kV
TO
BUTTERFIELD
TO
CHIRICAHUA
69 kV LINES
115 kV LINES
138 kV LINES
230 kV LINES
345 kV LINES
500 kV LINES
FUTURE SUBSTATION
SWTC SUBSTATION
OTHER SUBSTATION
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
AEPCO GENERATION
23
FIGURE 2
SWTC SOUTHERN AREA SYSTEM
TO
WINCHESTER
TO
REDTAIL
APACHE
SWTC 230 kV
TO
NOGALES TAP
BUTTERFIELD
COCHISE
(2016)
WESTERN 115 kV
TO
BICKNELL
MESCAL
PANTANO
ADAMS
TAP
COTTONWOOD
SSVEC 69 kV
SSVEC 69 kV
SSVEC 69 kV
TO
VAIL
KANSAS
SETTLEMENT
SSVEC 69 kV
BENSON
ST. DAVID
SWTC 230 kV
Capacitor Bank Additions
planned at:
CHIRICAHUA
TOMBSTONE
JUNCTION
SSVEC 69 kV
SWTC 115 kV
Ten Year Plan Projects in
Southern Area:
BOOTHILL
WEBB
HUACHUCA
TOMBSTONE
San Rafael (2016)
SSVEC 69 kV
APS 115 kV
SWTC 230 kV
SSVEC 69 kV
Butterfield (2016)
MURAL
KARTCHNER
DON LUIS
SIERRA V ISTA
SSVEC 69 kV
BEL LA
VISTA
PUEBL O
APS 69 kV
SAN
RAFAEL
KEA TING
(2016)
HAWES
APS 69 kV
FT. HUACHUCA
SUB
PAL OMINAS
RAMSEY
S SV EC 69 k V
HEREFORD
APS 69 kV
TO
SOUTH
McNEAL
SAN
PEDRO
APS 69 kV
46 & 69 kV LINES
115 kV LINES
138 kV LINES
230 kV LINES
345 kV LINES
500 kV LINES
FUTURE SUBSTATION
SWTC SUBSTATION
OTHER SUBSTATION
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
AEPCO GENERATION
24
TO
HAYDEN
FIGURE 3
SWTC WESTERN AREA SYSTEM
APS 115 kV
ORACLE
SAGUARO
SAN
MANUEL
APS 115 kV
SADDLEBROOKE
RANCH
TORTOLITA
THORNYDALE
RATTLESNAKE
MARANA
SWTC 115 kV)
Capacitor Bank additions planned at:
Three Points (2015 – In-Service)
NORTH
LOOP
TWIN
PEAKS
TO
GREENLEE/
SPRINGERVILLE
CAP
SANDARIO
AVRA
VALLEY
SWTC 115 kV
Bicknell (2016)
SWTC 115 kV
Ten Year Plan Projects in Western Area:
TE P 46 kV
MARANA
TAP
Sahuarita (2015 – In-service)
SANDARIO
TUCSON
BRAWLEY
SWTC 115 kV
WINCHESTER
BLACK
MOUNTAIN
VALENCIA
THREE
POINTS
SWTC 115 kV
CAP
SOUTH
DEL BAC
NOGALES
TAP
APACHE
SWTC 345 kV
SWTC 345 kV
BICKNELL
(2016)
TEP 345 kV
SWTC/TEP 345 kV
(2015)
SWTC/TEP
345 kV
TO
REDTAIL
VAIL
CAP 115 kV
CAP
SAN
XAVIER
WESTERN 115 kV
SWTC 115 kV
TO
PINAL WEST
SAHUARITA
(2015)
NEW
TUCSON
BUTTERFIELD
(2016)
WESTERN 115 kV
PANTANO
ADAMS TAP
69 kV LINES
115 kV LINES
138 kV LINES
230 kV LINES
345 kV LINES
500 kV LINES
FUTURE SUBSTATION
SWTC SUBSTATION
OTHER SUBSTATION
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
AEPCO GENERATION
25

