Six Sigma Approach to Real Time Cast In-Situ Slab Concreting Process Improvement Seyed Ali Mousavi Niaraki A PROJECT REPORT SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENT FOR THE AWARD OF THE DEGREE OF MASTER OF SCIENCE (CONSTRUCTION MANAGEMENT) FACULTY OF CIVIL ENGINEERING UNIVERSITI TEKNOLOGI MALAYSIA April, 2010 To My Lovely Father & Mother… ACKNOWLEDGEMENT I would like to give my sincere appreciation to my project supervisor Assoc. Prof. Dr. Abdul Kadir Bin Marsono for being patience with me, and his friendly guidance, critic advices, motivation and last not least the valuable encouragement. While preparing this project, I was in contact with many academicians’ student and lecturers from Faculty of Civil Engineering, Built Environment, Geo-technique, besides construction professionals in construction firm, consultants. They have contributed towards my understanding and thoughts. In particular, I am also very thankful to all of them for their willingness to share their valuable knowledge, expertise and technical know-how which assist me a lot in preparing this project. Without their continued support and interest, this project would not have been the same as presented here. I am also would like to thank all the lecturers who have conducted the course from the beginning of this master program and not hesitating to share their knowledge with us. My fellow postgraduate students should also be recognized for their support. My sincere appreciation also extends to all my classmates Ali, Mohsen, Farahbod, Niloofar, Hamed, Masoud and others which unfortunately, it is not possible to list all of them in this limited space, which have provided individually and sometime group assistance at various occasions. Finally, I want to give my special thanks to my panels Dr. Aminah, Dr. Shaiful, Mr. Bachan Singh, for their kindly advises. ABSTRACT The best way of construction processes improvement is by problem solving approaches. Before problems start to emerge in construction phases. In accordance to experiencing in real time problem solving approaches in other industries processes this study suggest that its time to go toward other industries experiences in real time problem solving. Proposing check sheet for real time problem solving within Six Sigma by; Identifying problem’s root causes and taking preventive actions before facing problem during construction phase, is main target of this study. This study were conducted as project experience and data gathering from interview with related experts. For achieving this goal, study adopting cast in-situ slab concreting quality improvement. Finding root causes of plastic crack in cast in-situ slab concreting and eliminating them in first place by applying Six Sigma tools and techniques. ABSTRAK Cara terbaik proses perbaikan pembinaan adalah dengan pendekatan penyelesian masalah.Sebelum masalah mulai muncul dalam fasa pembinaan, Sesuai untuk yang mengalami masalah pendekatan penyelesaian real time dalam industri lain proses kajian ini menunjukkan bahawa masa untuk pergi ke arah pengalaman industri lain dalam penyelesaian masalah real time. Mengajukan helai semak untuk menyelesaikan masalah real time dalam Six Sigma oleh; Mengidentifikasi akar penyebab masalah dan mengambil tindakan preventif sebelum menghadapi masalah selama fasa pembinaan, merupakan target utama dari kajian ini. Studi ini dilakukan sebagai pengalaman projek dan pengumpulan data dari wawancara dengan para ahli berkaitan. Untuk mencapai matlamat ini, kajian mengadopsi cor concreting peningkatan high in-situ slab. Mencari akar penyebab retak plastik di cor concreting slab-situ dan menghilangkan mereka di tempat pertama dengan menerapkan Six Sigma dan alat teknik. CONTENTS CHAPTER DESCRIPTION PAGE TITLE DECLARATION DEDICATION ACKNOWLEDGEMENT ABSTRACT ABSTRAK CONTENTS LIST OF TABLES LIST OF FIGURES LIST OF APPENDICES CHAPTER 1 INTRODUCTION 1.1 Introduction 1 1.2 Problem statement 2 1.3 Objectives of the Research 3 1.4 Scope of the Study 3 CHAPTER 2 LITERETURE REVIEW 2.1 2.2 Construction Process 4 2.1.1 Background of CPI 4 2.1.2 CPI Tools & Techniques 5 Six Sigma 8 2.2.1 Historical Background of Six Sigma 8 2.2.2 What is Six Sigma? 12 2.2.2.1 Why Six Sigma? 14 2.2.3 Six Sigma Problem Solving Process 20 2.2.4 DMAIC 21 2.2.5 Six Sigma Champion 21 2.2.5.1 Master Black Belt 22 2.2.5.2 Black Belt 23 2.2.5.3 Green Belt 23 2.2.5.4 Yellow Belt 24 2.2.6 Six Sigma Principles & Metrics 24 2.2.7 Six Sigma as a Quality Movement 28 2.2.7.1 (1.5 Sigma) 29 2.2.7.2 (3 Sigma (TQM)) 29 2.2.7.3 (3 Sigma with 1.5 Sigma Shift) 31 2.2.7.4 (4.5 Sigma) 32 2.2.7.5 (4.5 Sigma with 1.5 Sigma Shift) 32 2.2.7.6 (6 Sigma) 33 2.2.8 Six Sigma in Construction 35 2.2.8.1 Pervious Application of Six Sigma in Construction 2.3 Cast-In-Situ Concreting Process 37 37 2.3.1 Design of Mix & Reinforcing 38 2.3.2 Ready-Mix & Hand-Mix 38 2.3.3 Workability of Concrete 39 2.3.4 Access to Site 40 2.3.5 Formwork 40 2.3.6 Placement 41 2.3.7 Curing 42 2.4 Reinforced Concrete Cracks 45 2.4.1 Structural Cracks 45 2.4.2 Application Based Cracks 45 2.4.2.1 Fresh Concrete Cracks 45 2.4.2.2 Settlement Cracks 46 2.4.2.3 Plastic Shrinkage Cracks 46 2.4.2.4 Over Aged Concrete Cracks 48 CHAPTER 3 CHAPTER 4 RESEARCH METHODOLOGY 3.1 Introduction 50 3.2 Method of Data Collection 50 3.3 Data Collection 50 DATA ANALYSIS 4.1 Introduction 53 4.2 DPMO Calculation of Current Cast-In-Situ Slab Concreting Process 54 4.3 Identify Causes & Root Causes of Plastic Crack in Cast-In-Situ Slab Concreting Process 61 4.4 Identify Potentials Level of Each Root Causes 68 4.5 Identify Frequency Level of Each Root Causes 69 4.6 Proposed Check Sheet for Real Time Improving Cast-In-Situ Slab Concreting Process 70 4.7 Explanation of Items of Proposed Check Sheet 4.8 Explanation of Proposed Check Sheet CHAPTER 5 74 75 CONCLUSION AND RECOMMENDATION 5.1 Conclusion 77 5.4 Recommendation 77 REFERENCES 79 APPENDICES 81 LIST OF TABLE TABLE NO. TITLE PAGE Table 2.1 Contrasting Six Sigma and Total Quality Management 17 Table 2.2 Simplified Sigma Conversion Table 27 Table 4.1 Root Causes of Plastic Crack in Cast-In-Situ Slab Concreting Process Table 4.2 66 Percentage of each category in each potential level according to number of root causes in each category which is placed in each potential level Table 4.3 68 Percentage of each category in each frequency level by considering number of root causes which is placed in each frequency level 69 LIST OF FIGURE FIGURE NO. TITLE PAGE Figure 2.1 Traditional bell curve of normal distribution of data 14 Figure 2.2 3.4 deviate from either side of the average 15 Figure 2.3 Process of introducing Six Sigma 18 Figure 2.4 Systematic and scientific approach of Six Sigma 18 Figure 2.5 1.5 Sigma 29 Figure 2.6 3 Sigma (TQM) 30 Figure 2.7 3 Sigma with 1.5 Sigma Shift 31 Figure 2.8 4.5 Sigma 32 Figure 2.9 4.5 Sigma with 1.5 Sigma Shift 33 Figure 2.10 6 Sigma 34 Figure 2.11 Six Sigma’s Structured Methodology (DMAIC) 35 Figure 2.12 Operations involved in traditional concrete Construction (schematic) 44 Figure 2.13 Classifications of Cracks in Reinforced Concrete 49 Figure 3.1 Methodology Flow 52 Figure 4.1 Concerting process 55 Figure 4.4 Cracks which is investigated from the site 58 Figure 4.5 Fish Bone Diagram 62 Figure 4.6 Pareto Chart 67 Figure 4.7 Proposed Check Sheet 71 LIST OF APPENDICES APPENDICES TITLE PAGE A Questionnaire Form A 82 A Questionnaire Form B 89 B Six Sigma Conversion Table 96 1 CHAPTER 1 INTRODUCTION 1.1 Introduction In the recent years, construction projects have turned into a more complicated, dynamic and interactive scenario. Project managers are constantly required to speed-up reflective decision-makings on time. Construction is an experience-based discipline, knowledge or experience accumulated from pervious projects, plays very important role in successful performance of new works. If experience and knowledge are shared, then the same problems in construction projects will not be repeated. Several enabling activities should be considered to help to achieve the ultimate goal of efficient experience and knowledge reuse; experience and knowledge should be preserved and managed; that is, they should be captured, modeled, stored, retrieved, adapted, evaluated and maintained and updated (Bergmann, Ralph (2002). The reuse of information and knowledge minimizes the need to refer explicitly to past projects; reduces the time and cost of solving problems, and improves the quality of solutions during the construction phase of a construction project. The knowledge can be reused and shared among the involved engineers and experts to improve the construction process and reduce the time and cost of solving problems. Only in recent years has sparing the six-sigma method been utilized by some of the major players in the construction sector. While traditional quality programs have 2 focused on detecting and correcting mistakes, six-sigma encompasses something broader: it provides specific methods to re-create the process itself so that the defects are never produced in the first place. The concept seeks to continually reduce variation in processes with the aim of eliminating defects from every transaction (Hahn et al., 1999; Tennant, 2001). The main advantage of the six-sigma method is that it shares much of the same values and uses similar tools to TQM. The tools are nothing new, but the strategic way that the six-sigma programme proactively uses them, within its structured framework, is what generates improved results. (Hagemeyer, C; Gershenson, J.K; Johnson D.M, 2006). By considering previous project experiences we can find problematic element of defects in previous project learn it, and find the defect’s root causes by eliminating root causes in current project systematically. For achieving this goal this study has choose Six Sigma problem solving approach. 1.2 Problem Statement In accordance real time delay and defect problem. Approaches of “quality record and document” and “corrective and preventive actions” with different objectives, major process, information requirements industries processes is use in the project. The study suggest that several amount of defect and late delivery of project in times need to be learned. 3 1.3 Objectives 1- To identify and analyze the root causes of plastic crack to Six Sigma problem solving approach. 2- To propose check sheet for real time problem solving cast in situ slab concreting process from the outputs of pervious problem and solutions. 1.4 Scope of Study In this research cause of different nature of construction projects like dam, road, air port, high rise building, office buildings project and further; researcher has selected office building construction. With focusing on cast in situ slab concreting process. In this research, researcher has concentrated on DMAIC methodology of Six Sigma problem solving approach. The study conducting site survey on construction project in Universiti Teknologi Malaysia (UTM). 4 CHAPTER 2 LITERATURE REVIEW 2.1 Construction Process 2.1.1 Background of Construction Processes Improvement The aim of process improvement in construction is to produce something of equal or better worth, at a lower cost. Brown and Adams (2000) reported that in the procurement of projects, leading clients are increasingly demanding a high quality product at a low cost, which is also reliable and delivered on the date required. The major feature of construction processes is that they are notorious for their complexity and changes during the construction process (Van der Aalst et al., 2002). The construction industry has few structured frameworks on which to based on process improvement initiatives and achieving total quality. The absence of clear guidelines has meant that improvements are often isolated and benefits cannot be coordinated or repeated. The construction industry is a business sector that plays a substantial role in many economies. However, the attainment of acceptable levels of quality in the construction industry has long been a problem. Significant quantities of resources, both human and material, are wasted each year as a result of inefficient or non-existent quality 5 management procedures (Arditi and Gunaydin, 1997). There exists great potential for quality improvements in the construction industry; its importance cannot be understated, regardless of a nation’s primary business, and organizations will always require interaction with the construction industry to source physical assets to house operations (Cox and Ireland, 2002). In recent years, globalization and deregulation of markets has led to increased foreign participation in domestic construction, placing further pressure on local leading firms for major reforms. The cause of many problems lies in the organization of the industry and associated processes. Firms need to build on their competitive strengths through a deliberate and managed process to improve the capacity and effectiveness of the industry and to support sustained national economic and social objectives. 