THE APPLICATION OF “PAY WHEN PAID” PROVISIONS IN CONSTRUCTION SUB-CONTRACT NASYIRA BINTI IBRAHIM UNIVERSITI TEKNOLOGI MALAYSIA THE APPLICATION OF “PAY WHEN PAID” PROVISIONS IN CONSTRUCTION SUB-CONTRACT NASYIRA BINTI IBRAHIM A project report submitted in partial fulfillment of the requirements for the award of the degree of Master of Science (Construction Contract Management) Faculty of Built Environment Universiti Teknologi Malaysia JULY 2009 iii DEDICATION Specially dedicated ……… To my parents …… ‘Encik Ibrahim Mohd Amin & Puan Jaradah Hj Abdul Majid’ To my sisters …… ‘Nadya Alina, Nadwanie Harniza, Nazlin, Nazirah’ To my brother …… ‘Mohd Nazriey’ To my lovely friends …… ‘Sakina, Hairani, Roslinda, Haizan’ ………………………………… Thank you for everything iv ACKNOWLEDGEMENT A debt of gratitude is owed to many individuals who have given me the benefit of their unconditional help, tolerance and knowledge in writing and completing this master project. First for all, I would like to express my highest gratitude to my supervisor, Encik Norazam Othman for his guidance, advice and support in order to complete this master project. Next, to my special thanks are due to all the lecturers for the course of Master of Science (Construction Contract Management), for their patient and kind advice during the process of completing of master project. Not forgetting my dearest parents, brothers and sisters, a token of appreciation goes to then for giving full support. Lastly, I would like to express my special thanks my fellow classmates, who have in their own way helped me a great deal throughout the preparation and production stages of this master project. v ABSTRACT For years, general contractors have often enclosed a contractual provision of “pay when paid” in their subcontracts providing that payment to the subcontractor is conditioned upon the general contractor’s actual receipt of payment from the owner. “Pay-when-paid” clauses while seemingly straightforward at first glance but many are actually ambiguous. Instead of “pay when paid” arrangement waiving the right of the subcontractor to be paid, there is competing argument that this clause speaks to timing of payment. Hence, this research intends to identify whether “pay when paid” arrangement in construction subcontract waiving the right of the subcontractor to be paid or simply a timing mechanism. This research was carried out mainly through documentary analysis of law journals and law reports. Results shows that 8 out of 11 cases identify that “pay when paid” provision in the sub-contract constitute as timing mechanism. “Pay When Paid” provision may become either as timing mechanism and waiving the subcontractor right to be paid. Most of the cases cited that wording of the contractual language in the sub-contract is critical in identify the application of “pay when paid” provis ion. Unambiguously and sufficiently clearly contractual language must have been used in order for a court to construe such a clause imposed payment to the main contractor as condition precedent to the subcontractor’s right to be paid, rather than limiting the time for payment. Once a judge decides that provision is ambiguous there is nothing for the jury to decide or interpret. Therefore, the subcontractor may take the legal action to challenge the enforceability of the clause to seek immediate payment when they have suffering the risk of non-payment due to the performance problems unrelated to their own work. vi ABSTRAK Selama bertahun-tahun, kontraktor utama kerap kali memasukkan peruntukan berkontrak “bayar apabila dibaya r” dalam sub-kontrak pembinaan dengan memperuntukkan bahawa pembayaran kepada subkontraktor berdasarkan keadaan kontraktor menerima pembayaran sebenar daripada pemilik. Kluasa “bayar apabila dibayar” sekilas pandang jelas dan mudah maknanya tetapi kebanyakkannya adalah kabur maknanya. Selain daripada provisyen “bayar apabila dibayar” mengenetepikan hak subkontrak untuk mendapat pembayaran, terdapat percaturan lain yang menyatakan bahawa klausa ini bercakap mengenai masa untuk mendapatkan pembayaran. Oleh itu, kajian ini bertujuan untuk mengenalpasti samada peruntukan “bayar apabila dibayar” di dalam sub-kontrak pembinaan mengenepikan hak subkontraktor untuk mendapatkan pembayaran atau ianya mengenakan tempoh masa untuk membuat pembayaran. Kajian ini dijalankan melalui analisis dokumen, iaitu laporan dan jurnal undang-undang. Kajian ini menunjukkan 8 daripada 11 kes menunjukkan klausa “bayar apabila dibayar” mengenakan tempoh masa untuk membuat pembayaran. Peruntukan “bayar apabila dibayar” boleh dianggap sebagai mekanisme masa dan juga sebagai mengenepikan hak subkontraktor untuk mendapat pembayaran. Kesuluruhan kes menyatakan bahawa bahasa kontrak adalah kritikal (amat penting) dalam menentukan aplikasi klausa “bayar apabila dibayar”. Klausa yang cukup jelas dan terang tanpa maksud yang samar adalah penting untuk memastikan mahkamah memutuskan bahawa klausa tersebut mengenakan pembayaran kepada kontraktor adalah duluan kepada hak subkontraktor untuk dibayar, selain daripada menghadkan tempoh pembayaran. Apabila hakim memutuskan apabila klausa tersebut samar maknanya adalah tiada kemungkinan untuk juri dan hakim untuk memutuskan dan mengolahkannya lagi. Oleh itu, subkontraktor boleh mangambil tindakan mahkamah dalam mencabar keberkuatkuasaan klausa tersebut dalam mendapatkan pembayaran secara cepat apabila mereka dalam risiko tidak dibayar berdasarkan masalah perlaksanaan yang tiada kaitan dengan kerjanya. vii TABLE OF CONTENT CHAPTER TITLE PAGE DECLARATION....................................................................................... ii DEDICATION.......................................................................................... iii ACKNOWLEDGEMENT....................................................................... iv ABSTRACT ............................................................................................... v ABSTRAK ................................................................................................ vi TABLE OF CONTENTS ....................................................................... vii LIST OF TABLES .................................................................................... x LIST OF ABBREVATIONS ................................................................... xi LIST OF CASES .................................................................................... xiii LIST OF APPENDICES ...................................................................... xvii 1 INTRODUCTION..................................................................................... 1 1.1 Background of Research ....................................................................... 1 1.2 Problem Statement ................................................................................ 3 1.3 Objective of Research ........................................................................... 8 1.4 Scope and Limitation of Research ........................................................ 8 1.5 Significance of Research....................................................................... 9 1.6 Research Methodology.......................................................................... 9 1.6.1 Stage 1: Identifying the Research Issue ..................................... 10 1.6.2 Stage 2: Literature Review ......................................................... 10 1.6.3 Stage 3: Data Collection............................................................. 11 1.6.4 Stage 4: Data Analysis ............................................................... 11 1.6.5 Stage 5: Conclusion and Recommendations .............................. 12 viii 2 LIABILITY OF THE SUB-CONTRACTOR ...................................... 13 2.1 Introduction ......................................................................................... 13 2.2 The Contractual Chain ........................................................................ 14 2.3 The Contractual Status of a Subcontractor with the Owner................ 15 2.4 Liability of the Sub-Contractor ........................................................... 16 2.4.1 Liability in Contract .................................................................... 16 2.4.2 Liability in Tort ........................................................................... 17 2.5 Legal and Contractual Background of Subcontractor Rights to Payment ........................................................................................... 18 2.6 Relationship of Subcontractor’s Statutory Right to Recover for Non-Payment with “Pay When Paid” Provisions in the Sub-Contract ......................................................................................... 19 2.6.1 Security of Payment ..................................................................... 19 2.6.2 Enforcement of Payment .............................................................. 21 2.7 Summary .............................................................................................. 22 3 APPLICATION OF “PAY-WHEN-PAID” PROVISIONS IN SUB-CONTRACT .............................................................................. 23 3.1 Introduction .......................................................................................... 23 3.2 Definition of “Pay When Paid” ............................................................ 25 3.3 “Pay When Paid” Provisions in Sub-Contracts.................................... 26 3.4 Non-Payment by the Employer/Owner (Relying on “Pay When Paid” Provision in Sub-Contract) .................. 29 3.4.1 Contractor Contribution to Non-Payment by the Employer ........ 29 3.4.2 The Insolvency by the Employer ................................................. 30 3.4.3 Final Payment Pending Dispute between the Employer and the Main Contractor ............................................................... 32 3.5 Application of “Pay When Paid” Provisions in Sub-Contract ............ 33 3.5.1 The “Pay When Paid Clause is a Covenant Establishing the Time of Payment ..................................................................... 33 3.5.2 “Pay When Paid” Provisions as Condition Precedent .................. 40 ix 3.6 Reasonable Time ................................................................................. 55 3.6.1 A Mechanism to Determine When Payment is due ................... 56 3.7 Issues Regarding to “Pay When Paid” Provisions .............................. 59 3.7.1 Prevention Doctrine ................................................................... 59 3.7.2 Summary Judgment.................................................................... 61 3.7.3 Payment Bond Surety................................................................. 63 3.7.4 Contractor’s Own Default .......................................................... 65 3.8 Conclusion........................................................................................... 67 4 ANALYSIS ON THE APPLICATION OF “PAY WHEN PAID” PROVISIONS IN SUB-CONTRACTS .................................................. 69 4.1 Introduction .......................................................................................... 69 4.2 The Application of “Pay When Paid” Provision in Sub-Contract ....... 70 4.2.1 “Pay When Paid” Suggest Time of Payment .............................. 72 4.2.2 “Pay When Paid” As Condition Precedent ................................. 95 4.3 Conclusion.......................................................................................... 106 5 CONCLUSION AND RECOMMENDATIONS ................................. 109 5.1 Introduction ........................................................................................ 109 5.2 Summary of Research Finding ........................................................... 109 5.3 Problem Encountered during Research.............................................. 128 5.4 Conclusion.......................................................................................... 128 REFERENCES ....................................................................................... 129 APPENDIX A ......................................................................................... 133 x LIST OF TABLES TABLE NO 3.1 TITLE The Application of the “Pay When Paid” Provisions PAGE 48 In Construction Sub-Contracts 5.1 Judgment on the Application of the ‘Pay When Paid” Provisions in Construction Sub-Contracts 111 xi LIST OF ABBREVATIONS AC Law Report Appeal Cases ALJ Australian Law Journal ALR Australian Law Report CA Court of Appeal CIDB Construction Industry Development Board DC Division Court England DLR Dominion Law Reports FC Federal Court HL House of Lords HKC Hong Kong Case HKLR Hong Kong Law Reports IEM The Institution of Engineers, Malaysia LGR Local Government Reports LR Law Reports JP Justice of the Peace MBAM Master Builders Association MLJ Malayan Law Journal NS Nova Scotia NZLR New Zealand Law Reports PAM Pertubuhan Arkitek Malaysia PWD Public Work Development PD Probate, Divorce, and Admiralty Division of High Court xii SLR Singapore Law Report UM University of Malaya USA United State of America WLR Weekly Law Report WR Weekly Reports xiii LIST OF CASES CASES PAGE Timbro Development Ltd. v. Grimsby Diesel Motors Inc. et. al. (1988) 32 C.L.R. 32 (Ontario Court of Appeal) 6,44 Arnoldin Construction & Forms Limited v. Alta Surety Co (1995) 19 C.L.R. (2d) 1 (Nova Scotia Court of Appeal) 6 Schindler Lifts (Hong Kong) Ltd v. Shui On Construction Co Ltd (1984) 7 Nin Hing Electronic Engineering Ltd v. Aoki Corporation (1987) 7 Brightside Mechanical & Electrical Services Group Ltd v. Hyundai Engineering & Construction Co Ltd (1988) 7 Thomas J Dyer vs. Bishop International Engineering Co. 303 F 2d 655 (1962) 7,31, 35,37 Markel & Co. Contractors vs. Christian Co 7 Tweddle v. Atkinson (1861) IB & S 393 14 R&G Engineering Sdn Bhd v. ESPL (M) Sdn Bhd[2004] 4 CLJ 674 20 Kah Seng Construction Sdn Bhd v. Selsin Development Sdn Bhd [1997] 1 CLJ Supp 448 21 DEC Elec., Inc. v. Raphael Construstion. Corp 558 So. 2d 427 (Fla. 1990) 25,30, 34,43 xiv North Market Assn., Inc. v. Case Lezzi Construction Pty Ltd v. Watkins Pacific (Queensland) Pty Ltd (1995) 2QdR350 25 Moore Brothers Co. v. Brown Root Inc. (2000) 207 F.3d 717 29 Aqua Design and Play International Limited and Fenlock Hansen Limited v. Kier Regional Limited (2002) CA 31 United Plate Glass Co. v. Metal Trims Indus Inc. (1987) 106 Pa. Commw. 22,525 A.2d 468 32 28 Pace Construction Corporation v. OBS Co[1988] 531 So. 2d 737 Fla. Dist. Ct. App. David C. Olson, Inc. v. Denver & Rio Grande W.R.R. Co., 789 P.2d 492 (Colo. Ct. App. 1990) 33 Power & Pollution Services, Inc. v. Suburban Power Piping Corp 47 Ohio App. 3d 89 (Cuyahoga County 1991) 36 Seal Tite Corp. v. Ehret, Inc589 F. Supp. 701 (D.N.J. 1984) 37 Mignot v. Parkhill391 P.2d 755, 758 (Or. 1964) 37 Berkel & Company Constractors v. Christman Company 210 Mich. App. 416, 533 N.W.2d 838 (1995) West-Fair Electric Contractors v. Aetna Casualty & Surety Company 87 N.Y. 2d 148, 638 N.Y.S. 2d 394, 661 N.E.2d 967 (1995) 38 A.J. Wolfe Co. v. Baltimore Contractors Inc., 244 N.E.2d 717, 720 (Mass. 1969) 38 Southern States Masonry Inc. v. JA Jones Construction Company (1987) 507 So. 2d 198 39 John J. Calnan Co. v. Talsma Builders, Inc., 395 N.E.2d 1076, 1080 (lll App. Ct. 1979). 41 Harvey Concrete, Inc. v. Agro Construction & Supply Co. 939 P.2d 811 (Ariz. Ct. App. 1997) 41 Printz Services Corp. v. Main Electric Ltd. 949 P.2d 77 (Colo. Ct. App. 1997) 42 xv Robert F. Wilson, Inc., v. Post-Tensioned Structures, Inc., 522 So. 2d 70 (Fla. 3d DCA 1988) 42 Peacock Construction Co., Inc. v. Modern Air Conditioning, Inc353 So.2d 840 (Fla. 1977) 44,45 OBS v. Pace Construction Corporation 558 So. 2d 404 (Fla. 1990) 44 Kor-Ban Inc. v. Pigott Construction Ltd. 44 J.J. Shane v. Aetna Casualty & Surety Company 723 So. 2d 302 (Fla. 3d DCA 1998), reh. den. 46 Smith & Smith Glass Ltd. v. Winstone Architectural Cladding System Ltd. (1991). 60 Goldblatt v. Longacre Const. Co. 170 N.Y.S. 54 (1st Dept. App.T. 1918) 61 Wetter v. Kleinert139 A.D. 220, 123 N.Y.S. 755 (2nd Dept. 1910) 61 ADF Int’l, Inc. v. Baker Mellon Stuart Court., Inc. Case No. 6:98-cv-1310-Orl-31B, (M.D.Fla.Dec.28, 2000), 2000 U.S.Dist.LEXIS 22597 62 R&L Acoustics v. Liberty Mut. Ins. Co. (September 27, 2001) Conn. Super., LEXIS 2854 62 Framingham Heavy Equip. Co. v. John T. Callahan & Sons No.02-P-1159 (2003) 61 Mass. App. Ct. 171, 807 N.E.2d 851 62 Lafayette Steel Erectors, Inc. v. Roy Anderson Corp. 71 F. Supp. 2d 582; (S.D. Miss. 1997) LEXIS 23587 63 Lowy and Donnath, Inc. v.New York98 A.D.2d 42, 469 N.Y.S.2d 760 (1st Dept. 1983), aff’d 62 N.Y.2d 746, 476 N.Y.S.2d 830 (1984). 64 Grossman Steel and Aluminum Corp. v. Samson Window Corp., 78 A.D.2d 871, 433 N.Y.S.2d 31 (2nd Dept. 1980), aff d 54 N.Y.2d 653, 442 N.Y.S.2d 769 (1981) Galloway Corp. v. S.R. Ballard Constr. Co. 250 Va 493, 494 S.E.2d 349 (1995) (Virginia Supreme Court) 64 xvi Blakeslee Arpaia Chapman v. EI Construction, Inc. 239 Conn. 708, 687 A.2d 506 (1997) 64 Moore Brothers Co. v. Brown & Root, Inc. 207 F.3d 717 (2000) 66,69 Northeast Drilling, Inc. v. Inner Space Services, Inc. 66 Alloy Automotive Sdn Bhd v. Perusahaan Ironfield Sdn Bhd [1986] 1 MLJ 382 (SC) 67 Malayan Insurance (M) Sdn Bhd v. Asia Hotel Sdn Bhd [1987] 2 MLJ 183 (SC), 67 Hong Kong Teakwood Works Ltd. v. Shui On Construction Co. Ltd. [1984] HKLR 23 68 Schindler Lifts (Hong Kong) Ltd. v. Shui On Construction Co. Ltd. [1985] HKLR 118 68 United States ex rel. Walton Technology v. Weststar Engineering Inc. 290 F.3d 1199 (9th Cir. 2002) 69 Brown & Kerr, Inc. v. St. Paul Fire and Marine Insurance Co. 940 F. Supp. 1245, 1249 (N.D. III. 1990) 70 Casey Indus. Inc. v. Seaboard Surety Co 2006 WL 2850652, *7 (E.D. Va. 2006) 71 Durabella Limited v. J. Jarvis & Sons Limited (2001) 70 Sassenrath v. Sassenrath657 S.W. 2d 671, 674 (Mo. Ct. App. 1983) 73 AEE-EMF v. Passmore906 S.W. 2d 714 (Mo. Ct. App. 1995) 73 Preload v. Marino Construction1991 WL 202651 (N.D. I11. 