System Status Briefing (January – March 2016) BRIAN MOLEFE Group Chief Executive May 2016 CONFIDENTIAL Contents 1 Executive summary of performance 2 Maintenance overview 3 Outlook 4 New build update 5 Majuba power station silo & Duvha unit 3 updates 6 Conclusion Performance Highlights since October 2015 (1/2) Description • No load shedding has been implemented since August 2015 Maintenance without load shedding • Average planned maintenance (PCLF) 12.52% since August 2015 • Eskom’s prognosis for FY2016/17 is that there will be no load shedding • Availability has increased from ~70% in October 2015 to ~76% in April 2016 • This is largely due to a decrease in breakdowns (Unplanned Capacity Loss Increased availability factor and other loss factors) from ~18% in October 2015 to ~12% in April 2016 • Additional capacity added to the national grid excluding Medupi through improvements in EAF from ~70% to ~76% in April is 2 599 MW • Including Medupi the total capacity added is 3 279 MW Performance Highlights since October 2015 (2/2) Description • Eskom has managed to synchronise the first two Ingula units (3 & 4) to the New capacity national grid, ahead of schedule on 3 March and 25 March 2016 respectively • Medupi unit 6 commercially operational since August 2015 • OCGT energy sent out has decreased from 381GWh in October 2015 to Low diesel usage and spend 6GWh April 2016 • This resulting in a decrease in diesel costs from R854m to less than R25m from October 2015 to April 2016 Contents 1 Executive summary of performance 2 Maintenance overview 3 Outlook 4 New build update 5 Majuba power station silo & Duvha unit 3 updates 6 Conclusion Eskom has excess capacity of up to 11 000 MW after evening peak, as a result of improved Eskom performance Illustration of the summer and winter profiles MW Insights Average System Summer Profile • After evening peak, Eskom is required to drop load of approximately 11 000 MW, however this capacity will be required for the next evening peak 11 000 MW • Eskom has had to manage the excess capacity by either • operating a unit for two 8 hour shifts instead of three 8 hour shifts • switch units off for longer periods 00:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 35000 34000 33000 32000 31000 30000 29000 28000 27000 26000 25000 24000 23000 22000 21000 20000 Average System Winter Profile 6 Maintenance overview • The Tetris maintenance plan has been optimised to ensure no load shedding • The optimisation of the Tetris plan has been completed within the following criteria: • summer maintenance budget 11 500 MW • winter maintenance budget 8 500 MW • maximum OCGT load factor of 6% • Our month to date performance on the 11 May 2016 • 78.1 % - Energy availability • 9.2% - Break downs1 • 12.7 % - planned outages • In terms of our existing Generation Sustainability Strategy, our aim is to achieve 80% plant availability, 10% planned maintenance and 10% unplanned maintenance over the medium term 1 Includes breakdowns and other non plant losses Plant performance has been improving steadily since October 2015 Performance over the past seven months Percentage Breakdowns1 Planned maintenance Available energy Insights 18,1% 12,0% 70,0% Oct-15 17,4% 12,3% 70,3% Nov-15 14,7% 16,0% 69,3% Dec-15 17,0% 11,2% 71,8% Jan-16 15,6% 9,8% 74,7% Feb-16 12,9% 11,8% 9,2% 12,9% 12,0% 12,7% 76,2% 74,2% Mar-16 Apr-16 1 - Includes breakdowns and other non plant losses 2 – month to date performance on 11 May 2016 8 78,1% May-162 • Available energy has steadily increased since October 2015 • In December the availability dropped to 69%, because Eskom took advantage of the lower demand to perform more planned maintenance • The increase in availability is also attributed to the decrease in breakdowns • Additional capacity added to the national grid excluding Medupi through improvements in EAF from ~70% to ~76% in April is 2 599 MW • Including Medupi the total capacity added is 3 279 MW OCGT usage and costs have both decreased as a result of improved Generation availability OCGT performance over the past seven months Energy Send Out (GWh) 400 381 Insights 350 • The load factor has decreased from ~21.2% to ~0.4% 288 300 250 200 180 • The energy sent out from OCGT’s has decreased from 381 GWh to 6 GWh 150 100 100 50 21 6 6 0 Oct Nov Dec Jan Feb Mar Apr Load Factor (%) 21.2 16.6 10.6 5.6 1.3 0.4 0.4 Cost (R’m) 854 555 278 187 62 25 25 9 • The above mention has resulted in costs decreasing from R854 m to R25 m Today’s performance Screen shot of Eskom’s Generation Dashboard Insights • • The maintenance budget was 8 788 MW as of 12 May 2016 at 07h53 (sum of planned maintenance, forced outages and partial load losses) This translates into an EAF of 80%1 1 