2.1.2 Construction Processes Improvement Tools & Techniques A number of techniques and tools can be found under the TQM/Continuous Process Improvement (CPI) umbrella, including the process cost model, standardized process improvement for construction organizations, the balanced scorecard, Kaizen and statistical process control. Traditionally, businesses have tended to measure performance using only financial measures. As a result, organizations adopted techniques similar to the process cost model (PCM). This concept was developed in manufacturing industry and has been moulded into a workable strategy suitable to construction applications (Aoieong et al., 2001). The PCM is a process-orientated approach that values client satisfaction and continuous process improvement. PCM uses financial theory to analyse and direct efforts for improvement; which has its advantages and disadvantages. The use of a single measure clearly illustrates the tangible benefits in a compatible format that is easy to interpret (Arditi and Gunaydin, 1997; Moen, 1998). However, the weakness of financial metrics stems from their failure to measure and monitor multiple dimensions of performance. Additionally, financial measures used in isolation create problems in that they are characterized as lagging measures, i.e. they are the result of past events. Consequently, PCM is a reactive approach, because waste and associated non-value adding activities have already transpired. For construction 6 firms to succeed in the future they need to implement a more proactive approach to improving processes (Moen, 1998). To look beyond financial measures, Sarshar et al. (2000) developed the standardized process improvement for construction enterprises (SPICE) framework. This framework was founded on the principles of the capability maturity model (CMM) and argues that the outcome of a process is a function of the maturity of the organization and its associated processes (Hutchinson and Finnemore, 1999; Sarshar et al., 2000). The philosophy of this framework is that a process becomes more predictable and reliable as the organization and its processes simultaneously mature. SPICE provides a structured framework with a definite starting point that assists the process improvement teams to prioritize areas for improvement. The SPICE framework provides a good process diagnostics tool with a strong process focus. Sarshar et al. (2000) demonstrated the application of the SPICE framework in two case studies aimed at improving construction processes. An interesting outcome of these studies was that an organization does not have the capability to capture best practices until ‘level 3 (defined)’ of the framework. In light of this, the SPICE framework has many similarities with six-sigma, particularly in its ability to address priority processes. Although the two previous techniques provide an indication as to the success or failure of a project, they do not provide a balanced view of a project’s performance. Kaplan and Norton (1992) developed the balanced scorecard (BSC) to capture both the tangible and intangible perspectives of performance. The BSC provides information on four perspectives, including customer perspective, internal business perspective, learning and growth perspective and financial perspective. However, this approach is far from simple and requires a comprehensive understanding of the fundamental characteristics of performance measurement as well as a significant commitment from top management and employees (Chan et al., 2002). Moreover, construction firms may find implementation difficult due to the diversity of their projects (Sommerville and Robertson, 2000). Hubbard (2000) also felt that the BSC was too generic in design and 7 did not consider a specific industry’s needs or the strategic desires of individual organizations. Another process improvement technique that was developed by the Japanese and was a contributor to their economy’s rapid growth in the second half of the twentieth century was Kaizen. This technique was formed from a quality culture that emphasizes continuous process improvement through standardization – i.e. establish a standard, maintain it and then improve it (McGeorge and Palmer, 2002). However, the technique tends to be difficult to adopt for firms that have already implemented the TQM culture. In view of this, the authors do not believe that Kaizen can offer the construction industry substantial benefits since it merely promotes similar ideals already created through TQM. What the industry needs is a structured datadriven approach to direct its efforts. A more data-driven technique is statistical process control (SPC), which has an emphasis on numbers, fact-based analysis and tangible decision-making. Consequently, due to its technical nature, it has never been fully embraced (Dale et al., 2000). With managements becoming more interested in performance and profitability, they are beginning to divert attention back to the analysis of process variation and elimination through root cause analysis and problem solving. Use of SPC identifies overall process capabilities and areas that need improvement. Although SPC equips the users with an extensive array of measurement techniques it appears to lack a strong organizational supportive framework. The tools employed by SPC have, to a large extent, fuelled the development of the latest addition to the TQM/CPI umbrella that is Six-Sigma. 8 2.2 Six Sigma 2.2.1 Historical Background of Six Sigma Sigma is a letter in the Greek alphabet that has become the statistical symbol and metric of process variation. The sigma scale of measure is perfectly correlated to such characteristics as defects-per-unit, parts-per million defective, and the probability of a failure. Six is the number of sigma measured in a process, when the variation around the target is such that only 3.4 outputs out of one million are defects under the assumption that the process average may drift over the long term by as much as 1.5 standard deviations. Six Sigma may be defined in several ways. Tomkins(1997) defines that Six Sigma is "a programme aimed at the near-elimination of defects from every product, process and transaction". Harry(1998) defines that Six Sigma is "a strategic initiative to boost profitability, increase market share and improve customer satisfaction through statistical tools that can lead to breakthrough quantum gains in quality". Six Sigma was launched by Motorola in 1987. It was the result of a series of changes in the quality area starting in the late 1970s, with ambitious ten-fold improvement drives. The top management with CEO Robert Galvin developed a concept named Six Sigma. After some internal pilot implementations, Galvin, in 1987, formulated the goal of "achieving Six-Sigma capability by 1992" in a memo to all Motorola employees (Bhote, 1989). The results in terms of reduction in process variation were on-track and cost savings totalled US$13 billion and improvement of labor productivity became 204% increase during 1987-1997 (Losianowycz, 1999). In the wake of successes at Motorola, some leading electronic companies such as IBM, DEC, Texas Instruments launched Six Sigma initiatives in early 1990s. However, it was not until 1995 when GE and Allied Sigma launched Six Sigma as strategic initiatives that a rapid dissemination took place in non-electronic industries all over the 9 world(Hendricks and Kelbaugh, 1998). In early 1997, Samsung and LG groups in Korea began to introduce Six Sigma under their companies. The results were amazingly good in those companies. For instance, Samsung SDI, which is a company under Samsung group, reported that the cost savings by Six Sigma projects totalled US$150 million (Samsung SDI, 2000). At the present time, the numbers of big companies applying Six Sigma in Korea are exponentially growing, with a strong vertical deployment into many small and medium sized enterprises as well. Through the consulting experiences of Six Sigma in Korea, the author believes that Six Sigma is a new strategic paradigm of management innovation for a company to survive in this 21st century(Park et. al, 2000). Six Sigma implies three things; statistical measurement, management strategy and quality culture. It tells us how good our products, services and processes really are through statistical measuring of quality level. It is a new management strategy under leadership of the top management to create quality innovation and total customer satisfaction. It is also a quality culture. It provides the way to do things right the first time and to work smarter by using data information. It also provides an atmosphere to solve many CTQ (critical-to-quality) problems through team efforts. Motorola, Inc. invented Six Sigma, and we have learned a great deal about it over the last 18 years. During that time, Six Sigma has evolved from its roots as a measure of quality to an overall business improvement methodology and to what it is today at Motorola – a fully integrated management system. In 1986, Bill Smith, a senior engineer and scientist within Motorola’s Communications Division, introduced the concept of Six Sigma in response to increasing complaints from the field sales force about warranty claims. It was a new method for standardizing the way defects are counted, with Six Sigma being near perfection. Smith crafted the original analysis and tools that were the beginnings of Motorola’s Six Sigma methodology. He took his ideas to CEO Bob Galvin, who was struck by Smith’s passion and came to recognize the 10 approach as key to addressing quality concerns. Six Sigma became central to Motorola’s strategy of delivering products that met the high quality standards our customers deserved. Following a common Six Sigma methodology, Motorola began its journey of documenting key processes, aligning these processes to critical customer requirements and installing measurement and analysis systems to continuously improve the process. Past definitions of quality were found to have focused on ‘‘conformance to standards’’ where companies strived to create products and services that fell within certain specification limits. In Six Sigma, the definition of quality is broadened to include economic value and practical utility to both the company and the customer. Six Sigma recognizes that business quality is the highest when costs of delivering products and services to meet customer requirements are at the absolute lowest for both the producer and the consumer. Six Sigma is therefore developed as a business strategy and philosophy built around the concept that companies can gain a competitive edge and stay ahead of the competition by reducing defects in their industrial and commercial processes (Harry and Schroeder 2000). Various authors have defined Six Sigma in the following ways. Harry and Schroeder 2000, who are the key developers and proponents of the Six Sigma program at Motorola, defined SixSigma as ‘‘a disciplined method of using extremely rigorous data gathering and statistical analysis to pinpoint sources of errors and ways of eliminating them.’’ Snee 2000, indicated that ‘‘Six Sigma should be a strategic approach that works across all processes, products, company functions and industries.’’ Chowdhury 2001, explained that Six Sigma represents a statistical measure and a management philosophy that teaches employees how to improve the way they do business, scientifically and fundamentally, and how to maintain their new performance level. It gives discipline, structure, and a foundation for solid decisionmaking based on simple statistics. Pande et al. 2000, defined Six Sigma as a way of 11 measuring processes, a goal of near perfection represented by 3.4 defects per million opportunities (DPMO); and more accurately, a comprehensive and flexible system for achieving, sustaining, and maximizing business success. It is uniquely driven by a close understanding of customer needs, disciplined use of facts, data, and statistical analysis, and diligent attention to managing, improving, and reinventing business processes. Pande and Holpp 2002, defined Six Sigma as a statistical measure of the performance of a process or a product; A goal that reaches near perfection for performance improvement; and a system of management to achieve lasting business leadership and world-class performance. In general, the above definitions of Six Sigma may be summarized into the following two aspects: Six Sigma is a statistical measure used to measure the performance of processes or products against customer requirements. This is known as the ‘‘technical’’ definition of Six Sigma; and Six Sigma is a ‘‘cultural and belief’’ system and a ‘‘management philosophy’’ that guide the organization in repositioning itself towards world-class business performance by increasing customer satisfaction considerably and enhancing bottom lines based on factual decision making. In the last 10 years, Six Sigma has risen to the top as one of the most talked about process improvement and quality management programs available. It rivals ISO 9001 and CMMI in interest and adoption. But of the three, it is often the least understood. There are a couple of reasons for this. The first is that compared to ISO and CMMI, Six Sigma has the potential to be imminently more complex. By moving seriously into its statistical and quantitative aspects, it can be both powerful (to the informed) and powerfully daunting (to the uninformed). 