NATURAL JUSTICE IN ADJUDICATION LING TEK LEE UNIVERSITI TEKNOLOGI MALAYSIA PSZ 19: 16 (Pind. 1/97) UNIVERSITI TEKNOLOGI MALAYSIA BORANG PENGESAHAN STATUS TESIS ♦ JUDUL: NATURAL JUSTICE IN ADJUDICATION SESI PENGAJIAN : 2005 / 2006 Saya LING TEK LEE ___________________________ (HURUF BESAR) mengaku membenarkan tesis (PSM / Sarjana / Doktor Falsafah)* ini disimpan di Perpustakaan Universiti Teknologi Malaysia dengan syarat-syarat kegunaan seperti berikut: 1. Tesis adalah hakmilik Universiti Teknologi Malaysia. 2. Perpustakaan Universiti Teknologi Malaysia dibenarkan membuat salinan untuk tujuan pengajian sahaja. 3. Perpustakaan dibenarkan membuat salinan tesis ini sebagai bahan pertukaran antara institusi pengajian tinggi. 4. ** Sila tandakan (9) 9 SULIT (Mengandungi maklumat yang berdarjah keselamatan atau kepentingan Malaysia seperti yang termaktub di dalam AKTA RAHSIA RASMI 1972) TERHAD (Mengandungi maklumat TERHAD yand telah Ditentukan oleh oprganisasi/ badan di mana Penyelidikan dijalankana) TIDAK TERHAD Disahkan oleh __________________________________________ (TANDATANGAN PENULIS) Alamat Tetap: 31, Jalan Impian Emas 60, Taman Impian Emas, 81300 Skudai, Johor Bahru. Tarikh: _____________________ CATATAN: __________________________________________________ (TANDATANGAN PENYELIA) En. Norazam Othman Nama Penyelia Tarikh: ______________________ * Potong yang tidak berkenaan. ** Jika tesis ini SULIT atau TERHAD, sila lampirkan surat daripada pihak berkuasa/organisasi berkenaan dengan menyatakan sekali sebab dan tempoh tesis ini perlu dikelaskan sebagai SULIT atau TERHAD. Tesis dimaksudkan sebagai tesis bagi Ijazah Doktor Falsafah dan Sarjana secara penyelidikan, atau disertasi bagi pengajian secara kerja kursus dan penyelidikan, atau Laporan Projek Sarjana Muda (PSM). “We hereby declare that we have read this thesis and in our opinion this thesis is sufficient in terms of scope and quality for the award of the degree of Master of Science in Construction Contract Management.” Signature : ................................................................. Name of Supervisor I : ................................................................. Date : ................................................................ Signature : ................................................................ Name of Supervisor II : ................................................................ Date : ................................................................ NATURAL JUSTICE IN ADJUDICATION LING TEK LEE A thesis submitted in fulfillment of the requirements for the award of the degree of Master of Science in Construction Contract Management Faculty of Built Environment Universiti Teknologi Malaysia MARCH, 2006 ii DECLARATION I declare that this thesis entitled “Natural Justice in Adjudication” is the result of my own research except as cited in the references. The thesis has not been accepted for any degree and is not concurrently submitted in candidature of any other degree. Signature : ................................................................. Name : ................................................................. Date : ................................................................. iii Specially dedicated to Ayln, Marcus, Audrey and Lucas for their love and support. iv ACKNOWLEDGEMENT I’m deeply grateful to all my lecturers in the Faculty of Built Environment, Universiti Teknologi Malaysia, in particular, Associate Professor Dr. Rosli Abdul Rashid, Associate Professional Dr. Maizon Hashim, En. Jamaludin Yaakob and En. Norazam Othman for their tireless effort in guiding me throughout the duration of the course. I wish to extend my sincere appreciation to En. Norazam for his helpfulness, advice, encouragement, courtesy and friendship in helping me to complete this thesis. I’m also deeply beholden to my good friends and coursemates, Yong Mei Lee, Nor Jalilah Idris and in particular Dennis Oon Soon Lee for their kindness and encouragement during the duration of the course when I was despaired with competing demand. Ling Tek Lee March, 2006 v ABSTRACT Statutory Adjudication has been widely adopted by many countries and Malaysian construction industry is actively advocating to the Malaysia Government to enact this legislation to improve the present poor payment practices in the Malaysian construction industry. However, Adjudication with its rough nature of its processes is said to deliver rough justice. Therefore, this research thesis seeks to determine the relevant of the principles of natural justice in Adjudication through the decided cases in various jurisdictions. The research revealed that the principles of natural justice clearly apply in Adjudication. An Adjudicator is required to conduct the Adjudication proceeding in a way that will not lead to any element of bias or even on the perception of bias. Each party will be afforded an opportunity to present his case and to adduce evidence in support of his case. Nevertheless, the main challenge here is for the Adjudicator to maintain his sense of even handedness while managing the Adjudication proceeding in the midst of a very demanding timeframe. Decisions from the decided cases in various jurisdictions clearly show that the courts are prepared to consider the circumstances under which the Adjudicators operate and will undoubtedly enforced the Adjudicators’ determination unless there is a clear breach on the principles of natural justice within the main issue that is of considerable importance to the outcome. vi ABSTRAK Undang-undang adjudikasi telah diterima pakai oleh banyak negara secara luasnya dan industri pembinaan Malaysia kini giat menganjurkannya kepada kerajaan Malaysia supaya undang-undang ini diperintahkan bagi mengatasi masalah pembayaran dalam industri pembinaan Malaysia. Walaupun begitu, adjudikasi dikatakan memberi keadilan secara kasar kerana ciri-ciri prosedurnya yang mudah dan cepat. Oleh itu, kajian ini dijalankan untuk mengenalpasti kesesuaian prinsip asal keadilan dalam adjudikasi melalui keputusan-keputusan mahkamah dari pelbagai bidang kuasa. Kajian ini mendapati bahawa prinsip asal keadilan diberi perhatian dalam adjudikasi. Seseorang adjudikater dikehendaki mengendalikan prosedur adjudikasi secara tidak berat sebelah. Setiap pihak mempunyai peluang yang sama untuk mengemukakan kesnya dan bukti-bukti bagi menyokong hujahnya. Walau bagaimanapun, cabaran utama kepada adjudikater ialah mengekalkan kesedarannya semasa menguruskan prosedur adjudikasi dalam tempoh masa yang singkat. Keputusan-keputusan mahkamah dari pelbagai bidang kuasa jelas menunjukkan bahawa mahkamah bersedia untuk mempertimbangkan keadaankeadaan dimana adjudikater beroperasi dan penentuannya dikuatkuasakan tanpa keraguan kecuali terdapat pemungkiran prinsip asal keadilan yang jelas dan ianya dianggap sebagai isu utama yang boleh mempengaruhi keputusan akhir kes tersebut. vii TABLE OF CONTENTS CHAPTER TITLE PAGE TITLE i DECLARATION ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF CASES x LIST OF ABBREVIATIONS xiii LIST OF APPENDICES xiv CHAPTER 1 INTRODUCTION 1.1 Background Of Study 1 1.2 Problem Statement 5 1.3 Objective Of The Study 7 1.4 Scope And Delimitation Of The Study 7 1.5 Research Methodology 8 1.6 Previous Study 8 1.7 Significance Of The Study 9 viii CHAPTER 2 THE DELIMMAS IN THE CONSTRUCTION INDUSTRY 2.1 Introduction 10 2.2 The Malaysian Scenario 12 2.3 Why Adjudication? 16 2.4 Conclusion 17 CHAPTER 3 THE NATURE OF ADJUDICATION 3.1 Introduction 19 3.2 Statutory Adjudication 22 3.3 Challenges to Adjudicator’s Decision 23 3.3.1 Erroneous Decision 27 3.4 Determinations beyond the Stipulated Time Limits 31 3.5 Conclusion 34 CHAPTER 4 NATURAL JUSTICE IN ADJUDICATION 4.1 Introduction 36 4.2 Rule Against Bias 39 4.3 Rule To ‘Hear The Other Side’ 46 4.4 Conclusion 49 CHAPTER 5 BREACH OF THE PRINCIPLES OF NATURAL JUSTICE 5.1 Introduction 51 5.2 The Position Of The Various Jurisdiction 52 5.2.1 Discain Project Services Ltd v Opecprime Development Ltd 5.2.2 53 Glencot Development And Design Co Ltd V Ben Barrett & Son (Construction) Ltd 54 ix 5.2.3 Balfour Beatty Construction Ltd v Lambeth London Borough Council 5.3 5.4 56 Does Limitation Of Documentation Constituted A Breach? 59 Conclusion 69 CHAPTER 6 CONCLUSION AND RECOMMENDATIONS 6.1 Introduction 71 6.2 Research Findings 73 6.3 Recommendations 76 6.4 Conclusion 77 REFERENCES 79 APPENDICES A Housing Grants, Construction And Regeneration Act 1996, United Kingdom B 83 Building and Construction Industry Security of Payment Act 1999, New South Wales 94 x LIST OF CASES CASE PAGE Anisminic Ltd v Foreign Compensation Commission (1969) 2 AC147 31 Balfour Bratty Construction Ltd v Lambeth London Borough Council (2002) EWHC 597 6, 47, 52, 56, 74, 75, 77 Ban Hong Joo Mines Ltd v Chen & Yap Ltd (1969) 2 MLJ 83 15 Beaufort Developments (NI) Ltd v Gilbert-Ash NI Ltd (1998) 2 All ER 778 27 Bouyques (UK) Ltd v Dahl-Jensen (UK) Ltd (1999) 70 ConLR 41 Brodyn Pty Ltd v Davenport (2003) NSWSC 1019 28 52, 70, 72 Carrillion Construction Ltd v Devonport Royal Dockyard (2003) BLR 79 23, 60 Cib Properties Ltd v Brise Construction (2004) EWHC 2365 64 C & B Concept Design Ltd v Isobars Ltd (2002) EWCA Civ 46 29 Dawnays Ltd v FG Minter Ltd (1971) 1 WLR 74 1 Dawnays Ltd v FG Minter Ltd & Anor (1971) 1 WLR 1205, 2 All ER 138913 14 Discain Project Services Ltd v Opecprime Development Ltd (2001) BLR 285 5, 6, 73 Disdain Project Services Ltd. v Opecprime Development Ltd. (2001) CILL 1698 44, 54 Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd (1974) AC 689; (1973) 3 All ER 195; (1973) 3 WLR 421 14 xi Glencot Development and Design Co Ltd v Ben Barrett & Son (Contractors) Ltd (2001) BLR 207 13, 43, 54, 74 Government of Ceylon v Chandris (1963) 2 QB 327 Hock Hua Bank (Sabah) Bhd v Yong Liuk Thin (1995) 2 MLJ 313 48 40, 42 Hoenig v Issacs (1952) 2 ALL ER 176 12 Interbulk Ltd v Aiden Shipping Co Ltd (‘The Vimeira’) (1984) 2 Lloyd’s Rep 66 46 Kah Seng Construction Sdn Bhd v Selsin Development Sdn Bhd (1997) 1 CLJ Supp 448 14 Kuala Ibai Development Sdn Bhd v Kumpulan Perunding (1988) Sdn Bhd (1999) 5 MLJ 137 40 London and Amsterdam Properties Ltd v Waterman Partnership Ltd (2004) BLR 179 61 Macob Civil Engineering Ltd v Morrison Construction Ltd (1999) BLR 93 20, 73 Mercury Communications Ltd v Director General of Communications (1996) 1 WLR 48 27 Modern Engineering (Bristol) v Gilbert-Ash (Northern) 1 Mohan Lal Mirpuri v Amarjit Singh Jass (1997) 56 ConLR 31 44 Monatech (M) Sdn Bhd v Jasa Keramat Sdn Bhd (2002) 4 CLJ 401 15 Mottram Consultants Ltd v Bernard Sunley & Sons Ltd (1975) 2 Lloyd’s Rep 197 14 MPM Constructions Pty. Ltd. v Trepcha Constructions Pty. Ltd. (2004) NSWSC 103 32 Musico & Ors v Davenport & Ors (2003) NSWSC 977 47 New South Wales case of Musico v Davenport (2003) NSWSC 977 63 Nikko Hotels (UK) Ltd v MEPC Plc (1991) 2 EGLR 103 28 Progressive Insurance Sdn Bhd v Kumpulan Perunding (1988) Sdn Bhd Pacol Ltd v Joint Stock Co Rossakhar (2000) 1 Lloyd’s Rep 109 40,41 63 Pembenaan Leow Tuck Chui Sdn Bhd v Dr Leela Medical Centre Sdn Bhd (1995) 2 MLJ 57 14 Project Blue Sky Inc. v Australian Broadcasting Authority (1998) 194 CLR 355 33 xii Reg v Gough (1993) AC 646 39, 55, 56 R v Camborne Justices, ex p Pearce (1955) 1 QB 41 39 R v Rand (1866) LR 1 QB 230 42 R v Sussex Justices, ex p McCarthy (1924) 1 KB 256 42 R J T Consulting Engineers Limited v D M Engineering (Northern Ireland) Limited (2002) EWCA Civ 270; (2002) 1 WLR 2344 RSL (South West) Ltd v Stansell Ltd (2003) EWHC 1390 Transgrid v Siemens Ltd (2004) NSWCA 395 63 47 34,52 Turner (East Asia) Pte Ltd v Builders Federal (HK) Ltd (1988) 2 MLJ 503 VC Jacob v Attorney-General (1970) 2 MLJ 133 45 30 xiii LIST OF ABBREVIATIONS AC - Appeal Cases All EL - All England Law Reports BLR - British Law Reports Con LR - Construction Law Reports CLJ Supp - Current Law Journal Supplement KB (or QB) - King’s (or Queen’s) Bench Lloyd’s Rep - Lloyd’s List Law Reports MLJ - Malayan Law Journal NSWSC - New South Wales Supreme Court WLR - Weekly Law Reports xiv LIST OF APPENDICES APPENDIX A TITLE Housing Grants, Construction and Regeneration Act 1996, United Kingdom B PAGE 83 Building and Construction Industry Security of Payment Act 1999, New South Wales 94 CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 Background of Study The origins of adjudication go back to the 1970s when it was introduced for a limited purpose in the construction industry between main contractor and sub contractor. At that time there were complaints that the main contractors were defaulting their payments to the sub contractors on the account of spurious claims of delay. After the case of Modern Engineering (Bristol) v Gilbert-Ash (Northern) 1 , the construction industry decided that for a main contractor to withhold payments to a sub contractor, he must notify the sub contractor of an intention with the ground of defense, set-off or counter-claim. Only then if dispute arises, it will be referred to an adjudicator, who will decide whether the amount disputed will be withheld or paid. The history of Statutory Adjudication can be traced to the introduction of the Housing Grants Regeneration and Construction Act 1996 (HGCRA 1996) which came into force in the United Kingdom in May 1998 pursuant to Sir Michael Latham reports “Constructing the Team” in 1994 which reported the woes of the UK’s 1 (1974) AC 689 2 construction industry. In his report, Sir Michael Latham recommended among other things that ‘a system of adjudication should be introduced within all standard forms of contract and that this should be underpinned by legislation’. This recommendation therefore led to the move from consensual adjudication to statutory adjudication. This was followed by New South Wales, Australia with the Building Industry Security of Payments Act 1999. Since then, the legislation has come into force in New Zealand, Victoria, Queensland, Western Australia and finally Singapore (Building and Construction Industry Security of Payment Act 2004) in April 2005. Lord Denning in his now famous judgment in the Court of Appeal in Dawnays Ltd v Minter Ltd 2 has this to say about construction disputes: “There must be cash flow in the building trades. It is the very lifeblood of the enterprise”. In his usual vintage style, Lord Denning did not mince his words in criticizing the frustrating effects of a long-drawn dispute resolution process, unfortunately common to construction disputes due to its complexity: “One of the greatest threats to cash flow is the incidences of disputes, resolving them by litigation is frequently lengthy and expensive. Arbitration in the construction industry is often as bad or worst”. Ask any contractor what is his constant headache or fear is and he will lament that it is not about being able to do a good job or getting the building built but the endemic problems of poor payment practices. These place unwarranted hurdles to 2 (1971) 1 WLR 1205 3 cash flowing smoothly downstream through the whole construction chain. In Malaysia, it is not uncommon to read press reports on the woes and cries from main contractors, subcontractors and suppliers on the shortcomings of the payment regime in the Malaysian construction industry. Nevertheless, such practices were never an issue during good times when jobs were aplenty and many contractors or even subcontractors will tolerate late payments or even part payments. However, these problems will magnify when the construction industry is deeply scathed by bleak market sentiments and falling construction demand. Several countries have enacted the legislation on Adjudication to ensure that regular and prompt payments for works under the contracts in the construction industry – to maintain progress payments under dispute. Under the legislation – claimants who provided works, goods and services can force the respondent to make payments on account. The scheme is thus a process which enables a dispute to be quickly decided on a provisional or interim basis. The scheme also provides for the Adjudicator’s decision to be immediately enforceable subject only to the final determination of the dispute in arbitration or litigation. The obvious attraction of the process of Adjudication is that it is a fairly quick process in comparison to arbitration or litigation. Whilst the objective of various Construction Contracts or Payment related Acts is consistent, the legislations in various jurisdictions lack uniformity, for instances, from the Notice of Referral, the Adjudicator has 28 days in United Kingdom, 10 working days in New South Wales, Australia, 20 days in New Zealand and 14 days in Singapore, to render a decision. Once the Adjudicator’s decision has been rendered, the winning party can enforce it summarily in the Court if the losing party refuses to comply with the Adjudicator’s decision. Therefore, the robustness of the Courts in dealing with jurisdictional challenges and the Court’s willingness to enforce the Adjudicator’s decision by way 4 of summary judgment must certainly have contributed to the enormous growth and widespread use of Adjudication. Statistics from United Kingdom has been encouraging. Since the implementation of Housing Grants Regeneration and Construction Act 1996 on May 1998, over 7500 cases have been referred to Adjudication and only 195 cases have been challenged in the Technology and Construction Court or TCC. It is undoubtedly an awesome record to have only about 2.6 percent of the Adjudicator’s decisions being challenged in the Court. In response to the growing concerns about cash flow problems, which are frequently encountered by main contractors, sub-contractors, suppliers in the construction industry in Malaysia, the construction industry, spearheaded by Construction Industry Development Board (CIDB) and Institute Surveyors Malaysia (ISM), is actively advocating the legislation on Adjudication in Malaysia. The enactment of the Adjudication Act will introduce new developments in our law. For instance, it provides for entitlement to progress payments to main contractors, subcontractors, and suppliers in construction and supply contracts and perhaps the consultants, even if no such entitlement is provided in their contracts. What is more important is that the commonly used ‘pay when pay’ provisions in construction contracts will be unenforceable. Statutory adjudication imposes prescriptive time limits to make payments and provides for an effective fast track adjudication to resolve payment disputes and the right to suspend work amongst other remedies where the adjudicated amount is unpaid. In short, it is about getting paid on time and in the amounts rightfully due. 5 Nevertheless, there is some misconception surrounding the use of adjudication namely that adjudication delivers ‘rough justice’ 3 . The issue which arises is the extent to which adjudication conducted under the intense time pressures and within the limitations envisaged for the process under the present legislations can be expected to observe the rules of fair play which are normally described as “natural justice”. Judge Bowsher QC in his judgment in the case of Discain Project Services Ltd v. Opecprime Ltd 4 observed the following: “… [One] has to recognize that the adjudicator is working under pressure of time and circumstance which makes it extremely difficult to comply with the rules of natural justice in the manner of a Court or an Arbitrator”. This research thesis is intended to provide a better understanding on the process of Adjudication to all practitioners in the Malaysia construction industry. More importantly, focus is given to determine the relevant of the principles of natural justice in adjudication. This paper is written based on a research on relevant decisions of the courts of United Kingdom and Australia, where the courts have interpreted provisions in their legislations that could be used as a useful guide and a valuable point of reference. 