1991) 73 xvii LIST OF APPENDICES APPENDIX A TITLE PAGE Contingent Payment Clauses in the 50 States” by the Foundation of the American Subcontractors Association (FASA) 133 1 CHAPTER 1 INTRODUCTION 1.1 Background of Research The modern construction project is so marvelously complex that is amazing that anything ever gets built 1 . Construction projects can best be understood in the context of the whole industry. Technological complexity ranges from the familiar, well knownmaterials and trades through to highly complex facilities involving multiple interacting sub-systems 2 . Besides that, it is labor intensive with manpower remaining the most important and critical resources for a cons truction project 3 . Project have multitude of 1 Fullerton, J.D. (2008). Changes, Delays and Other Claims. Murdoch, J. and Hughes, W. (2008). Construction Contracts: Law and Management 4th Edition. London and New York: Taylor & Francis. Pg 3 3 Ng Chu Yin (2006). Problems Associated With Nominated Subcontractor in Malaysian Construction Industry. Johor: Universiti Teknologi Malaysia. Pg1 2 2 players, including owners, general contractors, subcontractors, architects, engineers, and various material suppliers and laborers 4 . Letting work to subcontractors is a very common practice in construction industry. It is common for 80 percent to 90 percent of the work to be performed by subcontractors 5 . Subcontractor is specialized providers of particular construction services and often the necessary materials for their work. Subcontractors include masons, plumbers, electricians, painters, glaziers, roofers, and other mechanics. Traditionally, subcontractors enter into contracts with the Contractor (not the Owner) and acquire the materials necessary to perform the subcontracts from Supplier. First-tier Subcont ractors often subcontract various portions of their responsibilities to lower-tier subcontractors, each of which may acquire their materials from numerous suppliers 6 . The general contractor is responsible for coordination of all these subcontractors. Variance in experience or competence in this coordination can dramatically impact a project 7 . Subcontracting has always been important in the construction industry, particularly in building construction where the production process is divided into number of discrete. These task or activities are often carries out sequentially and may require specialized labor. Subcontractors help contractors overcome problems including the need of special expertise, shortage in resources, and limitations in finance 8 . The successful completion of construction contracts, particularly in building construction, depends in large measure on the quality and timely performance of the subcontractor. 4 Rippeon, Z. (2007). Conditional Payment Clauses in Construction Contracts. Georgia: Georgia State University College of Law. 5 Ng Chu Yin (2006). Problems Associated With Nominated Subcontractor in Malaysian Construction Industry. Johor: Universiti Teknologi Malaysia. Pg 2 6 McCarroll, B. (2006). The Construction Process from Start to Finish in Texas. Lorman Education Services, Texas. Pg4-5 7 Fullerton, J.D. (2008). Changes, Delays and Other Claims. 8 Ng Chu Yin (2006). Problems Associated With Nominated Subcontractor in Malaysian Construction Industry. Johor: Universiti Teknologi Malaysia 3 Contingent payment provisions are found in nearly every construction contract, particularly for commercial development 9 . A contingent payment clause is a contractual provision that makes payment contingent upon the happening of some event. In construction subcontracts, the typical contingent payment clause makes the subcontractor’s payment contingent upon the payment of the contractor by the owner10 . One common form is the “pay when paid” clause, which establishes a reasonable timeframe for subcontractor payment to occur, not when the relevant sum was certified by the contract administrator, but only when the general contractor actually received the money from the employer11 . The “pay when paid” clause does not shift the risk of owner nonpayment to the subcontractor, unless specifically and unambiguously stated otherwise 12 . 1.2 Problem Stateme nt Contractors and subcontractors in the construction industry know the real meaning of the famous phrase “cash flow is the lifeblood of the industry”. A contractor, who pays a subcontractor before being paid by the employer, is effectively funding the project. Add to this the cost of pursuing the employer for non-payment and the precarious nature of construction becomes obvious. Insolvency of the employer in that 9 Rippeon, Z. (2007). Conditional Payment Clauses in Construction Contracts. Georgia: Georgia State University College of Law. 10 Hill, K.B. & Ritter (2008). Contingent Payment Clauses in the 50 States. Ohio: Foundation of the American Subcontractors Association 11 Murdoch, J. and Hughes, W. (2008). Construction Contracts: Law and Management 4 th Edition. London and New York: Taylor & Francis. Pg 276 12 Rippeon, Z (2007). Conditional Payment Clauses in Construction Contracts. Georg ia: Georgia State University College of Law. 4 situation can threaten the continued existence of the contractor. In the Government Inspired Banwell Report in 196413 , Sir Harold Banwell commented that: “The operation of the payment system is not always smooth. Payments to the main contractor by the clients are often slow and uneven, with consequential delays in payment to suppliers and subcontractors. This has an adverse effect on the efficiency and stability of the whole industry …” A recent survey done by the Construction Industry Development Board (CIDB) in collaboration with the University Malaya (UM) ‘merely’ formally documents what many in the construction industry already know is there is a chronic problem of delayed and non-payment in the Malaysian construction industry affecting the entire delivery chain 14 . Master Builders Association (MBAM) has long been lamenting on the problems of delayed and non-payment in the construction industry. Industry form documents can be used to create a fair contract for both parties. Those same documents, however, can also be manipulated to gain unbalance the agreement. While there are a multitude of clauses that can cause substantial and unexpected financial trouble for the company, one of the most flagrant is the payment clause 15 . In every construction contract, the general contractor and its subcontractors must allocate the risk that the owner of the project either cannot, or will not, pay for the work performed. The allocation of the risk can have a significant impact on the profitability of the project for all parties, and can lead to protracted litigation16 . 13 Pettigraw, R. (2005). Payment under Construction Contracts Legislation. Thomas Telford Ltd: London. Pg 2 14 Sr Nourshad Ali Naseem Ameer Ali (2006). A “Construction Industry Payment and Adjudication Act”: Reducing Payment-Default And Increasing Dispute Resolution Efficiency In Construction. Master Builders Journal 3rd Quarter 2006. Pg 4. 15 Russell, R. (2003). The Right Contract Means Preserving Cashflow. Builder Exchange Magazine Vol 8 Issue 03 16 .Goodin, P.W. and Dickinson, J.C. (2002). Who Bears the Risks of Owner Non-Payment.? Midwest Construction Law, Contracts and Claims.) 5 General contractors sometimes try to avoid being stuck with liability for subcontractor claims which can be passed through by writing “pay-when-paid” clauses into their contract. These clauses attempt to pass the risk of the owner not paying on to the subcontractor. This is something that may be missed by the subcontractor and can work unfairly, especially where the subcontractor as in no position to assess the financial strength of the owner 17 . In the absence of any such clause, if an owner fails to pay the contractor for the work performed by the subcontractor, the main contractor is still responsible for making any contractual payments due to the subcontractor 18 . Dealing with contingent payment clauses is a frequent headache for subcontractors. Contingent payment clauses make subcontractors bear numerous risks completely unrelated to their own performance. Delayed approval of applications for payment by the architect, cash flow problems, pending and unpaid claims, and defective performance by other subcontractors all may prevent payment to the general contractor through no fault of the subcontractor. The resulting delay in payment impairs the subcontractor's credit rating, depletes operating capital and lines of credit, and hurts the subcontractor's relationships with its own trade creditors. Even worse, contingent payment clauses compel subcontractors to continue to work even though they have not been paid 19 . The Employer may for instance withhold payment because of default by the contractor or other subcontractors. Not surprisingly, contractors argue that “pay-whenpaid” clauses are a valid and legitimate protection against these risks. The subcontractor on the other hand has an equally valid argument against “pay when paid” clauses. If he has properly carried out the work, he argues, he should be entitled to be paid; otherwise 17 Logan, J.M. Pay-When-Paid Clauses-Construction Law. Canada. Pg1 Beckwith, A (2002). Pay-When-Paid Clauses: Risk Allocation and the need for Careful Drafting. Miller Thomson Construction Law Newsletter Summer 2002, Miller Thomson LLP:Washington DC, Pg 1 19 Nadine, H. G. and Patrick, C. B. (1999). Waiting to Get Paid: Pay When Paid Provisions a Matter of When or If. The Florida Bar Journal Volume LXXII No.9, October 1999, pg 64 18 6 he will run the risk of continued existence instead of the contractor. He should not become involved in disputes between the employer and contractor, which may have nothing at all to do with his work20 . Huxtable (1988) cited that, the way in which “pay when paid” clauses shift the risks on to subcontractors has for a long time been criticized as unfair but they are still in everyday use in standard form of sub-contracts in the countries of South-East Asia (Murdoch, 2008). Therefore, it is no surprise that the courts have struggled. From the cases of Timbro Development Ltd. v. Grimsby Diesel Motors 21 and Arnoldin Construction & Forms Limited v. Alta Surety Co.22 , there are two lines of arguments. The first is that if a clause indicates that the subcontractor will be paid when the contractor is paid, that is a clear indication that “unless and until the contractor is paid the subcontractor has no right to be paid and the risk of non payment by the owner is borne by the subcontractor.” The competing argument is that the “pay-when-paid” clause speaks to the timing of the payment but is not conclusive right to be paid. In other words, in the ordinary course “the subcontractor will have to wait until the contractor is paid but does not give their right to recover against the contractor in the event the owner never pays the subcontractor23 .” Therefore, the issue is whether a payment clause is a true “pay when paid” arrangement waiving the right of the subcontractor to be paid which payment to the subcontractor is condition precedent to payment by the owner to the main contractor or is simply a timing mechanism. Throughout the country, courts have differed on the interpretation of “pay-whenpaid” clauses which purport to make a general contractor’s duty to pay a subcontractor conditional on its receiving payment from the owner. Some courts maintain that these clauses should be loosely construed to mean that the general contractor’s obligation to 20 Atkinson, D (2001). Payment-Pay-When-Paid Clauses. England: Daniel Atkinson Limited. Inc. et. al. (1988) 32 C.L.R. 32 (Ontario Court of Appeal) 22 (1995) 19 C.L.R. (2d) 1 (Nova Scotia Court of Appeal) 23 Logan, J.M. Pay-When-Paid Clauses- Construction Law. Pg 1 21 7 pay is not excused in the event of nonpa yment by the owner 24 . Courts in Hong Kong and Singapore have treated “pay when paid” clauses as valid and enforceable, at least to the extent of protecting the main contractor’s cash flow by merely delaying the obligation to pay the subcontractor 25 . Courts in several jurisdictions have followed the reasoning of Dyer 26 to conclude that such a clause merely establishes a reasonable time in which contractor can delay payment, but that is does not completely excuse payment. The Michigan Court of Appeals in the case of Markel & Co. Contractors vs. Christian Co27 has held that such provisions are enforceable and that they indefinitely suspend the contractor’s obligation to pay subcontractors until it has received payment from the owner. However, such a provision may be excused under some circumstances, and they may be unenforceable. “Pay-when-paid” provisions may vary widely from state to state. Just because a contractor presents a subcontractor with a contract provision does not mean that provision is legally enforceable 28 . So, this research is looking to identify the application of “pay when paid” clauses in construction sub-contracts, either “pay when paid” arrangement in construction sub-contracts waiving the right of the subcontractor to be paid or simply a timing mechanism. To what extend the “pay when paid” provisions constitutes as a timing mechanism and as waiving the right of subcontractor to be paid. 24 Reeves, G.D. (1999). Enforceability of Conditional Payment Provisions in Construction Subcontracts. CAM Magazine August 1999 Edition 25 Schindler Lifts (Hong Kong) Ltd v. Shui On Construction Co Ltd (1984); Nin Hing Electronic Engineering Ltd v. Aoki Corporation (1987); Brightside Mechanical & Electrical Services Group Ltd v. Hyundai Engineering & Construction Co Ltd (1988) 26 The 1962 6th Circuit United States Court of Appeal decision in Thomas J Dyer vs. Bishop International Engineering Co. 303 F 2d 655 (1962). The approach taken principles in mind, which has been followed by most courts, is to examine the principles in mind: (1) the clear intention of the parties’ control; (2) ambiguous contracts should be construed against the drafter; and (3) conditions precedent is generally disfavored. 27 Reeves, G.D. (1999). Enforceability of Conditional Payment Provisions in Construction Subcontracts. CAM Magazine August 1999 Edition 28 Danner, P.D. Enforceability of Pay-When-Paid and Pay-If-Paid Clauses May Vary From State to State. 8 1.3 Objective of Research Following the issues stated above, this research attempts: 1. To identify whether “pay when paid” arrangement in construction subcontract waiving the right of the subcontractor to be paid or simply a timing mechanism. 1.4 Scope and Limitation of Research The approach adopted in this study is case law based. The court cases referred in this study include Malaysia, Singapore, Hong Kong, Florida, Ohio, Ontario, Illinois and English cases. There is no limit to the cases chosen in terms of time frame, as long as it has not been overruled by higher court and establishes a good law. 9 1.5 Significance of Research Basically, this study is expected to answer some of the uncertain issues that arise in “pay-when-paid” provisions in construction sub-contract. In accordance to that, issues will be analysed based on the judge interpretation and judgment by the courts in various state. Thus, by identifying the application of “pay when paid” arrangement either waiving the right of the subcontractor to be paid or is simply a timing mechanism, it is hope that this study would contribute toward enhancement of the subcontractor’s knowledge and more understanding on how to defense their rights and take the legal action to challenge the enforceability of the clause to seek immediate payment when they have suffering the risk of non-payment due to the performance problems unrelated to their own work. Finally, hopefully it assists in avoiding unnecessary disputes while assuring the success and better relationship among the contractual parties. 1.6 Research Methodology In order to achieve the objectives of this study, a systematic process of conducting this study had been organized. Basically, this study process comprised of five major stages, which involved identifying the study issue, literature review, data collection, data analysis, conclusion and recommendations. 10 1.6.1 Stage 1: Identifying the Research Issue The study issue arises from intensive reading of books, journals and articles which can be attained from the UTM library and from internet. At the same time, discussion with supervisors, lecturers, as well as friends, were held more ideas and knowledge relating to the topic could be collected. Based on the study issue, the objective of the study has been identified. In addition to that, this research is executed to review the relevant court decisions, with the intention of identifying and determining the application of “pay-when-paid” arrangement, either merely as timing mechanism or a true “pay when paid” arrangement waiving the subcontractor(s) rights to be paid. To what extend the court judgment tend to held that the application of “pay when paid” provisions constitutes as a timing mechanism and waiving the right of subcontractor to be paid. 1.6.2 Stage 2: Literature Review Afterward, a research outline will be prepared in order to identify what kind of data will be needed in this research. Collection of various documentation and literature regarding the study field is of most important in achieving the research objectives. Besides, secondary data is collected from reading materials in printing form like books, journals, research paper, magazines, reports, proceedings, seminar paper as well as information from internet and also by referring to standard contract forms (the PAM 1998 Form, PAM 1998 Sub-Contract Form, JKR PWD Form 203A and JKR PWD Form 203N). 11 Books, articles and journals relating to sub-contracting, “pay-when-paid” clauses, and payment under construction contract will be read to know depth the theories relating to the research field. All sources are important to complete the literature review chapter. 1.6.3 Stage 3: Data Collection Data will be collected mainly through documentary analysis. All collected data and information were recorded systematically. Data collected to analyse mainly from Malayan Law Journal, Hong Kong Law Report, Singapore Law Report, Building Law Report, All England Law Report, and other law journals via UTM library electronic database, namely Lexis-Nexis Legal Database. All the cases relating to the research topic will be sort out from database. Important cases will be collected and used for the analysis at the later stage. 1.6.4 Stage 4: Data Analysis Once the previous related court cases are collected, it will be conducted by reviewing and clarifying all the important facts of the cases and critical issues and judgments. The application of “pay when paid” arrangement where the judges tend to held that the contingent payment provision on “pay when paid” clauses in construction subcontract merely as a timing mechanism or as waiving the subcontractor(s) rights to be paid will be determined from the relevant cases. After issues presented by each cases, thorough discussion and comparison will be done in order to achieve objectives of this study. 