SWTC currently has several projects under
consideration, and these are included in the
2016-2025 Ten Year Plan Filing These
include:
◦
◦
◦
◦
◦
◦
◦
Apache/Hayden to San Manual 115 kV Line
Saguaro to Thornydale 115 kV Line
Thornydale to Twin Peaks 115 kV Line
CAP 115 kV Line Tap to SWTC Sandario Sub
Valencia to CAP Black Mountain 115 kV Line
Tombstone Junction Project
Move one of the 50MVAr Capacitor Banks from
Morenci to Dos Condados
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
26

Generation interconnection requests:

Transmission interconnection requests

Currently involved in transmission study work
with the following entities:
◦ None
◦ None
◦ Tucson Electric Power Company
◦ Arizona Public Service Company
◦ Western Area Power Administration
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
27

Currently no Economic Study Requests have
been received by SWTC
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
28

December 14, 2015
Any Questions?
TEP & SWTC 4th Quarter
Stakeholder Meeting
29



Open Discussion
◦ Stakeholder submittal of requests for additional transmission
studies:
Requests can be made at any time to:
swtctransmission@swtransco.coop
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
30






TEP/UNSE Planning Calendar & Methodology
2014-2023 Ten Year Plan Review
Interconnection Requests and Transmission
Service Requests
Economic Study Requests of TEP
Stakeholder comments/questions on study
plan
Stakeholder submittal of requests for
additional transmission studies
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
31
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
32



NERC Planning Standards
WECC System Performance Regional
Business Practices
Internal planning criteria
◦ TEP Planning Guidelines are posted on the TEP
OASIS at http://www.oasis.oati.com/tepc/
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
33


2015-2024 Ten Year Plan was submitted to
the ACC on January 31, 2014
Proposed 2015-2024 Ten Year Plan was
submitted to WestConnect in December
2014
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
34
Sigurd
Glen Canyon
Shiprock
Navajo
Four Corners
San Juan
LEGEND

500 kV
345 kV
230 kV
Facilities Proposed by
TEP
Moenkopi
Jointly Proposed Facilities
McKinley
Ya-Ta-Hey
PNM
Facilities Proposed by
Others
Cholla
Coronado
Springerville
TBD
Westwing
Pinnacle
Peak
Palo Verde /
Hassayampa
Hassayampa –
Pinal West 500kV
Line Loop-in to
Jojoba Switchyard
(2017)

Silver
King
Browning
Liberty
Copper
Verde
Kyrene
Jojoba
Gila River
Gila
(Jointly owned)
Bend
Frisco
Abel
Duke
Pinal Central
Pinal
West
Morenci
North
Gila
Saguaro
TBD
Dos
Condados
TBD
Tortolita
TBD
TBD
Greenlee
Greenlee
SWTC
PD-Morenci
Irvington TBD
Winchester
Red Tail
Vail
South
TBD
Bicknell
December 14, 2015
Luna
EPE
Pantano
Butterfield
Apache
Hidalgo
EPE
Completed Projects
◦ Pinal Central – Tortolita 500kV
Line
◦ Tortolita 500kV Expansion
◦ Springerville – Vail 345kV Line
Series Capacitor Replacement
at Vail
◦ Winchester – Vail 345kV Line
Series Capacitor Replacement
at Vail
◦ Springerville – Greenlee 345kV
Line Series Capacitor
Replacement at Greenlee
Planned Projects
◦ South 345kV Substation
Conversion (2016)
◦ Greenlee 345kV Substation
Conversion (2017)
◦ Hassayampa-Pinal West Loopin to Jojoba (2017)
TEP & SWTC 4th Quarter
Stakeholder Meeting
35
Sigurd
Glen Canyon
Shiprock
Navajo
Four Corners
San Juan
LEGEND