1.2 Problem Statement It has been suggested that, while the manner by which the principles of natural justice apply to arbitration and court proceedings have been well established, it may be unrealistic to expect adjudicators acting under severe time constraints in the context of the legislations to comply with these principles to the same extent. 3 Refer to the rough nature of its process; see Judge Humphrey Lloyd’s judgment in Balfour Beatty Construction Ltd v Lambeth London Borough Council (2002) EWHC 597. 4 (2000) BLR 402 6 Given that adjudication is but an imperfect mirror of arbitration in terms of objectives and hence the very nature of the processes involved, to what level of compliance to the principles of natural justice is expected of an adjudicator? Humphrey Lloyd QC J in his judgment in the English case of Balfour Beatty Construction Ltd v Lambeth London Borough Council 5 , concurred that, “principles of natural justice applied to adjudication may not require a party to be aware of the case that it has to meet in the fullest sense since adjudication may be inquisitorial or investigative rather than adversarial” Judge Bowsher QC in his judgment in the case of Discain Project Services Ltd v. Opecprime Ltd 6 observed the following: “… [One] has to recognize that the adjudicator is working under pressure of time and circumstance which makes it extremely difficult to comply with the rules of natural justice in the manner of a Court or an Arbitrator. Repugnant as it may be to one’s approach to judicial decision-making, I think the system created by the (HGCRA) can only be made to work in practice if some breaches of the natural justice which have no demonstrable consequence are disregarded”. Duncan Wallace, the learned editor of Hudson, called the HGCRA Act 1996, ‘pro-producer ’, ‘anti-customer’ and ‘anti-paymaster biases’ 7 . 5 (2002) EWHC 597 (2000) BLR 402 7 (2000) 16 Const LJ 102 6 7 1.3 Objective of the Study The concept of “natural justice” is normally understood in relation to the fairness of the procedures adopted for arbitration or courts proceedings. The primary objective of this research is to determine the relevant of the principles of natural justice in adjudication. This research is intended to enhance the confidence of practitioners in the Malaysian construction industry on the use of Adjudication in the construction industry as an effective alternative dispute resolution despite the rough nature of the process. 1.4 Scope and Delimitation of the Study This paper seeks to discuss the various dispute resolutions that are being practiced in the Malaysian and around the world namely, litigation, arbitration, mediation, adjudication, med-arb, conciliation, early neutral valuation, and dispute board. This research will review the existing legislations on adjudication. This research will also review the relevant published case law on adjudication and discussed the relevant decisions of the courts on the subject of the principles of natural justice. As the adjudication act has yet to be enacted in Malaysia, this research shall be limited to the relevant decision of the courts from countries that have enacted the act. 8 1.5 Research Methodology The methodology of this research is by way of literature review. Much has been written on the topic on adjudication and many books have been published on the regime under the adjudication act of various jurisdiction. This research will review those regimes and their provisions on the subject of the principles of natural justice. This research will also review the relevant case law with regards to adjudication and seek to investigate the interpretation of the principles of natural justice in adjudication by the courts. Case law journals are readily available through the Lexis-Nexis database via the Internet. Since this research is by way of literature review only, no surveys will be conducted. Therefore, the views and sentiments of those affected parties shall be based on the books and journals that have previously written. 1.6 Previous Research An extensive research was done by Sir Michael Latham and his report “Constructing the Team” (1994) was the backbone to the construction of the UK’s Housing Grant and Construction Regeneration Act 1996. Many books have been published on the regimes of the respective countries’ Adjudication Act. Many journals were also published on this topic. This research 9 will also review all the relevant court decisions on the issue on the principles of natural justice. 1.7 Significance of the Study Malaysian construction industry is proposing to the Government on the enactment of the Adjudication Act. Once the Act is adopted, it will introduce a totally new regime of claims, adjudications and enforcement procedures (including the right to suspend works and to exercise a lien on goods supplied) in the event of non-payment, all quite unfamiliar to the Malaysian construction industry. In the light of the tight timeframes and repercussions of the proposed Act, it is necessity for every practitioner in the construction industry to familiarize themselves on the subject of adjudication and its processes. Adjudication is constrained especially by the time within which a decision is required. Given that, construction dispute is known to be usually complex in nature, it will be a tall order for an adjudicator to meet the time constrain yet observe the principles of natural justice as seen in arbitrations and litigations. Failure to comply could then be the cause of the adjudicator’s decision being challenged. It is therefore, important to determine the level of compliance of the principles of natural justice in the adjudication process as this will help to instill confidence on the part of practitioner when adopting the system. CHAPTER 2 THE DELIMMAS IN THE CONSTRUCTION INDUSTRY CHAPTER 2 THE DILEMMAS OF THE CONSTRUCTION INDUSTRY 2.1 Introduction Disputes and claims are something that those involved in the construction industry must live with despite their best effort to avoid them. Nevertheless, how they choose to resolve their differences, however, is often something that is within their control. The decision should require careful deliberation because it can have a significant affect on the ultimate cost of the project. Imagine this: A contractor suffers significant cost overruns on a long, difficult and delayed project. There is finger pointing from start to finish and by the end of the construction, there is much resentment and distrust between the client and contractor or even the sub-contractors. Each of them has been severely wounded by the project and blamed each other for their respective pain. The contractor quantifies its pain and submits a ‘global impact’ claim at the end of the project 1 . 1 Refers to claims where the causal connection between the matters complained of and their consequences, whether in terms of time or money, are not fully spelt out. Also see Idris, N.J., et al., ‘Global Claims – The Way Forward’, Paper presented for the 11 The client is outraged. From the client’s perspective, the contractor’s claim have grossly mischaracterizes the facts of the project and thereby, ignores the contractor’s problem and refuses to comply with the contract provisions or establish a cause and effect relationship between the contractor’s allegations and cost claims. The client simply rejects the contractor’s claim. Believing that the only way to get his concerns heard by someone other than the ‘biased’ client that he dealt with, the contractor decides to commence legal proceeding. When the litigation starts, communication between the two stops and everything is filtered through their lawyers. As a result, both sides start forgetting their vulnerabilities and begin to fall in love with their positions. In addition, the payments they made to the lawyers and consultants get larger and more frequent and they begin to add up to be significant amounts of money but with no end in sight. The parties finally start to realize that litigation is very expensive and slow. Worse yet, they learn that they cannot control nor guarantee the outcome. It is then, only after a requisite amount of ‘blood letting’ has taken place, the parties decided to cut a deal that is driven more by the desire to stop the bleeding rather than by the merits of their position. Or after years of more legal expenses, the claim ultimately settles on the court house steps or in the courtroom itself by the people that had nothing to do with the project and for the amount that leaves both sides unsatisfied. Once, there is this contractor friend who made an observation that goes something like this: “All construction disputes have one thing in common – they are ultimately resolved either by surrender, compromise or in court. Anyone familiar with the legal proceedings will tell you that it is the second least preferable way.” Master of Science in Construction Contract Management course in UTM, 2005. Unpublished. 12 2.2 The Malaysian Scenario The construction industry is an important cog in the wheel propelling the Malaysian economy. The industry provides work for many ranging from professionals such as architects, engineers and surveyors to main contractors, sub contractors, suppliers and ultimately laborers who are employed by these contractors. The industry works and will only continue to work on the premises that these people are paid for work and services properly rendered. The quantum of payment for work and services rendered are often huge in the thousand, if not in the millions of Ringgit. Payment in any industry has generally been an issue of concern. In the construction industry, payment is an issue of major concern. The reasons among others can be listed as follows: 1. Unlike many other industries, the durations of construction projects are relatively long. 2. Contract sums involved are often relatively large. 3. Payment terms are usually on credit rather than payment on delivery. In common law, as observed in the case of Hoenig v Issacs 2 , the contractor in the absent of any express or implied provision (in their construction contract) for progress payments during the progress of work, he would not be entitled to claim for their work done unless he has substantially completed the work. Therefore, in the absence of the substantial completion, the contractor would not be able to claim for the percentage of work done or even on the basis of quantum meruit. This can be detrimental to the financial health of the contractor and incidentally, the contractor 2 (1952) 2 ALL ER 176 13 would end up being the financier of the project until such times that the work is substantially completed. Nevertheless, in the present Malaysian construction industry, the existing standard contract forms invariably provide for payments to be paid progressively (PAM 1998 – Clause 30) to the contractor for the duration of the project. These progress claims or payments are pegged to the work done or materials supplied and the standard forms of contract will also contain express provisions dealing with how these progress claims are to be evaluated. That notwithstanding, the construction industry is a dispute prone one. It is therefore not uncommon for the contractor pursuing his claim for the work done or materials or services rendered to meet with a counter claim instead for defective, delayed completion, etc. Therefore, payment is postponed until the resolution of the dispute. There can be multitude of reasons for the dispute. As it stands today, the legal enforcement of the claim and counter claim is unlikely to be summarily concluded but more likely to involve a protracted trial. This post to be a huge problem among main contractors, sub contractors, suppliers as their cash flow and profitability are often put in jeopardy. This scenario was clearly illustrated in the case of Pembenaan Leow Tuck Chui Sdn Bhd v Dr Leela Medical Centre Sdn Bhd 3 and Federal Court Judge Edgar Joseph echoed the problems: “It is well known to lawyers engaged in the field construction contract law that the question whether a building owner or main contractor is entitled to refuse to make payment of the money to a contractor or contractor, as the case may be, alleged due and payable under an interim certificate issued by an architect or engineer, pursuant to provisions in a RIBA contract and other 3 (1995) 2 MLJ 57 14 known forms of building contracts and sub contracts, on the ground that he has cross-claims alleging defective work or over-valuation or damages for delay, is a question of ever-recurring importance, which inevitably throws open for discussion the actual terms of the particular contract or sub contract in the case and the all too familiar trilogy of case of Dawnays Ltd v FG Minter Ltd & Anor (1971) 1 WLR 1205; 2 All ER 1389, Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd (1974) AC 689; (1973) 3 All ER 195; (1973) 3 WLR 421, Mottram Consultants Ltd v Bernard Sunley & Sons Ltd (1975) 2 Lloyd’s Rep 197 and their progeny.” The common modes of enforcement of construction claims in Malaysia are presently by way of litigation and arbitration. Litigation as noted earlier is expensive and it takes too long. On the other hand, arbitration can be marginally faster but it is also very expensive. On top of that, both the procedures can only commence upon the completion of the projects or when the contracts had been determined. This was illustrated in the case of Kah Seng Construction Sdn Bhd v Selsin Development Sdn Bhd 4 ; Judge Low Hop Bing held that; “In my judgment, it is trite law that a contractor can only terminate his contract with the employer (at common law, as opposed to the exercise of an express termination clause) if he shows, inter alia, a repudiatory breach by the employer in the sense that the employer has evinced an absolute refusal not to perform his side of the contract. There is no intermediate right in a building contract to suspend works. If the contractor insists on the continued performance of the contract, i.e. he affirms the contract; he must himself continue to perform his primary obligations under the contract, i.e. to continue performing the contract works. 4 (1997) 1 CLJ Supp 448 15 This is why suspension of the works by the contractor, i.e. not continuing with his primary obligations, becomes itself a repudiatory breach by the contractor. Even if the plaintiff can establish that the defendant is in repudiatory breach of contract, the plaintiff would have no right to suspend works, but instead would have had to elect to either terminate the contract or insist on the due performance. By suspending works without valid legal cause, the plaintiff has in fact repudiated its contractual obligations.” Therefore, under the standard forms of contract in Malaysia, the unpaid contractors are left with little option but to continue with the works and perhaps concurrently sue for the payments with interest. Alternatively, the contractors can opt to terminate the contract if the non payment is so serious that it constitutes a repudiatory breach as illustrated in the case of Ban Hong Joo Mines Ltd v Chen & Yap Ltd 5 . In other words, there is no guarantee that the unpaid contractor will be paid or that there are assets available for execution upon obtaining a successful result after a lengthy arbitration or litigation process. Nevertheless, there is the availability of the Mareva injunction procedure in Malaysia. To be successful in the Mareva injunction, the claimant has the onerous burden to proof that he has a good arguable case (and this is usually difficult in the light of counter claim and set-off). However, if the Mareva injunction is granted, there is some comfort to the contractor because breaching the injunctive order or even taking willful steps to frustrate the application to obtain the order might constitute contempt of court as shown in the case of Monatech (M) Sdn Bhd v Jasa Keramat Sdn Bhd 6 . Despite all that, the unpaid contractor is still an unsecured creditor. 