12 1.6.5 Stage 5: Conclusion and Recommendations The last stage of the research mainly involves writing up and checking the writing. In this stage, reviews on the whole process of the study will be made with the intention to identify whether the study objective has been achieved. Conclusion and recommendation were made based on the findings during the stage of analysis. 13 CHAPTER 2 LIABILITY OF THE SUB-CONTRACTOR 2.1 Introduction Construction was in highly technical in its nature. Even for those in the industry, every trade in the team has varying levels of understanding and individual areas to focus for the same item of work and, as such, everyone experience and point of view may be unique. 29 Construction projects generally involve a complex network of complimentary and occasionally conflicting contractual rights and obligations. Standard forms of contract exist which, with varying degrees of success, are meant to address the 29 Teresa Cheng, Evia Wong and Gry Soo (2004). Construction Law and Practice in Hong Kong. Sweet & Maxwell Asia. Pg 7 14 commercially reasonable balancing of rights and obligations, risks and rewards that is necessary to the orderly functioning of this important construction industry30 . The used of standard form provides many advantages, and although standard forms are not mandatory in practice their used should be encouraged in all possible circumstances31 . Sub-contracting as a phenomenon is not unique to the construction sector. There are many influences on a business that encourage sub-contracting, and it is useful to distinguish those pressures that are general (affecting all business) and those that are specific (affecting the unique position of construction). 32 This chapter provides an overview on the sub-contracting in the construction industry. This include the contractual chain, the liability of the sub-contractor in contract and tort, the subcontractors right to payment and the statutory rights to recover nonpayment by the main contractor relying to the “pay when paid” provision in sub-contract. 2.2 The Contractual Chain The basic position in law that the main contract and sub-contract and the subsub-contract (if there is one), are regarded as links in a chain 33 . The doctrine of privity of contract means that the rights and obligations contained in each contract apply only to 30 Sternlieb (2007). Subcontractor’s Right to Payment. New Jersey Law Journal Vol. CXC-No.4-Index 399 October 22, 2007. 31 Ashworth, A. (1986). Contractual Procedures in the Construction Industry. London and New York: Logman. Pg 8 32 Murdoch, J. and Hughes, W. (2008). Construction Contracts: Law and Management 4 th Edition. London and New York: Taylor & Francis. Pg 267 33 Ibid. Pg 270 15 those who are parties to it 34 . The ‘chain liability’ works perfectly well as long as all the links are intact. However, a chain can only as strong as its weakest link, and considerable problems arise as soon as one of the links breaks 35 . 2.3 The Contractual Status of a Subcontractor with the Owner There are normally exists no what one could call, in legal terms, ‘privity of contract36 ’ between an Owner and his contractor’s sub-contractor. An owner is not normally liable to a sub-contractor for payment, whether or not there is a “pay-whenpaid” provision in the sub-contract. The simple reason for this is that the owner is not a party to the sub-contract. In the case of nominated sub-contracts under P.A.M. Form, it is the case that the sub-contract entered into is instructed by the Owner or by the Architect acting as an agent of the Owner, but the contractor in all such instances accept as a term of his contract with the Owner that he will enter into the sub-contract and will take the risk of non-performance by the sub-contractor 37 . 34 Ibid Pg 270 Ibid Pg 276 36 “Privity of Contract” provides that only the parties to the contract can claim benefits under it or be subject to the obligations which it imposes, See Tweddle v. Atkinson (1861) IB & S 393 37 Ir. Oong Chee Keng (2004). Institution of Engineering Public Forum On “Pay-When-Paid” Clauses in Construction Sub-Contracts-Held on 27 November 2004. Kuala Lumpur: IEM 35 16 2.4 Liability of the Sub-Contractor As with other relationship in construction, liability may in principle arise either in contract or in tort. 2.4.1 Liability in Contract The doctrine of privity of contract means that it is not possible for a subcontractor to be made directly liable to the employer for a breach of the main contract. Equally the employer, who is not a party to the sub-contract, cannot claim damages for breach of it. This means that, unless the main contractor is liable to reimburse the employer for the loss caused by the sub-contractor, neither of them can sue the sub-contractor for the loss. The only possible exception to this would be if the sub-contractor specifically undertakes not to raise the ‘no loss’ defence when sued by the main contractor 38 . The normal contractual structure consist a ‘chain of contract’ does not provide for a direct claim by an employer against a sub-contractor. However, it is common for nomination procedures to include a requirement that the sub-contractor and the employer should enter into a direct contractual agreement. Where this is done, the agreement is likely cover such matter as design warranty from the subcontractor and a direct payment undertaking by the employer. 39 38 Murdoch, J. and Hughes, W. (2008). Construction Contracts: Law and Management 4 th Edition. London and New York: Taylor & Francis. Pg 273 39 Ibid Pg 289 17 In addition to direct contracts that are expressly entered into, there is the possibility that a court may construct, which means invent a collateral contract between the employer and a subcontractor or supplier. 40 2.4.2 Liability in Tort There is at least the possibility that a nominated sub-contractor might incur direct liability to the employer in tort of negligence in respect of work which is simply defective. However, even if such liability can arise, it appears very unlikely that it will extend to domestic sub-contractors, since their relationship with the employer is not normally of sufficient ‘proximity’ to carry with a legal duty of care. 41 As for the domestic sub-contractors who negligently cause physical damage, either to the contract works or to existing structures (in cases where the contract is not a new build), a different legal problem surfaces. It is whether something that appears to be a straightforward case of negligence may be affected by the way in which the main contract and sub-contract have chosen to allocate the risk among the parties. 42 A nominated subcontractor is specifically selected by the employer raises an additional possibility. This is that the reliance placed on the sub-contractor by the employer may give rise to a relationship of such ‘proximity’ that the sub-contractor will owe the employer a duty of care in tort not to cause pure economic loss through negligence of performance of the sub-contract. 40 Murdoch, J. and Hughes, W. (2008). Construction Contracts: Law and Management 4 th Edition. London and New York: Taylor & Francis. Pg 289 41 Ibid Pg 273 42 Ibid Pg 274 18 2.5 Legal and Contractual Background of Subcontractor Rights to Payment The vast majority of commercial construction is performed by subcontractors. It has been estimated that subcontractors accomplish between 80 percent and 90 percent of the commercial construction. Subcontractors provide the majority of labor and materials and have more capital invested in a construction project than general contractors and design professionals. Thus, it could be argued that the subcontracting industry has more at risk that those other segments of the construction industry43 . A subcontractor’s rights against the main contractor are concerned mainly with payment. A straightforward application of contract law leads to the conclusion that the payment rights of a sub-contractor are to be found exclusively within the terms of the relevant sub-contract and that the main contract has no bearing on “pay-when-paid” issue 44 . A prime contractor prefers not to pay subcontractors until it is paid for their work by the owner. If the contractor must pay despite the owner’s inability or refusal to pay, the contractor in effect is acting as the owner’s surety, a role for which it is not really suited. On the other hand, the subcontractor if anything is less equipped to handle owner nonpayment. It has no direct contractual rights against the owner. Its contract instead is with the prime. Unless the subcontracts validly provides otherwise, the failure of an owner to pay the prime will not relieve the prime of its duty to pay a subcontractor 45 . 43 Thomas , R.G. (2007). Killer Subcontractor Clauses. Texas:Thomas, Feldman & Wilshusen, L.L.P. Murdoch, J. & Hughes, W. (2008). Construction Contracts Law and Management-Fourth Edition. London: Taylor & Francis Group 45 Lybeck, K.L. and Shreves, H.B. (1998). The Law of Payment Bonds. American Bar Association. Pg 262 44 19 2.6 Relationship of Subcontractor’s Statutory Right to Recover for NonPayment with “Pay When Paid” Provisions in the Sub-Contract 2.6.1 Security of Payment It has been suggested that there are only three effective legal mechanisms to provide security of payment, i.e the concept of the lien, trust and bond. Federal and statutes govern mechanics’ liens (absent in Malaysia) on private projects and performance and payment bonds on public projects that for subcontractors remain the primary techniques for remedying nonpayment by a contractor. Legislation of these remedies guarantees a subcontractor’s right to receive payment. Subcontractors, which typically stand in a weaker bargaining position vis -à-vis contractor, depend on this legislation to guarantee that contractors do not utilize their greater leverage during contract formation to avoid payment for their subcontractors’ work46 . The availability of bonding and mechanics’ lien remedies may offer addition protections to alleviate the subcontractor risks under “pay-when-paid” clause 47 . The problem of security is to a considerable extent addressed in USA and Canada by way of mechanic lien statutes which is absent in Malaysia. In gist, any unpaid claimant who has expended labour or material to build has the right to apply for a lien to be attached to the land whereon the building was constructed. After the entry of the lien, the claimant can then apply to auction the building wherein the proceeds of sale will then be utilized for payment. The dispute thus always centers on the unpaid claimant’s application for lien which is often resolved via arbitration. The lien security nevertheless usually takes effect from visible construction of the building long before the conclusion 46 Crushman , R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 895 47 Hughes, T.R. (2008). To Pay or Not to Pay. Hughes & Associates P.L.L.C. 20 of the arbitration and this makes the unpaid claimant a secured creditor usually second only to the lending financier bank taking first priority as an even earlier secured creditor 48 . The trust concept is not alien in Malaysia in respect of retention monies. It is provided in PAM 1969/1998 Form, CIDB 2000 Form and PAM NSC Form. The trust is however a conditional one in that it permits the employer or the contractor to set off permissible deductions there from. In the absence of the set off, the employer or the main contractor may be compelled by way of an injunction to set aside the retention money into a trust account. However, most of the time, the application is defeated by set offs. In the unusual case of R&G Engineering Sdn Bhd v. ESPL (M) Sdn Bhd 49 , the Malaysia Court of Appeal found that the progress payment under a sub-contract was subject to an express trust and the Court ordered that the corpus of the trust i.e. unpaid progress payment money be interlocutory secured pending trial notwithstanding set offs50 . Courts find that conditions precedent do not waive a subcontractors’ statutory rights to file a mechanic’s lien or collect on a surety bond unless, in the case of mechanic’s lien s, the legislation does not explicitly preclude the enforcement of conditions precedent or, in the case of surety bonds, the subcontract has met the requirements for an effective waiver 51 . 48 Lim Chong Fong . The Malaysian Construction Industry-The Present Dilemmas of the Unpaid Contractors. 49 [2004] 4 CLJ 674 50 Lim Chong Fong. The Malaysian Construction Industry-The Present Dilemmas of the Unpaid Contractor. 51 Crushman R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 895 21 2.6.2 Enforcement of Payment In United Kingdom, New Zealand, the states of New South Wales, Victoria and Western Australia and now Singapore, the principal mode of construction dispute resolution has shifted to adjudication. This is a swift dispute resolution process that results in a decision which carries “temporary finality” unless reversed in arbitration or litigation. In the meanwhile the successful claimant is at liberty to enforce the decision 52 . There are limited remedies and security pending dispute resolution for the unpaid claimant in Malaysia. There is no general common law right of suspension of work for non payment. In the Kah Seng Construction Sdn Bhd v. Selsin Development Sdn Bhd 53 , Low Hop Bing J succinctly held:- “In my judgment, it is trite law that a contractor can only terminate his contract with his employer (at common law, as opposed to the exercise of an express termination clause) if he shows, inter alia, a repudiatory breach by the employer in the sense that the employer has evinced an absolute refusal not to perform his side of the contract. There is no intermediate right in a building contract to suspend works. If the contractor insists on the continued performance of the contract, i.e. he affirms the contract he must himself continue to perform his primary obligations under the contract, i.e. to continue performing the contract works. This is why suspension of the works by the contractor, i.e. not continuing with his primary obligations, becomes itself a repudiatory breach by the contractor. Even if the plaintiff can establish that the defendant is in repudiatory breach of contract, the plaintiff would have no right to suspend works, but instead would have had to elect to wither terminate the contractor or insist on due 52 Lim Chong Fong. The Malaysian Construction Industry-The Present Dilemmas of the Unpaid Contractors. 53 [1997] 1 CLJ Supp 448 22 performance. By suspending works without valid legal cause, the plaintiff has in fact repudiated its contractual obligations.” The standard forms of construction contract do not provide for such a remedy other than the CIDB 2000 Form and the PAM-NSC Form. The right of suspension is quite useless if the sub-contracts are subjected to a “pay-when-paid” condition which is rather common unless of course the contractor has absconded with the money paid by the employer 54 . 2.7 Summary The practice of efficient and timely payment in construction projects is a major factor leading to a project’s success. Payment had been referred to as the lifeblood of the construction industry due to latter’s inherent nature that takes relatively long durations and large amounts to complete. Payment, or rather late and non-payment issues are considered to affect many players in the local construction industry, whether in government or private projects 54 Lim Chong Fong. The Malaysian Construction Industry-The Present Dilemmas of the Unpaid Contractors. 23 CHAPTER 3 APPLICATION OF “PAY-WHEN-PAID” PROVISIONS IN SUBCONTRACT 3.1 Introduction For years, throughout the country up-stream contractors, such as general contractors, have often included a contractual provision in their subcontracts providing that payment to the subcontractor is conditioned upon the general contractor’s actual receipt of payment from the owner55 . If drafted correctly, these clauses require the subcontractor to wait for payment on their completed work until the general contractor receives payment from the owner56 . This essentially passes on the owner’s solvency risk to the downstream subcontractor. No payment from the owner means no payment is due 55 Perlmuter, G.E. (2007). Michigan’s Winning Economy Wallops Construction Contractors. Has the Sting of a Pay-When-Paid Clause Gotten Your Attention?. Foster, Swift, Collins & Smith Construction Law Newsletter, November 2007. 56 Ibid 24 to the subcontractor. This clause, depending on their language, is commonly know n as “pay when paid” clauses 57 . “Pay when paid” clauses while seemingly straightforward at first glance but many are actually ambiguous 58 . Therefore, a subcontractor may want to take legal action to challenge the enforceability of the clause and seek immediate payment from the general contractor 59 . Construction sub-contracts which include the “pay when paid” clauses are the most troublesome for the subcontractors and suppliers. One practical reason for risks allocation in this manner is that owners were frequently successful transferring many of these risks to general contractors in prime contracts. Having contractually accepted these risks in prime contracts, it’s become prudent for general contractors to attempt to pass them along the subcontractors. Regardless of the merits of the rationale behind the extreme shifting of risks to subcontractors, the practice had many practical effects. First, most subcontractors were smaller than the general contractors and less sophisticated in these matters. That created unequal bargaining position in favor of the general contractors. The studies conducted by the Construction Industry Institute 60 find that the risks shifting practice, unfortunately, promoted an adversarial attitude between the parties which promoted disharmony on projects. Disharmony, in turn, created disputes on the job site resulting in legal battles where no one is the real winner. In the end, unreasonable and inequitable risk shifting in contracts worked to the detriment of overall project performance 61 . 