12 2.2.2 What is Six Sigma? Six Sigma is different from ISO 9001 and CMMI in that its focus is on measuring existing processes with a view to making them more efficient and effective. Six Sigma assumes there are processes in place. Maybe they are formal, maybe they are informal, but they are definitely doing something to produce something. At its core, Six Sigma is a way to measure processes and then modify them to reduce the number of defects found in what you produce. With this program, they study the sources of defects and then analyze ways to make the processes more resilient, so that defects are not introduced or have fewer opportunities to creep in. Many people think that the idea behind Six Sigma is to have a system that produces zero defects. That's not really true. But, statistically, the rote measure of "six sigma" means that your system will turn out only 3.4 defects per million opportunities for defects. The real idea behind Six Sigma is to manage process improvement quantitatively. It seeks to put measures and controls in place so that you can readily and regularly monitor the performance of your processes and, using performance data, adjust them to maximize their ability to produce predictable, quality results. They can think of Six Sigma as the evaluation side to a process improvement program. That's why many organizations pair Six Sigma with programs like ISO 9001, CMMI, or LEAN. Six Sigma gives you the tools you can use to rate how well these programs are performing for you. And this rating is not qualitative. It is not instinctive or intuitive. It is a rating based on hard data, on fact. By looks at the high-level focus of Six Sigma, that it is a cycle of seven general steps: 1. Look at the product. Put a critical eye on what is producing. Continually examine what it is making and how is made it so that you can always seek ways to make it better. There are few sacred big issues Six Sigma. 13 2. Identify defects. Examine the product and identify defects. Count them. Measure them. Know what is mean by the term "defect." a defect can be as anything that holds the product back from being the best and it can be in the minds of customers. 3. Look to the process. If the product is not all it can be, then chances are the processes could be improved. Examine the processes. What's happening with the current processes that might be letting defects in? What opportunities might see to keep defects out? 4. Determine sources of defects. Analyze how the process works. Study its flows and structure to determine where in its operations defects are seeping in. 5. Improve the process. Based on the analysis of process performance and understanding of the process structure, now adjust the process with the intention of improving its performance. The goal is to lock defects out. 6. Use the new process. Now that the processes have improved, put it to work. Set it into the production environment and let the improvements make their mark. 7. Look at the product. Take a fresh look at the product. Did the improvement make a difference? Is the product better? If it is, look for new improvement opportunities and the cycle continues. The philosophy behind Six Sigma could be summarized as "Deliver Quality." That capital Q in Quality is important. It implies a certain kind of quality, and that is what Six Sigma drives at, a very special definition of quality. Quality is not whatever happens to be the biggest, the strongest, the prettiest, the best, or the coolest. It is not what organization says it is. It is not what competition thinks it is. In the world of Six Sigma, quality is what the customer wants. That is all it is. The meaning of the word quality comes from that source and that source only. Nothing else matters. Everything else is irrelevant. GE calls this the Voice of the Customer (VOC). 14 2.2.2.1 Why Six Sigma? Six Sigma is all about the spread of variation in a set of measured data. In a normal distribution, data tends to spread out in a very predictable pattern. Most of the values fall around the middle. Some fall more or less to either side. By plotting the result, the figure will look like a bell. As shown in Figure 2.1. Figure 2.1 The traditional bell curve shows a normal distribution of data. The "average" values fall in the middle and the less common values fall to either side of the center. A chart such as that illustrated in Figure 2.1 is called a normal distribution. It has the general shape of a bell, and known from statistics that's a normal way that data like that should fall. Six Sigma predicts that when a process run, the way the performance varies over time will dance up and down around the center line, the average line just like the range of heights in nature. But here is the key with Six Sigma: it wants to put techniques in place to control what numbers (what data points) are going to most influence the average. The common understanding of achieving Six Sigma performance is that for every 1,000,000 data points, only 3.4 will deviate from either side of the average. In a grossly exaggerated example, that might look more like Figure 2.2. 15 Figure 2.2 In Figure 2.2, shows the hardly any variation. Everything is grouped right at the middle. In general, that's not a bad understanding. But the technical explanation is better, and it sheds more light on the purpose and design of Six Sigma. Let's get at this by looking at the name Six Sigma. Sigma means the same thing as standard deviation. Standard deviation (SD) is a well-founded measure of the range of variation from the average for a group of measurements. In any set of data, 68 percent of all the measurements will fall within one standard deviation of the average. 95 percent of all the measurements will fall within two standard deviations of the average. By the time you're out to six standard deviations six sigma you've accounted for 99.9997 percent of the data. Practically nothing is out of those bounds. Six Sigma is about process control. The more to able to control a process, the better will be able to make it hit the performance numbers wanted. Six Sigma is a program that works best when it uses hard data as the foundation for process improvement. That's why one of the general interpretations of this program is that it is heavy on statistics. So far, we've looked at a few common Six Sigma concepts: Voice of the Customer and X=f (Y). Here's another one: DPMO. DPMO is Defects Per Million Opportunities for defects. When they are building a product, they want their production processes to be predictable. They want to know how many microns of carbon coating they are going to lay onto a filament. No process is 16 perfect. No process operates without variance. One of the things they need to establish with Six Sigma is the number of process variations. To get a valid statistical indicator of the reliability of this process (the talent of the catcher), we have to repeat the transaction over and over. Measure and measure. When we have a process that achieves statistical six sigma, we can pretty much guarantee that we'll have only 3.4 defects for every million transactions. That's 3.4 misses for every million throws. Whatever we are doing, it is so controlled, so streamlined, so proven that the outcome is a safe bet. The Six Sigma methodology is an alternative to TQM for obtaining: manufacturing defect reduction, cycle time reduction, cost reduction, inventory reduction, product development and launching, labor reduction, increased usage of resources, product sales improvement, capacity improvements, and delivery improvements. Six Sigma is based on a measurement strategy focused on customer satisfaction & financial benefits through variance reduction and continuous process improvement. Six Sigma uses two methodologies named ‘DMAIC’ (Define, Measure, Analyze, Improve, Control) and ‘DFSS’ (Design For Six Sigma). While Six Sigma was originally created as a continuous quality improvement technique, today it is significantly different than the total quality management (TQM) approach of the 1980s. Table 1 shows the key differences between Six Sigma and TQM. 17 Table 2.1 Six Sigma is very popular in Korean industry. There are several reasons for this popularity. First, it is regarded as a fresh quality management strategy which can replace TQC, TQM and others. In a sense, it view the development process of Six Sigma as shown in Figure 1. Many companies which were not quite successful in implementing the previous management strategies such as TQC and TQM, are eager to introduce Six Sigma. 18 Figure 2.3 QC: quality control SQC: statistical quality control TQC: total quality control TQM: total quality management ISO: International Organization for Standardization SPC: statistical process control TPM: total productive maintenance QE: quality engineering TCS: total customer satisfaction Six Sigma is viewed as a systematic and scientific approach for management innovation by the integration of four elements; customer, process, manpower and strategy as shown in Figure 2. Figure 2.4 19 Second, Six Sigma provides a scientific and statistical basis for quality assessment for all processes through measurement of quality level. The Six Sigma method allows to draw comparisons among all processes, and tells how good a process is. By this information, the top management knows what to do for process innovation and accordingly for customer satisfaction. Third, Six Sigma provides an efficient manpower cultivation and utilization. It has a belt system in which there are green belt, black belt, master black belt and champion. As a person in a company gets some education, he belongs to a belt. Usually, a black belt is the leader of a project team and several green belts work together for the project team. Lastly, there are many successful stories of Six Sigma in well known world-class companies. Besides Motorola, GE, Allied Signal, IBM, DEC and Texas Instruments as mentioned above, Sony, Kodak, Nokia, Philips Electronics, Samsung Electronics, LG Electronics among others have been quite successful in Six Sigma. Six Sigma is a long-term, forward-thinking initiative designed to fundamentally change the way corporations do business. It is first and foremost “a business process that enables companies to increase profits dramatically by streamlining operations, improving quality, and eliminating defects or mistakes in everything a company does. While traditional quality programmes have focused on detecting and correcting defects, Six Sigma encompasses something broader: it provides specific methods to re-create the process itself so that defects are never produced in the first place”. [“Management Processes for Quality Operations”, Richard S. Johnson, 2002.] While Six Sigma is a long-term strategy, it is designed to generate immediate improvements to profit margins too. Compared to traditional quality management programmes, such as TQM, that project three or more years into the future, Six Sigma focuses on achieving financial targets in twelve-month increments. The Six Sigma breakthrough strategy is a disciplined method of using extremely rigorous data- 20 gathering and statistical analysis to pinpoint sources of errors and find ways of eliminating them. 2.2.3 Six Sigma Problem Solving Process The original problem-solving process for Six Sigma developed from Motorola is MAIC which means measurement, analysis, improvement and control. Later, DMAIC instead of MAIC is advocated from GE where D stands for definition. MAIC or DMAIC is mostly used as the unique problem-solving process for manufacturing areas. However, for DFSS there are multiple proposed processes. They are as follows. 1) DMADV (Define - Measure - Analyse - Design - Verify). MADV was suggested by Motorola for DFSS, and D was added to it for definition. DMADV is similar to DMAIC. 2) IDOV (Identify - Design - Optimize - Validate). This was suggested by GE and has been used most frequently in practice. 3) DIDES (Define - Initiate - Design - Execute - Sustain). This was suggested by Qualtec Consulting Company. It seems that the above problem-solving processes for manufacturing and R&D areas are not quite suitable for service areas. The author believes that DMARI (Define Measure - Analyze - Redesign - Implement) is an excellent problem-solving process for non-manufacturing service areas. Here, the phase 'redesign' means that the system for service works should be redesigned in order to improve the service function. 21 2.2.4 DMAIC Six Sigma employs two basic methodologies to problem solving. The first is termed DMAIC. DMAIC is used to improve existing processes in an organization. The other methodology is DFSS. It is used when you want to design a new process and introduce it into an organization in a way that supports Six Sigma management techniques. DMAIC is the one that gets the most press. There are five basic steps in the methodology: define, measure, analyze, improve, control. DMAIC is used to improve and increase the efficiency and reliability of processes that exist in an organization. It is a process improvement methodology that employs incremental process improvement using Six Sigma techniques. DFSS stands for Design for Six Sigma. It is also sometimes referred to as DMADV. This methodology also has five steps: define, measure, analyze, design, verify. DFSS is used when an organization wants to design and produce new products in a timely, costeffective manner to meet exact customer needs. It is a business development methodology. The core steps, DMADV, are used to create reliable processes in an organization that does not have processes, or when an organization must discard a deeply faulted process. DFSS is a process design approach. 