5 6 (1969) 2 MLJ 83 (2002) 4 CLJ 401 16 2.3 Why Adjudication? Legislation providing protection for cash flow to the construction industry and introducing statutory adjudication has swept across the world. While it started in United Kingdom through the introduction of the Housing Grants Construction and Regeneration Act (HGCRA 1996) in 1998, it had since spread to four states in Australia, New Zealand and finally in Singapore in April, 2005. Cash flow in the construction industry is critical because of the relatively long duration of projects. Deficiency in cash flow in a corporation often led to insolvency. It is the effect of insolvency in each of the above countries’ construction industry that has been one the main factors driving the need for statutory adjudication to provide protection to cash flow in the construction industry. The Construction Industry Employers Council in the United Kingdom (UK) reported figures which were picked up by the Latham report titled “Constructing the Team”, shows that the total output for the UK construction industry in 1993 alone was over RM 320.7 Billion or about 8 percent of the UK Gross Domestic Product (GDP). From 1989 to 1994 in UK alone, over 35,000 business and companies became insolvent and almost a half a million jobs had been lost. In Australia, the Australian Corporate Reporting (ACR) 1998 reported that in June 1998, the number of insolvencies within the building and construction industry in New South Wales (NSW) was three times higher than any other state in Australia. This explained the reason why the state of New South Wales was the first to enact the adjudication Act. 17 In New Zealand, the Motu Economic and Public Policy Research 7 reported that for the period from 1989 to 1993 and 1997 to 2000, there were approximately 1000 involuntary liquidations in New Zealand per year and within the construction industry alone in New Zealand from January 2000 to January 2001, a sample of 13 construction related companies became insolvent with a consequent reduction in the total yearly output by NZ$315 Million (or 7.2 percent of the total New Zealand construction industry turnover that year). The total output for the New Zealand construction industry in 2000 was over NZ$4.4 Billion (RM11.8 Billion) or 4.2 percent of New Zealand Gross Domestic Product. Much has been said and written on statutory adjudication since the Housing Grants Construction and Regeneration Act (HGCRA 1996) came into operation in 1998. The legislation provides a statutory right to payment for work done, goods and materials supplied and services performed and consequently, improved the cash flow in the construction industry. It imposes prescriptive time limits to make payments and provides for an effective fast track dispute resolution to resolve payment dispute and the right to suspend work amongst other remedies where the adjudicated amount is unpaid. In short, it is about getting paid on time and in the amounts rightfully due. 2.4 Conclusion The payment predicament of the construction industry cannot be singly explained. All parties whether they are the owners, consultants, main contractors, sub contractors and suppliers have an important role and must act in concert to take ownership of the problems and challenges. 7 refers to Motu Economic and Public Policy Research working paper 03-18 dated February 2004 18 The adjudication Act when enacted simply means that a party who has carried out any construction works or supplied any goods or services under a construction contract is entitled to a statutory right to progress payment. The Malaysian Works Minister, Dato’ Seri S Samy Velu, confirmed at the International Forum for Construction Industry Payment Act and Adjudication in September, 2005 that the Malaysian Government is looking forward to have a legislation to improve our present poor payments practices in the Malaysia construction industry. Nevertheless, this proposed legislation if materialized will not be a panacea for all of the local construction industry ills and woes but for financial health sake, it will go a long way in throwing a vital lifeline. What it essentially means for the construction industry is simply a more disciplined approach. Prescribed time frames must be strictly complied with by all parties to avoid default consequences of failure to pay. The time limits to respond to claim applications and for making payments and quick adjudication embedded in the legislation to resolve payment dispute ensures cash flow are passed on downstream engendering security for payment due. Ultimately, the legislation will unsurprisingly impose a mindset change in the processing of and compliance with a protocol for progress payment. CHAPTER 3 THE NATURE OF ADJUDICATION CHAPTER 3 THE NATURE OF ADJUDICATION 3.1 Introduction For most of the construction industry in the United Kingdom, Australia, New Zealand and Singapore, adjudication now means a process by which within a short and defined time and with a curtailed procedure left primarily to the adjudicator, all disputes under most construction contracts have to be presented to, for preliminary determination by, a person (the adjudicator) who will not later be the arbitrator or the judge (unless of course the parties agree). The decision is binding (and is swiftly enforceable) until the dispute is considered and decided later by an ultimate tribunal. That tribunal considers the dispute on its own merits, without regard to the decision of the adjudicator so that there is, in this sense, no appeal from the adjudicator. Until that time arrives, there are very limited means of challenging or otherwise avoiding the result of the adjudication. The aims of adjudication are (or, rather, were) simply that a dispute is resolved in such a manner that the parties perforce have to put it behind them and get on with the contract or with the remainder of their relationship (if either still exists). The decision of an adjudicator may also give the parties a forecast of the 20 likely decision of the ultimate tribunal, whether an arbitrator or a judge. Obviously the reliability of any such prediction in turn depends upon the quality of the decision and the material and time available to the adjudicator, as well as, of course, the ability of the person involved. In 1993 Sir Michael Latham was asked by the government to inquire into and report on various malaises that were supposedly affecting the construction industry. Sir Michael produced his final report in July 1994: "Constructing the Team: Joint Review of Procurement of Contractual Arrangement in the UK Construction Industry." In his report he recommended amongst other things that; "a system of adjudication should be introduced within all standard forms of contract (except where comparable arrangements already existed for mediation or conciliation) and that this should be underpinned by legislation". This recommendation had led to the move from consensual adjudication to statutory adjudication. Malaysian construction industry is advocating the legislation and takes from the International Forum on Construction Industry Payment Act and Adjudication (September, 2005), in Kuala Lumpur, have indicated that a draft copy of the legislation will be ready to be debate in the Parliament this year. The forum also confirmed that the proposed legislation have received overwhelming support from the various parties in the Malaysian construction industry. The general nature of Adjudication was succinctly and clearly summarized by Dyson J in the landmark case of Macob Civil Engineering Ltd v Morrison Construction Ltd 1 in the following passage from his judgment at page 97, a passage which remains definitive and is well worth repeating: 1 (1999) BLR 93 21 “The intention of Parliament in enacting the Act was plain. It was to introduce a speedy mechanism for settling disputes in construction contracts on a provisional interim basis, and requiring the decisions of adjudicators to be enforced pending the final determination of disputes by arbitration, litigation or agreement: see s.108 (3) of the Act and paragraph 23(2) of Part 1 of the Scheme. The timetable for adjudications is very tight (see s.108 of the Act). Many would say unreasonably tight, aware of this. So far as procedure is concerned, the adjudicator is given a fairly free hand. It is true (but hardly surprising) that he is required to act impartially (s.108 (2) (e) of the Act and paragraph 12(a) of Part 1 of the Scheme). He is, however, permitted to take the initiative in ascertaining the facts and the law (s.108 (2) (f) of the Act and paragraph 13 of Part 1 of the Scheme). He may, therefore, conduct an entirely inquisitorial process, or he may, as in the present case, invite representations from the parties. It is clear that Parliament intended that the adjudication should be conducted in a manner which those with the grinding detail of the traditional approach to the resolution of construction disputes apparently find difficult to accept. But Parliament has not abolished arbitration and litigation of construction disputes. It has merely introduced an intervening provisional stage in the disputes resolution process. Crucially (Parliament) has made it clear that decisions of adjudicators are binding and are to be complied with until the dispute is finally resolved.” Nevertheless, statutory adjudication too had its fair share of critics and among its famous critics is none other than Duncan Wallace, the learned editor of Hudson. The author ridiculed the legislation that: “an adjudicator’s decision, if arrived at in serious breach of a principle of natural justice, must as a matter of law nevertheless be enforced in circumstances where payment under an invalid decision could turn out to be irretrievable and precipitate the insolvency of the party affected.” 22 Duncan Wallace went on to call the HGCRA Act 1996, ‘pro-producer ’, ‘anti-customer’ and ‘anti-paymaster biases’, he continued, “Parliament can only have intended adjudicators’ decisions validly arrived at on the merits or law of a properly referred dispute to be binding on the parties for the comparatively lengthy period which could be involved before final judgment or award and it is almost inconceivable that Parliament intended to accord to adjudicators’ decisions or conduct an immunity and enforceability not accorded by law to arbitrators and their awards or even to the judiciary and their judgments.” 3.2 Statutory Adjudication Statutory adjudication model is something of a hybrid. Unless the contract being a construction contract, as defined under various jurisdictions, it is made by law into a contract that does not comply. The process remains essentially contractual and, in principle, once a contract is made that complies with the Acts the parties are free to vary or waive its terms. Adjudication produces a decision that is binding, but not finally, as its effect can be altered by the tribunal ultimate competent to resolve the dispute that to the adjudication (or the dispute resulting from the adjudicator’s decision). It is not therefore arbitration; its characteristics are close to what English law recognizes in the determination of expert. It is in reality unequalled (sui generic) and, since it is essentially contractual, every case has to be considered carefully in case there are contractual which require to be observed. 23 3.3 Challenges to Adjudicator’s Decision The Acts in the various jurisdictions make it clear that the decision is provisionally binding and that the underlying dispute will be decided by the ultimate tribunal, court proceedings or arbitration, if the parties do not accept the decision or use it as a means of arriving at a settlement, although in practice this is apparently quite frequent. In legal terms the validity of the decision of an adjudication stems from the simple contractual proposition that if parties have agreed to leave a dispute to be resolved by a third party, such as an adjudicator, and to be bound by the decision, they will be held to their mutual promises. If enforcement is needed, e.g. of the amount which the adjudicator has decided is due, the claimant then commences proceedings in the courts. The defendant should not be able to deny that the sum is due since it is bound by the agreement to accept the decision as provisionally binding. Accordingly a party cannot escape the consequences of adjudicator decision since otherwise the contract will not be enforced in accordance with the parties’ intentions. In the case of Carrillion Construction Ltd v Devonport Royal Dockyard 2 , the Honorable Mr. Justice Jackson stated four simple principles that he considered applied to any consideration of the enforcement of adjudication’s decision. Devonport Royal Dockyard refits and refuels warships and nuclear submarines for the Royal Navy. In early 1997, the dockyard was privatized and at that time it was decided that the existing facilities should be upgraded and new facilities provided. Part of the purpose of these works was to enable the dockyard to refit and refuel the most recent classes of submarines employed by the Royal Navy. The Ministry of Defense engaged Devonport to carry out these works under a cost reimbursable contract with a target cost mechanism. 2 (2003) BLR 79 24 Devonport in turn engaged Carillion as subcontractor to carry out the upgrading of one of the docks, which included replacing the dock walls and base and constructing four new buildings. One of the new buildings was a decontamination building which would contain apparatus for removing nuclear contamination. The contract between Devonport and Carillion included an ‘Alliance Agreement’ which supplemented the provisions of the subcontract in order to promote partnering and harmonious relations between thee parties. The Alliance Agreement included a dispute resolution procedure which provided that disputes would first be referred to the ‘Alliance Board’ and then to the incongruously named ‘Star Chamber’. The original Star Chamber was an English court of law active in the Tudor and early Stuart periods which was abolished by parliament in the 1600’s, by which time its name had become synonymous with secret and irresponsible court proceedings. Nevertheless, neither the Alliance Agreement, the Alliance Board nor the Star Chamber proved up to the task of maintaining harmonious relations between the parties. The target cost, which was initially set at £56 million, rose by a series of steps contained in amendments to the contract to approximately £96 million. This was well below the figure of £114 million that Carillion was arguing for. Furthermore, disputes existed concerning the reimbursable costs due under the contract, including claims for defective works presented in a sum of some £21 million. With nowhere left to turn under the terms of the Alliance Agreement, Carillion served on Devonport a notice of adjudication in respect of these disputes. 25 Faced with the unenviable task of resolving these differences within 42 days, the adjudicator wisely directed that the parties should provide written summaries of their cases limited to four pages in length. The remaining referral and response documents were considerably more extensive however. Each party served numerous witness statements; expert reports and supporting documentation which in all amounted to some 29 lever arch files. In his determination, the adjudicator found substantially in favor of Carillion and ordered an immediate payment to Carillion of a sum in excess of £10 million. Unsurprisingly, Devonport declined to pay the sum due under the adjudicator’s decision. In order to justify their respective positions, both parties commenced proceedings in the Technology and Construction Court, Carillion claiming an order enforcing the adjudicator’s decision and summary judgment on its claim and Devonport claiming declarations that the adjudicator’s decision be regarded as invalid. The Honorable Mr. Justice Jackson carried out a very careful review of recent case law and concluded by restating four simple principles which he considered applied to any consideration of the enforcement of an adjudicator’s decision: 1. The adjudication procedure does not involve the final determination of anybody’s rights, unless all parties so wish; 2. The Court of Appeal has repeatedly emphasized that the adjudicator’s decisions must be enforced, even if they result from errors of procedure, fact or law; 3. Where an adjudicator has acted in excess of his jurisdiction or in serious breach of the rules of natural justice, the court will not enforce his decision; and 26 4. Judges must astutely examine technical defenses with a degree of skepticism consonant with the policy of the HGCRA 1996. Errors of law, fact or procedure by an adjudicator must be examined critically before the court accepts that such errors constitute excess of jurisdiction or serious breaches of the rules of natural justice. Based upon those four principles, Mr. Justice Jackson dealt with each of the challenges put forward by Devonport to resist enforcement of the adjudicator’s decision. Crucially, the fact that the adjudicator’s approach to the assessment of target cost might have embodied errors of both fact and law was insufficient to be characterized as an excess of jurisdiction. The evidence showed that the adjudicator had not simply carried out a judgment of Solomon, but had reviewed the material put forward by both parties in a manner that was perfectly appropriate considering the constraints under which he was operating and the sheer volume of evidence and intricate submissions which were thrust upon him. Similarly, Mr. Justice Jackson was satisfied that the adjudicator had properly considered and addressed Devonport’s claims for defects and whether he was right or wrong in his decision, it could not be said that he had acted in disregard of the rules of natural justice. Finally, Mr. Justice Jackson held that paragraph 20(c) of the Scheme for Construction Contracts provided a freestanding power to the adjudicator to award interest whether or not there was an express term contained within the contract for the payment of interest. In conclusion, Carillion obtained judgment in respect of the entirety of the adjudicator’s decision. 