57 Sklar, A.J. & Sternlieb, M. (2007): The “Pay-If-Paid” Clause-A Suspect Subcontract Provision. Cole Schotz Docket, Fall 2007 58 Goodman, N.H. and Barthet, P.C. (1999). Waiting to Get PAID: Are Pay When Paid Provisions A Matter of When or If? The Florida Bar Journal, October 1999 Volume LXXIII, No.9 59 Sklar, A.J. & Sternlieb, M. (2007): The “Pay-If-Paid” Clause-A Suspect Subcontract Provision. Cole Schotz Docket, Fall 2007 60 Thomas R.G. (2007). Killer Subcontractor Clauses. Texas:Thomas,Feldman & Wilshusen, L.L.P. 61 Ibid. 25 This chapter provides the discussion on the non-payment regarding to the issues of “pay when paid” provision in construction sub-contract. This discussion also concentrates on the application of “pay-when-paid” provisions or arrangement in sub-contract and the reasonableness of time the subcontractor have to wait to get paid from the general contractor in the present of “pay when paid” provision in the sub-contract. 3.2 Definition of “Pay When Paid” In the case of DEC Elec., Inc. v. Raphael Const. Corp.62 , the “pay when paid” language can be interpreted on the one hand as establishing a condition precedent in which payment must first be received from the owner before it can be paid out to the service provider, or, on the other hand, as simply fixing a reasonable time frame for when payment is to be made 63 . Rosenberg (2007) stated that a clause that provides that payment is due when a certain performance is completed is a pay-when-paid clause, imposing the obligation to pay upon the general contractor within a specified or reasonable time. Further, in North Market Assn., Inc. v. Case, a clause providing that payment is due if and when funds are available was held to be pay-when-paid clause. 62 558 So. 2d 427 (Fla. 1990) Goodman, N.H. and Barthet, P.C. (1999). Waiting to Get PAID: Are Pay When Paid Provisions A Matter of When or If?. The Florida Bar Journal, October 1999 Volume LXXIII, No.9 63 26 Pay-when-paid clauses are those clauses which defer the time when payment is due from say a main contractor to a sub-contractor until the main contractor has received payment from the client 64 . Devine (2006) stated, the “pay-when-paid” language is an absolute agreement of the general contractor to pay the subcontractor within a period of time after the general contractor is paid by the owner. The general contractor has made an unconditional promise to pay with the time payment postponed until happening of a certain event, or for a reasonable period of time if the owner’s payment does not happen. Such provisions do not absolutely bar payment, but merely delay the payment by the contractor to the subcontractor for only a reasonable period of time to allow the general contractor to attempt to collect payment from the project owner65 . Unlike a “pay-if-paid” clause, where the obligation to pay the subcontractor may never ripen, a “pay-when-paid” clause is arguably only acts to delay payment to the subcontractor 66 . 3.3 “Pay When Paid” Provisions in Sub-Contracts None of the nominated sub-contracts published in Malaysia including under the PAM 69, PAM 98, PWD 203 series, IEM or CIDB 2000 contracts contain a “pay when paid” clause. They all have “pay when certified” clauses. In other words, payment must 64 Sr Nourshad Ali Naseem Ameer Ali (2006). A “Construction Industry Payment And Adjudication Act”: Reducing Payment-Default And Increasing Dispute Resolution Efficiency In Construction. Master Builders Journal 3rd Quarter 2006. Pg 11 65 Devine, P. (2006). When Must A Subcontractor Be Paid Under A “Pay-When-Paid” Clause. Business Credit July/August 2006. National Association of Credit Management 66 Sklar, A.J. & Sternlieb, M. (2007). The “Pay-If-Paid” Clause-A Suspect Subcontract Provision. Cole Schotz Docket, Fall 2007. 27 be made by the main contractor upon certification by the certifier whether or not the main contractor is paid in a timely manner as provided under the main contract 67 . In PAM 98 contract form Clause 27.2 (vii) and Clause 11.3 in PAM Subcontract form, the main contractor has to pay within 14 days to the nominated subcontractor after he received payment certificate from the architect. It does not states that the contractor has to wait until receipt of payment by the employer. So, in PAM 98 contract form, the condition precedent of a nominated subcontractor to get his payment is certificate issued to the main contractor. Many contractor drafted ‘domestic’ sub-contract or sub-sub-contract contain “pay-when-paid” provisions. Domestic sub-contracts are contracts which a contractor enters into with a sub-contractor chosen by the contractor. The only standard terms of ‘domestic’ sub-contract published in Malaysia is the ‘Model Terms of Construction Contract for Subcontract Work’ published in September 2006 does not have “pay-whenpaid” provision68 . Section 113(1) of the Housing Grants, Contract (sic “Construction”) and Regeneration Act 1996 provides: “(1) A provision making payment under a construction contract conditioned on the payer receiving payment from a third person is ineffective, unless that third person, or any other person payment by whom is under the contract (directly or indirectly) a condition of payment by that third person, is insolvent. 67 Sr Nourshad Ali Naseem Ameer Ali (2006). A “Construction Industry Payment And Adjudication Act”: Reducing Payment-Default And Increasing Dispute Resolution Efficiency In Construction. Master Builders Journal 3rd Quarter 2006. Pg 10. 68 Ibid. Pg 11 28 It is submitted that under the 1996 Act, ‘pay when paid’ arrangement is illegitimate. Hence, all contractors need to pay subcontractor despite they may not receive interim payment from the Employer, unless the Employer is insolvent. This is the UK scenario. In Australia, the main contractor would be required to pay the subcontractor even when the Employer went into liquidation as reported in an Australian case Lezzi Construction Pty Ltd v. Watkins Pacific (Queensland) Pty Ltd (1995) 2QdR350.69 According to Hudson’s 70 , under a Joint Venture attitude, the Contractor should not be liable to pay nominated subcontractor (NSC) when the Employer goes bankrupt. The proposed Construction Industry Payment and Adjudication Act (CIPAA) aims to prohibit the practice of “pay when paid” in all construction contracts. All work done and all services rendered must be paid upon the services being rendered. If there is default up the chain of contracts the parties must resolve it themselves and not pass that risk to third parties. The effect of “pay when paid” clauses is that sub-contract may well end up not being paid for reasons beyond their control. Worse still is a situation where s client may set off amounts due to main contractor due to the main contractor’s own fault. The subcontractor then does not get paid although they may have done their work properly and were not in breach of their contract. 69 Bernard S C Wu (2005). Pay When Paid/Pay If Paid Under the Standard Form of Building Contract 2005. Hong Kong: Surveyors Times. Pg 38-39 70 Hudson’s Building & Engineering Contracts 11th Edition 29 3.4 Non-Payment by the Employer/Owner (Relying on “Pay When Paid” Provision in Sub-Contract) As stated in standard form of contract, the contractor have to pay the nominated subcontractor when he receive s payment certificate from the employer (PAM 98) or when he receive payment from the employer (JKR 203N). The problems occur when the employer does not pay the main contractor. There are three reasons contribute to nonpayment by the employer which are contractor contribution to non-payment by the employer, the insolvency by the employer and final payment pending dispute between the employer and the main contractor. 3.4.1 Contractor Contribution to Non-Payment by the Employer The non-payment by the employer does not necessarily due to the employer default in payment but the employer might withhold the payment due to the contractor default. Question arises when the subcontractor request for payment but there is a paywhen-paid provision in construction subcontract between general contractor and subcontractor(s). It was illustrated in the case Moore Brothers Co. v. Brown Root 71 . The case arose out of construction of a toll way in Virginia. Brown & Root was the general contractor and also was an equity owner in the project. The developer was Toll Road Investors Partnership II (TRIP). Moore Brothers (Moore) was a subcontractor on the project. In the subcontract, there was “pay when paid” provision. The lender (financing company for client) insisted that Brown & Root provide assessments of the total project cost with a 71 Inc. (2000) 207 F.3d 717 30 high degree of certainty. TRIP and Brown made changes of scope of works but those changes were not revealed to the lender and the subcontractor. The subcontractors were instructed by Brown & Root to perform the work. Because the lenders had not been made aware of the change orders, financing had not been arranged for the extra work. TRIP was unable to obtain sufficient funding to pay Brown & Root, thus triggering the paywhen-paid clause in the subcontractor. The issue arose in this case was whether the contractor can based on the paywhen-paid provision and withhold the payment to the subcontractor. It was held that the main contractor has misled the lenders regarding possible costs of the project and thus, the lender refused additional funding for the changes orders, the owners lacked sufficient funds to pay Brown & Root, which then did not pay the subcontractor. So, the main contractor was not entitled to the protection of the clause. 3.4.2 The Insolvency by the Employer Problems arose when the main contractor refused to make payment to the subcontractor when the employer become insolvent before full payment was made. This problem is illustrating in the following cases. There are two different decision held regarding to the issue of “pay when paid”, which is “pay when paid” provision in enforceable and unenforceable. There are some cases which held that the pay-when-paid clauses enforceable. In DEC Electric, Inc. v. Rapheal Construction Corp.72 ., the subcontractor provided that ‘No funds will be due to the subcontractor unless the general contractor is paid by the owner 72 (1989) 538 So. 2d 963, 964 31 in accordance to the sworn statement’. The court found, as a matter of law, that the language was a condition precedent and that the subcontractor was not entitled to payment from the general contractor because the general contractor had not been paid by the owner. Besides that in Aqua Design and Play International Limited and Fenlock Hansen Limited v. Kier Regional Limited (2002) CA, Kier were the main contractors for fitting out of a health and fitness centre at Chelmsford in Essex for a company called Heathland. Aqua was engaged as subcontractor for the supply and installation of a swimming pool, sauna room, and showers. Fenlock was subcontractor for glazed screens. Both commenced proceedings against Kier who had refused payment on Clause 32 of the contract, stated that “ Notwithstanding anything to the contrary elsewhere in this subcontract, if the employer is insolvent as defined in Clauses 32.2, 32.3 and 32.4, the Contractor shall not be obliged to make any further payment to the subcontractor of any amount which is due or may become due to the subcontractor unless the Contractor has received payment in respect thereof from the Employer and only to the extent of such receipt”, Healthland went into administration. It was held that Kier was entitled to rely upon the pay-when-paid provision afforded by the clause following the insolvency of its client. It means that the contract clearly provides that payment is not due from the general contractor to the subcontractor until the general contractor has been paid by the owner or it is clearly stated that the contractor does not need to pay the subcontractor if the employer has not pay the main contractor on the event of employer’s insolvency, such clauses are enforced. In the case of Thomas J.Dyer v. Bishop International Engineering Co.73 , the owner become insolvent before full payment was made to the general contractor, who in turn refused to make full payment to the subcontractor. The court reviewed a provision which stated that payment to the subcontractor shall not be due ‘until five days after the 73 (1962) 303 F.2d 655, 659 32 owner shall have paid the contractor’. It was held that ‘… it seems clear to us under the facts of this case that it was the intention of the parties that the subcontractor would be paid by general contractor for the labour and materials put into the project. We believe that to be the normal construction of the relationship between the parties. If such was not the intention of the parties it could have been expressed in unequivocal terms dealing with the possible insolvency of the owner … to construe it as requiring the subcontractor to wait until the general contractor has been paid by the owner, which may never occur, is to give it an unreasonable construction which the parties did not intend at the time the subcontract was entered into’. The court concluded that such a clause merely establishes reasonable time in which the general contractor can delay payment, but that it does not completely excuse payment. Next, in the case of United Plate Glass Co. v. Metal Trims Indus74 , the court found that under the glass contracts in question, payment by the owner to the contractor and approval by the architect were not absolute prerequisites to the contractor’s duty to make final payment to the subcontractor. Rather, those conditions were timing mechanism. Besides, the courts are reluctant to find that a subcontractor assumed the risk of the owner’s insolvency absent extremely clear and unambiguous language. 3.4.3 Final Payment Pending Dispute between the Employer and the Main Contractor The problem which frequently arises is the subcontractor’s right to receive final payment when there is a dispute pending between the employer and the contractor. It was described in Pace Construction Corporation v. OBS Co.75 . In this case, the agreement between the contractor and the subcontractor contained a pay-when-paid clause, which 74 75 Inc. (1987) 106 Pa. Commw. 22,525 A.2d 468 [1988] 531 So. 2d 737 Fla. Dist. Ct. App. 33 provided that final payment of the subcontractor would not be made until the contractor received final payment for the subcontractor’s work from the owner. The subcontractor successfully completed its work. The court stated that this “pay when paid” clause clearly shown that payment from the owner was a condition precedent to the contractor’s obligation to make final payment to the subcontractor. The subcontractor was found to have assumed the risk of owner non-payment. It was held that because the owner had not make final payment to contractor, neither the contractor nor the surety could be held liable unless the contractor received payment for the subcontractor’s work. 3.5 Application of “Pay When Paid” Provisions in Sub-Contract 3.5.1 The “Pay When Paid Clause is a Covenant Establishing the Time of Payment Courts take a uniform stance on a general contractor’s duty to pay subcontractors, stating that absent a contrary contractual provision, failure of an owner to pay a general does not relieve the general contractor of the obligation to pay a subcontractor or supplier76 . Inclusion of a third – party payment provisions (“pay when paid” provisions) refutes the presumption that the contractor has an absolute duty to pay the subcontractor for services despite the nonperformance of the owner. Nonetheless, the majority of jurisdictions still find a duty for the general contractor to pay any subcontractors or suppliers when the construction contract includes a “pay when paid” provision. Instead of interpreting such a clause as waiving the contractor’s financial obligations to the 76 David C. Olson, Inc. v. Denver & Rio Grande W.R.R. Co., 789 P.2d 492 (Colo. Ct. App. 1990) 34 subcontractor, courts hold that the clause merely delays the time of payment for a reasonable time 77 . In arriving at this conclusion, courts typically concentrate on the specific contract language used as expressing the intention of the parties. When analyzing a “pay when paid” provision, courts generally find that “if a provision is clear and unambiguous, it is interpreted as setting a condition precedent to the general contractor’s obligation to pay. If a provision is ambiguous, it is interpreted as fixing a reasonable time for the general contractor to pay78 .” While a general understanding persists on when a court will find a “pay when paid” provision as only delaying the time of payment, no clear guidelines exist for when a court will find the terms of a particular provision to be ambiguous. However, analysis of some of the cases reveals a visible trend79 . The “pay when paid” clause is interpreted by courts across the country to relate only to the timing of payment. A subcontractor still will be entitled to payment from a general contractor after a reasonable period even if the building owner has not paid the general contractor. Although there is no set time period to define what constitutes a reasonable period, the critical lega l point is that the subcontractor ultimately is entitled to payment 80 . If the event that was to trigger payment does not occur for reasons not within the subcontractor’s control, the subcontractor will be entitled to payment within a reasonable time after completion81 . 77 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 891 78 DEC Elec., Inc. v. Raphael Constr. Corp., 558 So. 2d 427, 429 (Fla. 1990) 79 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 892 80 Felin, M.S. and Philips, S.M. (2003). Understanding Payment Provisions. Roofing Magazine February 2003; Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 891 81 Bruner, P.L. and Haley, T.L. Managing and Litigating the Complex Surety Case. American Bar Association. Tort Trial and Insurance. Pg 749 35 Timing mechanism means the clause merely provide general contractor with some reasonable time period within which to make payment. When the payment provisions seen as fixing a reasonable time frame for payment, the “pay-when-paid” language is treated as absolute, unconditional promise by the general contractor to pay the subcontractor, with the understanding that the payment may be delayed for some reasonable time while the general contractor obtains payment from the owner 82 . Specifically, when the “pay-when-paid” provision omits key words, or if the provision contains language that mentions an amount of time when payment becomes due, courts find the provision ambiguous 83 . Those jurisdictions that uphold conditional payment clauses do so only where the intent of the contracting parties is unquestionably clear 84 . In Thomas J. Dyer Co. v. Bishop International Engineering Co.85 , it is stated that the court rejected the general contractor’s defense that the contractual language which provided that “no money owed to the subcontractor was due until five days after the contractor’s receipt of funds from the owner” was a condition precedent that prevented payment where the owner was insolvent. Concluding “that it was the intention of the parties that the subcontractor would be paid by the general contractor for the labor and material put into the project,” the Sixth Circuit determined that the provision was designed to allow the contractor a reasonable period of time in which to pay the subcontractor for work performed. Id. at 661. The Sixth Circuit opined that the credit risk inherent in the general contractor’s undertaking could be shifted to the subcontractor, but only where the contract contained express language “clearly showing that to be the intention of the parties.’ The court interpreted these standard “pay-when-paid” clauses, not as creating an absolute condition precedent to payment to the subcontractor, but rather as affording the general contractor a postponement of payment for a reasonable period of time to allow the general contractor an opportunity to collect funds due from 82 Goodman, N.H. and Barthet, P.C. (1999). Waiting to Get PAID: Are Pay When Paid Provisions A Matter of When or If?. The Florida Bar Journal, October 1999 Volume LXXIII, No.9) 83 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 892 84 Perry II, R.L. (2005). Nos. 31869 and 31870. Supreme Court of Appeals of West Virginia. Pg 3 85 303 F.2d 655, 661 (6th Cir. 1962) 36 the owner to pay the subcontractors, and not to require the subcontractor to wait an indefinite period of time until the general contractor was paid by the owner. Most court, including an Ohio appellate court in Power & Pollution Services, Inc. v. Suburban Power Piping Corp86 ., has agreed with the analysis in Dyer. The general rule in most jurisdictions is that, unless the contract clearly shows that the parties intended to make payment from the owner a “condition precedent” to payment of the subcontractor, the pay-when-paid clause governs only the timing of payments to the subcontractor but does not allow the general contractor to avoid paying the subcontractor altogether. As in Dyer, most courts interpret pay-when-paid clauses to require the general contractor to pay the subcontractor within the “reasonable time” after the work is completed, even if the owner has not paid the general contractor 87 In paragraph 13.111 Hudson’s Building & Engineering Contracts 11th Edition, it is stated: “In the United States, however, there have undoubtedly been a number of cases of where the courts have held ‘pay-when-paid’ provision to be no bar to subcontractor recovery once the subcontract has been properly completed.” Hudson’s continues in paragraph 13.113 that ‘…those United States judgments which have followed this trend have paid insufficient regard, it is submitted, to the commercial background underlying subcontracting in the construction industry, and in particular to the factor of potential owner insolvency…(for example, administration severity by government or supervisory officers) it might also be intended that the risk should be similarly shares … For this reasons, it seems unlikely that English Courts 86 47 Ohio App. 3d 89 (Cuyahoga County 1991) Gurney, D.S. (2007). “Pay-When-Paid” Clauses: What Happens When the Owner Doesn’t Pay?. Published in The Constructor. Ohio: Frost Brown Todd LLC 87 37 would afford assistance to an unpaid subcontractor … or would afford dispense with the condition imposed by a “pay-when-paid” provision … provided they considered that the intention of the language was clear” The 1984 Federal District of New Jersey case, Seal Tite Corp. v. Ehret, Inc. 88 and a 1962 Sixth Circuit Ohio law, Thomas J. Dyer Co. v. Bishop International Engineering Co.89 decision also suggested that the parties to a subcontract could shift the risk of the owner’s insolvency to the subcontractor, and make payment to the general contractor an absolute condition precedent to payment to the subcontractor, provided that the subcontract clearly and unequivocally so provides. In Mignot v. Parkhill 90 , the Oregan Supreme Court construe a clause stating that the “It is fully understood by and between the parties hereto that Contractor shall not be to pay Subcontractor for any of the work until such time as Contractor has himself received the money from [ the Owner]” only affected the time of payment. The court concluded that: “Where the contract contains a definite and unambiguous promise to pay for labor and materials performed and furnished, or for other services, equally clear an unambiguous language, expressing the intention that the happening of a contingency over which the promise has no control shall be a condition precedent to payment, must be found in the contract before the positive and absolute agreement to pay will be considered as superseded.” The key words of this provision, “until such time as,” combined with the absence of any clear language that expresses the parties’ intention to create a condition precedent, 88 589 F. Supp. 701 (D.N.J. 1984) 303 F.2d 655, 661 (6th Cir. 1962) 90 391 P.2d 755, 758 (Or. 1964) 89 38 appeared as a stipulation for payment on receipt of a fund “ ‘inserted merely for the purpose of fixing the time at which performance shall become due.’ ” Initially, this provision seems to clearly express an intention to make payment to the subcontractor conditional upon the owner’s payment to the general contractor, but the court required language of a more specific nature. Short of any precise terms, such as “condition precedent,” the contractual language could not be construed as anything but merely fixing the time for payment. In Berkel & Company Constractors v. Christman Company 210 Mich. App. 416, 533 N.W.2d 838 (1995), a subcontractor argued that the clause at issue was merely a provision that postponed payment for a reasonable period of time, not indefinitely. The Michigan Court disagreed, holding that: “The contract clearly provides that all payments made to the subcontractor are to be made only from equivalent payments received by [the general contractor] for work done, “the receipt of such payments by the [general contractor] is being a condition precedent to payments to the subcontractor.” In West-Fair Electric Contractors v. Aetna Casualty & Surety Company91 , the New York Court of Appeal held that “a “pay when paid” provision which forces the subcontractor to assume the risk that the owner will fail to pay the general contractor is void and unenforceable as contrary to public policy.” However the court also said “by contrast, a pay-when-paid provision which merely fixes a time for payment does not indefinitely suspend a subcontractor’s right to payment upon the failure of an owner to pay the general contractor and does not violate public policy.” A Massachusetts in the case of A.J. Wolfe Co. v. Baltimore Contractors92 , court found that a contract which provided that “payment will be made on monthly requisitions 91 92 87 N.Y. 2d 148, 638 N.Y.S. 2d 394, 661 N.E.2d 967 (1995) Inc., 244 N.E.2d 717, 720 (Mass. 1969), 39 for progress payments “within 10 days after … [the owners’] payment of such monthly progress payments … [has] been received’ ” by the contractor merely set the time for payment and did not create a condition precedent. The court concludes that this language did not amount to a clear provision “should be viewed only as postponing payment by the general contractor for a reasonable time.” In Southern States Masonry Inc. v. JA Jones Construction Company (1987) 507 So. 2d 198, the Supreme Court of Louisiana had interpreted a clause reading: “3 … Contractor shall pay to Sub-contractor upon receipt of payment from the Owner…” “A final payment … shall be made within forty-five (45) days after the last of the following to occur: (a) full completion of the Work by Subcontractor, (b) final acceptance of the work by the Architect … (c) final payment by Owner …” The court there held that clause could not be interpreted to mean “if” the subcontractor was to be paid but rather “when” it was to be paid. It interpreted the clauses in that case as relating to the time when a contractor must pay the subcontractor and not to the issue of whether the sub-contractor got paid at all. Other reasons exist for rejecting an interpretation of third-party payment provisions besides ambiguous contractual language. Invariably, courts hesitate to enforce these provisions as conditions precedent if enforcement of the terms would result in an extreme forfeiture by the subcontractor. Courts do not look favorably upon conditions precedent, and if failure to meet conditions precedent results in a windfall to the general contractor, courts may consider the condition excused. Furthermore, courts consider general contractors to be in the best position to assess the solvency of the owner and bear 40 the risk of nonpayment. Unless absolute certain, courts do not transfer this risk from the general contractor to the subcontractor. Finally courts have even determined that subcontractors are an oppressed class that needs protection. Liberal application of thirdparty payment provisions as conditions precedent adds another commercial advantage for genera contractors, who already stand in a position of a greater resourcefulness and bargaining power 93 . The courts decisions noted above, do acknowledge that third-party payment clauses can constitute condition precedent. When the contractual language explicitly stated the conditional nature of the payment relationship between the three parties, courts have upheld the third-party payment provisions as precluding subcontractors from recovery. The court decisions noted above, however, do acknowledge that third-party payment clauses can constitutes conditions precedent when the contractual language explicitly stated the conditional nature of the payment relationship between the three parties, courts have upheld the third-party payment provisions as precluding subcontractors from recovery. 3.5.2 “Pay When Paid” Provisions as Condition Precedent Despite the fact that one jurisdiction may conclude that a third-party payment provision merely delays the time of payment, certain language, such as an agreement with terms that explicitly state that the provision function as a condition precedent, may lead the same jurisdiction to a different result 94 . An analysis of jurisdictions that have ruled in favor of contractors on this issues helps to explain when “pay-when-paid” 93 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 894 94 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 894 41 provisions do not create an absolute duty to pay subcontractors 95 . When payment provisions interpreted as a condition precedent, the provider will get paid only after payment by the owner96 . Most courts have held that a “pay when paid” clause constitutes a conditional promise and thus a condition precedent to the contractor’s obligation to pay the subcontractor. These courts, however, have generally done do only after finding the clause clearly and unambiguously expressed the intention of the parties to have the clause work as a condition precedent 97 . If there is a valid condition precedent in a contract, the party in whose favor the condition exists is not obligated to perform an action required by the contract until the condition has been satisfied98 . Most obviously, when the language within a third-party payment provision explicitly states that the owner’s payment to the contractor is a condition precedent to the contractor’s payment to the subcontractor; courts enforce the provision as a condition precedent 99 . In other word describe intend of the general contractor to shift the risk of non-payment to the subcontractor 100 . The Arizona Court of Appeal in Harvey Concrete, Inc. v. Agro Construction & Supply Co.101 , held that the following clause was plain enough to shift the credit risk to the subcontractor: “Subcontractor agrees as a condition precedent to payment…that the owner shall have first paid the payment…to the contractor, and that payment for wither 95 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 894 96 Goodman, N.H. and Barthet, P.C. (1999). Waiting to Get PAID: Are Pay When Paid Provisions A Matter of When or If?. The Florida Bar Journal, October 1999 Volume LXXIII, No.9 97 Bruner, P.L. and Haley, T.L.. Managing and Litigating the Complex Surety Case. American Bar Association. Tort Trial and Insurance. 98 See John J. Calnan Co. v. Talsma Builders, Inc., 395 N.E.2d 1076, 1080 (lll App. Ct. 1979). 99 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook . Published by Aspen Publishers Online. Pg 894 100 Gurney, D.S. (2007). “Pay-When-Paid” Clauses: What Happens When the Owner Doesn’t Pay?. Published in The Constructor. Ohio: Frost Brown Todd LLC 101 939 P.2d 811 (Ariz. Ct. App. 1997) 42 progress payments or final payment is not due and owing to the subcontractor as provided for herein until the owner has made such payment to the contractor” The language that included the term “condition precedent” sufficed to create an enforceable condition. Furthermore, the court held that a condition precedent is established when expressions like “exclusively” or “only” demonstrate that payment was to be made from a particular fund and no other. Without these key words, one may assume that these provisions would only effect the time of payment and not waive the contractor’s duty to pay for services rendered by the subcontractor. In order to create a condition precedent to the subcontractor’s payment, there must be contractual language demonstrating the parties ‘unequivocal intent’ that the subcontractor will only be paid if the contractor is paid. However, in Printz Services Corp. v. Main Electric Ltd.102 , the court found that a third – party payment provision that stated the contractor would pay the respective subcontractor “ ‘provided like payment shall have been made by the Owner to Contractor’ ” did relieve the contractor of the obligation to pay a subcontractor absent the contractor’s receipt of full payment from the owner. This ruling, as noted by the court, represents a minority position. Typically, a court requires a third-party payment provision in a construction contract to contain more definite language than “provided like payment shall have been made” to create a condition precedent. The Third District in Robert F. Wilson, Inc., v. Post-Tensioned Structures, Inc., 103 confirmed that the following provision shifted the risk of nonpayment to the subcontractor: 102 103 949 P.2d 77 (Colo. Ct. App. 1997) 522 So. 2d 70 (Fla. 3d DCA 1988) 43 No Change Orders will be issued for additional work of any kind unless so approved by the Architect and Owner prior to its issuance. In the event a controversy occurs between the Owner and the General Contractor concerning the Contract with the Owner or these Change Order(s), then it is expressly agreed hat no compensation for these items shall be due the Subcontractor from the Contractor until payment for them is received by the Contactor, regardless of the fact that payments is delayed due to the Contractor negotiating with the Owner, arbitration, administrative actions, litigation, appeals or other similar activities. In 1990, the Supreme Court in DEC Electric, Inc., v. Raphael Construction Corporation, quoting from its earlier reasoning in Peacock Construction Co., Inc. v. Modern Air Conditioning, Inc. 104 , held a “pay-when-paid” clause to be condition precedent to payment from the general contractor to the subcontractor. However, the same year the Supreme Court decided OBS v. Pace Construction Corporation105 and concluded that an ambiguity existed between the general conditions to the subcontract and the apparent intent to the subcontract itself, thereby nullifying an attempt to shift the risk of nonpayment. Payment by the owner to the contractor is a precondition to payment to a subcontractor. In Timbro Development Limited v. Grimsby Diesel Motors Inc., Timbro performed construction work for Grimsby. When the owner failed to pay Timbro, it refused to pay its subcontractors, relying on a clause in its purchase orders: “Payments will be made not more than 30 days after the submission date or 10 days after certification or when we have been paid by the owner, whichever is the later”. 