2.2.5 Six Sigma Champion The Six Sigma Champion is usually an executive or high-level manager in the organization with the ability to promote and sponsor the use of Six Sigma. Champions may manage a series of Six Sigma teams, or they may simply fund and support Six Sigma projects. Champions should have a pretty good working knowledge of Six Sigma, but more than that, they should share an enthusiasm for the promise and approach of Six Sigma, believing in the Six Sigma vision of improvement through data 22 management and quantitative analysis. Well-positioned Champions will possess authority to: • Control resources • Allocate budgets • Assign responsibility • Set strategic direction Champions are the executive sponsors of the Six Sigma world, and they usually direct and develop the organization's Six Sigma programs. 2.2.5.1 Master Black Belt Master Black Belt is the highest level of Six Sigma certification. This is an individual who has not only had extensive training in the methodology and techniques of Six Sigma, but who has also had extensive experience designing and implementing Six Sigma projects in a variety of organizations. Master Black Belts possess a deep understanding of DMAIC, as well as Design for Six Sigma and the Design Measure Analyze Validate Deploy methodologies. They are considered experts at applying statistical measurements to diverse and heterogeneous data sets, and they have a solid grasp of the use and application of quantitative techniques to understand process performance and derive empirical process improvements. Master Black Belts have the ability to manage Six Sigma programs as well as program teams. The tradition with Master Black Belts is that they can empirically demonstrate that their projects designed and managed by them have saved companies hundreds of thousands of dollars. The term "hundreds of thousands" is not used here for dramatic purposes. It's to be taken literally. In the true Six Sigma culture, no one will call herself a Master Black Belt if she is not able to put that data in front of a client. 23 2.2.5.2 Black Belt Black Belts typically lead Six Sigma projects. They may design the project with the help of a Master Black Belt, or they may design it on their own. They are usually highly trained in Six Sigma methods, with solid experience in DMAIC, DFSS, and DMAVD. Like Masters, they should have sound knowledge in applying statistical measurements to diverse and heterogeneous data sets. And they should have broad experience applying Six Sigma methods to a number of process improvement projects. They should be able to demonstrate very strong statistical and quantitative analysis skills, effective project management skills, strong interpersonal and communication skills, and strong writing and organizational skills. Like Masters, Black Belts should also be able to show empirical cost savings or ROIs as a result of their Six Sigma project work. Most reputable Six Sigma Black Belt courses require that the candidate design, plan, and execute a real-world project with the potential to save an organization at least $100,000. 2.2.5.3 Green Belt Six Sigma teams are usually mostly composed of Green Belts. These are people with at least one pretty in-depth course in Six Sigma applications and the interest (and opportunity) to work on a Six Sigma project. They have a beginning ability to produce statistical control charts, calculate percent noncompliance, plot histograms and Pareto charts, identify common-cause and special-cause variation, and calculate process sigmas. They have a good working knowledge of DMAIC, DSFF, and DMAVD and are positioned to participate in Six Sigma projects of varying complexity, size, and duration. They are the field soldiers in the world of Six Sigma. 24 2.2.5.4 Yellow Belt Green Belt, Black Belt, and Master Black Belt are well-accepted Six Sigma designations. Yellow Belt is less so. Many people think there should be no such things as a Yellow Belt. I tend to agree. Because when you think about it, under a Green Belt, a Yellow Belt can only be a Six Sigma team contributor. And if someone is on a Six Sigma team but is not really trained in any of the methodologies, design considerations, or statistical techniques, they can't really be expected to contribute a lot. I guess he could perform measurements and collect data; those are valuable activities, but they probably don't warrant a belt of distinction on their own. What does it take to be recognized as a Yellow Belt? If you read this chapter, twice, slowly, you might be able to qualify. 2.2.6 Six Sigma Principles and Metrics The principles of Six Sigma can be distilled into the following six themes (Pande et al. 2000; Pande and Holpp, 2002): 1. Genuine focus on the customer. While profits and statistical tools seem to get the most publicity, the emphasis on customers is the most remarkable element of Six Sigma. 2. Data and fact-driven management or metrics for decision making. Six Sigma takes the concept of ‘‘management by facts’’ to a new and more powerful level. Instead of basing business decisions on opinions and assumptions, Six Sigma builds the foundation of decision making by using metrics in building up key measures that represent and calculate the success of everything an organization does. 3. Process focus, management, and improvement. Six Sigma positions the process as the key vehicle of success, be it in design of products and services, measuring performance, improving efficiency and customer satisfaction, etc. 25 4. Proactive management. Proactive means action in advance of events rather than reacting to them. An example of proactive management in Six Sigma is the focus on eliminating defects at the source instead of trying to manage the defect or problem after it has occurred. It tries to solve why the bad results are occurring. 5. Boundless collaboration. Boundless means working to break down corporate barriers and to improve teamwork up, down, and across organizational lines. 6. Drive for perfection, tolerate failure. Although these two ideas sound contradictory, they are actually complementary. The bottom line is that any company that makes Six Sigma its goal will have to keep pushing to be more perfect while being willing to accept and manage occasional setbacks. There are several models that can be used in the implementation of Six Sigma in an organization, for example, the five-phase improvement cycle that has become increasingly common in Six Sigma organizations: define, measure, analyze, improve, and control (DMAIC). The steps involved are: • Define. Define the customers, their requirements, the team charter, and the key processes that affect the customers. Goals and/or objectives of a certain process are then set based on the customer’s requirements. • Measure. Identify the key measures, the data collection plan or the plan for measurement for the process in question, and execute the plan for data collection. • Analyze. Analyze the data collected as well as the process to determine the root causes of the problem that need improvement. • Improve. Generate and determine the potential solutions and plot them on a small scale to determine if they positively improve the process performance. Successful improvement methods are then implemented on a wider scale. • Control. Develop, document, and implement a plan to ensure that performance improvement remains at the desired level (Pande et al. 2000; Eckes 2001). 26 The sigma concept of measuring defects was started by Motorola in the early 1980s as a way to develop a universal quality metric that applied regardless of product complexity or dissimilarities between different products or processes. Higher sigma values indicate better products or processes with fewer numbers of defects per unit of product or service. Products produced at a Six Sigma level of quality operate virtually defect-free by definition, with only 3.4 defects per million opportunities (DPMO) as shown in Table 2. Through Six Sigma, every measurable can be compared on the same platform ~through converting yields or DPMO to sigma level!, no matter how different they may be. All the organization needs to do is to set out guidelines in determining measurable during implementation. From Table 2, at 3.8 sigma, companies would be getting it right 99% of the time. This may seem very good, but this 1% margin of error can add up to a lot of mistakes. Chowdhury, 2001 estimates it to be approximately 20,000 lost articles of mail every hour, 5,000 botched surgical procedures every week, and four accidents per day at major airports. Hence six is the sigma level of perfection that companies should be aiming for. The statistical theory of variation for Six Sigma is based on the supposition that all things, when measured fine enough, vary and this is called ‘‘natural variation.’’ Assuming this is true, anything that can be measured on a continuous scale, such as height, length, and weight would follow a bell-shaped curve. Theoretically, this bell-shaped curve also called the ‘‘standard normal distribution’’ or the ‘‘Gaussian Curve’’ after the German mathematician who empirically determined its characteristics! Has been extensively studied and has been proven very useful as numerous natural continuous phenomena seem to follow it or can be approximated by it. The standard normal distribution curve has the following characteristics: • It is bell-shaped and is symmetrical in appearance; • It represents virtually 100% of whatever is being measured, referred to as ‘‘population’’ in statistical terms; • The peak of the curve represents the most commonly occurring value, and 27 • The curve can be divided into a series of segments. Each segment represents a certain percentage of what is being measured. For example, the area under the curve from the center line to the first segment line to the left or right represents approximately 34% of what is being measured, the area of the curve from the first to second segment line represents approximately 14% and so on. The technical name for each segment is the standard deviation from the mean, represented by the lower case Greek letter, sigma. Although the distribution extends to infinity in both directions, usual drawings of the distribution frequently only show the area from 23 standard deviations to 13 standard deviations because this range includes 99.73% of the data. The technical concept of Six Sigma is to measure current performance and to determine how many sigma exists is measured from the current average before customer dissatisfaction occurs. When customer dissatisfaction occurs, a defect (defined as any event that does not meet the requirements) occurs.(Eckes,2001). Six Sigma describes a process that produces no more than 3.4 DPMO, which represents near perfection. For reasons of brevity, this review of the technical concept of Six Sigma has not covered other issues in the Six Sigma literature such as the singlestage process or multistage process. It also does not cover other more complex methods of calculating sigma using the discrete method or the continuous method which involves the capability ratio (CR), the capability index (Cp), and the ‘‘Capability Index compared to some constant (Cpk).’’ Table 2.2 simplified Sigma Conversion 28 2.2.7 Six Sigma as a Quality Movement As a quality movement, Six Sigma is about process capability. It is about reducing the variation in a process, and increasing our control over a process, so that we can predict with considerable accuracy exactly how the process will behave. This level of capability can be used to implement improvements in the process where we set targets for future behaviors, and achieve those targets within the levels of quality control that we choose to design into the improvements. An understanding of Six Sigma Math requires a clarification of a few specific terms that are used by quality professionals, the meanings of which are somewhat narrower than might be expected by a novice: • Defective – Any product or service instance that fails to meet the requirements of the customer, whether or not those requirements were clearly specified. • Defect – Any characteristic of a product or service instance that doesn’t conform to its specification, whether such a specification was explicit or implied. Typically, defective products or services are caused by one or more defects and are referred to as defectives. Not all defects cause defectives. Defects in a product or service that don’t result in the product or service being considered defective are often referred to as latent defects. The distinction between defect and defective is very important in Six Sigma. All processes exhibit some variability in their outcomes. Inevitably, some portion of the output of a process will contain defects. If the variability of a process can be reduced enough, these inevitable defects will be so close to specification that the customer is unlikely to consider the resulting products or services defective. Process variability can be seen by selecting one or more important measurable characteristics from a process and then monitoring those characteristics over time. The tool most likely to be used for such monitoring is the Statistical Process Control Chart, or SPC. The basics of SPC can be used to review the history of thinking about defects leading up to Six Sigma. 