500 kV
345 kV
230 kV
Facilities Proposed by
TEP
Moenkopi
Jointly Proposed Facilities
McKinley
Ya-Ta-Hey
PNM
Facilities Proposed by
Others
Cholla
Coronado
Springerville
TBD
Westwing
Pinnacle
Peak
Palo Verde /
Hassayampa
Hassayampa –
Pinal West 500kV
Line Loop-in to
Jojoba Switchyard
(2017)
Silver
King
Browning
Liberty
Copper
Verde
Kyrene
Jojoba
Gila River
Gila
(Jointly owned)
Bend
Frisco
Abel
Duke
Hidalgo
EPE
Pinal Central
Pinal
West
Morenci
North
Gila
Saguaro
TBD
Dos
Condados
TBD
Tortolita
TBD
TBD
Greenlee
Greenlee
SWTC
PD-Morenci
Irvington TBD
◦ Vail to Irvington 345kV
◦ Irvington to South 345kV
◦ Tortolita to Winchester
500kV
◦ Vail to South #2 345kV
◦ Springerville to Greenlee
#2 345kV
◦ Tortolita to South 345kV
◦ Westwing to South #2
345kV
Winchester
Red Tail
Vail
South
TBD
Bicknell
December 14, 2015
Luna
EPE
Conceptual Projects
(TBD)
Pantano
Butterfield
Apache
TEP & SWTC 4th Quarter
Stakeholder Meeting
36
138kV Ten Year Plan Map
(2016 – 2025)
CHOLLA
(Yr 2015)
PINAL CENTRAL
500
SAGUARO 500
= Existing Substation
TORTOLITA 500
Existing EHV / HV Line
TORTOLITA 138
= New Substations
= New 138kV Line
= Reconductored 138kV Line
= New EHV Line
2017 Reconfigure: Tortolita-Rancho
Vistoso (disconnect)
Tortolita-North Loop (connect)
North Loop-Rancho Vistoso (connect)
(Yr 2022)
NORTH LOOP
MARANA
(Yr 2022)
(Yr 2018)
RANCHO VISTOSO
NARANJA
(Yr 2023)
r
(Y
LA CANADA
20
(Yr 2015)
)
15
WEST
INA
(Yr 2016)
ORANGE
GROVE
( Yr
20
15
)
DEL
CERRO
(Yr 2021)
CRAYCROFT
- BARRIL
RILLITO
SNYDER
(Yr 2020)
r2
02
HARRISON
(Y
3)
(Yr 2015) NORTHEAST
DMP
ROBERTS
EAST
LOOP
TUCSON
(Yr 2020)
(Yr 2020)
22ND ST
SANTA
CRUZ
KINO
(Yr 2020)
SPANISH
TRAIL
IRVINGTON
MIDVALE
DREXEL
PANTANO
CORONA
(Yr 2024)
LOS
REALES
RBWILMOT
CIENEGA
VAIL
VAIL2
345
T2
n.o.
SOUTH
138
T1
SOUTH
345
T3
VAIL
345
AS&R
MISSION
Ft. Huachuca
TBD
Toro
HARTT
(Yr 2021)
CYPRUS
SIERRITA
GREEN
VALLEY
TBD
Duval
CLEAR
Switchyard
Rosemont
CANOA
RANCH
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
37

Completed Projects
◦
◦
◦
◦
◦
◦
◦
◦
◦
◦
North Loop 138kV Reconfiguration
DMP – Tucson 138kV Line
DMP – Northeast 138kV Reconductor
North Loop – DMP 138kV Reconductor
Northeast – Rillito 138kV Reconductor
West Ina – Del Cerro 138kV Reconductor
North Loop – Rillito 138kV Reconductor
North Loop – West Ina 138kV Reconductor
Rillito 138kV Capacitor Bank #1 Upgrade
South Loop 138kV Capacitor Bank #1 Upgrade
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
38

Planned Projects (2016)
◦ Toro Switchyard
 Loop-in of South Loop – Green Valley 138kV
◦ Rosemont 138kV Line
◦ North Loop Capacitor Banks #1 & #2 Upgrades
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
39

Planned Projects (2017)
◦ Tortolita – Rancho Vistoso Reconfiguration
 Tortolita – North Loop #5
 North Loop – Rancho Vistoso
◦ Orange Grove Substation
 Loop-in of La Canada – Rillito 138kV
◦ Canoa Ranch 138kV Capacitor Bank
◦ Roberts 138kV Capacitor Bank
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
40

