Revision: January 20, 2016 NorthWestern Energy Transmission Planning and Attachment K Business Practice Links Document This Business Practice provides URLs addresses to NorthWestern Energy’s (“NWE”) local planning documents and business practices. URL addresses for Northern Tier Transmission Group (“NTTG”) regional and Western Electric Coordinating Council (“WECC”) interconnection wide planning documents are also included within this business practice. These links are directed to specific documents, business practices and folders that are stored on the following websites: NWE OASIS (http://www.oasis.oati.com/NWMT/index.html) NTTG Regional website (http://www.nttg.biz/site/) WECC Interconnection wide website (http://www.wecc.biz/) Accessing these documents will provide information on NWE’s Attachment K, local transmission planning business practices, processes and results and other informational documents. Please refer to the Index table on page 2. Broken Link Please report any broken link to: kelly.lovell@northwestern.com Page 1 of 16 Revision: January 20, 2016 Section Index: 1. FERC Order 890 & 1000 Local Transmission Planning and Attachment K Link Information ........................................................................................................................ 4 A. Attachment K ............................................................................................................. 4 B. Attachment K – Intervention ...................................................................................... 4 C. CEII ............................................................................................................................ 4 D. Calendar of Events and Study Cycle.......................................................................... 5 E. Comments on behalf of... ........................................................................................... 5 F. Confidentiality Agreement ......................................................................................... 5 G. Economic Congestion Studies (Economic Studies) ................................................... 5 H. Frequently Asked Questions ...................................................................................... 5 I. How to Contact Us ...................................................................................................... 5 J. L&R Data Request ...................................................................................................... 6 K. LTP Study Cycle – Data Collection ........................................................................... 7 L. Load Forecast – Forecast ............................................................................................ 7 M. Local Cost Allocation Methodology ......................................................................... 7 N. Local Transmission Plan ............................................................................................ 7 O. NWE Anti-Trust and SOC ......................................................................................... 8 P. Attachment K Business Practice ................................................................................. 8 Q. Business Practice ETP Method Criteria & Process ................................................... 8 R. Open Access Transmission Tariff (OATT) ................................................................ 9 S. Planning Docs Process for Amending Documentation .............................................. 9 T. Transmission Advisory Committee (TRANSAC) – How to Become Involved ........ 9 U. Transmission Advisory Committee (TRANSAC) Charter ...................................... 10 V. Other Transmission Planning Links ......................................................................... 10 W. Public Policy Project Request ................................................................................. 10 2. NTTG Regional Link Information ............................................................................ 11 A. NTTG Home Page (includes map)........................................................................... 11 B. Planning - Biennial Reports ..................................................................................... 