29 2.2.7.1. 1.5 Sigma The early quality movement began in the face of very high rates of defectives. A process with a very high defect rate is illustrated in Figure 3. The illustrated process has a quality level of 1.5σ, meaning that the characteristic represented by the chart only falls within the customer’s specification limits about 50% of the time. Figure 2.5 Normal distribution of 1.5 Sigma Because the chart’s control limits would be set at 3σ above and below the target, they do not even appear on the scale of Figure 3. Organizations with defect rates this high were unlikely to be using SPC effectively, but the figure illustrates the problems faced by the early quality movement. 2.2.7.2. 3 Sigma (TQM) With the advent of quality programs in the 1980s, including Total Quality Management (TQM), the use of SPC to monitor and control processes became more common. TQM programs worked to reduce process variation so that most of the expected variability would fall with the customer’s requirements as represented by the specification limits. Figure 4 illustrates a process that has been brought up to a quality level of 3σ, meaning that the defect rate associated with the charted characteristics could be expected to consistently fall below 10%. 30 Figure 2.6 Normal distribution of 3 Sigma TQM thinking aligned defects and defectives. Defectives included any observation outside of the specification limits. Defects included any observation outside of the more restrictive of the control or specification limits. Because many TQM change initiatives designed processes that would achieve customer tolerance, the target control limits often ended up being roughly the same as the customer’s specification limits. The relatively few defect observations that would fall outside of the control limits would be defectives by definition, but the frequency of such observations was dramatically improved compared to pre-TQM programs. 31 2.2.7.3. 3 Sigma with 1.5 Sigma shift One problem with TQM-based alignment of defectives with defects was that processes didn’t remain stable after they were improved. Processes tended to increase their variability over time as a result of everyday deterioration of the conditions under which those processes operated. Such deterioration might include a loss of calibration of sensors, wear and tear on machinery, operator fatigue, supplier quality variation, etc. Process characteristics were seen to wander from their original values by as much as 1.5σ in either direction. This wandering came to be known as the 1.5σ shift, and is illustrated in Figure 5. Figure 2.7 Normal distribution of 3 Sigma with 1.5 Sigma shift This shift resulted in more defects occurring as the process wandered. Under a 1.5σ shift, a process characteristic that had achieved 3σ performance would slip back to 1.5σ performance. Without a proper recognition of the causes of the shift, or corrective actions taken to avoid the shift, it was often perceived that the investment in improving the process had been wasted. TQM programs often fell into disfavor as a result of this fundamental misunderstanding of process behavior. 32 2.2.7.4. 4.5 Sigma For organizations that recognized the problem of shift, the answer became to reduce process variability further in order to allow for the naturally occurring shift. To achieve the benefits of 3σ quality originally achieved by TQM programs, process variability had to be reduced an additional 1.5σ. Figure 6 illustrates such a process characteristic at a 4.5σ quality level. Figure 2.8 Normal distribution of 4.5 Sigma Such low process variability was extremely difficult to achieve, but seemed to provide extremely low defect levels, usually measured in fractions of a percent. In the competitive environment of the late 1980s, such improvements were becoming necessary to survive. 2.2.7.5. 4.5 Sigma with 1.5 Sigma shift The reality of the 1.5σ shift gave rise to the concepts of short-term sigma, and longterm sigma. Short-term sigma was the quality level designed into a process and typically achieved on process launch. Long-term sigma was the expected quality level 33 of the process over the time periods in which the 1.5σ shift could be expected to materialize. Figure 7 illustrates the long term shift of a 4.5σ process back toward 3σ performance. Figure 2.9 Normal distribution of 4.5 Sigma with 1.5 Sigma shift By taking into account the long-term shift associated with all processes, quality improvement programs could provide the 3σ levels of quality originally targeted by the earlier TQM programs. However, along with this realization came increasing pressure to achieve even higher levels of quality in the late 1980s. 2.2.7.6 Six Sigma The Six Sigma movement pushed these concepts to the extreme of targeting 6σ quality levels in the short-term that would achieve 4.5σ quality levels in the long-term. Defect rates at this quality level fall at about 3.4 defects per million opportunities. The variability of a 6σ process relative to its specification limits is illustrated in Figure 8. 34 Figure 2.10 Normal distribution of Six Sigma The quality movement toward Six Sigma effectively decoupled the definition of defects from defectives. At Six Sigma, defectives are still any observation outside of the customer’s specification limits, although such observations become exceedingly rare. Defects remain however, as roughly 3-7% of all observations will continue to fall outside of the control limits. With the control limits at 3σ, and the specification limits at 6σ, the vast majority of defects do not rise to a level close to resulting in a customer defective. Each defect, though, remains an opportunity to continue to improve the process and bring the expected process shift under control. By managing these defects effectively, the process continuously improves without ever producing a defective for the customer. 35 2.2.8 Six Sigma in Construction Six-sigma is a new way of managing business processes. Since its publicized adoption at Motorola and General Electric in the early 1980s, six-sigma has evolved into a leading method for managing process efficiency, not just in manufacturing industry but increasingly in other areas close to project managements’ ‘heart’ such as construction management. It is a formal and disciplined method for defining, measuring, analysing, improving and controlling (DMAIC) processes (see Figure 9). Figure 2.11 Six Sigma DMAIC Process 36 These five steps form the backbone of the six-sigma methodology and work on the principle of a stage/gate process that requires certain deliverables to be met at the gate before the firm can proceed to the next stage or phase (Marves, 2000). Six-sigma has different interpretations and definitions for different applications; in this case we refer to its proposed application to the construction/engineering sector. For this sector, Six-Sigma improvement methods are not about being totally defect-free or having all processes and products at six-sigma levels of performance – another misconception of the six-sigma philosophy (Linderman et al., 2003). The appropriate level will depend on the strategic importance of the process and the cost of its improvement relative to the benefit (Brue, 2002). In the application of six-sigma there are typically a number of common features, which include: it is a top-down rather than bottom-up approach; it is a highly disciplined approach that typically includes five stages (i.e. DMAIC); and it is a data-oriented approach using various statistical and non-statistical decision tools (Klefsjo et al., 2001). This use of a structured approach to improving processes in construction helps to reduce task complexity while increasing performance and commitment from team members (Linderman et al., 2003). The DMAIC methodology simplifies the process improvement project because it acts like a road map for the improvement team. In the manufacturing industry, six-sigma has typically been applied in an organization-wide manner, choosing macro opportunities as Six-Sigma projects. Consequently, in manufacturing, we have tended to witness revolutionary changes. These projects have tended to involve the design and development of an entirely new product or service or the major redesign of an existing one. Conversely, at this stage, the deployment of Six-Sigma in the construction industry has been predominately aimed at micro-opportunities. This means that six-sigma projects would be smaller in scope and likely to relate to a sub-task within a macro opportunity. Keeping with the philosophy of CPI and TQM, the application of SixSigma at this early stage of its development is to argue enhancements for evolutionary rather than revolutionary changes (Maleyeff and Kaminsky, 2002). Applying six-sigma in construction typically involves breaking down large tasks into smaller ones that can be re-engineered and improved. 37 2.2.8.1. Previous Application of Six Sigma In Construction Despite the large number of studies having addressed the concept of quality in construction, there is limited research into the use of Six Sigma as a strategy for process improvement in construction. In 2002, Bechtel Corporation, one of the largest engineering and construction companies in the world reported a savings of $200 million with an investment of $30 million in its Six Sigma program to identify and prevent rework and defects in everything from design to construction.( Eckhouse, 2003) Rodney A. Stewart and Clinton A. Spencer 2006, described in their research study the outcomes of a Six Sigma process improvement project (PIP) conducted for the construction of concrete longitudinal beams on St Pancras raised railway station in London, UK. The outcome of the Six Sigma PIP was the improved productivity of beam construction, enhanced interaction between project teams and reduced project delays. In summary, the Six Sigma approach provided the PIP team with a structured process improvement strategy to reduce waste and other non-value adding activities from the construction process. 2.3 Cast In-Situ Concreting Process Successful concreting relies on two things; firstly the concrete has to be the right specification for the job and secondly it has to be placed correctly. Handling concrete effectively and safely requires careful planning, preparation. Concrete itself consists of a mixture of cement, large fines (usually 20mm aggregate but this is dependent on the application), small fines (usually building sand but this is also job specific) and water. The mix may have other admixtures added for special reasons (waterproofing, frost protection, colour, etc.). 38 2.3.1. Design of Mix & Reinforcing A good design and specification of concrete structures should be followed and any deviations should be fully discussed with the engineer beforehand. The overall job of describing what sort of concrete want has been made easier by the introduction of designated mixes into the British Standard for concrete (BS 5328). However, it is important that a site leader can understand all the possible mixes he may be requested to work with. To arrive at a specification for concrete mix a decision first has to be made as to which of the typical applications given matches with application and whether the concrete will be reinforced or not. Consideration must also be given to the ground conditions and the quality of the water the concrete will come into contact with. For most applications Ordinary Portland Cement (OPC) will be used however other cements exist for specialist applications such as high sulphate resistance (Sulfacrete), high initial strength (Ferrocrete). . 2.3.2 Ready-Mix And Hand Mix Using concrete ready mixed is simpler, quicker and less wasteful. By using hand mix concrete the people that mix the concrete is responsible for ordering and storing the bulk ingredients and ensuring enough competent volunteers to mix and place the concrete. By ordering from a ready mix company the responsibility for all these factors rests with the company. There is an additional direct cost is that ready mix usually costs about twice the price of the raw materials. If ready mix is the chosen technique then the supplier should be given the mix designation, the required workability, the intended placement method and finish required. To make sure that the quality of concrete is going to be right, dealings should only be with suppliers who operate an independent 39 assessed quality system, or from producers who hold third party product conformity certification. 