104 105 353 So.2d 840 (Fla. 1977) 558 So. 2d 404 (Fla. 1990) 44 The pay-when-paid clause was printed in red ink on the general contractor’s Purchase Order. The Ontario Court of Appeal found in 1988 that the clause specified the condition governing the subcontractors’ legal entitlement to payment and not merely the time of payment. The court further found that, under the clause the subcontractors clearly assumed the risks if the owner did not pay the contractor. Since Timbro was not paid, it was not obliged to pay the subcontractors. The subcontractors had effectively waived their right to paid until the contractor had been paid. Further appeal to the Supreme Court of Canada was refused. Another variation of a pay-when-paid clause was considered by an Ontorio Superior Court in Kor-Ban Inc. v. Pigott Construction Ltd.106 . Payment to be made as follows: “Ninety percent (90%) of the value of the completed work done by the subcontractor and ninety percent (90%) of the value of the materials delivered to the site from time to time as the Work progresses, provided the amounts of such payments are certified by the Architect under the terms of the contract between the owner and contractor, and Five (5) days after payment of such amount has been received by the contractor from the owner. The balance of the contract Price will be paid in accordance with the Construction Lien Act 1983 and Ten (10) days after payment of such amounts has been received by the contractor from the owner and provided the subcontractor has fulfilled all of its obligations under this agreement”. The court in Kor-Ban also found that the subcontractor assumed the risk of nonpayment by the owner to the general. The court also held that on the evidence, it was apparent that the subcontractor had been made aware of the pay-when-paid clause in 106 (1993) 11 C.L.R. (2d) 160 (Ont. Gen. Div.) 45 contract even though it was not as obvious as the red inked clause in Timbro. Again, the court interpreted the payment clause as a waiver of the entitlement to be pa id. If the intent of the general contractor is to not be responsible for owner’s insolvency or refusal to pay, then the contract language must be precise to shift the risk of payment failure by the owner to the subcontractor 107 . How do contractors shift the burden of nonpayment by the owner? Say it clearly in a contract provision. What should be said? The contract which stated that: i. The subcontractor is paid only if the general contractor is paid or the subcontractor will not be paid unless the general contractor receives payment from the owner; and ii. The subcontractor assumes the risks of nonpayment by the owner due to insolvency or the inability to pay. Such contract language has been held by many courts to sufficiently shift the burden of nonpayment to the subcontractor 108 . The court in Peacock Construction Co. v. Modern Air Conditioning 109 , did recognize that nothing prevents parties from shifting the risk of an owner’s nonpayment provided the contract expressly and unambiguously states such intent. The burden of clear expression is on the party seeking to pay only when paid, and any ambiguity will be construed against it as a matter of law. 107 Devine, P. (2006). When Must A Subcontractor Be Paid Under A “Pay-When-Paid” Clause. Business Credit July/August 2006. National Association of Credit Management 108 Fortney & Klingshirn . Contingent Payment Clauses. Ohio. 109 Inc., 353 So. 2d 840 (Fla. 1977) 46 In J.J. Shane v. Aetna Casualty & Surety Company110 , a subcontractor found itself in the unexpected position of waiting to get paid until the party with whom it contracted was paid by the owner. The dispute involved the interpretation of the following payment provision contained in the written subcontract between the parties: Article XIII Method of Payment a) Subcontractor is relying upon the financial responsibility of Owner in performing the Work. It is understood by Subcontractor that payment for the work is to be made from funds received from Owner by Contractor in respect to the Work. The subcontractor argued that the foregoing term simply fixed a reasonable time for payment by the contractor. Florida’s Third District Court of Appeal rejected that argument, holding instead that the subject provision plainly and unambiguously made payment by the owner a condition precedent to payment by the general contractor to the subcontractor. For over thirty years, most state courts have held that contractor cannot indefinitely withhold payment from subcontractors based upon a “pay-when-paid” clause. Instead, “pay-when-paid” clause requires a contractor to pay its subcontractors within a “reasonable time” of the completion of satisfactory work. The article on “Contingent Payment Clauses in the 50 States” by the Foundation of the American Subcontractors Association (FASA) attempt s to summarize the basic stance of each of the fifty stated with respect of two types of contingent payment clause, “pay when paid” and “pay if paid.” The information displayed for all states that have applicable law on this issue revolved around (a) whether “pay-when-paid” clauses allow a contractor in the state to only delay payment to its subcontractors for a reasonable time (b) whether a “pay-ifpaid” clause will be enforced in that state if it is unambiguously drafted (c) whether “pay110 723 So. 2d 302 (Fla. 3d DCA 1998), reh. den. 47 if-paid” clause will be enforced in that state if it is unambiguously drafted (d) key statutes and cases that describe the state’s positions on contingent payment clauses (See Appendix A). In a nutshell, the summary of the interpretations on the application of “pay when paid” provisions in the construction sub-contract from the literature review can be concluded and shown in Table 3.1 as follow: 48 Table 3.1: The Application of “Pay When Paid” Provisions in Construction Sub-Contract No Case Law 1 Thomas J. Dyer Co. v. Bishop International Engineering Co. 303 F.2d 655, 661 (6th Cir. 1962) “Pay When Paid” Suggest Time For Payment “Pay When Paid” as Condition Precedent Judgment • X • • 2 Power & Pollution Services, Inc. v. Suburban Power Piping Corp47 Ohio App. 3d 89 (Cuyahoga County 1991) X • • It was the intention of the parties that the subcontractor would be paid by the general contractor for the labor and material put into the project. The Sixth Circuit opined that the credit risk inherent in the general contractor’s undertaking could be shifted to the subcontractor, but only where the contract contained express language “clearly showing that to be the intention of the parties.’ The court interpreted these standard “pay-when-paid” clauses, not as creating an absolute condition precedent to payment to the subcontractor, but rather as affording the general contractor a postponement of payment for a reasonable period of time to allow the general contractor an opportunity to collect funds due from the owner to pay the subcontractors and not to require the subcontractor to wait an indefinite period of time until the general contractor was paid by the owner. Agreed with the analysis in Dyer Unless the contract clearly shows that the parties intended to make payment from the owner a “condition precedent” to payment of the subcontractor, the pay-when-paid clause governs only the timing of payments to the subcontractor but does not allow the general contractor to avoid paying the subcontractor altogether 49 No Case Law 3 Seal Tite Corp. v. Ehret, Inc589 F. Supp. 701 (D.N.J. 1984) 4 Mignot v. Parkhill “Pay When Paid” Suggest Time For Payment X X “Pay When Paid” as Condition Precedent Judgment • • • The parties to a subcontract could shift the risk of the owner’s insolvency to the subcontractor, and make payment to the general contractor an absolute condition precedent to payment to the subcontractor, provided that the subcontract clearly and unequivocally so provides. Where the contract contains a definite and unambiguous promise to pay for labor and materials performed and furnished, or for other services, equally clear an unambiguous language, expressing the intention that the happening of a contingency over which the promise has no control shall be a condition precedent to payment, must be found in the contract before the positive and absolute agreement to pay will be considered as superseded. “until such time as,” combined with the absence of any clear language that expresses the parties’ intention to create a condition precedent, appeared as a stipulation for payment on receipt of a fund “ ‘inserted merely for the purpose of fixing the time at which performance shall become due.’ ” Initially, this provision seems to clearly express an intention to make payment to the subcontractor conditional upon the owner’s payment to the general contractor, but the court required language of a more specific nature. Short of any precise terms, such as “condition precedent,” the contractual 50 No 5 6 7 Case Law Berkel & Company Constractors v. Christman Company 210 Mich. App. 416, 533 N.W.2d 838 (1995) West-Fair Electric Contractors v. Aetna Casualty & Surety Company 87 N.Y. 2d 148, 638 N.Y.S. 2d 394, 661 N.E.2d 967 (1995) A.J. Wolfe Co. v. Baltimore Contractors Inc., 244 N.E.2d 717, 720 (Mass. 1969), “Pay When Paid” Suggest Time For Payment X X “Pay When Paid” as Condition Precedent Judgment language could not be construed as anything but merely fixing the time for payment. • The Michigan Court disagreed, holding that: “The contract clearly provides that all payments made to the subcontractor are to be made only from equivalent payments received by [the general contractor] for work done, “the receipt of such payments by the [general contractor] is being a condition precedent to payments to the subcontractor.” • A pay-when-paid provision which merely fixes a time for payment does not indefinitely suspend a subcontractor’s right to payment upon the failure of an owner to pay the general contractor and does not violate public policy. • X A contract which provided that “payment will be made on monthly requisitions for progress payments “within 10 days after … [the owners’] payment of such monthly progress payments … [has] been received’ ” by the contractor merely set the time for payment and did not create a condition precedent. The court concludes that this language did not amount to a clear provision “should be viewed only as postponing payment by the general contractor for a reasonable time.” 51 No Case Law 8 Southern States Masonry Inc. v. JA Jones Construction Company (1987) 507 So. 2d 198 9 Harvey Concrete, Inc. v. Agro Construction & Supply Co. 939 P.2d 811 (Ariz. Ct. App. 1997) “Pay When Paid” Suggest Time For Payment “Pay When Paid” as Condition Precedent Judgment • X • X • • The court there held that clause could not be interpreted to mean “if” the sub-contractor was to be paid but rather “when” it was to be paid. It interpreted the clauses in that case as relating to the time when a contractor must pay the subcontractor and not to the issue of whether the subcontractor got paid at all. Held that the following clause was plain enough to shift the credit risk to the subcontractor: “Subcontractor agrees as a condition precedent to payment…that the owner shall have first paid the payment…to the contractor, and that payment for wither progress payments or final payment is not due and owing to the subcontractor as provided for herein until the owner has made such payment to the contractor” The language that included the term “condition precedent” sufficed to create an enforceable condition. A condition precedent is established when expressions like “exclusively” or “only” demonstrate that payment was to be made from a particular fund and no other. Without these key words, one may assume that these provisions would only effect the time of payment and not waive the contractor’s duty to pay for services rendered by the subcontractor. In order to create a condition precedent to the subcontractor’s payment, there must be contractual 52 No 10 11 12 Case Law “Pay When Paid” Suggest Time For Payment “Pay When Paid” as Condition Precedent • Printz Services Corp. v. Main Electric Ltd949 P.2d 77 (Colo. Ct. App. 1997) X Robert F. Wilson, Inc., v. PostTensioned Structures, Inc., 522 So. 2d 70 (Fla. 3d DCA 1988) X DEC Electric, Inc., v. Raphael Construction Corporation (1990) Judgment • X • language demonstrating the parties ‘unequivocal intent’ that the subcontractor will only be paid if the contractor is paid The court found that a third – party payment provision that stated the contractor would pay the respective subcontractor “ ‘provided like payment shall have been made by the Owner to Contractor’ ” did relieve the contractor of the obligation to pay a subcontractor absent the contractor’s receipt of full payment from the owner The following provision shifted the risk of nonpayment to the subcontractor:“… In the event a controversy occurs between the Owner and the General Contractor concerning the Contract with the Owner or these Change Order(s), then it is expressly agreed had no compensation for these items shall be due the Subcontractor from the Contractor until payment for them is received by the Contactor, regardless of the fact that payments is delayed due to the Contractor negotiating with the Owner..” Quoting from its earlier reasoning in Peacock Construction Co., Inc. v. Modern Air Conditioning, Inc., held a “paywhen-paid” clause to be condition precedent to payment from the general contractor to the subcontractor. However, the same year the Supreme Court decided OBS v. Pace Construction Corporation and concluded that an ambiguity 53 No 13 Case Law Timbro Development Limited v. Grimsby Diesel Motors Inc “Pay When Paid” Suggest Time For Payment “Pay When Paid” as Condition Precedent Judgment • X • 14 15 Kor-Ban Inc. v. Pigott Construction Ltd(1993) 11 C.L.R. (2d) 160 (Ont. Gen. Div.) Peacock Construction Co. v. Modern Air Conditioning Inc., 353 So. 2d 840 (Fla. 1977) • X • X existed between the general conditions to the subcontract and the apparent intent to the subcontract itself, thereby nullifying an attempt to shift the risk of nonpayment. A clause in its purchase orders: “Payments will be made not more than 30 days after the submission date or 10 days after certification or when we have been paid by the owner, whichever is the later”. The Ontario Court of Appeal found in 1988 that the clause specified the condition governing the subcontractors’ legal entitlement to payment and not merely the time of payment. The court further found that, under the clause the subcontractors clearly assumed the risks if the owner did not pay the contractor The subcontractor assumed the risk of non-payment by the owner to the general. The court also held that on the evidence, it was apparent that the subcontractor had been made aware of the pay-when-paid clause in contract That nothing prevents parties from shifting the risk of an owner’s nonpayment provided the contract expressly and unambiguously states such intent. The burden of clear expression is on the party seeking to pay only when paid, and any ambiguity will be construed against it as a matter of law. 54 No 16 Case Law J.J. Shane v. Aetna Casualty & Surety Company723 So. 2d 302 (Fla. 3d DCA 1998), reh. den. “Pay When Paid” Suggest Time For Payment “Pay When Paid” as Condition Precedent Judgment • X The subject provision plainly and unambiguously made payment by the owner a condition precedent to payment by the general contractor to the subcontractor. 55 3.6 Reasonable Time of Payment Often domestic subcontractors would find themselves contracting under heavily amended bespoke contract with payment provisions that were weighted heavily in favour of main contractors. “Pay when paid” provisions were legion, and under such arrangements the payee was usually unaware of the time when payment would be made. Payment was almost entirely dependent on when the client paid the main contractor. This also caused significant difficulties for many, particularly subcontractor, in trying to establish when a legally enforceable debt was due. Debt is an important factor in any payment arrangement because until the debt is created there is no legally enforceable means of recovering sums that one party may believed to owed. For subcontractors operating under “pay-when-paid” provisions, the condition precedent to the debt being established was the payment to the main contractor. Only then could the subcontractor’s debt crystallize and action be taken to recover111 . Often, the agreed payment cycle would be replaced with a valuation arrangement to correspond with the release of payment to the main contractor. Similar problem were encountered with bespoke contracts and many subcontractors often did not know when they were going to be paid and how much they would be paid; in other words, they did not know the timing of the payment or amount of payment that was going to be made 112 . 111 Pettigrew, R. (2005). Payment Under the Construction Contract Legislation. Published by Thomas Telford. Pg 75-76 112 Ibid Pg 76 56 The American Institute of Architects (AIA) A401 and the Associated General Contractors (AGC) 650 subcontract forms contain pay-when-paid terms 113 . With “pay when paid” clause, as long as the cause for the owner’s nonpayment to the general contractor is not related to the subcontractor immediately following the expiration of a reasonable time period. The time period is like grace period for the general contractor, but if the general contractor does not receive payment from the owner through no fault of the subcontractor, the general contractor will still be liable to the subcontractor 114 . 3.6.1 A Mechanism to Determine When Payment is due A common judicial limitation is to hold that the general contractor is required to pay the subcontractor within a reasonable time. Some courts have held that the “paywhen-paid” clause does not allow non-payment for an indefinite period, but rather, that the subcontractor must be ultimately paid, regardless of whether the general contractor has been paid. These courts may interpret the payment clause’s “pay-when-paid” language as merely a timing provision, rather than a condition precedent 115 . The “pay-when-paid” indicates the time for payment which the time for payment is calculated from the date when payment should have been made by the employer, whether or not payment has in fact been made. This is illustrates by Smith & Smith Glass Ltd. v. Winstone Architectural Cladding System Ltd. (1991). 113 Hess, S.A. & Bales, J.V. (2007). Design Professional and Construction Manager Law. American Bar Association - Forum on the Construction Industry. Chapter 15 Pg 500 114 Ibid Pg 500 115 Murphey, D.R. (1999). Surety’s Reliance on Pay-When-Paid Clause Rejected. Smith, Currie & Hancock LLP. 57 Atkinson (2007) cited that, a “pay-when-paid” could only be effective so long as the main contract machinery of payment was capable of being operated. For the clause to be effective the Contractor impliedly undertaken that it will pursue all means available to obtain payment or it will not be able to rely on the clause to defeat the subcontractor’s claim for payment. Across the country, in Massachusetts, New York, Maryland, North Carolina and Oklahoma, the courts have construed “pay-when-paid” provisions to mean that the contractor shall pay his or her subcontractors within a stated number of days or a reasonable time thereafter 116 . Where no duration is set forth in the contract documents, the courts will interpret that to mean that the contract should last a reasonable time 117 . A general contractor had delayed payment to a subcontractor since the owner had not yet paid the general contractor. The general contractor could not show that the owner’s delay in payment was due to any purported acts or omissions on the part of the subcontractor. The court found that the subcontractor was, therefore, entitled to payment of its retained percentage 118 . A variation of a contingent payment clause arose in Lowy and Donnath, Inc. v.New York119 . The court found that an electrical subcontractor was entitled to receive payment for the labor and materials furnished to the general contractor. The purchase order form of subcontract between the general contractor and the electrical subcontractor made the subcontract subject to the contract between the general contractor and the 116 A.J. Wolfe Co. v. Baltimore Contractors, Inc., 355 Mass 361 (1969), Schuler-Haas Elec. Co. v. Aetna Cas. & Sur. Co., 49 A.D.2d 348 (1976), Fishman Const. Co. v. Hansen, 238 Md. 418 (1965), HowardGreen Elec. Co. v. Chaney & James Const. Co., 12N.C.App.63 (1971), Moore v. Continental Cas. Co., 366 F.Supp. 954 (W.D.Okl.1973) 117 Krol, J.J.P (1993). Construction Contract Law. Published by John Wiley and Sons. Pg 34 118 Grossman Steel and Aluminum Corp. v. Samson Window Corp., 78 A.D.2d 871, 433 N.Y.S.2d 31 (2nd Dept. 1980), aff d 54 N.Y.2d 653, 442 N.Y.S.2d 769 (1981) 119 98 A.D.2d 42, 469 N.Y.S.2d 760 (1st Dept. 1983), aff’d 62 N.Y.2d 746, 476 N.Y.S.2d 830 (1984). 