Procurement Services Updated August 2012 Guidance notes of STANDARD TERMS AND CONDITIONS FOR SYSTEM / ICT SUPPLY The Terms and Conditions (T&Cs) are designed to offer both a generic option and opportunities for the user to add specific requirements. This guidance is intended to assist key personnel to consider where specific clauses may be needed/adapted. Please read in conjunction with the flowchart: Establishing which Terms and Conditions to use when Tendering/Procuring Goods and/or Services (LINK) Please read the T&Cs carefully. You should work through each of the sections below – editing as per the requirements of the contract and completing the schedules as appropriate. Please ensure that you check consequential numbering following any deletions/additions. Where options are included - in these brackets [ ] - the user will be required to consider if the clause is necessary and input/delete if required. Any changes to clauses should be agreed in collaboration with Procurement Services. Items highlighted [ ] require input. Section Guidance The ‘words and expressions’ included here should relate to the final T&Cs. Additional ‘words and expressions’ may be needed if any bespoke/unique clauses are required. Check consequential numbering following any deletions/additions: “EMU Compliant” – should be considered if appropriate “Training” – elements such as training expectations should be clearly set out “University Group” - can be defined in a further schedule if required – consider including PCMD and INTO expressly if they need to be covered by the Services 5. Price and Payment* The Price should correspond with the agreed price (submitted at tendering). Schedule 2 (below) offers a further opportunity to set out agreed prices. These clauses should also reflect the intended payment process that will be adopted for the project. It is good practice to produce a Payment Schedule if this is key to the project. 5.2. Software Hosting and The clauses here are designed to accommodate the requirements Maintenance/Licence for Maintenance and Licensing. Consider carefully against project Charges requirements. See also Schedule 4. 7. Performance and Delay Establishing the supplier’s ability to deliver specified requirements and to carry out due diligence, is crucial to the success of the contract. Consider carefully and include in Schedule 5 (below). Advice is available on the Procurement Services web-pages. 8. Change Control Proce- These clauses should reflect the intended Change Control Procedures that will be adopted for the project. If it is crucial/vital to produres ject delivery It is good practice to produce a Schedule as outlined at Schedule 7 1. Definitions and Interpretation 9. Installation/ Acceptance Testing The clauses here are designed to accommodate such testing and include provisions for software/hardware/system tests. Please read the ‘General Provisions’ carefully to check that they meet the needs of the project. See also Schedule 6. 1 Procurement Services Updated August 2012 You will want to be assured that the system is operational and running satisfactorily before the contract is complete. Schedule 6 can be used to set put precisely what is expected. “Delivery” - Check that delivery requirements clearly set out (when, how and where the system is to be integrated to existing buildings and systems). 10. Warranties The clauses here are designed to accommodate the requirements in respect of Warranty. Consider carefully against project requirements. See also Schedule 1 13. Loss of Software and Such provisions are likely to be crucial to the project. Consider Data Security carefully who will be involved in this process and include in the Terms and Conditions 22. Intellectual Property The clauses here are designed to accommodate the Intellectual Property requirements. Consider carefully against project requirements. Consider the extent to which these clauses are necessary based on the Services that the Consultant will be providing. If you are concerned about IP issues, Legal Services may be able to advise. 30. Disaster Recovery Such provisions are likely to be crucial to the project. Consider carefully who will be involved in this process and include in the Terms and Conditions 37. Dispute Resolution For more complex contracts it is important to have a procedure for Dispute Resolution in place. Consider carefully who will be involved in this process and include in the Terms and Conditions NB: TUPE clauses are not included in these T&Cs. If there are TUPE considerations seek advice from Procurement Team.** Schedules The schedules are designed to firm up the agreement once the contract has been won (a successful bidder at tender stage). The Schedules should prevent any misconceptions about contract delivery and assist contract management. For a more complex System/ICT supply contract many of these schedules will be intrinsic to the project and should support effective delivery and any dispute resolution. Potential suppliers may have already provided these as part of the tender process when they were chosen as the successful bidder. Schedule 1: Contract Information Schedule 2: Price/Payments Schedule Schedule 3: Project Plan This is often helpful to define the understanding of the contract. Consider adopting as part of the contract. “Insurance Annex” – also included in this section to underline what has been the basis for delivering the system at tender. Please note that the cost of insurances will be one of the elements that a contractor/supplier will factor into price. Ensuring this is clear prevents reasons for increased prices. The inclusion of a Price Schedule on the basis of the winning tender will enable contract managers to check actually prices with those agreed. You should consider any special elements e.g. payment of instalments, payment on completion/installation of individual modules. More complex projects will require a detailed Project Plan that agrees progress at the key stages. 2 Procurement Services Updated August 2012 Schedule 4: Software Hosting and Maintenance Services [and Hardware Maintenance Services] More complex projects will require that these are set out in more detail if applicable. These are encouraged in all projects as they will formalise the arrangements such as call-out, reporting and maintenance. NB: the Project Lead will have already identified these during the tender stage and, as such, will be a matter of extracting from the bidder’s submission. Schedule 5: Service Levels KPIs set as part of Service levels will allow the contract manager to (Key performance Indica- assess the delivery of the contract. For further advice on Assessing tors) Supplier Performance visit Good Practice 4. The schedule is in the form of a template that covers most areas. You should look to adopt some processes for measuring the success of the project/contract Schedule 6: Acceptance This schedule offers the opportunity to set out clearly the requireTesting ments for acceptance testing. You should review at the specific provisions that form the template and adapt for the requirements of the project/contract requirements. There may be other testing you will want to include and this should be set out clearly here. Schedule 7: Change Con- More complex projects will require a more formal Change Control trol Procedures (+ Change process is advised to provide the opportunity for considered Control Note) changes to the contract to enable delivery, installation and ongoing improvements. Schedule 8: University FaThis schedule offers the opportunity to set out clearly the University cilities Facilities and campuses’ structure. This may be useful when a variety of deliverables is implicit. Schedule 9: Additional This schedule offers the opportunity to set out clearly any additionServices al requirements. This is often useful to mitigate against unforeseen eventualities Appendix 1: Additional Services This schedule offers the opportunity to re-iterate the functional Specification. This should already have formed part of tender submission. – a simply referral to the submission and responses top requirements therein may be sufficient For further Procurement Advice please visit Procurement Services - Finance Services - University of Exeter * following a recent Government announcement, departments in government are now encouraged to pay their suppliers within 10 days of a valid invoice. This is to help businesses that are faced with increased cash flow problems in the current economic climate. It should be noted however that the standard payment terms (which can be modified) set out in these Standard Terms and Conditions state that contractuallybinding arrangements remain at 30 days. **The Transfer of Undertakings (Protection of Employment) Regulations (TUPE) protects employees' terms and conditions of employment when a business is transferred from one owner to another. Please consider carefully and seek advice where employees of the previous provider may be employed on the same contract with the new provider. 3