2.3.3 Workability of Concrete As soon as the concrete arrives on site, it needs to be inspected. Check the actual delivery ticket to ensure what has arrived is actually what is ordered (volume, grade, etc.). This is the only chance to get to send it back. Should be checked the workability of the concrete to determine its suitability for placing. On an important job this would be a full slump test (q.v.), however on most sites it usually takes the form of a token load checked for “shovelability”. If testing indicates that the workability is below the lower limit, it is fine for the driver to add water to the load to increase the workability within specified tolerance, this is the usual case as the mix will leave the mixing plant a little drier than specified and water will be added by the driver on delivery. However, if the concrete arrives and find that its workability needs to be increased to assist placing then must be asked for water to be added. But note that if this is done then all liability for the properties of the concrete will be disclaimed by the producer. If the concrete arrives and on site delays make it too stiff to use, then adding water is not the correct solution. A plasticizer admixture should be added for the concrete to reach its lowest possible water content, but still be suitable for placing. Concrete can also arrive too wet due to excess water added at the mixing plant, though this is unusual. If this occurs, the concrete should not be used until the supplier has been contacted and the concrete’s suitability has been checked. 40 2.3.4 Access to Site It is important to check the total weight and axle weight of the wagon. If concrete is to be directly unloaded from the wagon then check the wagon can safely and easily get into position. If it is to be transported by dumper then check the run is short enough to ensure the vibration does not segregate the mix. Another option is the use of a concrete pump. Pumping concrete is a very specialist technique that should be approved by the design engineer and the manufacturer should be made aware of the intention to pump as it will affect the mix required. Further, do not forget to finish off the surface. 2.3.5 Formwork This is the item most often hurried on a concrete pour. The main failing (literally) of concrete shuttering is not understanding how much force a concrete pour hits the ground with or how much weight is associated with a mix (especially if it is being vibrated). Remember that concrete weighs in at 2.4 tons per cubic meter and will be ejected from the back of the wagon at a height of 3 meters so it should not be too much of a shock that poorly erected shuttering often gets swept away. Another most common mistake is that not enough thought has been given to the removal of the shuttering. Another common mistake is designing shuttering with lips, projections or nails that are then gripped by the concrete and become impossible to remove without damage to the face of the pour. Nails should always be on the outside of shuttering and should not be driven fully so that they can be removed easily. Obviously the wood should be shuttering grade or better and it is strongly recommended that the internal faces of the shuttering are coated with a proprietary Mould Release Oil. Oiling the shuttering makes it easier to strike, produces a better 41 finish and allows the ply to be reused many times. Any joints in the shuttering should be sealed otherwise the grout will leak out (especially if vibrated) leaving only the larger fines around the joint producing a distinctive honeycomb effect. The finishing of faces is often specified in the design. A smooth finish that is free of voids and air bubbles and it applies to exposed faces. Other finishes are “brushed” and “wet brushed”. The brush finish is used to provide a rough but regular surface whilst the wet brushed is a refinement of the technique whereby once the surface has undergone the first stages of curing a wet brush is used to wash away the surface grout leaving the larger fines exposed. The common mistake made regarding shuttering is to strike it too early, if this is done then damage may occur not only as the shuttering is removed but also due to the concrete curing too quickly. 2.3.6 Placement Generally any blinding should be good enough to walk on, if not then it is not up to the job of supporting the pour. When preparing an excavation always ensure that all edges and blanks are stable and will not collapse during the placement. Ensure all organic matter is removed and any rubble, dust, etc. is removed. Concrete needs to be placed so that it does not segregate and at a speed which allows it to be compacted properly. This is achieved through placing it in a series of layers. Then the concrete is vibrated to literally shake out the trapped air and encourage the mix to flow to all the extents of the formwork. The layers of concrete should not be too deep otherwise the weight of the material at the top makes it almost impossible to compact the bottom layer. If this happens, air will be trapped in the mix leaving voids and blow-holes that will result in surface blemishes and more importantly a loss of strength. 42 In all cases, a layer must be fully compacted before any more concrete is placed on top of it as voids in the lower concrete cannot be removed once the next layer is placed on top. However, the bottom layer still needs to be workable enough to respond to vibration so that the two layers can knit together without any joints, which is another reason for getting the material into position as quickly as possible. The use of a vibrator will also allow the concrete to flow around coping stones or similar when backfilling thus providing a far better job. Petrol driven vibrators are undoubtedly the most popular but they are notoriously unreliable. Diesel models are slightly heavier and harder to start but more robust. It is also possible to get electric models which are much lighter but more susceptible to damage. Various support systems exist for reinforcing and although they may seem more expensive than half bricks they will remove a common weak point in concrete pours. 2.3.7 Curing Curing is the last and one of the most important stages of concrete construction. The “curing” problem is caused by the concrete giving off heat and shedding water too quickly leading to cracking. If curing is not done properly, the concrete will not develop its full strength. Properly cured concrete is stronger, more resistant to chemical attack and erosion, and more watertight and frost proof. The surface of the concrete is worst affected by poor curing, and it is this skin which gives concrete the ability to withstand wear and that protects both the reinforcement and the ‘heart’ of concrete. Therefore, if concrete is inadequately cured the effectiveness and the life-span of the concrete will be reduced. It is, therefore, important for curing to take the proper time and this can be achieved in one of two ways: 43 • The first involves keeping the concrete moist by the use of ponding, spraying/sprinkling, damp sand or hessian. • The second method prevents the loss of moisture from the concrete by covering it with polythene sheeting, spraying on a curing membrane or leaving the formwork in place. The first methods are undoubtedly the more correct. However, they are expensive, labor intensive and time consuming. The second group of methods, while not so efficient, are usually satisfactory for all except very special work and they can be carried out more easily. Note that curing strengths given in specifications relate to the strength of the concrete after 28 days. 44 Figure 2.12 Operations involved in traditional concrete construction 45 2.4 Reinforced Concrete Cracks 2.4.1. Structural Cracks The structural crack results from the tensions that the structure must carry due to its function. They take place in structures without projects, and when the ground problem is not solved, and are very dangerous; they have nothing to do with the concreting and the concreting conditions. In such cases we must certainly consult the relevant authorities (engineering office, university etc.). No such problem is witnessed when the structure is engineered properly and when there is no overloading. These types of cracks occur vertically to the tensile strengths in reinforced concrete agents. Cracks occurring in the middle of a simple girder interval or on a corbel bearing are of this type. 2.4.2 Application Based Cracks This type of crack is seen in fresh concretes or over aged concretes. 2.4.2.1 Fresh Concrete Cracks Fresh concrete cracks occur within the first 30 minutes to 5 hours following the placement of the concrete to the formwork, generally in concretes with wide surfaces such as floor concretes. The depth of these cracks can reach 10 cm and their length can vary from a few centimeters to 2m. Deep and long cracks can be very harmful to the concrete in terms of its strength and durability. The two most significant reasons for fresh concrete cracks are settlement differences and plastic shrinkage. 46 2.4.2.2 Settlement Cracks These cracks occur in newly poured concretes in which concrete cover is forgotten, cure isn’t applied and excessive water is added, in reinforced concrete agents with voids, in areas having too many reinforcements, on the reinforcements close to the surface, and when the placement isn’t done properly. In fresh concrete, the water containing cement particles rise up to the surface, while the big aggregate grains sink to the bottom. The girders and floor reinforcements close to the surface resist this replacement and the fresh concrete can not settle completely in these regions. The unsettled concrete cracks throughout the steel. There is less settlement in flooring due to its fineness and so cracks aren’t seen very often. There is more settlement in girders due to their depth, and the map of the steel rods is seen on the concrete surface; the cracks make the reinforcement places visible. As the water content of the concrete increases, the amount of settlement increases. The settlement, and thus the cracks, increases unless the concrete is placed, compacted and vibrated properly. The way to prevent these cracks is to use concrete in normal consistency (- 12 cm slump), avoid concretes to a high consistency with excessive water, and apply good vibration to the concrete. 2.4.2.3 Plastic Shrinkage Cracks This type of crack, randomly spread in various sizes, may occur especially on concretes (floor, ground, road, port etc.) poured on windy days, with low humidity, and high temperature. The crack width is usually less than 1 mm and it is on the surface, not deep. It is not dangerous in terms of the building’s safety. When floor concrete is poured, the water in the upper surface starts to vaporize. It leaves the concrete and rises into the air. In place of this water, the water inside the concrete comes up to the surface. If the speed of vaporization is higher than that of the water coming up to the surface the surface starts to dry, and therefore to shrink and crack. The same cracks may result from the absorption of the concrete water by other materials such as briquettes in hollow-tile floor slabs or moisturized concretes. Factors increasing the vaporization speed are: 47 Air Temperature: The higher the temperature, the more the vaporization. The increase of the temperature increases the vaporization approximately twofold. If the concrete is hotter than the air, the vaporization speeds up. The Humidity of the Air: The less the humidity in the air, the more and the easier the vaporization. The vaporization increases fivefold when the relative humidity decreases from 90% to 5%. The Speed of the Wind: The more the wind, the faster the vaporization. The vaporization increases fourfold when the wind speed increases from 0 to 20 km/h. Sun Rays: If the concrete surface is open to direct sunlight, the temperature of the concrete and therefore the speed of the vaporization increases. The two main factors affecting the water desorption speed of the concrete are the compactness of the concrete and the granulometry of the aggregates. The less voids in the aggregate granulometry, the higher the strength in the concrete, however since there aren’t too many voids, it gets harder for the desorption water to go up; it delays and the desorption speed decreases. As long as the desorption water can’t replace the vaporization water, the concrete surface dries and cracks. In ready-mixed concrete, there are more shrinkage cracks because the granulometry is well adjusted so that desorption becomes difficult. These are the precautions to be taken in order to decrease shrinkage and the cracks caused by shrinkage: • Avoid the formwork agents absorbing the concrete water and speed up concrete’s desiccation by moisturizing the formwork and the reinforcement bar. • Protect the concrete from the sun (by pouring at night), and the wind (by means of a wind screen). 48 • Avoid water vaporization (by covering with wet burlaps, nylon blankets or by sprinkling cure materials). • Pour concrete very quickly by using a sufficient number of quality workers, apply surface finishing and start the cure as soon as possible, and continue the cure for at least 3 days. Plastic shrinkage cracks may occur in 30 - 45 minutes, which is even before the concreting is completed. Therefore the desiccation precautions should be taken for the poured parts while the concreting still goes on. These precautions can be taken step by step as the surface finished pieces are covered with wet burlaps, nylon blankets and sprinkled with cure materials. Otherwise, the concrete cracks in different amounts, varying according to the temperature, humidity and wind conditions. It is in your power to reduce and minimize these cracks. 