58 owner, to the extent that the electrical work was to be in strict accordance with the contract plans and specifications. Absent from the language was any indic ation that payment for the electrical work was subject to verification or audit by the public agency or payment from the owner to the general contractor. In addition, the purchase order did not contain any provision regarding to timing of payment. Therefore, payment was due immediately upon completion of the work. With a “pay-when-paid” clause, as long as the cause for the owner’s nonpayment to the general contractor is not related to the subcontractor’s work, the general contractor will remain liable to the subcontractor immediately following the expiration reasonable time period. The time period is like a grace period for the general contractor, but if the general contractor does not receive payment from the owner through no fault of the subcontractor, the general contractor will still be liable to the subcontractor 120 In Galloway Corp. v. S.R. Ballard Constr. Co.121 , Stein states that: “Traditionally, courts have refused to strictly enforce “pay-when-paid” clauses, holding that they merely grant the contractor a reasonable time to obtain payment from the owner when that payment is due. When this reasonable period has expired, the contractor is obligated to pay the subcontractor whether or not the contractor has received payment from the owner. Recently, however, courts have become more receptive to enforcing “pay-whenpaid” clauses so long as the clause unequivocally provides that receipt of payment by the contractor is a condition precedent to the contractor’s obligation to pay its subcontractor.” The most comprehensive analysis seems to be that of the Connecticut Supreme Court in Blakeslee Arpaia Chapman v. EI Construction, Inc. 239 Conn. 708, 687 A.2d 506 (1997) even though the court did not decide the issue: 120 Hess, S.A. & Bales, J.V. (2007). Design Professional and Construction Manager Law. American Bar Association - Forum on the Construction Industry. Chapter 15 Pg 500 121 250 Va 493, 494 S.E.2d 349 (1995) (Virginia Supreme Court) 59 The plaintiff and the amicus American Subcontractors Association advance several arguments for not enforcing such a clause. These arguments can be summarized as follows: (1) a “pay-when-paid” clause, which transfer the credit risk incurred by the general contractor, can only be enforced if the language in the subcontract is clear and unequivocal and, in this case, the subcontract language was equivocal;…(2)such a clause does not relieve contractors of their duty to pay the subcontractor because it conflicts with the contract read in its entirety or the intent of the parties;…(3) “pay-when-paid” clauses are not enforceable when the conduct of the contractor is the cause of the failure;…(4) such a clause merely sets the time for payment, and “should be viewed only as postponing payment by the general contractor for a reasonable time after requisition…so as to afford the general contractor an opportunity to obtain funds from the owner”; and (5) that a “pay-when-paid” clause is a condition precedent that is contrary to public policy and therefore unenforceable 3.7 Issues Regarding to “Pay When Paid” Provisions 3.7.1 Prevention Doctrine The Prevention Doctrine provides that a party who prevents performance of a contract may not complain of such nonperformance. The Prevention Doctrine may have an effect on a carefully drafted pay-when-paid provision. This is one that attempts to 60 condition and limit a subcontractor’s right to receive payment on whether the general contractor has received payment from the owner 122 . Even a pay-when-paid clause that qualifies as a condition precedent will not be regarded as an absolute transfer of the risk of owner nonpayment. A pay-when-paid defense cannot be asserted by a contractor who frustrates or prevents the owner’s payment by its own material breach. As the beneficiary of a condition payment by the owner to its duty to pay the subcontractor, the contractor is itself subject to an implied condition that it not frustrates the fulfillment of that condition. However, the mere fact that the owner is refusing to pay because of a dispute with the contractor; such a refusal could be a risk contemplated by the parties to the subcontract 123 . Where the general contractors’ own actions or inactions contribute to the nonoccurrence of a condition precedent, the condition precedent to pay out is deemed to waived or excused. This is known as the “Prevention Doctrine”. As refer to the case of Moore Brothers Co. v. Brown & Root, Inc. 207 F.3d 717 (2000), the Prevention Doctrine provides that the general contractor cannot cause the non-payment to occur and then rely on the came condition as a basis to occur and then rely on the same condition as a basis not to pay its subcontractor. If the owner fails to pay the general contractor because of the general contractor’s own fault, the general contractor will not be able to rely on the “paywhen-paid” clause to withhold the payment to the subcontractor 124 . In the case of Northeast Drilling, Inc. v. Inner Space Services, Inc., the 8th Circuit Court of Appeals held that a subcontractor could not invoke a pay-when-paid clause after it prevented fulfillment of a condition precedent. Because the subcontractor failed to 122 Sienicki, J. and Roth, J. (2007). The Prevention Doctrine and Its Effect on ‘Pay-If-Paid’ and ‘PayWhen-Paid’ Clauses. Snell & Wilmer L.L.P. 123 Lybeck, K.L. and Shreves, H.B. (1998). The Law of Payment Bonds. American Bar Association. Pg 265 124 Ahlers J.P. (2008). “Pay When Paid” vs. “Pay If Paid” Clauses: Mystery vs. Myth. 61 submit a change -order request to the contractor after drilling in an expanded area, it contributed to the contractor’s failure to pay. Thus , the subcontractor was required to pay the sub-subcontractor because the prevention doctrine applied and rendered the paywhen-paid clause void. 3.7.2 Summary Judgment Summary judgment is a decision made on the basis of statements & evidence presented for the record without a trial. It is used when there is no dispute as to the fact of the case & one party is entitled to judgment as a matter of law. The principles applied in a summary judgment proceedings is clearly illustrated in the case of Alloy Automotive Sdn Bhd v. Perusahaan Ironfield Sdn Bhd [1986] 1 MLJ 382 (SC) where the Supreme Court had stated (at p 390) that: “Where all the issues are clear, summary judgment should be given. An appellant ought not to be shut out from defending unless it is very clear that he has no case in the action. A complete defence need not be shown. The defence setup need only show that there is a triable issue or question or that for some reason there ought to be a trial.” Similar principles were further illustrated in the case of Malayan Insurance (M) Sdn Bhd v. Asia Hotel Sdn Bhd [1987] 2 MLJ 183 (SC), where the Supreme Court had held as follows: 62 “… the underlying philosophy in the O 14 provision is to prevent a respondent clearly entitled to the money from being delayed his judgment where there is no fairly arguable defence to the claim. The provision should only be applied to cases where there is no reasonable doubt that the respondent is entitled to judgment. Order 14 is not intended to shut out an appellant. The jurisdiction should only be exercised is very clear cases.” The High Court in Hong Kong Teakwood Works Ltd. v. Shui On Construction Co. Ltd. [1984] HKLR 23 and The Court of Appeal in Schindler Lifts (Hong Kong) Ltd. v. Shui On Construction Co. Ltd. [1985] HKLR 118 have considered the meaning of clause 11(b) in the context of an application for summary judgment. The Hong Kong Courts came to the view that it was arguable that “receipt of payment” in clause 11(b) means actual receipt of payment which does not embrace set-off for liquidated damages made under clause 22 of main contract. The Hong Kong Teakwood and Schindler Lifts (Hong Kong) cases cannot be regarded as authority to support the main contractor’s argument for not paying the sub-contractor since: 1. The burden of defendants in an application for summary judgment is only to show an arguable defence, the courts did not decide that the arguments advanced by the defendants were sustained. They only held that such arguments were not unsustainable. 2. The parties only argued whether a set-off exercised by the employer against payment due to the main contractor constituted receipt of payment by the main contractor. Whether receipt (in any sense) of payment by the main contractor is a condition precedent to payment by the main contractor to the sub-contractor has never been raised as an issue before the Courts in the above -mentioned cases. 63 3.7.3 Payment Bond Surety The payment bond is straight forward device basically requiring a third party such as a bank or an insurance company to guarantee payment in the event of default on the part of the paying party. The provision of bond by the employer is presently uncommon in Malaysia other than for bullet payment contracts. The CIDB 2000 Form nevertheless provides for it as an option125 . Many general contractors are needlessly exposing themselves to increased liability and legal risks. A general contractor on a public construction project have completed the works but have yet to be paid in full by the owner. When subcontractors ask for final payment, the general contractor will point to the subcontract’s “pay-whenpaid” clause. Then the subcontractor does something that the general contractor don’t expect instead of suing the general contractor, it sues the general contractor payment bong surety. The issue is whether the surety can enforce the pay-when-paid clause and tell the subcontractor that its bond claim must wait until the general contractor is paid by the owner. Most courts considering the issue have held that a surety cannot enforce a subcontract’s pay-when-paid clause and must reimburse an unpaid subcontractor even when the general contractor has not been paid by the owner 126 . The court decisions by two U.S. Circuit Courts in Moore Brothers Co. v. Brown & Root Inc. 127 , and United States ex rel. Walton Technology v. Weststar Engineering Inc.128 , are alarming for general contractors, who have come to rely upon pay-when-paid clauses to shift some of the risk of an owner’s non-payment to their subcontractors. The 125 Lim Chong Fong. The Malaysian Construction Industry-The Present Dilemmas of the Unpaid Contractors 126 Koprince, S.J. (2008). Is Your Pay-When-Paid Clause Worthless?. The Constructor January/February 2008. McGraw Hill Construction 127 207 F.3d 717 (4th Cir. 2000) 128 290 F.3d 1199 (9th Cir. 2002) 64 appellate court addressed “whether a surety can assert the principal’s defense based on ‘pay-when-paid’ language in the subcontract, where the surety did not expressly incorporate the ‘pay-when-paid’ language into the contract payment bond. 129 ” In rejecting the surety’s attempt to rely upon the contractor’s defense, the Fourth Circuit reasoned: There is no indication that the parties intended the phrase “sums justly due” to incorporate the contingency of payment by the Owners. On the contrary, the very purpose of secur ing a surety bond contract is to ensure that claimants who perform work are paid for their work in the event that the principal does not pay. To suggest that non-payment by the Owner absolutely absolves the surety of its obligation is nonsensical, for it defeats the very purpose of a payment bond. Just as in Moore Brothers, because the subcontractors are suing on the payment bond and not their subcontracts, and because there is no language in the payment bond that hinges payment by the surety on the contractor’s receipt of payment from the owner, there is no basis for denying the subcontractors payment under the performance bond. As the Fourth Circuit aptly noted in Moore Brothers, such a denial would frustrate the very purpose of the payment bond130 . In Brown & Kerr, Inc. v. St. Paul Fire and Marine Insurance Co. 131 the court opined that as the purpose of the bond is to assure that subcontractors be paid, subcontractors should not have to wait the determination of an unrelated legal dispute between the owner and the contractor. Instead of suggesting the surety was not entitled to assert the pay-when-paid defense under any circumstances, the court should have considered whether the contractor’s dispute with the owner amounted to frustration of the payment condition, a recognized bar to its enforcement. 129 Moore Brothers Co. v. Brown & Root Inc. 207 F.3d 723 (4th Cir. 2000) II, R.L. (2005). Nos. 31869 and 31870. Supreme Court of Appeals of West Virginia. Pg 8 131 940 F. Supp. 1245, 1249 (N.D. III. 1990) 130 65 Several courts have strongly suggested that had pay-when-paid language been included in the payment bond, rather than merely in the subcontract, the surety would have been permitted to delay payment until the general contractor had been paid by the owner 132 . In the case of Casey Indus. Inc. v. Seaboard Surety Co 133 ., the district court written that “a surety cannot assert its principal’s defense based on pay-when-paid language in the subcontract when the pay-when-paid provision is not expressly incorporated into the payment bond.” The clear and dangerous trend of cases like Moore Brothers and Walton Technology is to prohibit payment bond sureties from enforcing standard pay-when-paid clause. General contractors should aware of the significant liability problem. These cases may pose and take steps to strengthen their subcontracts and payment bonds before they are caught on the wrong end of an unenforceable pay-when-paid clause 134 . 3.7.4 Contractor’s Own Default It often happens that a main contractor would suffer liquidated damages as a result of his own default or that of one of a number of his subcontractors. The question whish arises in such situation is whether the main contractor is entitled to deduct the liquidated recovered by the owner from the sub-contractors who did not contribute to delay? 132 Koprince, S.J. (2008). Is Your Pay-When-Paid Clause Worthless?. The Constructor January/February 2008. McGraw Hill Construction 133 2006 WL 2850652,*7 (E.D. Va. 2006) 134 Koprince, S.J. (2008). Is Your Pay-When-Paid Clause Worthless?. The Constructor January/February 2008. McGraw Hill Construction 66 In Durabella Limited v. J. Jarvis & Sons Limited (2001), it was held that the Housing Grants Construction and Regeneration Act 1966 clearly envisaged that paywhen-paid clauses which shared the risk of insolvency were not unreasonable. A contractor cannot rely on a pay-when-paid clause if the reason for non-payment is its own breach of contract or default. A party cannot take an advantage from its own breach of contract135 . Hudsons Building and Engineering Contracts 11th Edition holds the view that a main contractor is not entitled to withhold payment in such a situation for the following reasons: 1.1 The deduction of, for example, liquidated damages or a sum for defective works amounts to a cross-claim or set-off which should count as credit given to the main contractor. In other words the work done by the main contractor and hence all sub-contractor are still being recognized and accordingly the relevant subcontractors should be paid; 2.1 The application of the “business efficacy” and “officious bystander” tests would favour the view that a sub-contractor had not agreed to withholding of payment when he did not cause his main contractor to suffer for example, liquidated damages. But as the parties to contracts can agree to whatever positions they may wish to take, it is open to the parties to agree otherwise; and 3.1 The “prevention principle” implies that a main contractor should not gain from his own negative act, i.e. default in sat, completing the works in a timely manner and thus take advantage of same to deny his sub-contractor from being paid. 135 Atkinson D. (2001). Payment – Pay When Paid Clauses. 67 Subcontractors can always also argue that the Owner’s nonpayment resulted from unrelated breaches of the general’s contract with the owner. The general rule is that “where defendant prevents the performance of a condition of a contract, the condition is excused. 136 ” In Sassenrath v. Sassenrath137 and AEE-EMF v. Passmore138 , if the owner has refused to pay the general contractor because of the general contractor’s own breaches, the general contractor has, in essence, prevented the occurrence of the condition precedent and cannot assert the Owner’s nonpayment as a defense. The Illinois case in Preload v. Marino Construction139 , the court held that a general contractor could not assert a “pay-when-paid” clause when the general contractor was responsible for the Owner’s nonpayment, reasoning that “the performance of a condition precedent is excused if the party for whose benefit the condition is created prevents the condition from occurring. 3.8 Conclusion As conclusion, with a few exceptions, courts do not interpret “pay when paid” provisions as conditions precedent without including explicit and unambiguous language. Once the courts interpret the pr ovisions as conditions precedent, the written agreement defeats the subcontractor’s claim against the contractor. A subcontractor will be entitled to payment if the general contractor causes the nonoccurrence of the condition precedent to payment or if the general contractor commits fraud or tortuously interferes with the contract. Condition precedents do not necessarily supersede a subcontractor’s statutory rights to file mechanic liens and recover against surety bonds. Payment provisions can have significant financial consequences for any party that has assumed the risk of non136 Goodin, P.W. and Dickinson, J.C.. Who Bears the Risks of Owner Non-Payment?. Midwest Construction Law, Contracts and Claims 137 657 S.W. 2d 671, 674 (Mo. Ct. App. 1983) 138 906 S.W. 2d 714 (Mo. Ct. App. 1995) 139 1991 WL 202651 (N.D. I11. 