11 C. Calendar ................................................................................................................... 11 D. Charters & Agreements ............................................................................................ 12 E. NTTG Cost Allocation Principles ............................................................................ 12 F. NTTG Attachment K Documents and NTTG Business Practices ............................ 12 G. NTTG Economic Congestion Studies ...................................................................... 12 H. NTTG Frequently Asked Questions ........................................................................ 12 I. NTTG Planning Committee Home Page ................................................................... 12 J. NTTG POR POD Map .............................................................................................. 12 K. NTTG Planning Cycle ............................................................................................. 13 L. NTTG Regional Planning and Cost Allocation Practices ........................................ 13 M. NTTG Study Plan .................................................................................................... 13 N. NTTG FERC Order 1000 Information..................................................................... 13 3. WECC Interconnection Wide Link Information ..................................................... 15 A. WECC Home Page................................................................................................... 15 B. WECC Planning Coordination Committee .............................................................. 15 Page 2 of 16 Revision: January 20, 2016 C. WECC Transmission Expansion Planning Policy Committee (TEPPC) Information & Documents ................................................................................................................ 15 D. WECC Closed Session Confidentiality Agreement for non-group member participants .................................................................................................................... 16 Page 3 of 16 Revision: January 20, 2016 1. FERC Order 890 & 1000 Local Transmission Planning and Attachment K Link Information Documents in this section address FERC Order 890 and FERC Order 1000 - Local Transmission Planning and are currently in effect. A. Attachment K LOCAL and REGIONAL *EFFECTIVE* Fourth Regional Compliance filing, submitted December 30, 2014 (which applies to the 2014-2015 Local Area Planning Cycle) was accepted by FERC March 24, 2015 with an Effective date of October 1, 2013 and matches the OATT. Attachment K revisions were submitted on December 30, 2014 in Docket No. ER13-67-003 to comply with FERC’s December 8, 2014 Order. FERC Acceptance Letter http://www.oasis.oati.com/NWMT/NWMTdocs/FERC_AcceptanceNWE_MT_O1K_4th_Regional_Compliance_Filing.pdf Attachment K-Effective 10/1/2013 http://www.oasis.oati.com/NWMT/NWMTdocs/Atth_K-Order_1000Effective_10-1-13_Order_Date_3-24-15.pdf INTER-REGIONAL *EFFECTIVE* Second Interregional, submitted February, 18, 2015 – NTTG FERC Order Joint Compliance filing was in response to the December 18, 2014 Order on Interregional requirements. On June 1, 2015 FERC issued a final order accepting the Western Filing Parties Interregional compliance filings in Docket No. ER13-1448-001. Attachment K-Effective 6/1/2015 http://nttg.biz/site/index.php?option=com_docman&view=download&alias=2427 -ferc-interregional-compliance-order-06-01-2015&category_slug=ferc-order1000-interregional&Itemid=31 B. Attachment K – Intervention Currently there are no intervention documents. C. CEII Posted Critical Energy Infrastructure Information (CEII) http://www.oasis.oati.com/NWMT/NWMTdocs/Posted_CEII.doc Page 4 of 16 Revision: January 20, 2016 D. Calendar of Events and Study Cycle 2016 Calendar of Events and Study Cycle http://www.oasis.oati.com/NWMT/NWMTdocs/2016_Calendar_of_Events_and_ Study_Cycle.doc 2015 Calendar of Events and Study Cycle http://www.oasis.oati.com/NWMT/NWMTdocs/2015_Calendar_of_Events_and_ Study_Cycle.doc E. Comments on behalf of... Currently there are no ‘Comments on behalf