27 3.3.1 Erroneous Decision Long standing principles of law applicable to tribunals or third party decisions show that a decision will be binding even though it may be erroneous in fact, or possibly in law, and that a person charged with making a decision is not authorized to do anything other than apply principles of law. Therefore, in agreeing to adjudication, the parties have to accept that the adjudicator may err. If the decision is one of fact and within the authority given to the adjudicator then the courts cannot and will not interfere. In the case of Mercury Communications Ltd v Director General of Communications 3 , Lord Hoffmann J made this observation; “This is because the court’s views about the right answer to the question are irrelevant. On the other hand, the court will intervene if the decisionmaker has gone outside the limits of his decision-making authority.” In Beaufort Developments (NI) Ltd v Gilbert-Ash NI Ltd 4 , Lord Hope of Craighead echoed what Lord Hoffmann J earlier statement; “The powers of the architect or arbitrator, whatever they may be, are conferred by the contract. It seems to me more accurate to say that the parties have agreed that their contractual obligations are to be whatever the architect or arbitrator interprets them to be. In such a case, the opinion of the court or anyone else as to what the contract requires is simply irrelevant. To enforce such an interpretation of the contract would be something different from what the parties had agreed. Provisions of this kind are common in contracts for the sale of property at a valuation or goods which comply with a specified description. The contract may say that the value of the property or the question of whether the goods comply with the description shall be determined by a named person as an expert. In such a 3 4 (1996) 1 WLR 48 (1998) 2 All ER 778 28 case, the agreement is to sell at what the expert considers to be the value or to buy goods which the expert considers to be in accordance with the description. The court’s view on these questions is irrelevant.” This principle is directly relevant to objections to the enforcement of decisions which may be disguised as challenges to jurisdiction or authority. The court will leave them to be decided by the ultimate tribunal as the decision is only provisional and if wrong should then be put right. However, as Beaufort shows, a court will otherwise be able to scrutinize an adjudicator’s decision to see if it is within the authority given to the adjudicator. The case of Bouyques (UK) Ltd v Dahl-Jensen (UK) Ltd 5 bears a striking illustration. The Court of Appeal considered an adjudicator’s decision which was wrong as it failed to make allowance for retention. As a result Bouygues was ordered to pay £208,000 to Dahl-Jensen when Dahl-Jensen ought to have been ordered to pay Bouygues £141,000. It held that the decision was nevertheless valid and enforceable as it stood, since the adjudicator had acted within his jurisdiction. The Court endorsed the principle summarized by Knox J in Nikko Hotels (UK) Ltd v MEPC Plc 6 (a rent review case); “If he has answered the right question in the wrong way his decision will be binding. If he has answered the wrong question, his decision will be a nullity.” This statement has become somewhat of a talisman. It encapsulates what Lord Hoffman said. There now seems general agreement that an adjudicator should have express power to correct slips or mistakes but there is no implied power to do. 5 6 (1999) 70 ConLR 41 (1991) 2 EGLR 103 29 Mistakes of law might be considered separately, if only because an adjudicator’s jurisdiction may be limited (e.g. to disputes under the contract, as in the UK). If they are part of the question that was asked and about the contract little or nothing can be done about them. A recent decision of the Court of Appeal in England provides helpful guidance, C & B Concept Design Ltd v Isobars Ltd 7 , Sir Murray Stuart-Smith gave the judgment with which the other members agreed; “22. The real question is whether this error on the part of the Adjudicator went to his jurisdiction, or was merely an erroneous decision of law on a matter within his jurisdiction. If it was the former the Recorder was right to hold that summary judgment should not be entered. If it was the latter, then in my judgment the proper course, subject to any question of stay of execution, is that the Claimant is entitled to summary judgment. 23. The whole purpose of s. 108 of the Act, which imports into construction contracts the right to refer disputes to adjudication, is that it provides a swift and effective means of resolution of disputes which is binding during the currency of the contract and until final determination by litigation or arbitration. s.108 (3). The provisions of s.109-111 are designed to enable the contractor to obtain payment of interim payments. Any dispute can be quickly resolved by the Adjudicator and enforced through the courts. If he is wrong, the matter can be corrected in subsequent litigation or arbitration. 24. In Northern Developments (Cumbria) Ltd v J & J Nichols, His Honour Judge Bowsher QC cited with approval the following formulation of principles stated by His Honour Judge Thornton QC in Sherwood & Casson v Mackenzie(2000) 2 TCLR 418 , 7 (2002) EWCA Civ 46 30 (i) a decision of an adjudicator whose validity is challenged as to its factual or legal conclusions or as to procedural error remain a decision that is both enforceable and should be enforced; (ii) a decision that is erroneous, even if the error is disclosed by the reasons, will still not ordinarily be capable of being challenged and should, ordinarily, still be enforced; (iii) a decision may be challenged on the ground that the adjudicator was not empowered by the Act to make the decision, because there was no underlying construction contract between the parties or because he had gone outside his terms of reference; (iv) the adjudication is intended to be a speedy process in which mistakes will inevitably occur. Thus, the Court should guard against characterizing a mistaken answer to an issue, which is within an adjudicator’s jurisdiction, as being an excess of jurisdiction; (v) an issue as to whether a construction contract ever came into existence, which is one challenging the jurisdiction of the adjudicator, so long as it is reasonably and clearly raised, must be determined by the Court on the balance of probabilities with, if necessary, oral and documentary evidence. 25. I respectfully agree with this formulation. I would also add, as I have already pointed out, the provisional nature of the adjudication, which, though enforceable at the time can be reopened on the final determination.” In Malaysia and Singapore, the position that was adopted the courts here is similar to that of United Kingdom. This can be seen in the case of VC Jacob v Attorney-General 8 (High Court, Singapore), in this case Wee Chong Jin CJ referred 8 (1970) 2 MLJ 133 31 to the House of Lord’s case of Anisminic Ltd v Foreign Compensation Commission 9 , in which Lord Pearse at page 192 was found to have quoted the following; “The courts have, however, always been careful to distinguish their intervention whether on excess of jurisdiction or error of law from an appellate function. Their jurisdiction over inferior tribunals is supervision, not review. That supervision goes to two points: one is the area of the inferiorjurisdiction and the qualifications and conditions of its exercise; the other is the observance of the law in the course of its exercise. It is simply an enforcement of Parliament’s mandate to the tribunal. If the tribunal is intended on a true construction of the Act to inquire into and finally decide questions within a certain area, the courts’ supervisory duty is to see that it makes the authorized inquiry according to natural justice and arrives at a decision whether right or wrong. They will intervene if the tribunal asks itself the wrong question (that is, questions other than those which Parliament directed it to ask itself). But if it directs itself to the right inquiry, asking the right questions, they will not intervene merely because it has or may have come to the wrong answer, provided that this is an answer that lies within its jurisdiction.” 3.4 Determinations beyond the Stipulated Time Limits The existing legislations have no express provision on the consequences of the adjudicator’s determination if an adjudicator fails to deliver his determination within the stipulated time limits or he delivers it beyond the stipulated time. 9 (1969) 2 WLR 163 32 The issue of late adjudicator’s determination was considered in the New South Wales Supreme Court in the case of MPM Constructions Pty. Ltd. v Trepcha Constructions Pty. Ltd. 10 In this case, the adjudicator formally accepted the adjudication application on the 7th. January, 2004. Section 21(3)(a) of the New South Wales Act stipulated that the adjudicator must delivers his determination within 10 working days, that is 21st. January, 2004. However, the adjudicator only delivers his determination on 25th. January, 2004, claiming that he mistakenly calculated the relevant time limit. The respondent deemed the determination invalid and obtained an injunction to prevent the claimant from enforcing the determination. The court upheld the adjudicator’s determination with the following reasons; “(a) This is confirmed because where a determination is not made within the relevant time limit, the only relief that a claimant seems to have under the Act is that for which section 26 of the NSW Act applies, namely, to withdraw the application (within five business days after the claimant becomes entitled to withdraw the previous adjudication application) and make a new application, It would be anomalous if the effect of noncompliance with the period allowed by section 21(3) of the NSW Act results in the claimants being unable to seek adjudication of the dispute, that would not be an outcome consistent with the evident objects of the legislation. (b) Additionally, section 26 of the NSW Act provides that should an adjudicator fail to determine the adjudication application within the time allowed, the claimant may withdraw the application. However, if the effect of non-compliance with section 21(3) of the NSW Act was to render it no longer possible for the adjudicator to proceed to determination, or to render any purported determination a nullity then it must be the case that effectively, the adjudicator becomes funtus officio upon the expiry of the 10 (2004) NSWSC 103 33 relevant time limit under section 21(3) of the NSW Act. If that were the case then there would be nothing for the claimant to withdraw. (c) Section 29(4) of the NSW Act is also significant, in that it disentitles the adjudicator to payment of his fees if he does not comply with the section 21(3) of the NSW Act, but says nothing about the validity of any determination or purported determination issued outside the time limit. (e) The position, therefore, is that the NSW Act provides in two specific ways (section 26 and 29) for the consequences of non-compliance with the section 21(3) time limits. The NSW Act does not provide specifically for the further consequence for which the respondent contends, namely that the determination (having been made out of time) was invalid. (f) In these circumstances, if one asks ‘whether it was the purpose of the legislation that the determination was invalid’, those matters would suggest that the answer should be ‘no’. Indeed, the contrary answer would not be consistent with the stated purposes of the NSW Act. The court in agreeing with the principles as set out in the case of Project Blue Sky Inc. v Australian Broadcasting Authority 11 , concluded that it is unlikely that the legislation intended that an act done in breach of the time set out in section 21(3) of the NSW Act would be invalid, therefore, he upheld the adjudicator’s determination. \ 11 (1998) 194 CLR 355 34 3.5 Conclusion In statutory adjudication, a frequently encountered concern is that, since an adjudicator has to reach his decision under considerable time pressures, there is a risk that the material aspects of the dispute may be overlooked and mistakes may be committed by the adjudicator in arriving at his decision. While this concern may be overstated, the existing legislations expressly retain the right of the aggrieved party to challenge the adjudicator’s decision in arbitration or litigation. However, it is important to note that a challenge is not necessary an appeal against the decision of an adjudicator, it would follow that the court in determine the case for a challenge does not have to theoretically revisit the matters dealt with by the adjudicator with respect to both questions of fact and of law. Therefore, in considering whether the adjudicator has exceeded his jurisdiction, it is necessary for the court to launch into a review of those issues of fact and law which pertain to jurisdiction. While the premises on which an adjudication’s determination may be challenge are ostensibly limited, experiences in jurisdictions such as United Kingdom and Australia suggested that there remains sufficient incentive for challenges to be aggressively formulated where the quantum of the sums involved are substantial. One of the reasons which led the dispute in Transgrid v Siemens Ltd 12 to be carried out all the way to the New South Wales Court of Appeal was, no doubt, the fact that the payment claim in that instance was very close to A$17 million. Decisions from the decided cases have clearly demonstrated that a challenge should not be abused by a party who merely intends to defer the reckoning of the 12 (2004) NSWCA 395 35 adjudicated amount. It is obvious that the court will only likely to consider intervening and refusing to give a judgment on enforcing an adjudicator’s decision unless something has gone really wrong. In considering whether there are realistic grounds for not enforcing an adjudicator’s decision, the courts do not look at the merits of the dispute. Naturally if there were a palpable error then a court would be sympathetic but sympathy itself is not enough. Therefore, the realistic ground to challenge an adjudicator’s decision shall be that the adjudicator’s acted beyond his jurisdiction or that he breached the principles of natural justice. CHAPTER 4 NATURAL JUSTICE IN ADJUDICATION CHAPTER 4 NATURAL JUSTICE IN ADJUDICATION 4.1 Introduction The principles of natural justice are the minimum standards of fair decisionmaking imposed on persons or bodies acting in a judicial capacity. Where the relevant person or body is required to determine questions of law or fact in circumstances where its decisions will have a direct impact on the rights or legitimate expectations of the individuals concerned, an implied obligation to observe the principles of natural justice arises. In the event of a hearing taking place or a decision being reached which breaches the principles of natural justice, the person charged may seek a review of the hearing or decision in the courts. Therefore, in the case of an adjudication process, if the adjudicator is in any doubt as to the procedure he is proposing to adopted, he should seek legal advice on them. The concept of ‘natural justice’ is formulated under two principles; “Nemo judex in causa sua” - The first principle is that no man may be a judge in his own cause or simply, the rule against bias; and 37 “Audi aiteram partem” - The second principle is the right of each party to be heard or simply, the rule to ‘hear the other side’. An adjudication determination may be challenged on the ground that the adjudicators, in arriving at his determination, had breached the rules of natural justice. Duties expressly imposed on the adjudicators under various legislations varied, with UK scheme (paragraph 12) provides that: The adjudicator shall-act impartially in carrying out his duties and shall do so in accordance with any relevant terms of the contract and shall reach his decision in accordance with the applicable law in relation to the contract; and shall avoid incurring unnecessary expense. The New Zealand Act section 41 provides that; an adjudicator must: 1. Act independently, impartially, and in a timely manner; and 2. Avoid incurring unnecessary expense; and 3. Comply with the principles of natural justice; and disclose any conflict of interest to the parties to an adjudication; and 4. If paragraph (d) applies, resign from office unless those parties agree otherwise. The Singapore Act under section 16(3) is similar to the New Zealand Act section 41(a)-(c). However, the Australia Acts do not deal with the question of the adjudicator’s duties. 38 In the Guidance for Adjudicators, a publication by Construction Umbrella Bodies Adjudication Task Group in United Kingdom accepts that; “the adjudicator has to conduct the proceedings in accordance with the rules of natural justice or as fairly as the limitations imposed by Parliament permit”. Since a decision cannot be challenged because, although authorized, it is only natural that an aggrieved party might wish to say that he was not fairly treated and accordingly question the decision. This has to be avoided if confidence in the system is to be maintained. As the quotation by the Guidance for Adjudicators recognizes, fairness is relative. Obviously “audi alterem partem” that is, being given a reasonably adequate opportunity to know and to be heard on the case against you. That includes points taken by the adjudicators. If an adjudicator has been selected for practical experience then the adjudicator is entitled to use it to assess what is learned and to arrive at a decision but the adjudicator may also use it to supplement other evidence. However if the practical experience could bear on the decision, the parties (and certainly the party affected) ought to be told of it, if forms part of the case to be met. An adjudicator may be empowered, and indeed required, to ascertain both the facts and the law. Arbitrators are frequently so empowered. However it is a mistake to think that such powers, commonly but not entirely accurately called ‘inquisitorial’, may be employed without regard to the rights of the parties to know the case they have to meet and to be given an opportunity in dealing with it. Those used to adversarial procedures and to the contractual and business practices based on dispute being resolved in that way must be careful before embarking on exercises with which they may not be familiar, even though they may have the best of intentions. Equally it is a mistake to think that the full panoply of the rules of natural justice apply to a procedure which is not final and which only binding provisionally. 