2.4.2.4 Over Aged Concrete Cracks This type of crack may be seen in concretes of different age groups (from few week old concretes to 30 year-old concretes). The cracks are chemical or physical based. These cracks seem like hairlines at the beginning but then they grow and combine. Stripping, outpouring and bursting occur following the crack formation. If no precautions are taken, the reinforced concrete agents fall completely into ruin as time passes. Among the reasons of these types of cracking, freezing - thawing, alkali -active silica reaction, carbonation, corrosion of the reinforcements and reactions caused by harmful materials such as sulphate, acids and salts can be counted. 49 50 CHAPTER 3 Methodology 3.1 Introduction There are various steps that can be adopted to fulfil the objectives of this study. Due to the numbers of the objectives in this study these steps have been defined. 3.2 Method of Data Collection Some of the data collected is form a literature review, which focused on Six Sigma problem solving approach and methodology, tools and techniques, besides, factors affecting to produce plastic crack. Further, some of data collected from questionnaire through professionals to determine potential and frequency of root causes of plastic crack in cast in-situ slab concreting process. 3.3 Data Collection Data collection which have been done relatively under objectives of study are in order as shown as below: • Conducting literature review on Six Sigma problem solving approach (DMAIC) 51 • Conducting literature review for indentifying plastic crack root causes and close group discussion through professionals. • Conducting multiple choice questionnaire for determining potential level of root causes to produce plastic crack in cast in-situ slab concreting process besides close group discussion. • Conducting multiple choice questionnaire to determine frequency of each root causes in cast in-situ slab concreting process besides close group discussion. 52 53 CHAPTER IV DATA ANALYSIS 4.1 Introduction This chapter finding the objectives 1 and 2. The findings of objective 1 is made through the study path to proposing one check sheet to fulfill the requirement of objective 2. Objective 1: To Identify and analyze of plastic crack root causes according to Six Sigma problem solving approach According to DMAIC methodology of Six Sigma problem solving study goes to achieve result of each stage of DMAIC methodology by step by step validation through close group discussion and questionnaire surveyor with related experts. At the first stage of DMAIC methodology of Six Sigma methodology study was carried out to define and identify problematic area and goal of application of Six Sigma problem solving on it. According to concept of define phase of DMAIC methodology with respect of scope of this study, cast in-situ concreting process have been selected for applying Six Sigma on it. Actually Quality of concrete depends on the constituent materials, their proportions, mixing, transporting, placing, compaction and curing of concrete. By not 54 enough attention to those items, Sometimes, concrete does not perform satisfactorily in the service life. One of the outcomes is fresh concrete cracks. The two most significant reasons for fresh concrete cracks are plastic settlement and plastic shrinkage. By above consideration this study define plastic crack as a problem which is introduced after few hours finishing cast in-situ concreting process in slabs. And this study tries to decrease or even eliminate the number of plastic cracks during this specific times as a scope by applying DMAIC Six Sigma problem solving approach. Actually this is the goal of this Six Sigma problem solving. Accordingly the number of plastic crack after finishing cast in-situ slab concreting process is the problem which is focused in this research study. 4.2 DPMO Calculation of Current Cast-In-Situ Slab Concreting Process According to concept of measure phase of DMAIC problem solving methodology of Six Sigma study was carried out to evaluate the sigma level of current cast in-situ slab concreting process by respect of DPMO’s concept. For this achievement, study was carried out to collect specific data from the current cast in-situ concreting process in University Technology Malaysia (UTM) “Cadangan Membina dan Menyiapkan Bangunan Tambahan Fakulti Alam Bina ( RMK9) di Universiti Teknologi Malaysia, Skudai, Johor Bahru, Johor, 81310” by investigation during the process performance and gather data during the process and also after finishing cast in-situ slab concreting process to achieve total number of cracks which is appeared in slabs. For this achievement researcher selected 5 slab as a focus. By two times checking each slab during few hours (6 hours ) after finishing concreting process researcher found 8 crack which is appeared during that time on slabs. Photos show below are the concreting process and total number of crack which is investigated. 55 Figure 4.1 Concreting Process 56 57 Figure 4.3 Concreting Process 58 Figure 4.4 Cracks which is investigated from the site 59 Data gathered during site visit determine the sigma level of current cast in-situ slab concreting process as below with respect of DPMO formula: By putting relevant data which is gathered during site investigation the DPMO (Defect Per Million Opportunity) has been calculated by using above actual formula. And by refer to the Six Sigma table the sigma level of current cast in-situ concreting process was achieved. In order to calculate the DPMO, three distinct pieces of information are required: • The number of units produced ( number of slabs unit which is checked ) = 5 slabs • The number of opportunities per unit ( number of checking which is checked for per slab ) = 2 times • The number of defects ( number of cracks which is found after few hours after process finished ) = 8 cracks 60 𝐒𝐒𝐒𝐒𝐒𝐒𝐒𝐒𝐒𝐒 𝐐𝐐𝐐𝐐𝐐𝐐𝐐𝐐𝐐𝐐𝐐𝐐𝐐𝐐 𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋𝐋 = 𝟎𝟎. 𝟖𝟖𝟖𝟖𝟖𝟖𝟖𝟖 + �𝟐𝟐𝟐𝟐. 𝟑𝟑𝟑𝟑 − 𝟐𝟐. 𝟐𝟐𝟐𝟐 ∗ 𝐥𝐥𝐥𝐥(𝑫𝑫𝑫𝑫𝑫𝑫𝑫𝑫) By above calculation the DPMO was calculated 160000 and by referring to Six Sigma table the sigma level of current cast in-situ slab concreting process was achieved as 2.5. From here, the approximate how much far from the Six Sigma level determine. It then push the process to achieve better sigma level in comparison with pervious process. 61 Identify Causes & Root Causes of Plastic Crack in Cast-In-Situ Slab Concreting Process After calculation of DPMO and sigma level of current cast in-situ slab concreting process, study was carried out to on collected data and related information from related professionals and review a literature to find which categories and factors involved to produce plastic crack as a defect during cast in-situ slab concreting process. For this achievement, this study used Fish Bone Diagram ( one of the Six Sigma problem solving tools ) to determine causes and root causes of plastic crack defect during cast insitu concreting process. 62 63 64 65 After that, by close group discussion with 3 related experts the 44 root causes has been found in 5 categories namely labour factor, materials factor, design & detailing factor, equipment factor and environment factor. Table 4.1 shows the root causes in each categories. 66 Table 4.1 Plastic Crack’s Root Causes 67 According to total number of root causes in each category, Pareto chart below shows the total number of root causes in each category and cumulative percentage of each category involved to produce plastic cracks in cast in-situ slab concreting process. The Pareto chart shows the first 4 categories ( design & detailing, labor, environment and materials) cover 89% of the total root causes which is involved to produce plastic crack in cast in-situ concreting process. Figure 4.6 Pareto Chart of Root Causes in Each Category 68 Identify Potentials Level of Each Root Causes Because of the each root cause does not have the same potential to produce plastic crack in cast in-situ slab concreting process, study was carried out to determine the potential of each root causes for producing plastic crack in cast in-situ slab concreting process with respect of pervious knowledge and experiences of related experts. For this achievement study was carried out to conduct multiple choice questionnaire to 3 professionals and close group discussion with them to finding potential of each root causes to produce plastic crack during cast in-situ slab concreting process. For this achievement four potential level has been defined to the questionnaire namely very low level potential, mean level potential, high level potential and very high level potential. And table below shows the percentage of each category in each potential level according to number of root causes in each category which is place in each potential level. Tbale 4.2 Percentage of each category in each potentia level according to number of root causes in each category As is mentioned in above table all professionals did not believe that any of these root causes having very low potential level to produce plastic crack in cast in-situ slab concreting process. And also that table shows that labor and design & detailing category having more percentage according to number of root causes which is placed in all potential levels. 69 Identify Frequency Level of Each Root Causes Further, to achieve some additional useful data, study was carried out to determine frequency of each root causes during cast in-situ slab concreting process with respect of pervious experiences of related experts in this particular manner. For achieving this specific information study was carried out to conduct multiple choice questionnaires through 3 professionals by defining 3 frequency level in questionnaires ( frequency less than 5 processes out of 10 processes, between 5 and 8 processes out of 10 processes and more than 8 processes to 10 processes). Below table shows the percentage of each category in each frequency level by considering number of root causes which is placed in each frequency level. Table 4.3 Percentage of each category in each frequency level according to number of root causes in each category According to above table, labor and design & detailing category having more percentage according to number of root causes which is placed in all potential levels. So, problem related to labor and design & detailing factors more occur during cast insitu slab concreting process in comparison with other categories. 70 Proposed Check Sheet for Real Time Improving Cast-In-Situ Slab Concreting Process Objective 2: To propose check sheet for real time problem solving cast in situ slab concreting process from the outputs of pervious objective. To achieve the purpose of last objective study was carried out to propose check sheet by the outputs of pervious objective. And the check sheet has been proposed for real time problem solving cast in situ slab concreting process by the result of pervious objective. The proposed check sheet are as follows: 71 72 73 74 Explanation of Items of Proposed Check Sheet • By refer to the proposed check sheet all items which is placed in specific check sheet are as follows: • Categories which is involved to produce plastic crack in cast in-situ slab concreting process • Specific root causes in each category which is had more influence to produce plastic crack in cast in-situ slab concreting process • Specific potential of each root causes to produce plastic crack in cast insitu slab concreting process by specific sign color which is defined for each potential level • Specific frequency of each root causes with respect of pervious experiences of related experts by specific sign color which is defined for each frequency level • Specific slab concreting process by separation in each floor of construction project • Specific area for mentioning “ √ “ or “ × “ to determine which root causes has been eliminated or not. If one root cause has been eliminated the “ √ “ sign has been mentioned in specific area and, if one root cause has not been eliminated the “ × “ sign has been mentioned in specific area. • Further, specific area for calculating the total number of the “ × “ sign in each slab concreting process in each floor 75 Explanation of Proposed Check Sheet Actually all of those items which is mentioned earlier help us to achieve specific results that is main reason for proposing check sheet. In fact, by using this specific check sheet on site during the cast in-situ slab concreting process we can determine which root causes exist in current cast in-situ concreting process before starting the process. And by this consideration we can identify root causes which is introduced in current process and we have excellence view about them for eliminating them before starting the process so that they never occur at the first place. And by this root cause elimination before starting concreting process we could decrease propensity to produce plastic crack during cast in-situ slab concreting process. And specific potential of each root causes in this check sheet help us to identify which root cause which is introduced in current concreting process has most powerful potential to produce plastic crack so that eliminate those at first and rapidly. And also consideration of potential of each root causes help us to do not skip or ignore some root causes which is had high potential level to produce plastic crack in cast in-situ concreting process. Further, frequency of each root causes in this check sheet help us to evaluate our current cast in-situ slab concreting process which is placed in which frequency level in comparison with current position of cast in-situ slab concreting process as a whole. And also push us to improve our current process to decrease of root causes’ number which is produced in current cast in-situ slab concreting process for future concreting process. 