of...’ documents. F. Confidentiality Agreement Confidentiality Agreement Form 3359 12.04 Shortcut to: http://www.oasis.oati.com/NWMT/NWMTdocs/Confidentiality_Agreement .doc G. Economic Congestion Studies (Economic Studies) Economic Congestion Study 2016/2017 Cycle Economic Study Request Listing & Meeting Information http://www.oasis.oati.com/NWMT/NWMTdocs/Economic_Study_Request_Listin g_&_Meeting_Info.xls 2016 Economic Congestion Study Submittal Reminder http://www.oasis.oati.com/NWMT/NWMTdocs/2016Annual_Stakeholder_Reminder.pdf Economic Study Request Form http://www.oasis.oati.com/NWMT/NWMTdocs/Economic_Study_Request_Form .xls Other Info on Economic Studies http://www.oasis.oati.com/NWMT/NWMTdocs/Other_Info_on_Economic_Studi es.doc Note: A description of the process, procedure, and methodology for processing Additional Economic Congestion Studies is available in the “Attachment K Business Practice”. See Section 1.P of this document. H. Frequently Asked Questions http://www.oasis.oati.com/NWMT/NWMTdocs/Frequently_Asked_Questions.do c I. How to Contact Us http://www.oasis.oati.com/NWMT/NWMTdocs/How_To_Contact_Us.doc Page 5 of 16 Revision: January 20, 2016 J. L&R Data Request L&R Data Request 2015 includes the following Documents: Attachment B 2015 http://www.oasis.oati.com/NWMT/NWMTdocs/Section_2.docx Generation Request Letter NWE 2015 http://www.oasis.oati.com/NWMT/NWMTdocs/Generation_Request_LetterNWE_2015.pdf LAR2015 http://www.oasis.oati.com/NWMT/NWMTdocs/LAR2015.pdf Load Data Request 2015 http://www.oasis.oati.com/NWMT/NWMTdocs/Load_Data_Request_2015.xls Load Request Letter-NWE 2015 http://www.oasis.oati.com/NWMT/NWMTdocs/Load_Request_LetterNWE_2015.pdf Narrative Request Letter 2015 http://www.oasis.oati.com/NWMT/NWMTdocs/Narrative_Discussion_LetterNWE_2015.pdf Note: Additional information regarding the Load and Resource (L&R) Data Requests can be found on NWE’s OASIS site in the “Transmission Planning – Attachment K” folder. Under the “L&R Data Request” folder there is a folder for individual annual L&R Data Request cycles (such as “Customer L&R Data Request Information-2015”). L&R Data Request 2014 includes the following Documents: Attachment B 2014 http://www.oasis.oati.com/NWMT/NWMTdocs/Attachment_B_2014.docx Generation Request Letter NWE 2014 http://www.oasis.oati.com/NWMT/NWMTdocs/Generation_Request_LetterNWE_2014.pdf LAR2014 http://www.oasis.oati.com/NWMT/NWMTdocs/LAR2014.pdf Load Data Request 2014 http://www.oasis.oati.com/NWMT/NWMTdocs/Load_Data_Request_2014.xls Page 6 of 16 Revision: January 20, 2016 Load Request Letter-NWE 2014 http://www.oasis.oati.com/NWMT/NWMTdocs/Load_Request_LetterNWE_2014.pdf Narrative Request Letter 2014 http://www.oasis.oati.com/NWMT/NWMTdocs/Narrative_Request_Letter_2014. pdf Note: Additional information regarding the Load and Resource (L&R) Data Requests can be found on NWE’s OASIS site in the “Transmission Planning – Attachment K” folder. Under the “L&R Data Request” folder there is a folder for individual annual L&R Data Request cycles (such as “Customer L&R Data Request Information-2014”). Shortcut to: http://www.oasis.oati.com/NWMT/index.html K. LTP Study Cycle – Data Collection 2016-2017 LTP Study Cycle – Data Collection – Timeline (effective 10-17-13 per FERC) http://www.oasis.oati.com/NWMT/NWMTdocs/LTP_Study_Cycle-2016-2017Effective_10-17-13.doc Annual Stakeholder Reminder Submittal-2016 http://www.oasis.oati.com/NWMT/NWMTdocs/2016Annual_Stakeholder_Reminder.pdf Submitting Alternative Solutions http://www.oasis.oati.com/NWMT/NWMTdocs/Submit_Alternative_Solutions.xl s L. Load Forecast – Forecast Winter 2013-2014 Load Forecast – 04-16-14 http://www.oasis.oati.com/NWMT/NWMTdocs/Winter_20132014_Load_Forecast_-_04-16-14.docx M. Local Cost Allocation Methodology 2008 Local Cost Allocation Methodology Projects outside OATT effective 05-14-08 Shortcut to: http://www.oasis.oati.com/NWMT/NWMTdocs/2008_Local_Cost_Allocatio n_Methodology_Projects_Outside_OATT_effective_5-14-08.doc N. Local Transmission Plan 2014-2015 Planning Cycle 2014-2015 Electric Transmission Local Area Plan – 11-10-15 Final http://www.oasis.oati.com/NWMT/NWMTdocs/NWMT_20142015_Local_Area_Plan_FINAL_11-10-15.pdf Page 7 of 16 Revision: January 20, 2016 NWMT 