39 4.2 Rule Against Bias The two main aspects of this rule are that a person adjudicating on a dispute must have no pecuniary or proprietary interest in the outcome of the proceedings and must not reasonably be suspected, or show a real likelihood of bias. Therefore, in an adjudication process, the adjudicator must be able to show that he has conducted a full enquiry into the circumstances involved before making his decision as to whether a breach has occurred, if so, what sanction should be imposed. There should be no suggestion in his conduct of the hearing that prior to its commencement, he has irrevocably decided on the outcome. In the case of Reg v Gough 1 , the House of Lords made it clear that in English law, the more stringent test of ‘real danger’ of bias should be applied in all proceedings whether in Court or in other tribunals or in arbitration. Lord Goff of Chieveley at page 669 considered cases concerning allegations of bias on the part of an arbitrator and found that the test adopted: “…has been whether the circumstances were such that a reasonable man would think that there was a real likelihood that the arbitrator would not fairly determine the issue on the basis of the evidence and arguments adduced before him… Such a test is, subject to the introduction of the reasonable man, consistent with the conclusion which I have reached, provided that the expression ‘real likelihood’ is understood in the sense I have described, i.e. as meaning that there is a real possibility or, as I would prefer to put it, a real danger of bias.” 1 (1993) AC 646 40 The case was cited with approval in various local cases. The test was also applied more recently by Judge Nik Hashim in Kuala Ibai Development Sdn Bhd v Kumpulan Perunding (1988) Sdn Bhd 2 In the case the learned judge held that a single telephone conversation to counsel of one party without the knowledge of the other party constituted gross misconduct. Also in Kuala Ibai case, the arbitrator after receiving the submission of counsel for the parties on an issue of law, went ahead to obtain a legal opinion without the knowledge or consent of the parties. He then in an interim award directed that two of the parties should be liable for the cost of the opinion. Nik Hashim J held that the arbitrator had misconduct himself because he was appointed to decide the dispute and therefore the arbitrator must make his own decision and not delegate to another or adopts the legal adviser’s decision as his own. The same test has also been applied by the Malaysian Court of Appeal in Hock Hua Bank (Sabah) Bhd v Yong Liuk Thin 3 and Progressive Insurance Sdn Bhd v Gaya Underwriting Services 4 . It is commonly perceived but in our erroneous view often expressed that once one of the parties has lost or claims to have lost confidence in an arbitrator, the arbitrator should stand down or be removed on the grounds that ‘justice should not only be done but seen to be done’. However the above pair of Malaysian Courts of Appeal cases shows clearly that the arbitrator should take a stronger and more robust position when he is personally satisfied that he is unbias and able to do justice between the parties. The Hock Hua Bank case did not involve an arbitrator but the principles enunciated may be applied to the arbitration parties. In that case a High Court had heard an interlocutory injunction application in a case and in ruling on that matter had expressed strong views on the nature of evidence. When the case was up for trial, one of the parties made an application to disqualify the Judge from hearing the trial on the basis of the remarks made by him at the injunction stage. The Judge did not find any substance in the grounds raised for the disqualification, but nevertheless 2 (1999) 5 MLJ 137 (1995) 2 MLJ 313 4 (1997) 3 MLJ 524 3 41 decided to disqualify himself for fear of accusations that he might be more accommodating to that party at the trial to dispel the allegations of bias. The Court of Appeal allowed the appeal and directed the same Judge to hear the trial. The substance of their reasoning can be found in the judgment of Sri Ram JCA at page 222H to 223B of the report; “Secondly, a judicial must decide any question presented to him for decision in the light of the objective facts and in accordance with settled principles. On no account should his personal sentiment enter upon the scene. Criticism of a judge is part of the territory in which he operates. So long as that criticism is made bona fide, based on the fact and in conformity with the law, none, least of all a judge, should mind: for there is no acquisition of knowledge without criticism. Over-sensitivity to criticism may result in ignorance, or much worse, intellectual arrogance. To decide a point in fear of criticism is to abdicate duty. These are matters that form part of a wellrecognized judicial philosophy and should require no reiteration. In my judgment the learned judge failed to act in accordance with these principles. He decided upon disqualification, not on grounds argued before him. The record makes no mention of the grounds relied upon by him as ever having been put to either side. His fear that an allegation may later be made against him is a non sequitur. In his carefully reasoned judgment, the learned judge was at pains to points out his lack of prejudice. Yet he was not prepared to bear the case. That to my mind is wrong”. In the Progressive Insurance case, the arbitrator took a stronger stand. One of the parties requested the arbitrator to stand down as the arbitrator on the grounds of a rather tenuous connection between a company of which the arbitrator was a director and the other to the arbitration. The arbitrator rejected the request holding that there was no conflict or bias and no question of his discharge. After that, the party making the application informed the arbitrator that it did not intend taking any further part in 42 the proceedings, and the arbitrator proceeded to make his award. That party then moved to have the award set aside on the ground of the arbitrator’s misconduct. The High Court granted an application to set aside the award, but on appeal, the decision was reversed and the award reinstated. The approach taken by Mahadev Shanker JCA in the Court of Appeal is instructive. After stating at page 529C that it was ‘a serious thing to allege bias against an arbitrator’ and finding the objection devoid of any merit, went on to say at page 530 B-F; “In Hock Hua Bank (Sabah) Bhd v Yong Liuk Thin & Ors (1995) 2 MLJ 213, this court dealt in some depth with the test for a real likelihood of bias. We only need to repeat a passage from R v Camborne Justices, ex p Pearce (1955) 1 QB 41 at page 51-52 (also at (1954) 2 All ER 850 at page 855) where Slade J formulates the test prescribes by Blackburn J in R v Rand (1866) LR 1 QB 230 at page 232 thus: Mahadev Shanker JCA on quoting the words of Lord Hewart in R v Sussex Justices, ex p McCarthy 5 continued: “The frequency with which allegations of bias have come before the courts in recent time seems to indicate that Lord Hewart’s reminder in R v Sussex Justices, ex p McCarthy (1924) 1 KB 256 at page 259, that it ‘is of fundamental importance that justice should not only be done, but should manifestly and undoubtedly be seen to be done’ is being urged as a warrant for quashing convictions, or invalidating orders upon quite unsubstantial grounds and, indeed, in some cases upon the flimsiest pretexts of bias. Whilst endorsing and fully maintaining the integrity of the principle reasserted by Lord Hewart, this court feels that the continued citation of it in cases to which it is not applicable may lead to the erroneous impression that it is more important that justice should appear to be done than that it should in 5 (1924) 1 KB 256 43 fact be done. Mr. Sinsua’s pretexts were intended to create a sinister impression which the facts do not support.” The message from a reading of these two important cases is clear. The emphasis should be on substance over appearance. An arbitrator should not step down although it may be attractive for him to do so on the grounds that ‘justice should be seen to be done’ just because one party claims to have lost confidence in him, if he himself feels he can proceed without danger of bias. One of the reasons for this is obvious. If a party or his counsel can easily bring about the resignation or removal of an arbitrator by simply alleging loss of confidence when he perceives that the case is not going well for him, then justice will be frustrated. If arbitrator A resigns or is removed from the office on such basis, what is to stop the same party making a similar complaint in respect of the replacement arbitrator? One often hears complaints by claimants in arbitration that the arbitrator is biased because he has made open comments tending to be dismissive of that claimants case. To avoid such complaints some arbitrator play safe by retaining a studious silence during the hearing; this is a tendency which is more common in the local environment than in the western world, where arbitrators are more likely to be vocal. It should be clear that an arbitrator is not biased or in danger of showing bias merely because he expresses strong views as the case proceeds. He is perfectly at liberty to do so. In Glencot Development and Design Co. Ltd. v Ben Barrett & Son (Contractors) Ltd. 6 , both parties actually invited Mr. Talbot, the adjudicator, to act as a mediator and as a result to his effort, the parties managed to agree on the valuation 6 (2001) BLR 207 44 of a particular claim but not the rest of the disputes. Mr. Talbot was again appointed the adjudicator for the rest of the disputes. The real issue here is the test of impartiality, namely whether the circumstances would lead a far-minded and informed observer to conclude that there was a real possibility of or a real danger that the adjudicator was biased. The court ruled that an adjudicator has to conduct the adjudication proceedings in accordance with the principles of natural justice or as fairly as limitations imposed by the Parliament. In the course of his judgment, Humphrey Lloyd QCJ emphasized that there was no question of actual bias on the part of the adjudicator, however, this was a case of apparent bias and this is considered sufficient to raise the prospect of bias on the adage that justice must not only be done but must be seen to be done. Therefore, the court held that there were real prospects that the adjudicator in this situation was no longer impartial as a result of his role as a mediator and consequently, it was held that the adjudicator’s decision was not enforceable. The learned observed the following: “Accordingly is Mr. Talbot’s conduct such as to be regarded as ‘impartial’? It must be emphasized that there is not a question of actual bias. It is a case of ‘apparent bias’…Hence there is a need for an objective test. The views of the person involved are either irrelevant or not determinative. The test is whether the ‘Circumstances would lead a fair-minded and informed observer to conclude that there was a real possibility or real danger, the two being the same, that the tribunal was biased’. In the case of Disdain Project Services Ltd. v Opecprime Development Ltd. 7 , Bowsher J held that the court would refuse to enforce an adjudicator’s decision if there had been a serious and substantial breach of the principles of natural justice. In this case, the adjudicator had failed to afford the other party an opportunity to deal with the submissions from its opponent. Having considered all the witnesses 7 (2001) CILL 1698 45 evidence, the judge found that there were serious risk of appearance of bias in the adjudicator’s failure to consult one party on the submissions made by the other party and consequently, the judge refused to enforce the award. This case concerned the conduct of the adjudicator in the adjudication proceeding. There were allegations that the adjudicator received telephone calls from the claimant’s surveyor, who was representing the claimant in the adjudication proceeding and this was confirmed at the trial. The respondent therefore applied to the court to invalidate the award because they were not informed of the contents of the conversation. The learned judge held that there was a breach of the principles of natural justice that: “…in my view, the adjudicator did not act in accordance with the rules of natural justice nor, in the words of Humphrey Lloyd QC did he conduct the proceedings ‘as fairly as the limitations imposed by the Parliament permit’. The limitations imposed by Parliament did not require the telephone conversations of which the complaint is made.” But in the case of Turner (East Asia) Pte Ltd v Builders Federal (HK) Ltd 8 the Singapore High Court applied the test of ‘reasonable suspicion’ i.e. would a reasonable and fair minded person sitting in court and knowing all the relevant facts have a reasonable suspicion that a fair trial for the applicant was not possible. This case is an instructive example of a case where the arbitrator has become too vocal in his constant criticism of one party and ended up on being removed for misconduct. While an arbitrator is certainly free to comment on the merits of any point in the arbitration, he should be careful to avoid giving the appearance to the parties that he has already made up his mind that the case is as good as over. 8 (1988) 2 MLJ 503 46 4.3 Rule to ‘hear the other side’ In respect of the rule to ‘hear the other side’, the adjudicator should refrain from making a particular determination on a ground for which neither party has contended without affording the parties notice of the same and an opportunity to respond. Each party must be afforded an opportunity to advance his case before the tribunal and to adduce evidence in support of his case. In Malaysia, the governing Article of the Constitution on this point is article 135(2) which came into operation on the Merdeka Day (31 August 1957): “135(2) No member of such a service as aforesaid (the police service is one of (these) shall be dismissed or reduced in rank) without being given a reasonable opportunity of being heard.” In the case of Interbulk Ltd v Aiden Shipping Co Ltd (‘The Vimeira’) 9 , the UK Court of Appeal was concern with an arbitrator’s decision, made on the basis of a point which was never raised as an issue or argued before the arbitrators. In concluding that there was technical misconduct on the part of the arbitrators which resulted in unfairness to the chatterer in that instance, Judge Goff confirmed that: “…(t)here is plain authority that for arbitrators so to decide a case, without giving a party any warning that the point is one which they have in mind and so giving the party no opportunity of dealing with it, amounts to technical misconduct and renders the award liable to be set aside or remitted.” 9 (1984) 2 Lloyd’s Rep 66 47 In Musico & Ors v Davenport & Ors 10 , Judge McDougall put the matter simply as follow: “If an adjudicator is minded to come to a particular determination on a particular ground for which neither party has contended then, in my opinion, the requirements of natural justice require the adjudicator to give the parties notice of that intention so that they may put submissions on it.” In the case of Balfour Beatty Construction Ltd v Lambeth Borough Council 11 , in a dispute involving delay claims, neither party furnished the adjudicator with a proper delay analysis to support their position. The adjudicator took it upon himself to conduct a delay analysis and there upon apply the result of the analysis to the adjudication without the consent from the parties. It was held that the adjudicator had committed a breach of the principles of natural justice because, when he did this, the adjudicator did not afford the parties an opportunity to review and address their position as to the adjudicator choice of method and analysis. In effect, the adjudicator simply denied the parties the opportunity from being heard. In RSL (South West) Ltd v Stansell Ltd 12 , the adjudicator in this case with the consent of the parties, engaged a planning expert to assist him with a dispute involving claim of extension of time to a construction contract. The parties consented the employment of the expert was subject to the condition that they would be given the opportunity to review the expert’s finding. However, when the expert’s preliminary advice was forwarded to the parties, Stansell found that the preliminary advice was to their favor and thereby decided that there was no need to ask for the final report. Stansell was completely shocked when they received the adjudicator’s decision, which was based on the expert’s final report, which turned out to be against them. The Court held that the adjudicator had breach the principles of natural justice 10 (2003) NSWSC 977 (2002) EWHC 597 12 (2003) CILL 2012 11 48 by not extending a copy of the expert’s final report to Stansell and therefore, he did not afford Stansell the opportunity to review and comment on the final report. The principles of natural justice demand that a party in any judicial or tribunal proceedings is entitled to address the evidence and submissions made by the other party. In Mohan Lal Mirpuri v Amarjit Singh Jass 13 , an arbitrator in a “document only” arbitration made an award notwithstanding that he was aware that one party had not received the other party’s document. In fact the solicitor for the aggrieved party knew about the documents but made no effort to obtain them. The Court held that this did not excuse the arbitrator’s failure to ensure that parties right to be heard and thereby, the award was remitted. In Government of Ceylon v Chandris 14 , Megaw LJ stated the principles as follows: “It is…a basic principle…that no one with judicial responsibility may receive evidence, documentary or otherwise, from one party without the other party knowing that the evidence is being tendered and being offered an opportunity to consider it, object to it, or make submissions on it. No custom or practice may over-ride those basic principles.” An adjudicator is duty bound to ensure that all copies of reports and submissions submitted by one party must be extended to the other party. Similarly, copies of correspondence and exchanges between an adjudicator and any parties should be likewise extended to the other parties. Where one party seeks the audience of the adjudicator, the other party should be notified and afforded an opportunity to attend. 13 14 (1977) 56 ConLR 31 (1963) 2 QB 327 49 4.4 Conclusion Where an adjudicator takes upon himself to conduct investigation or direct questions at the witnesses, he must do so in a manner which leaves the parties in no doubt that he has taken a balanced and fair approach to the adjudication process. Thus if the adjudicator received information from whatever source and if such information might have some bearing on his decision, both parties must be informed of this so that they are afforded the opportunity to comment or respond. This requirement to take a balanced approach is similar to that which is expected of an arbitrator. Nevertheless, while the idea of extending the criteria of impartiality or simply the principles of natural justice may appear to be essential, then again it must be noted that the principle behind the adjudication legislation intends the adjudication process to be exceptional and summary procedure, offering only an interim determination of a dispute. Furthermore, the inquisitorial character of adjudication as opposed to the adversarial nature of arbitration proceedings and the fact that the proceedings have to be compressed within a truncated time frame are factors which must invite a different perspective on the principles of natural justice are to be projected. While an arbitrator’s conduct is confined largely to the receiving of submissions and applications, presiding at hearings and making rulings, in appropriate circumstances, nevertheless, the adjudicator has to take the initiative to investigate the facts surrounding the dispute and direct questions at witnesses and experts. In particular, it is almost impossible for adjudicators to permit parties unfettered latitude to present their full arguments on every conceivable issue within the limited time frame. 