Planned Projects (2018-2019)
◦ None
December 14, 2015
TEP & SWTC 2nd Quarter
Stakeholder Meeting
41

Planned Projects (2020)
◦ Harrison Substation
 Loop-in of East Loop – Roberts 138kV
◦ Irvington – Tucson 138kV Transmission Line #2
 Loop-in at Kino Substation
◦ Irvington 138kV Substation Conversion
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
42

Planned Projects (2021)
◦ Craycroft-Baril Substation
 Loop-in of Northeast – Snyder 138kV
◦ Hartt Substation
 Loop-in of Green Valley – Future Toro
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
43

Planned Projects (2022)
◦ Marana Substation
 Loop-in of a Tortolita – North Loop 138kV circuit
December 14, 2015
TEP & SWTC 2nd Quarter
Stakeholder Meeting
44

Planned Projects (2023)
◦ Naranja Substation
 Loop-in of North Loop – Rancho Vistoso 138kV
December 14, 2015
TEP & SWTC 2nd Quarter
Stakeholder Meeting
45

Planned Projects (2024)
◦ Corona Substation
 Loop-in of Irvington – South Loop 138kV
December 14, 2015
TEP & SWTC 2nd Quarter
Stakeholder Meeting
46

Planned Projects (2025)
◦ None
December 14, 2015
TEP & SWTC 2nd Quarter
Stakeholder Meeting
47

Conceptual Projects
◦ Irvington – 22nd Street 138kV Line #2 (TBD)
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
48
1)
Griffith-North
Havasu Transmission
Project (TBD)
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
49
Vail
To Tucson
(WESTERN)
1)
No Projects
Del Bac
To Adams
(WESTERN)
Nogales
345 kV
Existing
Facilities
Kantor
138 kV
115 kV
F
Canez
Fossil Fuel
Generation
Sonoita
Valencia
(4 units)
F
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
50
•
Activity Since 4th Quarter Stakeholder Meeting








New Interconnection Requests –
Completed Feasibility Studies Completed System Impacts Studies –
Completed Facility Studies –
Projects Interconnected –
Interconnection Projects Withdrawn –
New Long-Term Firm Transmission Service Requests requiring SIS –
Long-Term Firm Transmission Service Requests Withdrawn -
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
51
Currently involved in scoping/feasibility
study work for the following entities:
◦ Western Area Power Administration - DSW
◦ Salt River Project
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
52

Currently no new Economic Study Requests
have been received by TEP
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
53

December 14, 2015
Any Questions?
TEP & SWTC 4th Quarter
Stakeholder Meeting
54
•
•

Open Discussion
– Stakeholder submittal of requests for additional
◦ transmission studies
Requests can be made at any time to:
Transcoord@tep.com
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
55

June 24, 2015 Board Meeting (minutes excerpts):
◦ Presentation on WECC activities, priorities and plans
◦ Presentation reviewing compliance process improvements
◦ Presentation on the activities and recommendations of the Member
Advisory Committee (MAC)
◦ Presentation on Market Interface Committee (MIC) discussions of the
Section 4.9 review work and the activities and concerns of the MIC.
◦ Presentation on Operating Committee (OC) activities and goals and
reported that the committee is working to bring its goals into alignment
with WECC’s strategic goals
◦ Presentation summarizing the Section 4.9 Review Summit held earlier in
the week
A complete draft of the WECC board minutes can be found at:
https://www.wecc.biz/Administrative/2015-06-24%20Draft%20Board%20Minutes.pdf

November 18 2015 Update from Section 4.9 Review Work Group:
◦ Section 4.9 Review Work Group provided a summary of feedback received during the
Sept/Oct public comment period on the draft of Section 4.9 Review Report to the
WECC Board of Directors. The Work Group reviewed the comments received and
modified several recommendations to reflect member input
◦
The full Section 4.9 Work Group report can be found at
https://www.wecc.biz/Administrative/Final%204%209%20Report%202015-12-02.pdf
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
56