2014-2015 Local Area Plan Development & Distribution http://www.oasis.oati.com/NWMT/NWMTdocs/NWMT_20142015_Local_AreaPlan_Development_&_Distribution.docx 2012-2013 Planning Cycle 2012-2013 Electric Transmission Local Area Plan – 12-16-13 Final http://www.oasis.oati.com/NWMT/NWMTdocs/NWMT_20122013_Local_Area_Plan_Final_12-16-13.pdf NWMT 2012-2013 Local Area Plan Development & Distribution http://www.oasis.oati.com/NWMT/NWMTdocs/NWMT_20122013_Local_AreaPlan_Development_&_Distribution.docx O. NWE Anti-Trust and SOC 2009 NWE Anti-Trust and SOC 03-17-09 Shortcut to: http://www.oasis.oati.com/NWMT/NWMTdocs/2009_NWE_AntiTrust_and_SOC_03-17-09.doc P. Attachment K Business Practice 2013 Attachment K Business Practice 10-18-13 (Effective 10-25-13) http://www.oasis.oati.com/NWMT/NWMTdocs/2013_Attachment_K_Business_ Practice-10-18-13_effective_10-25-13.pdf Q. Business Practice ETP Method Criteria & Process FINAL Approved Current B-PRACTICE effective 12-22-15 FINAL-2015-Business Practice ETP Method Criteria and Process (Approved 12/22/15, Effective 12-31-15) http://www.oasis.oati.com/NWMT/NWMTdocs/2015ETP_Method_Criteria_and_Process_BP_FINAL_12-22-15_Effective_12-3115.pdf REDLINE-2015 Business Practice ETP) Method Criteria and Process – 12-22-15 http://www.oasis.oati.com/NWMT/NWMTdocs/2015ETP_Method_Criteria_and_Process_BP_REDLINE_12-22-15.doc FINAL - 2015 Business Practice ETP Method Criteria and Process (Approved 12/01/15, Effective 12-07-15) http://www.oasis.oati.com/NWMT/NWMTdocs/2015_Business_Practice_ETP_M ethod_Criteria_and_Process_12-1-15_effective_12-7-15.pdf Page 8 of 16 Revision: January 20, 2016 FINAL Redline – 2015 Business Practice ETP Method Criteria and Process – 10-30-15 http://www.oasis.oati.com/NWMT/NWMTdocs/ETP_Method_Criteria_and_Proc ess_BP_Redline-10-30-15.doc FINAL - 2014 Business Practice ETP Method Criteria and Process (Approved 08/21/14, Effective 08-26-14) http://www.oasis.oati.com/NWMT/NWMTdocs/ETP_Method_Criteria_and_Proc ess_BP_Order1000-FinalApproved_08-21-14-Color.pdf FINAL Redline – 2014 Business Practice ETP Method Criteria and Process – 08-21-14 http://www.oasis.oati.com/NWMT/NWMTdocs/ETP_Method_Criteria_and_Proc ess_BP_Order1000-FinalRedline_08-21-14.doc R. Open Access Transmission Tariff (OATT) Transmission Services Procedures: Business Practice Open Access Transmission Tariff Vol. 5, 0.1.0 A Order date effective – 02-17-11 NorthWestern Corporation as of 9/10/2014 FERC Docket: ER10-03171-001 11 Table of Contents http://www.oasis.oati.com/NWMT/NWMTdocs/0_-_Table_of_Contents.pdf NOTE: Each Part, Attachment, and Schedule is posted separately and to lengthy to list. Please go to: 1) NorthWestern Energy’s OASIS website, (http://www.oasis.oati.com/NWMT/index.html) 2) open the ‘Tariffs/FERC Filings’ folder, 3) open the ‘Current NWE MT OATT’ folder – all files are listed in this sub-folder S. Planning Docs Process for Amending Documentation FINAL Approved Current 03-27-15 2015 Planning Documents Amend Process (Approved 03-27-15, Effective 04-1-15) http://www.oasis.oati.com/NWMT/NWMTdocs/PlanningDocumentsAmendProce ss_Aprvd03-27-15.doc Document Posting Log (tracks the documents being amended) (03-27-15) http://www.oasis.oati.com/NWMT/NWMTdocs/Document_Posting_Log.xls T. Transmission Advisory Committee (TRANSAC) – How to Become Involved http://www.oasis.oati.com/NWMT/NWMTdocs/TRANSAC__How_to_become_involved.doc Page 9 of 16 Revision: January 20, 2016 U. Transmission Advisory Committee (TRANSAC) Charter 2014 TRANSAC Charter 12-16-14 http://www.oasis.oati.com/NWMT/NWMTdocs/TRANSAC_Charter_12-1614.doc V. Other Transmission Planning Links On NWE’s OASIS website, there are a number of folders containing various documents and materials regarding transmission planning activities. The following shortcut will bring you to NWE’s OASIS website. Shortcut to: http://www.oasis.oati.com/NWMT/index.html The folders outlining Transmission Planning include: Transmission Planning Transmission Planning – Attachment K Transmission Planning – Economic Studies Transmission Planning – TRANSAC W. Public Policy Project Request Instructions for Public Policy Project Request http://www.oasis.oati.com/NWMT/NWMTdocs/InstructionsPublic_Policy_Project_Request.docx Workbook to