50 The better view, therefore, as also being rightfully interpreted by the courts is that, whilst both the adjudicators and arbitrators are required to observed the principles of natural justice in the conduct of their respective dispute resolution proceedings, the extend of compliance which an adjudicator is expected to display must necessarily take into account the different circumstances of adjudication as compared to arbitration. CHAPTER 5 BREACH OF THE PRINCIPLES OF NATURAL JUSTICE CHAPTER 5 BREACH OF THE PRINCIPLES OF NATURAL JUSTICE 5.1 Introduction An adjudication determination may be challenged on the ground that the adjudicator, in arriving at his determination, breached the principles of natural justice. It is interesting to note that only the New Zealand and Singapore Act which came in force in year 2002 and 2005 respectively provided an express provision on the principles of natural justice. The Housing Grants Regeneration and Construction Act 1996 which was enacted in 1998 only address the adjudicator’s duties, whereas, there is no equivalent provision extending the principles of natural justice to adjudications under the Australia Acts. The probable explanation would be that New Zealand and Singapore being the latest jurisdictions to have enacted adjudication found the need for the specific provision due to the high number of cases being challenged in court on the subject of principles of natural justice. The principles of natural justice have been considered in many English decisions in the context of adjudication. 52 5.2 The Position of Various Jurisdictions Although the New Zealand and Singapore Acts expressly required the adjudicators to comply with the principles of natural justice, it is not readily apparent that non-compliance to the principles of natural justice would render adjudication’s determination void. Nevertheless, the Acts also did not specify the ground in which the enforcement of the adjudication’s determination may be overturn by the Court. The British authorities through the numerous court decisions appear to suggest that the results of any breach of natural justice would depend on whether the breach relates to “a point or issue which is decisive or of considerable potential importance to the outcome”. In the British case of Balfour Beatty Construction Ltd v Lambeth London Borough Council 1 , the English Technology and Construction Court (TCC) basically set the tone of the English authority when Judge Humphrey Lloyd considered that; “the principles of natural justice applied to adjudication may not require a party to be aware of the case that it has to meet in the fullest sense.” The position of New South Wales, despite the absent of the express provision on the principles of natural justice, was largely re-stated as a result of two Court of Appeal’s decision in Brodyn Pty Ltd v Davenport 2 and Transgrid v Siemens Ltd3 . In his judgment in Brodyn Pty Ltd v Davenport 4 , Judge Hodgson considered that in order for an aggrieved party to resist the enforcement of an adjudicator’s decision, the respondent has to show that the determination did not satisfy the conditions laid down by the Act, in which he called, ‘the basic and essential requirements’ as opposed to, ‘more detail requirements’, which require exact compliance. In addition to the ‘the basic and essential requirements’, the judge insisted that there must have been ‘a bona fide attempt by the adjudicator to exercise the relevant power relating to the subject matter of the legislation’ and there must be ‘no substantial denial of the 1 (2002) EWHC 597 (2004) NSWCA 394 3 (2004) NSWCA 395 4 (2004) NSWCA 394 2 53 measure of natural justice that the Act requires to be given’. Therefore, a breached of the principles of natural justice, at least to the extent demanded by the Act, could render the adjudication’s determination void. The recourse available to an aggrieved party when faced with the adjudicator who had breached the principles of natural justice would be to seek an injunction from the Court to establish that the determination is void. The rules of natural justice have been considered in a number of English decisions in the context of adjudication which can be taken as a useful guide. 5.2.1 Discain Project Services Ltd v Opecprime Development Ltd 5 In Discain Project Services Ltd v Opecprime Development Ltd 6 , Bowsher J held that the court would refuse to enforce an adjudicator’s decision if there had been a serious and substantial breach of the rules of natural justice. In that case, the adjudicator had failed to afford the other party an opportunity to deal with submissions from its opponent. Having considered all the witness evidence, the judge found that there had been a serious risk of the appearance of bias in the adjudicator’s failure to consult with one party on the submissions made by the other party and, consequently, refused to enforce the award. The case concerned the conduct of the adjudicator in the adjudication proceedings. There were allegations, which were subsequently confirmed at trial, that the adjudicator received telephone calls from the claimant’s surveyor, who represent the claimants in the adjudication. The respondent applied to court to invalidate the adjudicator’s decision, as they were not fully informed of the contents of the 5 6 (2001) BLR 285 Ibid 54 communications, which were initiated in most cases by the claimant’s representative. The learned judge held in concluding that there was a breach of natural justice that: “... in my view, the adjudicator did not act in accordance with the rules of natural justice nor, in the words of Judge Humphrey Lloyd QC did he conduct the proceedings ‘as fairly as the limitations imposed by Parliament permit’. The limitations imposed by Parliament did not require the telephone conversations of which complaint is made.” 5.2.2 Glencot Development and Design Co Ltd v Ben Barrett & Son (Contractors) Ltd 7 In Glencot Development and Design Co Ltd v Ben Barrett & Son (Contractors) Ltd 8 , Humphrey Lloyd QC J reviewed authorities on the meaning of bias. The learned judge guidance in the case of Re Medicament and Related Classes of Goods (2001) 1 WLR 700, on the meaning of bias: “83 We would summarize the principles to be derived from this line of cases as follow of cases as follows. (1) If a judge is shown to have been influenced by the actual bias, his decision must be set aside by actual bias. (2) Where actual bias has not been established the personal impartiality of the judge is to be presumed. 7 8 (2001) 80 ConLR 14 Ibid 55 (3) The court then has to decide whether, on an objective appraisal, the material facts give rise to a legitimate fear that the judge might not have been impartial. If they do the decision of the judge must be set aside. (4) The material facts are not are ascertained were apparent to the applicant. They are those which are ascertained upon investigation by the court. (5) An important consideration in making an objective appraisal of the facts is the desirability that the public should remain confident in the administration of justice. 84 This approach comes close to that in R v Gough 9 . The difference is that, when the Strasbourg court considers whether the material circumstances give rise to a reasonable apprehension of bias, it makes it plain that it is applying an objective test to the circumstances, not passing judgment on the likelihood that the particular tribunal under review was in fact biased. 85 When the Strasbourg jurisprudence is taken into account, we believe that modest adjustment of the test in R v Gough 10 . is called for, which makes it plain that it is, in effect, no different from the test applied in most of the Commonwealth and in Scotland. The court must first ascertain all the circumstances which have a bearing on the suggestion that the judge was biased. It must then ask whether those circumstances would lead a fair minded and informed observer to conclude that there was a real possibility, or a real danger, the two being the same, that tribunal was biased. 86 The material circumstances will include any explanation given by the judge under review as to his knowledge or appreciation of those 9 [1993] 2 All ER 724, [1993] AC 646 [1993] 2 All ER 724, [1993] AC 646 10 56 circumstances. Where that explanation is accepted by the applicant for review it can be treated as accurate. Where it is not accepted, it becomes one further matter to be considered from the viewpoint of the fair-minded observer. The court does not have to rule whether the explanation should be accepted or rejected. Rather it has to decide whether or not the fair-minded observer would consider that there was a real danger of bias notwithstanding the explanation advanced. Thus in R v Gough 11 , had the truth of the juror’s explanation not been accepted by the defendant, the Court of Appeal would correctly have approached the question of bias on the premise that the fair-minded onlooker would not necessarily find the juror's explanation credible.” 5.2.3 Balfour Beatty Construction Ltd v Lambeth London Borough Council 12 The observations of Humphrey Lloyd QC J with respect to breaches of the principles of natural justice in the context of adjudication in the English case of Balfour Beatty Construction Ltd v Lambeth London Borough Council 13 also shed light on this subject. Although the case was decided in the context of a JCT contract, the honorable judge held at paragraph 29 of his decision that: “...in my judgment, that which is applicable in arbitration is basically applicable to adjudication but, in determining whether a party has been treated fairly, Or if) determining Whether all adjudicator lids acted impartially, it is very necessary to bear in mind that the point or issue which is to be brought to the attention of the parties must be one which is either decisive or of considerable potential importance to the outcome and not peripheral or irrelevant. It is now clear that the construction industry regards 11 [1993] 2 All ER 724, [1993] AC 646 (2002) EWHC 597 13 Ibid 12 57 adjudication not simply as a staging post towards the final resolution of the dispute in arbitration or litigation but as having in itself considerable weight and impact that in practice goes beyond the legal requirement that the decision has for the time being to be observed. Lack of impartiality or of fairness in adjudication must be considered in that light. It has become all the more necessary that, within the rough nature of the process, decisions are still made in a basically fair manner so that the system itself continues to enjoy the confidence it now has apparently earned. The provisional nature of the decision also justifies ignoring non-material breaches. Such errors, if apparent (as they usually are), will be rectified in any negotiation and settlement based upon the decision. The consequence of material issues and points is that the dispute referred to adjudication will not have been resolved satisfactory by any fundamental standard and the chances of it providing the basis for a settlement are much less and the chances of it proceeding to arbitration or litigation are much greater. However the time limits, the nature of the process and the ultimately non-binding nature of the decision, all mean that the standard required in practice is not that which is expected of an arbitrator. Adjudication is closer to arbitration than an expert determination but it is not the same.” The learned judge had to consider whether the adjudicator was obliged to inform the parties of the information obtained from his own knowledge and experience or from other sources and of the conclusions which he might reach, taking those sources into account. The judge ruled that the adjudicator was so obligated and there as a breach of natural justice, holding that reason lay, at least in part, in the requirement that: “... the adjudicator should act impartially. That must mean that he must act in a way that will not lead an outsider to conclude that there might be an element of bias, I.e. that a party has been treated fairly. In addition impartiality implies fairness although its application may be trammeled by the overall constraints of adjudication. Lack of impartiality carries with it overtones of actual or apparent bias when in reality the complaint may be 58 characterized as lack of fairness. Judge Bowsher QC put it very well in Disdain Project Services Ltd v Opecprime Development Ltd (2001) BLR 285, when he said at page 405: ‘I do understand that adjudicators have great difficulties in operating this statutory scheme, and I am not in any way detracting from the decision of Macob. It would be quite wrong for the parties to search around for breaches of the rules of natural justice. It is a question of fact and degree in each case, and in this case the adjudicator overstretched the rules. That scheme makes regard for the rules of natural justice more rather than less important. Because there is no appeal on the fact or law from the adjudicator’s decision, it is all the more important that the manner in which he reaches his decision should be beyond reproach. At the same time, one has to recognize that the adjudicator is working under intense pressure time and circumstances which makes it extreme difficult to comply with the rules of natural justice in the manner of a court or an arbitrator. Repugnant as it may be to one’s approach to judicial decision-making, I think that the system created by the HGCRA can only be made to work in practice if some breaches of the rules of the natural justice which have no demonstrable consequence are disregarded.’” The judge further held at paragraphs 33 and 36, that: “… 33 An adjudicator is of course entitled to use the power available to him but he may not of his own volition use them to make good fundamental deficiencies in the material presented by one party without first giving the other party a proper opportunity of dealing both with that intention and with the results. The principles of natural justice applied to an adjudication may not require a party to be aware of ‘the case that it has to meet’ in the fullest 59 sense since adjudication may be 'inquisitorial' or investigative rather than ‘adversarial’. That does not however mean that each party need not be confronted with the main points relevant to the dispute and to the decision…” 36….. an adjudicator does not act impartially or fairly if he arrives at a decision without having given a party a reasonable opportunity of commenting upon the case that it has to meet (whether presented by 'the other party or thought to be important by the adjudicator) simply because there is not enough time available. An adjudicator, acting impartially and in accordance with the principles of natural justice, ought in such circumstances to inform the parties that a decision could not properly reasonably and fairly be arrived at within the time and invite the parties to agree further time. If the parties were not able to agree more time then an adjudicator ought not to make a decision at all and should resign.” 5.3 Does Limitation of Documentations Constituted a Breach? As noted earlier in the discussion, the adjudicators are empowered to limit the amount of documentations submitted. This empowerment is evidence in the express provisions of the various legislations in specifying the duties of the adjudicators. In the Singapore Act, section 16(4) (a), expressly provides that an adjudicator may ‘conduct the adjudication in any manner he thinks fit’. And parties in adjudication are required, under section 16(6) in the Singapore Act, to ‘comply with any requirement made or direction issued by the adjudicator pursuant to the exercise of this power’. Having said that and taking into account of the practices in Malaysian which are more familiar to that of arbitration or litigation, parties are accustomed to make 60 elaborated submission in presenting their detail evidence. This could pose a big problem in adjudication as the issue may arise as to whether the adjudication procedural dateline should that precedence in cases where parties demanded that they would require more time to present their case fully. This insistence if refused would seem to deny the right for each party to be heard (the second pillar of the principles of natural justice). In the other hand, elaborated submission if allowed may give rise to tendency for claimant to ‘ambush’ the respondent in the actual adjudication proceeding. The other scenario which could pose a major problem in the adjudication proceedings is when a party argues his case without his legal representative (unlike litigation, legal representative is not compulsory in adjudication tribunal) may expect the tribunal to extend some latitude in presenting his case. This may result the adjudicator and the other party having to put up with more time taken by the unrepresented party and again the arguments and evidences presented could be of little relevance to the dispute at hand. Legislation in various jurisdictions demanded that no parties have the right to present submission or evidence in disregard of the tribunal’s directions. However, in issuing the direction to the parties, the adjudicator should ensure that all directions are formulated in a manner which will operate fairly as between the parties and at the same time comply with the time requirement as stipulated by the Act. In Carrillion Construction Ltd v Devonport Royal Dockyards Ltd 14 , facing with the unenviable task of resolving the differences within 42 days, the Honorable Mr. Justice Jackson ordered that all submission shall be limited to four pages of written summaries. A landmark decision on this point is provided in the decision of the UK TCC court in London and Amsterdam Properties Ltd v Waterman Partnership Ltd 15 . In 14 15 (2005) EWHC 778 (2004) BLR 179 61 this case, the terms for the appointment of the adjudicator had provided that the Referral Notice should not exceed 20 pages. The claimant in the case ignored this and served a Referral Notice in excess of 1,000 pages. The adjudicator accepted that the reference did not comply with the appointment terms. However, he decided that he would receive the first 20 pages as ‘the Referral’ so as to found his jurisdiction and then directed the respondent to limit its response to 20 pages. However, he then proceeded to receive in evidence the balance of the claimant’s non-compliant referral material amounting to 975 pages. The court held that the adjudicator was entitled to regard the shortened Referral received by him to be sufficiently compliant with the Scheme in the UK Act and that he was entitled to receive the other documentation in the manner that he did. However, the court took exception to that part of the adjudicator’s conduct where he subsequently received additional evidence from the claimant very late in the adjudication process and did not afford the respondent an opportunity to deal with this evidence. This was evidence which the claimant chose not to reveal until the adjudication commenced and the court found that the decision to serve the considerable body of evidence at the time of referral was ‘clearly deliberate’. Judge Wilcox, in the course of his judgment, considered the recourse available to the adjudicator in the situation posed before him: “Mr. Juniper [the adjudicator] did not appear to appreciate that in accordance with the rules of natural justice; he should either have excluded Mr. Baker’s supplemental statement, or should have given Waterman a reasonable opportunity of dealing with it. Under the applicable rules he was precluded from taking the latter course because LAP declined to agree to the necessary extension of time. He should therefore have excluded the evidence ... In fact he, avoided a decision as to whether or not the evidence should be admitted and then based his decision upon Mr. Baker’s evidence without giving Waterman a proper opportunity to deal with it. That was a substantial and relevant breach of natural justice.” 