The percentage difference between the available capacity and operational MW. The surplus at 12:00 will be 4 704 MW Source: Performance data as per GPSS Contents 1 Executive summary of performance 2 Maintenance overview 3 Outlook 4 New build update 5 Majuba power station silo & Duvha unit 3 updates 6 Conclusion Outlook • Our prognosis for winter is that there will be no load shedding • We will continue with a rigorous program of planned maintenance without implementing load shedding while also minimising usage of open cycle gas turbines • For winter, Eskom is targeting a maintenance budget of 8 500 MW, in summer we budget 11 500 MW • Renewable energy will continue to contribute up to Photovoltaic 800 MW and wind 500 MW of the total installed capacity of 2 310 MW of electricity generated during the day from solar and wind including Eskom’s Sere wind farm The Tetris plan indicates no loadshedding for the remainder of the year Available Capacity Operating Reserves Planned Maintenance Plant Breakdowns Peak Demand Installed Capacity 45000 Installed Capacity is the total generating capacity from Eskom’s Summer Plant Breakdowns combined fleet 7000 MW Winter Plant Breakdowns Plant Breakdowns 6000 MW 40000 Plant Breakdowns: from the available capacity we subtract the anticipated breakdowns Planned Maintenance 35000 Operating Reserve 30000 25000 Planned Maintenance: from this we also need to subtract the planned maintenance Operating Reserve: 2000 MW buffer to cater for sudden Increase in load or if generating units are lost Peak Demand: the forecasted demand does not exceed the available capacity and we still have the 2000 MW of operating Available Capacity reserve as a buffer. Therefore the prognosis is no loadshedding for the remainder of the year Available Capacity: the capacity available to meet the demand we now have to superimpose the demand forecast for the year to compare it with the this available capacity. 20000 May Jun Jul Aug Sep 2016 Tetris V4.15 Oct Nov Dec Jan Feb 2017 Mar 1 Planned Maintenance – May to August 2016 Available Capacity = Installed Capacity - Peak Demand - UCLF Eskom is targeting a maintenance budget of 8.5 GW for Winter months Available Capacity to do planned maintenance and meet operating reserve Komati 6 Tutuka 4 Kendal 1 Operating Reserve Tutuka 1 Matla 1 Grootvlei 5 Komati 5 Ankerlig 3 Tutuka 6 Grootvlei 6 Camden 3 Tutuka 2 Kendal 4 HCB 1 Matimba 4 Lethabo 1 Ankerlig 4 Gourikwa 1 Komati 7 Matla 2 Hendrina 1 Grootvlei 1 Grootvlei 2 Arnot 1 Drakensberg 4 Palmiet 1 Hendrina 6 Kendal 5 Komati 9 Camden 2 Majuba 6 Lethabo 6 Tutuka 3 Ankerlig 2 Komati 3 Kriel 3 Hendrina 7 The no loadshedding plan allows for available capacity as we seldom dip into the operating reserves Source: Tetris Plan V4.15 14 Planned Maintenance – September to December 2016 2 Available Capacity = Installed Capacity - Peak Demand - UCLF Eskom 10000 is targeting a maintenance budget of 11.5 GW for summer months 9000 Lethabo 4 8000 Hendrina 4 7000 Majuba 5 Duvha 6 6000 HCB 1 Tutuka 5 Matla 3 Drakensberg 1 Majuba 3 Hendrina 3 Ankerlig 1 Hendrina 7 Ankerlig 7 Koeberg 1 Ankerlig 3 The no loadshedding plan allows for available capacity 2016 as we seldom dip into the operating reserves 30-Dec 27-Dec 24-Dec 21-Dec 30-Nov 27-Nov 24-Nov 21-Nov 18-Nov 15-Nov 12-Nov 09-Nov Camden 1 Hendrina 10 06-Nov 03-Nov 31-Oct 28-Oct 25-Oct 22-Oct 19-Oct 16-Oct 13-Oct 10-Oct 07-Oct 04-Oct 01-Oct 28-Sep 25-Sep 22-Sep 19-Sep 16-Sep 13-Sep 10-Sep 07-Sep 04-Sep Grootvlei 2 Hendrina 1 Camden 2 01-Sep 0 Kriel 4 Drakensberg 2 Matla 2 Komati 7 1000 18-Dec Kendal 5 Lethabo 5 15-Dec Gourikwa 1 2000 Medupi 6 Gourikwa 2 Grootvlei 1 Gariep 4 Ankerlig 4 12-Dec Komati 5 Tutuka 4 Matimba 6 09-Dec 3000 Gourikwa 3 06-Dec Matimba 4 Majuba 4 Komati 6 Matla 1 Komati 4 03-Dec 4000 Lethabo 3 Majuba 2 Vanderkloof 1 Hendrina 2 Duvha 2 Kendal 1 Operating Reserve 5000 Kriel 1 1 3 Planned Maintenance – January 2017 to March 2017 Available Capacity = Installed Capacity - Peak Demand - UCLF Eskom is targeting a maintenance budget of 11.5 GW for summer months The no loadshedding plan allows for available capacity as we seldom dip into the operating reserves Source: Tetris Plan V4.15 1 6 Contents 1 Executive summary of performance 2 Maintenance overview 3 Outlook 4 New build update 5 Majuba power station silo & Duvha unit 3 updates 6 Conclusion New Build Update (1/2) • Eskom has managed to synchronise the first Ingula units (3 & 4) to the national grid, ahead of schedule on 3 March and 25 March 2016 respectively • Medupi Unit 6 was commissioned on 23 August 2015, adding 794 MW to South Africa’s electricity grid • Medupi Unit 5 draught group run and dry fires were completed in March 2016, followed by the