submit Public Policy Project Request http://www.oasis.oati.com/NWMT/NWMTdocs/Public_Policy_Project_Request_Wrkbk. xlsx Page 10 of 16 Revision: January 20, 2016 2. NTTG Regional Link Information Documents in this section address FERC Orders 890 & 1000 Regional (NTTG) Transmission Planning. These documents are currently in effect. A. NTTG Home Page (includes map) http://nttg.biz/site/index.php?option=com_content&view=featured&I temid=107 B. Planning - Biennial Reports 2014-2015 2014-2015 NTTG Final Regional Transmission Plan Approved-December 17, 2015 http://www.oasis.oati.com/NWMT/NWMTdocs/NTTG_2014_2015_Regional_Tr ansmission_Plan_for_Posting_010816_FINAL_ver2.pdf 2012-2013 2012-2013 Biennial Reports http://nttg.biz/site/index.php?option=com_docman&slug=final-approved-20122013-nttg-biennial-reports&Itemid=31&view=list 2012-2013 NTTG Biennial Transmission Plan Executive Summary Final http://nttg.biz/site/index.php?option=com_docman&view=document&layout=def ault&alias=2144-2012-2013-nttg-biennial-transmission-plan-executive-summaryfinal&category_slug=final-approved-2012-2013-nttg-biennial-reports&Itemid=31 2012-2013 NTTG Biennial Transmission Plan Final http://nttg.biz/site/index.php?option=com_docman&view=document&layout=def ault&alias=2139-2012-2013-nttg-biennial-transmission-planfinal&category_slug=final-approved-2012-2013-nttg-biennial-reports&Itemid=31 2012-2013 NTTG Cost Allocation Report Final http://nttg.biz/site/index.php?option=com_docman&view=document&layout=def ault&alias=2138-2012-2013-nttg-cost-allocation-reportfinal&category_slug=final-approved-2012-2013-nttg-biennial-reports&Itemid=31 C. Calendar http://nttg.biz/site/index.php?option=com_jevents&view=month&layo ut=calendar&Itemid=30 Page 11 of 16 Revision: January 20, 2016 D. Charters & Agreements Includes NTTG Agreements, NTTG Committee Charters, Executed NTTG Planning Agreements and Anti-Trust Policy http://nttg.biz/site/index.php?option=com_docman&view=list&slug=f erc-order-1000-committee-charters&Itemid=31 E. NTTG Cost Allocation Principles Contains an explanation of the NTTG cost allocation principles and process (Published September 6, 2007). http://nttg.biz/site/index.php?option=com_docman&view=document&sl ug=cost-allocation-principles-andprocess&layout=default&alias=193-cost-allocation-principles-andprocess&category_slug=cost-allocation-principles-andprocess&Itemid=31 2010-2011 NTTG Cost Allocation Committee Final Report (11/14/11 and published April 22 2013) http://nttg.biz/site/index.php?option=com_docman&view=document&alias=1981 -nttg-2010-2011-cost-allocation-committee-final-report-11-142011&category_slug=2010-2011-cost-allocation-report-development&Itemid=31 F. NTTG Attachment K Documents and NTTG Business Practices http://nttg.biz/site/index.php?option=com_content&view=article&id =129:nttg-members-order-890-attachment-k&catid=119:ferc-order890&Itemid=107 G. NTTG Economic Congestion Studies http://nttg.biz/site/index.php?option=com_content&view=category&l ayout=blog&id=108&Itemid=98 H. NTTG Frequently Asked Questions http://nttg.biz/site/index.php?option=com_content&view=category&l ayout=blog&id=102&Itemid=88 I. NTTG Planning Committee Home Page Contains members, process documents and meeting information, data submittals, reports, and other general information, in addition to the links to specific documents described below. http://nttg.biz/site/index.php?option=com_content&view=category&l ayout=blog&id=567&Itemid=26 J. NTTG POR POD Map A map of the Point-of-Receipt and Point-of-Delivery can be found on the NTTG website at the following URL address. http://nttg.biz/site/index.php?option=com_docman&view=download&la yout=default&alias=2264-december-2014-por-pod-mapfinal&category_slug=atc-information-2014&Itemid=31 Page 12 of 16 Revision: January 20, 2016 K. NTTG Planning Cycle http://nttg.biz/site/index.php?option=com_docman&view=document&alias=1458 -nttg-planning-cycle-calendar&category_slug=home-topmenu&Itemid=31 L. NTTG Regional Planning and Cost Allocation Practices This is part of the FERC Order 1000 filing. See Section 0. NTTG FERC Order 1000 Information. M. NTTG Study Plan Study plan containing the assumptions, data, and tools used in conducting the current biennial planning cycle. Revised