62 The decision suggests that had the respondent’s complaint was merely that he had been ambushed by an avalanche of evidence the court would still be compelled to enforce the adjudicator’s decision. The premise which justified the dismissal of the application for summary judgment in this case was the adjudicator’s failure to afford the respondent an opportunity to deal with the additional evidence when this was received. In an earlier part of his judgment, the learned judge had said: “I agree with the submissions of Mr. Akenhead that mere ambush however unattractive does not necessarily amount to procedural unfairness. It depends upon the case. It may be an important part the context in which the adjudicator is required to operate and in which his conduct may fall to be judged in the light of the fundamental common law requirements statutorily underpinned in... the Act.” Notwithstanding the powers of the adjudicator as set out in the various legislations, if an application and the response contain sufficient information, an adjudicator can in fact determine the application purely based on the application and response lodged, without the need for any further submission, inspection or conference. In alternative, an adjudicator can in fact determine the application based on additional submissions or documents which he can request from the parties. However, the danger in adjudication process is that whether with or without the additional submissions or documents, it must be highlighted to all parties and in his decision. In Pacol Ltd v Joint Stock Co Rossakhar 16 , when the matter came before the arbitrator, the issues between the parties had been defined, the arbitrators were in a position to decide as the only matters remained to be determined were related to the quantum and as for the liability, there were no doubts as the respondent had admitted liability. The arbitrators dealt with the matter as a document only arbitration. Notwithstanding the clear admission of liability on the part of the respondent, the 16 (2000) 1 Lloyd’s Rep 109 63 arbitrators went on to find that the respondent was not in breach of its payment obligations and dismissed the claimant’s claim in its entirety. In holding that there was serious irregularity within the meaning of the Arbitration Act 1996, Colman J accordingly set aside the award and cautioned: “It is particularly important in arbitrations which are conducted on documents alone that arbitrators should be alive to the dangers of introducing into their awards matters which have never been, or have ceased to be, matters in issue between the parties. This case is a particularly glaring example of the arbitrators simply ignoring the definition of issues which had been arrived at prior to the time when they had to determine the issues then referred to them. In a paper arbitration, the temptation to arrive at a conclusion which may not have been envisaged by either party by reference to matters upon which the parties have not had the opportunity of addressing the arbitrators or in respect of which they have not had an opportunity of adducing further evidence, may be a particular temptation which arbitrators should be careful to avoid.” The case of CIB Properties Ltd v Birse Construction 17 was one of the more extraordinary examples of adjudications and as far removed from the intention behind the HGCRA 1996 as one might get. In the case, CIB’s costs of two adjudications, one relatively short and the other lasting 100 days by agreement of the parties, amounted to £973,732.41 and Birse’s costs amounted to £1,161,341. The claim was from some £14m, and an award of over £2m was made by Mr. John Uff QC. There was a hearing in front of HHJ Toulmin QC on 19th October 2004 17 (2005) BLR 173 64 raising a number of issues. The key issue is that Birse argued that the size and complexity of the dispute meant that it could not be resolved fairly by adjudication. The starting point for the analysis of HHJ Toulmin QC was section 108 of the HGCR Act; Section 1 - gives a party a right to refer a dispute or difference adjudication. Section 2 - requires the Adjudicator to reach a decision provided the conditions in the clause could be met. This meant that the Adjudicator must be able to discharge his duty to reach a decision impartially and fairly within the time limit stipulated in section 2(c) and (d). As is well known, the time limit is 28 days, extended by 14 days with consent of the referring party or (implicitly) such other time as may be agreed. The Judge endorsed the approach of John Uff, who in turn had met the submissions of Birse by reference to the judgment of Judge Wilcox in London & Amsterdam v Watermans Partnership 18 , in which he said: “This scheme does not envisage that there should be a provisional resolution of a dispute by an Adjudicator at all costs. That would be far greater an injustice than that which the HGCRA Act was enacted to remedy”. Mr. Uff QC set himself some tests which could be transposed into questions which an adjudicator must be able to answer in the affirmative before he is capable of giving a decision compliant with the requirements of natural justice. 18 (2004) 94 Con LR 154 65 1. Have I sufficiently appreciated the nature of each issue referred to me so that I can give a decision on that issue? 2. Have I understood the case of each party in relation to the principal issues? 3. In relation to quantum, am I able to do substantial justice between the parties and arrive at an overall figure which reflects the merits of the case as I find them? The conclusion of John Uff was that if he had not been able to satisfy these conditions, he would not have reached a decision in the adjudication on some or all of the issues referred to him. In the event, Birse had agreed to a number of extensions throughout the adjudication amounting to 100 days. In the time period in fact allowed, and on the basis of the hearing as it proceeded and the written submissions, Mr. Uff considered that he could answer the questions in the affirmative and therefore decided the matters before him. The crucial finding of the judge was that a respondent is not bound to agree to any extensions of time, even if the refusal renders the task of the adjudicator impossible in relation to the dispute in the form in which it is referred to him. The recent decision of the Court of Session in the case of Ardmore Construction Limited v Taylor Woodrow Construction Limited is a useful to all practitioners that while it remains the courts’ stated policy not to interfere with adjudications’ decisions but in cases where there has been a clear breach of natural justice, they will refuse to enforce the decisions. Ardmore and Taylor Woodrow entered into a contract for the carrying out of certain ground works at a site in Glasgow. In May 2004 Ardmore made an 66 application to Taylor Woodrow for payment in respect of various heads of claim. There were five heads of claim, one of which related to overtime. Taylor Woodrow refused to make payment in respect of these items and the resulting dispute between parties was referred to adjudication. On 8 October 2004, having received written submissions from the parties and having held a hearing on 10 September 2004, the adjudicator issued a decision ordering that Taylor Woodrow make payment to Ardmore in respect of each of the various heads of claim. The claim in relation to overtime was based on an argument that a letter issued by Taylor Woodrow dated 2 July 2003 amounted to an instruction to accelerate which had been issued in accordance with the parties’ contract. This was the sole basis of Ardmore's claim for overtime. Taylor Woodrow, in response, argued that the letter did not amount to a valid instruction, but if it did, then it was limited in relation to its scope and it did not amount to an instruction that would allow Ardmore to be paid for all extra hours worked by them. The adjudicator, in his decision, said the following in relation to overtime: “The referring party’s working of weekend overtime was referred to in the respondent’s letter of 2 July 2003 to the referring party. The respondent contends that this was not an instruction, but on the plain reading of the letter, I find an acceptance of a proposal is an instruction. I find the instruction was limited to the areas for which the programmes had been prepared, at that time. I also find that there was sufficient evidence thereafter by way of correspondence, further programmes, Minutes of Meetings and respondent’s interim payment notices, that the respondent either verbally instructed the referring party to continue working weekends and other areas or acquiesced and agreed to that additional weekend working in other areas.” 67 Ardmore issued proceedings in the Court of Session to enforce the adjudicator’s decision. This action was defended by Taylor Woodrow on the basis that no submissions had been made to the adjudicator either in writing or at the hearing on 10 September to the effect that they had either acquiesced in the working of overtime or issued verbal instructions. Taylor Woodrow argued that to decide the dispute on either of these two alternative bases, without having heard submissions, amounted to a breach of natural justice by the adjudicator, rendering the whole decision unenforceable. The alleged breach of natural justice related only to that part of the decision on overtime and in January 2005 Ardmore successfully persuaded Lord Clarke that even if there were an issue regarding the overtime part of the award the other aspects of the decision were severable and that they could be enforced notwithstanding any issues regarding overtime. The court accepted these submissions (although no written judgment was issued) so the remaining issue between the parties related to the part of the award in respect of overtime. The case proceeded to a hearing with evidence at which the important issue for the court was whether or not submissions had been made to the adjudicator regarding either the issuing of verbal instructions or acquiescence on the part of Taylor Woodrow. It was accepted by Senior Counsel for Ardmore that unless the evidence showed that such submissions had been made the adjudicator would have been guilty of a breach of natural justice and that part of the decision relating to overtime would be unenforceable. Taylor Woodrow called as witnesses the people who had attended the meeting with the adjudicator on 10th. September, 2004. Their evidence was that there had been no discussion of either acquiescence or verbal instructions. They said that had such matters been raised then they would have objected and had that objection not been sustained they would have required an opportunity to investigate the new claim which was being made. 68 Ardmore called as witnesses the solicitor who had represented them at the hearing and the adjudicator himself. The adjudicator’s evidence was to the effect that the word ‘acquiescence’ had not been used at the hearing but that he had understood the general tenor of the Ardmore submission to be that because Taylor Woodrow had made payment in respect of overtime there had been ‘passive assent’ on their part which he took to be akin to acquiescence. He considered that this was a running feature of the submissions made by Ardmore at the hearing although he did not have any notes to confirm this. The solicitor who had acted for Ardmore at the hearing gave evidence to the effect that he had made submissions based upon personal bar at the hearing (such that Taylor Woodrow, by their words or conduct, were barred from asserting that they had not instructed or agreed to Ardmore working weekend overtime) and that he was confident they had been understood by the adjudicator. The court preferred the evidence of Taylor Woodrow’s witnesses and found that submissions of the sort described by the adjudicator and the solicitor acting for Ardmore had not been made at the hearing and, having formed that view, refused to enforce that part of the decision relating to overtime. In refusing to enforce the adjudicator’s decision on overtime Lord Clarke said the following: “I would like to stress, in conclusion, that I very much hope that this is a rare case, peculiar to its facts. I need no persuasion that, on the whole, the courts should be generally resistant to invitations to pick over adjudicator's decisions and to analyze over closely, and critically, their procedures. Nevertheless elementary and basic principles of natural justice have to be observed by adjudicators…and if they behave, in reaching their decisions, in a manner which, on an objective basis, involves a disregard of fair play, the consequences of which appear to have had a substantial and material effect on the adjudicator's decision, then the court should be prepared to intervene. The present case is, in my judgment, on the facts, one such situation. It 69 involves a clear and substantial breach of natural justice in relation to matters which were determinative of the adjudicator's decision.” As Lord Clarke indicated, this was an unusual case given that the adjudicator himself gave evidence and that there was such a stark difference between the parties’ evidence regarding what had been said at the hearing. The case serves to remind us that notwithstanding the less formal nature of the adjudication process (at least when compared to court or arbitration) there may be a limit to which a less formal approach is appropriate. However, it will be interesting to observe whether, in light of this case, adjudicators move towards more formal hearings where, for example, submissions and evidence are transcribed or minutes of the meeting are circulated for agreement. 5.4 Conclusion The English position was clearly established by the judgment of Humphrey Lloyd QCJ in the case of Balfour Beatty Construction Ltd v Lambeth London Borough Council 19 in which he noted with authority that the result of any breach of natural justice would depend on whether the subject breach relates to ‘a point or issue which is decisive or of considerable potential importance to the outcome’. The judgment also considered that the ‘principles of natural justice applied to an adjudication may not require a party to be aware of the case that it has to meet in the fullest sense’. Nevertheless, the New South Wales’s position was established by two Court of Appeal decisions of Brodyn Pty Ltd v Davenport 20 and TransGrib v Siemens 19 20 (2002) EWHC 597 (2004) NSWCA 394 70 Ltd 21 . The compliance with the principles of natural justice on both cases was envisaged to be higher that those propounded by the English Court. In his judgment, Hodgson JA considered that there must been ‘a bona fide attempt by the adjudicator to exercise the relevant power relating to the subject matter of the legislation’ and there must be ‘no substantial denial of the measure of natural justice that the Act requires to be given’. The recourse available to an aggrieved party in the face of the adjudicator’s failure to observe the principles of natural justice shall be to seek a court injunction and declaration that the adjudicator’s decision is void. Breach would therefore include dealing with one party in the absence of the other, an unjustified refusal to hear evidence, not giving opportunity to a party to be heard, having shown bias or the potential for bias against a party in the arbitration or adjudication, giving parties grounds to suspect that the arbitrator or adjudicator may not be able to act fairly in the resolution of the dispute. 