76 In fact, by using this check sheet on site during cast in-situ slab concreting process, if specific root cause has been eliminated, so we must mention “√ “ sign and, if specific root cause has been not eliminated, so we must mention “ × “ sign. After that, by calculating total number of “ × “ we can evaluate how many root causes has been eliminated in comparison with pervious slab concreting process and tries to decrease number of “ × “ in next slab concreting process for achieving zero number of “ × “ in slab concreting process. It means that we have eliminated all root causes, so concreting process have a very low potential as whole to produce plastic crack. And also by crack investigation after finishing slab concreting process we can determine the sigma level of each slab concreting process. Therefore, we can compare every slab concreting process with consideration of sigma level of each slab concreting process to determine how much far from the six sigma level are we?. And this consideration of sigma level for each slab concreting process or even each floor concreting process encourage us to achieve better sigma level in next slab concreting process. And this consideration encourage everyone which is involved the process to achieve best sigma level as a target. 77 CHAPTER 5 CONCLUSION & RECOMMENDATION 5.1 Conclusion Study was carried out step by step according to DMAIC methodology of Six Sigma approach. First the problem and project’s goal is defined after that Sigma level of current cast in-situ slab concreting process is calculated by gathering relevant data from the site investigation. After that study was carried out to find root causes of plastic crack in cast in-situ slab concreting process. For achieving useful information to propose check sheet, study was carried out to determine potential and frequency level of each root causes with respect of previous concreting process experiences from related experts. And then, study carried out to propose check sheet for real time improving and controlling the cast in-situ slab concreting process during process of work. Further, DMAIC “ Define- Measure- Analysis- Improvement- Control” methodology of Six Sigma problem solving has been adopted for cast in-situ slab concreting process through step by step validation through professionals with conducting questionnaire and close group discussion. 5.2 Recommendation This methodology (DMAIC) can be suitable for other processes in construction projects to identify defect and eliminating them in systematic and organized way. Identifying more root causes by investigating on site during specific process and make check sheet more updated. Implementing proposed check sheet in a case study to capture results in real condition. For future study can be recommended that to conduct research study to fine proper and more powerful methods for eliminating each root 78 causes during process of work. And also for future study can be recommended that to have effective outcome it is better to prepare software which is consist of all check sheets related to process that can be run on cell phone for using during process of work. This consideration can be more useful to achieve the zero defect target as an outcome of a specific process. And, go to granular level of defect of process and documenting in the newly proposed check list. 79 References Bamford, D.R; Greatbanks R.W. The use of quality management tools and techniques: a study of application in everyday situations. International Journal of Quality & Reliability Management, 22(4):376-392, 2005. Bergmann, Ralph (2002), Experience Management: Foundations, Methodology, and Internet-Based Applications, Springer, Germany. Development Eckhouse, 2003. In Pursuit of Perfection. Bechtel Briefs, August. Available online via !http://www.bechtel.com/sixsigma.htmO (accessed March.2, 2004). Hagemeyer, C; Gershenson, J.K; Johnson D.M. Classification and application of problem solving quality tools: A manufacturing case study. The TQM Magazine, 16(5):455-483, 2006. Hahn, G., Hill, W. and Hoerl, R. (1999) The impact of six sigma improvement – a glimpse into the future of statistics. The American Statistician, 53(3), 208–15. Harry, M., and Schroeder, R. ~2000!. Six Sigma: The breakthrough management strategy revolutionizing the world’s top corporations, Doubleday, New York. Hart, A. (1992), Knowledge Acquisition for Expert Systems. 2 nd ed., McGraw-Hill, New York. Hagemeyer, C; Gershenson, J.K; Johnson D.M. Classification and application of problem solving quality tools: A manufacturing case study. The TQM Magazine, 16(5):455-483, 2006. Klefsjo, B., Wiklund, H. and Edgman, R. (2001) Six sigma seen as a methodology for total quality management. Measuring Business Excellence, 5(1), 31–5. Li, H. and Love, P.E.D. (1998) Developing a theory of construction problem solving, Construction Management and Economics, Vol. 16, No. 6, 721-727. Love, P.D., Edum-Fotwe, F., Irani, Z. Management of knowledge in project environments, International Journal of Project Management, Vol. 21, No 3, 2003, pp. 155-156. Nadica Hrgarek and Kerri-Anne Bowers, Integrating Six Sigma into a Quality Management System in the Medical Device Industry, JIOS, VOL. 33, NO. 1 (2009). Pfeifer, T; Reissiger, W; Canales C. Integrating six sigma with quality management systems. The TQM Magazine, 16(4):241-249, 2004. 80 Robinson, H.S. Knowledge Management practices in large construction organizations, Engineering, Construction and Architectural Management, Vol. 12, No 5, 2005, pp. 431445. Stewart, Rodney A. and Spencer, Clinton A.(2006)'Six-sigma as a strategy for process improvement on construction projects: a case study',Construction Management and Economics,24:4,339 — 348. Tennant, G. (2001) Six Sigma: SPC & TQM in Manufacturing and Services, Gower Publishing, Hampshire. Wantanakorn, D., Mawdesley, M. and Askew, W. (1999) Management errors in construction. Engineering, Construction and Architectural Management, 6(2), 112–20. Yu, W.D., Lin, C.T., Yu, C.T., Liu, S.J., Luo, H.C., and Chang, P.L. (2007) Integrating emergent problem-solving with construction knowledge management system,” Proceedings of the CME 25 Conference, July 16~18, 2007, University of Reading, UK, 10 pp. Ma, Y., Tan, M. & Wu, K. (2002). Effect of different geometric polypropylene fibers on plastic shrinkage cracking of cement mortars, Materials and Structures 35 : 165-169. Branch, J., Rawling, A., Hannant, D.J. & Mulheron, M. (2002). The effects of fibers on the plastic shrinkage cracking of high strength concrete, Materials and Structures 35 : 189-194. Concrete Q & A, “Estimating Evaporation Rates to Prevent Plastic Shrinkage Cracking”, Concrete International, March 2007 Menzel, Carl; “Cause and Prevention of Cracks Developing in Plastic Concrete,” Portland Cement Association, Annual Meeting 1954. 81 APENDICES 82 QUESTIONNAIRE FORM A The purpose of this questionnaire is to get potential level of each root causes of plastic crack in cast in-situ slab concreting process during process of work. Root causes divided to five categories consist of Labor category, Design and Detailing category, Environment condition category, Material category and Equipment category. Please kindly answer the questions based on your experience and knowledge in cast in-situ slab concreting process by tick … in the box as shown using the rating scale below. Your co-operation is extremely appreciated. Thank you. Rating Scale: 1. 2. 3. 4. 5. = = = = = Very Low Potential Low Potential Mean Potential High Potential Very High Potential a) Root causes related to labor categories: 1. Rapid screeding 2. Late starting curing 3. Keeping surface wet lower than 3 days 4. Rapid trowelling 83 5. Improper placement of rebar; 6. Omitted rebar; 7. Insufficient vibration; 8. Excess vibration; 9. Improper reading design detail sheet; 10. Unwashed aggregate; 11. Rapid drying; 12. Incorrect using materials; 13. Reinforce moving; 84 14. Formwork moving; b) Root causes related to Design and Detailing category 1. Inadequate thickness or thinner section 2. Inadequate reinforcing 3. Incorrect geometry 4. Incorrect detailing 5. Low water content 6. Low slump 7. Depth of cover to the reinforcement greater than one third of the section depth 85 8. Decreasing cover limited range 9. Abrupt changes in section depth 10. Increasing bar size 11. Improper selection of reinforcement 12. Improper detailing reinforcement 13. High water contents 14. Increasing slump 15. Mix proportion tendency to bleed 86 c) Root causes related to materials 1. Poor quality of materials 2. Poor quality of reinforcement 3. Use retarders which increased time that it remains in plastic state 4. High proportion of fine materials 5. Low pozzolanic additions 6. High sedimentation 87 d) Root causes related to equipment category 1. Use leaking forms 2. Highly flexible forms 3. Not adequate braced forms 4. Shortage of equipments 5. Broken equipment e) Root causes related to environment conditions 1. Wind velocity excess of 5 mph 2. Low relative humidity 88 3. High ambient temperature 4. Large difference temperature between air and concrete 5. Large difference temperature between concrete and formwork 89 QUESTIONNAIRE FORM The purpose of this questionnaire is to get frequency level of each root causes of plastic crack in cast in-situ slab concreting process during process of work. Root causes divided to five categories consist of Labor category, Design and Detailing category, Environment condition category, Material category and Equipment category. Please kindly answer the questions based on your experience and knowledge in cast in-situ slab concreting process by tick … in the box as shown using the rating scale below. Your co-operation is extremely appreciated. Thank you. Rating Scale: 6. 7. 8. = = = Less than five out of ten cast in-situ concreting process Between five and eight out of ten cast in-situ concreting process More than eight to ten cast in-situ concreting process f) Root causes related to labor categories: 15. Rapid screeding 16. Late starting curing 17. Keeping surface wet lower than 3 days 18. Rapid trowelling 90 19. Improper placement of rebar; 20. Omitted rebar; 21. Insufficient vibration; 22. Excess vibration; 23. Improper reading design detail sheet; 24. Unwashed aggregate; 25. Rapid drying; 26. Incorrect using materials; 27. Reinforce moving; 91 28. Formwork moving; g) Root causes related to Design and Detailing category 16. Inadequate thickness or thinner section 17. Inadequate reinforcing 18. Incorrect geometry 19. Incorrect detailing 20. Low water content 21. Low slump 22. Depth of cover to the reinforcement greater than one third of the section depth 92 23. Decreasing cover limited range 24. Abrupt changes in section depth 25. Increasing bar size 26. Improper selection of reinforcement 27. Improper detailing reinforcement 28. High water contents 29. Increasing slump 30. Mix proportion tendency to bleed 93 h) Root causes related to materials 7. Poor quality of materials 8. Poor quality of reinforcement 9. Use retarders which increased time that it remains in plastic state 10. High proportion of fine materials 11. Low pozzolanic additions 12. High sedimentation 94 i) Root causes related to equipment category 6. Use leaking forms 7. Highly flexible forms 8. Not adequate braced forms 9. Shortage of equipments 10. Broken equipment j) Root causes related to environment conditions 6. Wind velocity excess of 5 mph 7. Low relative humidity 95 8. High ambient temperature 9. Large difference temperature between air and concrete 10. Large difference temperature between concrete and formwork 96 Six Sigma Conversion Table Yield % Sigma Defects Per Million Opportunities 99.9997 6.00 3.4 99.9995 5.92 5 99.9992 5.81 8 99.9990 5.76 10 99.9980 5.61 20 99.9970 5.51 30 99.9960 5.44 40 99.9930 5.31 70 99.9900 5.22 100 99.9850 5.12 150 99.9770 5.00 230 99.9670 4.91 330 99.9520 4.80 480 99.9320 4.70 680 99.9040 4.60 960 99.8650 4.50 1350 99.8140 4.40 1860 99.7450 4.30 2550 99.6540 4.20 3460 99.5340 4.10 4660 99.3790 4.00 6210 99.1810 3.90 8190 98.9300 3.80 10700 98.6100 3.70 13900 98.2200 3.60 17800 97.7300 3.50 22700 97.1300 3.40 28700 96.4100 3.30 35900 97 95.5400 3.20 44600 94.5200 3.10 54800 93.3200 3.00 66800 91.9200 2.90 80800 90.3200 2.80 96800 88.5000 2.70 115000 86.5000 2.60 135000 84.2000 2.50 158000 81.6000 2.40 184000 78.8000 2.30 212000 75.8000 2.20 242000 72.6000 2.10 274000 69.2000 2.00 308000 65.6000 1.90 344000 61.8000 1.80 382000 58.0000 1.70 420000 54.0000 1.60 460000 50.0000 1.50 500000 46.0000 1.40 540000 43.0000 1.32 570000 39.0000 1.22 610000 35.0000 1.11 650000 31.0000 1.00 690000 28.0000 0.92 720000 25.0000 0.83 750000 22.0000 0.73 780000 19.0000 0.62 810000 16.0000 0.51 840000 14.0000 0.42 860000 12.0000 0.33 880000 98 10.0000 0.22 900000 8.0000 0.09 920000