NTTG Biennial Study Plan APPROVED 3-9-2015 http://nttg.biz/site/index.php?option=com_docman&view=document&alias=2365 -revised-nttg-biennial-study-plan-approved-03-09-2015&category_slug=meetingmaterials-3&Itemid=31 NTTG 2012-2013 Study Plan and appendices NTTG 2012-2013 Approved Study Plan http://nttg.biz/site/index.php?option=com_docman&view=document&alias=2189 -2012-13-nttg-revised-approved-study-plan-06-12-2013&category_slug=20122013-nttg-study-plan&Itemid=31 Appendix A - CCTA document http://nttg.biz/site/index.php?option=com_docman&view=document&slug=20122013-study-plan-appendix-a&layout=default&alias=1755-2012-2013-study-planappendix-a&category_slug=2012-2013-nttg-study-plan&Itemid=31 Appendix B - TEPPC Data Analysis http://nttg.biz/site/index.php?option=com_docman&view=document&alias=1754 -2012-2013-study-plan-appendix-b&category_slug=2012-2013-nttg-studyplan&Itemid=31 Appendix C - Flow Diagram http://nttg.biz/site/index.php?option=com_docman&view=document&alias=1753 -2012-2013-study-plan-appendix-c&category_slug=2012-2013-nttg-studyplan&Itemid=31 The completed Biennial reports are shown in category B. of this document N. NTTG FERC Order 1000 Information At this site are documents and/or updates for Regional and Interregional documents for activity related to FERC Order 1000. http://nttg.biz/site/index.php?option=com_content&view=category&l ayout=blog&id=569&Itemid=136 Page 13 of 16 Revision: January 20, 2016 FERC Order 1000: Regional http://nttg.biz/site/index.php?option=com_content&view=article&id=350:fercorder-1000-regional&catid=341&Itemid=139 FERC Order 1000: Interregional http://nttg.biz/site/index.php?option=com_content&view=article&id=351&Itemid =138 Page 14 of 16 Revision: January 20, 2016 3. WECC Interconnection Wide Link Information Documents in this section address FERC Orders 890 & 1000 Interconnection Wide (WECC) information. These documents are currently in effect. A. WECC Home Page Shortcut to: http://www.wecc.biz/ B. WECC Planning Coordination Committee The WECC Planning Coordination Committee is made up of four subcommittees: Reliability Subcommittee (RS) Charter http://www.wecc.biz/Corporate/RS%20Charter.pdf#search=Reliability%20Subco mmittee%20Charter Remedial Action Scheme (RAS) Reliability Subcommittee Charter – approved March 25, 2014 http://www.wecc.biz/Corporate/RASRS%20Charter.pdf#search=RAS%20Reliabi lity%20Charter Loads & Resources Subcommittee (LRS) Charter http://www.wecc.biz/_layouts/15/WopiFrame.aspx?sourcedoc=/Reliability/LRS_ Charter_approved2010506.pdf&action=default&DefaultItemOpen=1 Technical Studies Subcommittee (TSS) Charter http://www.wecc.biz/Corporate/TSS%20Charter.pdf#search=Technical%20Studie s%20Subcommittee%20Charter Joint Synchronized Information Subcommittee (JSIS) Charter http://www.wecc.biz/Reliability/Joint%20Synchronized%20Information%20Subc ommittee%20Charter.pdf#search=Joint%20synchronized%20information%20sub committee%20charter C. WECC Transmission Expansion Planning Policy Committee (TEPPC) Information & Documents WECC Transmission Expansion Planning Policy Committee – Contains members, process documents, meeting information, reports, and other general information regarding the regional planning processes, in addition to the links to specific documents described below. Page 15 of 16 Revision: January 20, 2016 TEPPC Home Page Shortcut to: http://www.wecc.biz/TEPPC TEPPC Charter http://www.wecc.biz/Corporate/TEPPC_Charter.pdf#search=TEPPC%20Charter TEPPC Planning Protocol – May 22, 2012 http://www.wecc.biz/Corporate/TEPPC_PlanningProtocol.pdf#search=TEPPC%2 0Planning%20Protocol TEPPC 2015 Study Program http://www.wecc.biz/Pages/results.aspx?k=TEPPC 2015 Study Program TEPPC 2014 Study Program http://www.wecc.biz/_layouts/15/WopiFrame.aspx?sourcedoc=/Reliability/TEPP C_2014_StudyProgram.docx&action=default&DefaultItemOpen=1 TEPPC 2013 Study Program http://www.wecc.biz/Reliability/TEPPC_2013_StudyProgram.pdf#search=TEPP C D. WECC Closed Session Confidentiality Agreement for non-group member participants http://www.wecc.biz/_layouts/15/WopiFrame.aspx?sourcedoc=/Corporate/WECC %20Closed%20Session%20Confidentiality%20Agreement%20for%20NonGroup%20Members.pdf&action=default&DefaultItemOpen=1 Page 16 of 16