21 (2004) NSWCA 395 CHAPTER 6 CONCLUSION AND RECOMMENDATIONS CHAPTER 6 CONCLUSION AND RECOMMENDATIONS 6.1 Introduction The experience from United Kingdom and Australia with adjudication show that statutory adjudication does provides a quick determination or decision of a dispute on a provisional interim basis, a decision which intended to be readily enforceable pending the final determination of the disputes by arbitration or litigation. It is envisaged that adjudication would be less formal than arbitration with the adjudicator taking a somewhat more inquisitorial role as opposed to the arbitration which is more adversarial. Furthermore, while the adjudicator has to conduct himself fairly and impartially between the parties, the courts appear to countenance some flexibility in the application of the principles of natural justice. During the initial stage of operation of the Housing Grants, Construction and Regeneration Act 1996 in the United Kingdom, one English judge anticipated that the very essence of the adjudication as a fast-track approach to dispute resolution may unsettle, at least in the initial stage, members of the bar who have been 72 accustomed to the more gradual process in arbitration or litigation. Dyson J in Macob Civil Engineering Ltd v Morrison Construction Ltd 1 stated that: “It is clearly Parliament’s intention that the adjudication should be conducted in a manner which those familiar with the grinding detail of the traditional approach to the resolution of construction disputes apparently find it difficult to accept.” Einstein J of the New South Wales (NSW) Supreme Court concurred with the sentiment and in Brodyn Pty Ltd v Philip Davenport & Ors 2 , he conceded with undiluted candor the difficulties posed by the constraints within which an adjudicator has to arrive at his decision: “What the Legislature has effectively achieved is a fast track progress payment adjudication vehicle. That vehicle must necessarily give rise to many adjudication determinations which will simply be incorrect. That is because the adjudicator in some instances cannot be brought down; give the type of care and attention to the dispute capable to being upon a full curial hearing.” There is this understandable anxiety that in the attempt to provide a quick determination of a dispute, an adjudication process may not afford sufficient scope for the careful analysis of evidence and facts. However, adjudication is only intended as a fast track dispute resolution to ease the cash flow in the construction industry and is not intended to provide the final word on a dispute. 1 2 (1999) BLR 93 (2003) NSWSC 1019 73 6.2 Research Findings This research was conducted to determine the extend to which an adjudication process conducted under the intense time constraint and within the limitations envisaged for the process under the respective regimes can be expected to observed the principles of natural justice or simply regarded as the principles of fair play. While the manner by which the principles of natural justice apply to arbitrations and litigations have been well established, it has been suggested that it may be unrealistic to expect the adjudication process to adhered to the principles to the same extend considering that adjudicators were acting under severe time constraint. This was indeed the view gathered from the decisions of case law following the enactment of the Housing Grants, Construction and Regeneration Act 1996 which was enforced in 1998. In Macob Civil Engineering Ltd v Morrison Construction Ltd 3 , an adjudicator without inviting parties to make representations on the payment mechanism of the contract, decided that a notice to withhold payment was out of time. This essentially undermined the respondent’s defense to the payment claim and appeared to be in breach of the principles of natural justice. Nevertheless, the court held that this did not prevent the decision of the adjudicator from being enforced. In arriving at his decision, Dyson J considered that the courts should be prepared to tolerate a breach of the principles of natural justice so long as these relate to procedural errors. Subsequently, in Discain Project Services Ltd v. Opecprime Development Ltd 4 , Judge Bowsher QC construed the views expressed in Macob as suggesting that the court may disregard breaches of the rules of natural justice as long as they produce ‘no demonstrable consequence’ on the outcome of the decision. These views were roundly criticized by a number of writers. In particular, Duncan Wallace wrote scathingly that they attribute to Parliament a highly 3 4 (1999) BLR 93 (2002) BLR 402 74 improbable intention that ‘an adjudicator’s decision, if arrived at in serious breach of a principle of natural justice, must as a matter of law nevertheless be enforced in circumstances where payment under an invalid decision could turn out to be irretrievable and precipitate the insolvency of the party affected.’ Subsequent decisions in Scotland and the English Technology and Construction Court sought to distance themselves from the position taken in Macob. In Homer Burgess Ltd v Chirex (Annan) Ltd 5 the Outer House of the Scottish Court of Session expressly doubted the position taken in Macob while Judge Humphrey Lloyd, QC in Glencot Development and Design and Co Ltd v Ben Barrett & Son6 was to rule that an adjudicator ‘has to conduct the proceedings in accordance with the rules of natural justice or as fairly as the limitations imposed by Parliament permit’. The subject was considered further by Judge Lloyd in Balfour Beatty Construction Ltd v. Lambeth Borough Council7. In the course of his judgment in that case, the learned judge suggested that the basic principles relating to natural justice which are applicable in arbitration are basically applicable to adjudication. However, as to the significance of the breach, he thought that this would depend on whether it relates to a point or issue which ‘is either decisive or of considerable potential importance to the outcome’ or whether it is confined to a matter which is merely ‘peripheral or irrelevant’. It might be speculated that, from policy considerations, the early pronouncements on this issue proved quite untenable as experience with adjudication increases within the United Kingdom construction industry. Although adjudication was contemplated by Parliament as a temporary ‘staging post towards final resolution’ of a dispute, it turned out to be more than that. In Balfour Beatty, Judge Lloyd stated in his decision that it is clear that adjudication is recognized as ‘having in itself considerable weight and impact’ the effect of which goes beyond the originally intended result that it was merely a decision which has to be observed for the time being. In effect, in a vast 5 (2000) BLR 124 (2001) BLR 207 7 (2002) EWHC 597 6 75 majority of the cases, parties were prepared to accept the position as determined by the adjudicator despite the rough nature of the process. An adjudication process which is founded on the principles of natural justice enhance the opportunities for parties to use the adjudicator’s decision as a basis for the satisfactory resolution of the basic dispute and improve the chances that the subject dispute would not have to proceed to arbitration or litigation. As a consequence, after some initial uncertainty, it has been suggested that the position in the United Kingdom is that, in relation to the principles of natural justice, “that which is applicable in arbitration is basically applicable in adjudication”. The New Zealand and Singapore Acts affirm this position. They provide expressly that an adjudicator has to apply the principles of natural justice in the determination of the dispute before him. However, given that adjudication is but an imperfect mirror of arbitration in terms of objectives and hence the very nature of the processes involved, the question remains as to whether the standard required in practice is that which is expected of an arbitrator. In Balfour Beatty Construction Ltd v Lambeth London Borough Council 8 , Judge Humphrey Lloyd QC considered that the “principles of natural justice applied to an adjudication may not require a party to be aware of the case that it has to meet in the fullest sense since adjudication may be inquisitorial or investigative rather than adversarial.” In the same passage of his judgment, he further suggested that what the application of the principles of natural justice amount to is simply that each party should be confronted with “the main points relevant to the dispute and to the decision”. 8 (2002) EWHC 597 76 6.3 Recommendations Whilst Malaysia is presently contemplating the idea of adopting statutory adjudication, one very important issue that require great attention would be whether the Malaysian court will be able to compliment the new legislation when it come in force by ensuring that the enforcement of the decisions of adjudicators can be done very quickly, otherwise the objective of the legislation will be defeated. Considering the fact that the Malaysian judiciary system is faced with a humongous back-log of cases, it will be a tall order to expect the Malaysian court to swiftly enforce an adjudicator’s determination. Therefore, its essential for Malaysian Courts to resolve their present problems and be prepare to embrace the proposed legislation in order that confidence can be maintained in the system. Dr. Thomas E. Uher, in his paper presented in the international forum in Kuala Lumpur, 2005, indicated that the utilization of the Act for the initial five years in New South Wales has been slow and he attributed this mainly to the lack of awareness and knowledge of the Act. It is therefore essential for the Malaysian construction industry to promote the proposed Act vigorously through a range of programs among organizations and practitioners within the construction industry. Knowledge and awareness of the Act will be essential to ensure the success of the Act and the Malaysian construction industry achieving its quest for zero payment default. 77 6.4 Conclusion Hence, by looking at the decisions in UK and Australia on the subject of adjudication and the principles of natural justice, the level compliance with the principles of natural justice in adjudication although not comparable to litigations or arbitrations, but only on issues that are fundamentally important where the principles of natural justice will have to be strictly adhered despite its rough nature of the process in adjudication. While both adjudicators and arbitrators are required to be impartial in the conduct of the respective dispute resolution proceedings, the impartiality take into account the different circumstances of adjudication as compared to arbitration. This principle was clearly illustrated in the cases shown: Balfour Beatty Construction Ltd v Lambeth London Borough Council 9 ; Glencot Development and Design Co Ltd v Ben Barrett & Son (Contractors) Ltd 10 and the New South Wales case of Musico v Davenport 11 . Judges of the Technology and Construction Court have rightly been astute to examine technical defenses to such applications with a degree of skepticism consonant with the policy of the Act, aptly described by Ward LJ in R J T Consulting Engineers Limited v D M Engineering (Northern Ireland) Limited 12 as "pay now, argue later”. This will undoubtedly clear the fear in some practitioners that if strict adherence to the principles of the natural justice, it will lead cases of ‘ambush’. 9 (2002) EWHC 597 (2001) BLR 207 11 (2003) NSWSC 977 12 (2002) EWCA Civ 270; (2002) 1 WLR 2344 10 78 The experience from the United Kingdom as observed by Dr Robert Gaitskell QC in the recently concluded international forum in Kuala Lumpur, have suggested that even where a party feels that an adjudicator is quite wrong in the determination, there is a general reluctance to pursue the matter in arbitration unless the difference involved is of an intolerable level. He went on to conclude that statutory adjudication in United Kingdom is an overwhelming success. Although the critics’ main concern on adjudication is that being a fast track process, it can lead to an injustice. Whilst adjudication cannot be said to deliver ‘perfect’ justice, at least it overcomes some of the injustice and bias in the construction industry. It does provide justice for many who would not otherwise receive justice. Therefore, the critics should be directing their criticism to the injustices inherent in the legal system. If only the courts could deal with the issues in the construction industry inexpensively and expeditiously as the adjudicators do, then they would be no scope for the legislation. As it is often quoted, ‘Delayed Justice can be Justice Denied’. REFERENCES REFERENCES Ameer Ali, Noushad Ali Naseem, “A ‘Construction Industry Payment and Adjudication Act’ – Reducing Payment-Default and Increasing Dispute Resolution Efficiency (A Malaysian Perspective)”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Bayley, G., “Constructing the Act: The NZ Construction Contracts Act 2002 – From Conception to Delivery”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Bernstein, R., Handbook of Arbitration Practice, Sweet & Maxwell, 1987 Chan, P., “Some Operational Considerations in the Implementation of Security of Payment Type Legislation”, International Forum: Construction Industry Payment Act and Adjudication, 2005 Cheng, T., “A Comparison of the Methods of Dispute Resolution Adopted By the Construction Industry”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Chow, K.F., “Natural Justice In Construction Adjudication”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Chow, K. F., Security of Payments and Construction Adjudication, LexisNexis, 2005 Uff, John, Construction Law, Sweet & Maxwell, Sixth Edition, 1996 80 Constable, A., “Adjudication Legislation: Learning Positive Lessons from the UK Experience”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Davidson, W.S.W., “Misconduct of Arbitrators”, Selection Papers on Arbitration Presented at the Joint Bar Council/CIArb Talks, 2003 Gaitskell, R., “Adjudication: Its Effects on Other Forms of Dispute Resolution (The UK Experience)”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Gaussen, R., “Construction Industry Payments and Adjudication – The Australia Perspective”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Idid, S.A., “Appointing Bodies and Adjudication Rules and Procedures”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Idris, N.J., Yong, M.L., Ling, T.L. and Oon, D., “Global Claims – The Way Forward”, Paper Presented at Universiti Teknologi Malaysia, 2005. Unpublished. Kennedy-Grant, T., “A Review of the Existing Legislative Models for a Construction Industry Payment and Adjudication Act”, International Forum: Construction Industry Payment Act and Adjudication, 2005 Kennedy, P., “Statistics and Trends in Statutory Adjudication in the UK Since 1998”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Lim, C.F., “The Malaysian Construction Industry – The Present Dilemmas of the Unpaid Contractors”, International Forum: Construction Industry Payment Act and Adjudication, 2005 81 Lip, E., “Zero Default Payment – Possibility, Impossibility or Wishful-Thinking?” International Forum: Construction Industry Payment Act And Adjudication, 2005 Lloyd, H., “Adjudicators’ Decisions – When they may be Invalid – And Other Matters”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Lloyd, H., “The Role of the Court in Enforcing the Decisions of Adjudicators”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Murdoch, J. and Hughes, W., Construction Contracts, E & FN Spon, Second Edition, 1996 Oon, C.K., “‘Pay When Paid’ Clauses in Sub Contracts”, International Forum: Construction Industry Payment Act and Adjudication, 2005 Pillay, M., “Basis & Effect of the Adjudicator’s Determination in the Singapore Regime”, International Forum: Construction Industry Payment Act And Adjudication, 2005 Rajoo, S., Law, Practice and Procedure of Arbitration, Sundra Rajoo, 2003 Rajoo, S., The Malaysian Standard Form of Building Contract (The PAM 1998 Form), Malayan Law Journal Sdn Bhd., Second Edition, 1999 Robinson, N.M., Lavers, A.P., Tan, G. and Chan, R., Construction Law in Malaysia and Singapore, Second Edition, 1996 Stephenson, Douglas A., Arbitration Practice in Construction Contracts, E & FN Spon, Third Edition, 1993 Tan, K., Yeo, T.M., Lee, K.S., Constitutional Law in Malaysia and Singapore, Malayan Law Journal Sdn Bhd., 1991 82 Uher, T.E., “The First Five Years of Adjudication in New South Wales”, International Forum: Construction Industry Payment Act and Adjudication, 2005 Wongpartnership, Annotated Guide to the Building Industry Security of Payment Act 2004, Sweet & Maxwell Asia, 2004 APPENDICES A Housing Grants, Construction and Regeneration Act 1996, United Kingdom B Building and Construction Industry Security of Payment Act 1999, New South Wales APPENDIX A A Housing Grants, Construction and Regeneration Act 1996, United Kingdom 83 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 84 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 85 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 86 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 87 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 88 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 89 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 90 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 91 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 92 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom 93 APPENDIX A Housing Grants, Construction And Regeneration Act 1996, United Kingdom APPENDIX B B Building and Construction Industry Security of Payment Act 1999, New South Wales 94 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 95 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 96 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 97 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 98 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 99 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 100 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 101 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 102 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 103 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 104 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 105 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 106 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 107 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 108 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 109 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 110 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 111 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 112 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales 113 APPENDIX B Building And Construction Industry Security Of Payment Act 1999, New South Wales