completion of the chemical cleaning of the unit in April 2016, which are important milestones towards first oil- and coal fires, leading to boiler blow through and ultimately commercial operation of the unit • Medupi Unit 5 is expected to be commercially operational in March 2018 (P80) New Build Update (2/2) • Kusile power station continues to achieve set milestones on the path for Unit 1 commercial operation • Kusile Unit 1 is expected to be commercially operational in July 2018 (P80) • The construction of Transmission lines and the commissioning of transformers have exceeded the targets for the 2015/16 financial year. These are 346km of transmission lines constructed and 2 435 MVAs of substation capacity commissioned • Since inception in 2005, the capacity expansion programme so far added 7 031 MW of generation capacity, 6 162 km of transmission lines and 32 090 MVA of substation capacity to the national grid We remain focused on bringing new capacity online P80 dates CO = commercial operation CO in Mar 2015 CO in Aug 2015 CO by Mar 2017 100 794 333 333 800 Aug 2015 Medupi Unit 6 Mar 2017 Ingula Unit 4 Jul 2017 Ingula Unit 1 Jul 2018 Kusile Unit 1 Mar 2015 Sere Wind Farm CO by Jul 2018 CO by Jul 2017 5 620MW Post MYPD 3 Mar 2015 Majuba recovery Jan 2017 Ingula Unit 3 1200 333 CO by Jan 2017 600MW from Unit 3 gap solution in Feb 2015 600MW from Unit 4 in Mar 2015 Mar 2018 Medupi Unit 5 2019/20 Duvha Unit 3 333 794 600 CO by May 2017 CO by Mar 2018 Fully recovered Project falls outside MYPD3 window May 2017 Ingula Unit 2 New capacity will fuel the South African economy Additional MW to be added to the South African grid Installed capacity (MW) Medupi + Sere Ingula Kusile Current capacity 55,000 51,789 50,195 50,000 45,000 47,807 44,087 894 45,419 2,482 894 800 1,332 1,332 4,070 1,600 1,332 4,864 2,400 1,332 52,589 4,864 3,200 1,332 Insights • Eskom is progressively adding capacity over the next seven years 53,389 4,864 4,000 1,332 40,000 40,000 35,000 43,193 43,193 43,193 43,193 43,193 43,193 43,193 10,000 • Ingula will be fully commissioned in 2017 • Medupi will be fully commissioned by 2020 • Kusile will be fully commissioned by 2022 5,000 0 2016 2017 2018 2019 2020 2021 2022 Contents 1 Executive summary of performance 2 Maintenance overview 3 Outlook 4 New build update 5 Majuba power station silo & Duvha unit 3 updates 6 Conclusion Majuba Power Station silo & Duvha Unit 3 update Majuba Permanent solution • • Duvha unit 3 update Construction completion of the permanent solution for the recovery of the coal silo at Majuba is on track for completion by end December 2017 (P80) • The letter of contractor appointment has been issued • Finalisation of the contract detail is in progress Plans to accelerate completion are in place and progressing well • Contractors to be on site by midyear for construction to commence Contents 1 Executive summary of performance 2 Maintenance overview 3 Outlook 4 New build update 5 Majuba power station silo & Duvha unit 3 updates 6 Conclusion Reasons for no load shedding Description Leadership involvement • Alignment in all structures to new leadership’s vision • Adherence to maintenance plan and discipline execution • Tetris - outage planning tool to optimise when outages should be scheduled, with minimal diesel usage Additional capacity already added • Medupi Unit 6 in August 2015 – 700 MW • Dedisa an IPP in October 2015 – 334 MW • Ingula Unit 4 is available for dispatch – 333 MW New capacity to be added • Avon IPP Peaking will be fully commissioned by October 2016 • Ingula will be fully commissioned in 2017 • Medupi will be fully commissioned by 2020 • Kusile will be fully commissioned by 2022 Improved plant performance • Breakdowns including other capacity loss factors have decreased from ~18% down to 12% in seven months • A deliberate focus on ensuring our units run at optimum levels • Thus increasing the energy availability from 71% to 76% Conclusion • Eskom has stabilised and we don’t anticipate load shedding • To date we have not implemented load shedding in 9 months (except for 2 hours and 20 minutes) • We will continue with planned maintenance and we remain focused on delivering on our capital expansion programme • We appreciate the support of all our customers and urge them to continue to use electricity sparingly at all times • Once completed in the next five years, our capacity expansion programme will increase our generation capacity by 17 384MW, transmission lines by 9 756km and substation capacity by 42 470MVA • This will enable us to provide security of electricity supply to South African homes and businesses, powering economic expansion and extending electricity to millions of households Thank you