May 6-7th Quarterly Meeting:
◦ There are currently eight positions on the Scenario Planning Steering
Group (SPSG) that require appointments
◦ An update was provided on the WECC Board of Directors’ Section 4.9
Work Groups activities
◦ To more effectively incorporate the Integrated Reliability Assurance
Model, the WECC Reliability Planning and Performance Analysis
Department has been reorganized. The new structure consists of five
teams within the RPPA division: Performance Analysis, Event Analysis,
Situational Awareness, Reliability Planning and Standards Development
◦ An update was provided on the Reliability Planning Department’s
proposed work priorities for 2015.
◦ An Update was provided on the 2015 Study Program
◦ An Update was provided on the 2024 Common Case and 10-year
Study Cases
◦ WestConnect requested that its current three seats on TEPPC (Colorado
Coordinated Planning Group, Southwest Area Transmission and Sierra
Subregional Planning Group) be consolidated into a single seat
represented by WestConnect
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
57

August 12th-13th Quarterly Meeting
◦ A summary of the Final Clean Power Plan was presented. There are
interim compliance targets between 2022 and 2029. Mandatory
reductions will now occur in that time frame with a three-step
implementation approach
◦ There was a discussion about the future of the Base Case
Coordination System (BCCS). It is an online resource for
information to produce base cases. The contract for developing
the system was awarded to Siemens, and is now three and a half
years behind schedule. The System Review Work Group (SRWG)
has been fully involved in testing and voted to give BCCS a sixmonth extension. The Technical Studies Subcommittee (TSS),
SRWG’s parent committee voted later the same day to recommend
terminating the BCCS
Information can be found at the following link:
www.wecc.biz/TEPPC/Pages/Default.aspx
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
58

August 11th-12th Meeting:
◦ Members recommended adding additional functionality WECC’s Environmental Data
Viewer that would allow users to analyze their transmission line against WECC’s
Environmental Risk Data.
◦ Members reviewed the Energy-Water-Climate Change Scenario to determine the
extent to which potential changes to the climate might pose significant risks to the
reliability and efficiency of the electric system in the Western Interconnection

Information can be found at the following link:
https://www.wecc.biz/teppc/Pages/spsg.aspx
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
59




Vijay Satyal, Senior Energy Policy Analyst, Reliability Planning at WECC, is the staff liaison to the
RPCG. He is assisted by Colby Johnson, Associate Staff Engineer, System Adequacy.
Chair is Gary DeShazo, CAISO and Vice Chair is Jeff Hein, Excel Energy
RPCG meetings happen every other year depending on the needs of WECC members. RPCG is
not a “formal standing WECC Committee,” but is a member-driven effort to guide and assist
WECC staff in their planning efforts.
An RCPG–CCTA Process Meeting was held on April 28, 2015:
◦
◦
◦

Purpose of the RPCG is:



To solicit input on potential transmission projects with probability of being in-service in the next 10 years.
To assist with best-estimates on transmission topology.
Be stakeholder driven to reflect diversity of views.






Critical for WECC Interconnection-wide planning
Criteria-driven process (quantitative & subjective)
Stakeholder input before submittal to TAS
Valuable for future planning for Regional Planning Groups
Valuable for resolving inaccurate data/assumptions on transmission projects; inconsistency in modeling
assumptions and potential under/over estimation of transmission utilization/congestion levels.
Process results - 2400 miles of regionally significant transmission



Project kick-off in April 2015.
April – August 2015: Develop and revise CCTA Assumptions
September – December 2015: 2026 Common Case Kickoff
2024 CCTA Process:
2026 CCTA Process:
The documents can be found at this link:
www.wecc.biz/TEPPC/Pages/RPCG.aspx
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
60

Open discussion
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
61


Review of action items
A status update of the action items to be
provided during 2016 2nd Quarter
Stakeholder Planning Meeting
December 14, 2015
TEP & SWTC 4th Quarter
Stakeholder Meeting
62
Download