1991) 68 payment, and can have significant financial benefits for the party that has shifted the risk of the non-payment. Parties negotiating a construction contract should scrutinize conditional payment provisions to determine the effect of such provisions before entering into the contract. The Arizona Court of Appeal in Harvey Concrete, Inc. v. Agro Construction & Supply Co.140 , The language that included the term “condition precedent” sufficed to create an enforceable condition. Furthermore, the court held that a condition precedent is established when expressions like “exclusively” or “only” demonstrate that payment was to be made from a particular fund and no other. Without these key words , one may assume that these provisions would only effect the time of payment and not waive the contractor’s duty to pay for services rendered by the subcontractor. In order to create a condition precedent to the subcontractor’s payment, there must be contractual language demonstrating the parties ‘unequivocal intent’ that the subcontractor will only be paid if the contractor is paid. In determining what constitutes a “reasonable time” for payment under such provisions, courts have (1) looked to other provisions within the contract at issue which set forth the time periods for performance of analogous act; and (2) have determined, as matter of law, when a reasonable time has elapsed 140 939 P.2d 811 (Ariz. Ct. App. 1997) 69 CHAPTER 4 ANALYSIS ON THE APPLICATION OF “PAY WHEN PAID” PROVISIONS IN SUB-CONTRACTS 4.1 Introduction The preceding chapter discussed in detail the topic of the application of “pay when paid” provisions in construction sub-contract. This chapter is done in order to achieve the objective of this project report, which to identify whether “pay-when-paid” arrangement in construction sub-contract waiving the right of the subcontractor to be paid or simply a timing mechanism. Besides, the ground constitutes the application of “pay when paid” provisions was discuss in detail to give the readers an insight the circumstances where the subcontractor entitle to get payment by the main contractor when they have suffering the risk of non-payment. 70 This chapter discusses the judicial interpretation on the application of “pay when paid” provisions in construction sub-contract. The circumstances behind the application of “pay when paid” provisions were collected through the documentary analysis of law journals and law report, e.g. Malayan Law Journal, Hong Kong Law Journal, All Engla nd Report, Construction Law Report, etc. The decided court cases will be analysed and being categorized under the terms which constitute the “pay-when-paid” arrangement as condition precedent to the payment by the owner to general contractor and timing mechanism (time for payment). It is done mainly through in Sub-Contract. A total number of eleven (11) cases centered the issue of “pay when paid” provisions in construction sub-contract were studied. Out of the eleven (11) cases chosen, eight (8) cases gave illustration that “pay when paid” constitutes as timing mechanism and the remaining constitutes the “pay when paid” provision as condition precedent. The cases will be discussed in detail in order to give better understanding to the readers to give a better understanding to the readers and the principle lying behind that drove the judge to come a judgment that “pay when pay” provisions as timing mechanism or waiving the subcontractor right to payment (condition precedent). 4.2 The Application of “Pay When Paid” Provision in Sub-Contract After reading chapter 2 and chapter 3, it is known the application for the payment provision of “pay when paid” in construction sub-contract which can result as time for payment within reasonable time and as condition precedent to general contractor get payment by the owner. “Pay when paid” provisions in sub-contract typically defer the 71 time when payment is due from say a main contractor to a sub-contractor until the main contractor has received payment from the client. The general contractor has made an unconditional promise to pay with the time payment postponed until happening of a certain event, or for a reasonable period of time if the owner’s payment does not happen. Whether the “pay when paid” provisions constituted time for payment or condition precedent to general contractor get payment by the owner is probably best judged objectively having regard to such matter as: a) The intention of the contractual parties (Dyer Interpretation); b) The contractual language either ambiguous or unambiguous; c) The subcontractor’s assumption of the risks of non-payment by the owner to general contractor; and d) The enforcement of the contractual terms or provisions. The above indicates the matters that constitute the application of “pay when paid” provisions from the literature. However, there is a great deal of uncertainty as to the exact judgment to the matter of interpretation of sub-contract language contain “pay when paid”. The judgments for the application of the “pay when paid” provisions in the subcontract are discussed below with illustration of cases relating to construction subcontract across the country. 72 4.2.1 “Pay When Paid” Suggest Time of Payment Case 1 The controlling factor as to whether the “pay when paid” clause was a conditional or unconditional promise was the intention of the parties. Whether the “pay when paid” clause is to be construed as a conditional promise to pay, enforceable only when and if the conditions precedent has taken place or is to be construed as an unconditional promise to pay with the time of payment being postponed until the happening of a certain event, or for a reasonable period of time if it develops that such event does not take place. To construe it as requiring the subcontractor to wait to be paid for an indefinite period of time until the general contractor has been paid by the owner, which may never occur, is to give to it an unreasonable construction which the parties did not intend at the time the subcontractor was entered into. In the case of Thomas J. Dyer Co. v. Bishop International Engineering Co. 303 F.2d 655, 661 (6th Cir. 1962), The contract between the contractor and the subcontractor provided in pertinent part: The total price to be paid to the Subcontractor shall be … ($115,000.00) …no part of which shall be due until five (5) days after Owner shall have paid Contractor therefore… The Sixth Circuit identified the crucial point of the dispute between the parties as follows: [W]hether … [the “pay-when-paid” clause] is to be construed as a conditional promise to pay, enforceable only when and if the conditions 73 precedent has taken place,… or … is to be construed as an unconditional promise to pay with the time of payment being postponed until the happening of a certain event, or for a reasonable period of time if it develops that such event does not take place.. After reviewing several earlier opinions in which similar “pay-when-paid” clauses had been interpreted, the court held that the controlling factor as to whether the “paywhen-paid” clause was a conditional or unconditional promise was the intention of the parties. To determine the parties’ intent, the court looked beyond the plain meaning of the terms of the contract to consider the usual and customary expectations of parties in the construction industry. Emphasizing that general contractors normally bare the risk of the owner’s insolvency, the court acknowledged that this normal allocation of risk could be varied by the terms of the subcontract, but only if unequivocal language was used to express the parties’ intention to shift such risk. The Court cited as follows: “In the case before us, we see no reason why the usual risk of the owner’s insolvency assumed by the general contractor should be transferred from the general contractor to the subcontractor. It seems clear to us under the facts of this case that it was the intention of the parties that the subcontractor would be paid by the general contractor for the labor and materials put into the project. We believe that to be the normal construction of the relationship between the parties. If such was not the intention of the parties it could have been so expressed in unequivocal terms dealing with the possible insolvency of the owner.” 74 Consequently, despite the rather explicit language of the “pay-when-paid” clause, the court purported to ascertain the intention of the parties and held that the “pay-whenpaid” clause was properly construed as follows: A reasonable provision designed to postpone payment for a reasonable period of time after the work was completed during which the general contractor would be afforded the opportunity of procuring from the owner the funds necessary to pay the subcontractor. To construe it as requiring the subcontractor to wait to be paid for an indefinite period of time until the general contractor has been paid by the owner, which may never occur, is to give to it an unreasonable construction which the parties did not intend at the time the subcontractor was entered into. While the Dyer case is relied upon by those who seek to enforce conditional payment provisions where the contracts at issue contain specific “pay-if-paid” or “paywhen-paid” language, enforcement of such language is still not automatic. Those courts that have adopted Dyer approach of enforcing conditional payment clauses only when the contract terms undeniably demonstrate the intent of the parties still “ recognize a general presumption against the enforcement of the clauses” and require “that the presumption can be overcome only by the use of clear an unambiguous contract language.” 141 141 Mootz, F.Z. (1990). The Enforceability of Pay When Paid Clauses in Construction Contracts, 64 Conn.B.J. 257,265 75 CASE 2 The “pay when paid” provision did not detract from the subcontractor’s right to paid if it had satisfactorily completed the works according to the contractual requirements. To interpret a pay-when-paid clause, sufficiently clear words must have been used in order for a court to construe that such a clause imposed payment to the main contractor as a condition precedent to the subcontractor's right to be paid, rather than limiting the time for payment. The Hong Kong Case of Falcon Building Materials Company Limited v. Fine View Engineering Limited [2008] HKCU 16 the court considered whether a “pay-when-paid” provision in a subcontract operated as a condition precedent for payment. The defendant argued that at the time the writ was issued, the plaintiff was not entitled to the amounts claimed, as the defendant had not been paid; therefore, under the “pay-when-paid” provision, the amounts were not yet due to the plaintiff. However, the plaintiff maintained that it was entitled to the sums claimed on the day the writ was issued. The defendant, Fine View, was the main contractor of a government contract for the design, supply and installation of automatic doors at a government hospital. The main contract was administered by the government's Electrical and Mechanical Services Department, the employer. The main contractor engaged the plaintiff, Falcon, as its subcontractor. The relevant part of the subcontract stated as follows: 76 "Payment terms: (a) 20% deposit... on confirmation of order; and (b) 80% to be settled by [Fine View’s] receipt of final payment from [the employer] within 45 days of the completion of testing and commissioning and the acceptance of the works by the [employer]. “This contract shall be executed on a back-to-back basis in accordance with the relevant clauses within the main contract." The 20% deposit was duly paid and the works were allegedly completed by the subcontractor by April 1 2006. Follow ing testing and commissioning on 26 April 2006, the subcontractor issued an invoice for the remaining 80% of the subcontract sum, believing it was entitled to be paid, as testing and commissioning had been carried out. However, it subsequently transpired that there were defects in the works and the employer delayed payment to the main contractor. The employer paid the main contractor on 4 January 2007 after deductions for the defects. Relying on the pay-when-paid provision in clause (b) of the payment terms, the main contractor did not settle the subcontractor's invoice for the remaining 80% of the subcontract sum immediately, as the main contractor had not been paid by the employer. The subcontractor, believing that the pay-when-paid provision did not affect its entitlement to payment, commenced proceedings on 16 November 2006 against the main contractor to recover the balance of the subcontract sum. The trial began on 8 October 2007. Between the commencement of proceedings and the trial, the main contractor paid the subcontractor the balance of the subcontract sum, less HK$73,700, which the main contractor had deducted for defects. Therefore, the subcontractor claimed only HK$73,700 at trial. 77 A preliminary issue was whether clause (b) amounted to a condition precedent to the main contractor's liability to pay the balance of the price. In deciding this issue, the court relied on Wo Hing Engineering Limited v Pekko Engineers Limited142 . In Wo Hing the judge reviewed a number of authorities from Australia, New Zealand and the United States and identified an underlying principle: “When having to construe a pay-when-paid clause, sufficiently clear words must have been used in order for a court to construe that such a clause imposed payment to the main cont ractor as a condition precedent to the subcontractor's right to be paid, rather than limiting the time for payment.” The judge held on the facts that, as the works had been completed in July 1995 and no complaint of unfinished or defective work had been raised, the plaintiff was entitled to be paid within a reasonable time of the completion of the works, despite the fact that the defendant had not been paid. The judge in Wo Hing was satisfied that a reasonable time had elapsed when the writ was issued in May 1996, and that the plaintiff was therefore entitled to be paid as of the date of the writ. Consequently, the plaintiff was entitled to costs. The court in the present case decided the preliminary issue in the subcontractor's favour and held that clause (b) did not amount to a condition precedent - the subcontractor's right to be paid did not depend on the main contractor being paid first. However, the subcontractor ultimately failed in its claim against the main contractor because of the existence of defects in the works. The court found that the clause "did not detract from the subcontractor's right to be paid if it had satisfactorily completed the works according to the contractual requirements". As there were defects in the works, the court found that the subcontractor had not satisfactorily completed the works according to 142 [1998] HKCU 2341, HCA5561/1996 78 the contractual requirements. The employer and the main contractor were thus entitled to withhold payment and to make a deduction against the final payment to account for the unrectified defects. Therefore, the subcontractor's claim was dismissed with costs. This case confirms that a pay-when-paid clause is not a condition precedent to a subcontractor's right to be paid. Provided that the subcontractor has carried out its work satisfactorily according to the terms of its subcontract, it is entitled to payment within a reasonable time of completing its works, notwithstanding a pay-when-paid clause and the question of whether the main contractor has been paid by the employer. CASE 3 Provision calling for payments after written acceptance by the architect and full payment by the owner do not set condition precedent. They constitute absolute promises to pay, fixing payment by the owner as a reasonable time for making payment to the subcontractor. Small subcontractors, who must have payment for their work in order to remain in business, ordinarily would not assume the risk of the owner’s failure to pay the general contractor. In order to properly shift the risk to the subcontractor must unambiguously express such intention and burden of clear expression is on the general contractor In the case of Peacock Construction Co., Inc. v. Modern Air Conditioning, Inc. , 353 So.2d 840 (Fla. 1977) , the issues are as follows” 79 1. Is payment by the owner to the contractor a condition precedent to payment by the contractor to the subcontractors? 2. Is the interpretation of a document a question of law or of fact? Modern Air Conditioning and Overly Manufacturing subcontracted with Peacock to perform heating/air conditioning and swimming pool work for a condominium construction project. The written subcontracts provided that Peacock would make final payment to the subcontractors “within 30 days after completion of the work included in this subcontract, written acceptance by the Architectural and full payment therefore by the owner.” When the subcontractors completed the work, Peacock did not pay then because the owner had not paid in full. Modern Air Conditioning and Overly Manufacturing brought separate suits against Peacock for payment. At trial the court rejected Peacock’s contention that payment by the owner was a condition precedent to paying the subcontractors and granted summary judgment in favor of Modern Air Conditioning. The Court of Appeals affirmed and Peacock appealed to the Florida Supreme Court. Unless expressly agreed, a subcontractor’s payment is not conditioned upon payment to the contractor by the owner. That intent is most cases is that payment by the owner to the general contractor is not a condition precedent to the general contractor’s duty to pay the subcontractors. The interpretation of a document and its terms and conditions is a question of law. Provision calling for payments after written acceptance by the architect and full payment by the owner do not set conditions precedent; they constitute absolute promises to pay, fixing payment by the owner as a reasonable time for making payment to the 80 subcontractor. The Supreme Court without the benefit of any statistical data or supporting evidence concluded: A number of courts, with whom we agree, have recognized that contracts between small subcontractors and general contractors on large construction projects are such transactions. Cf. Thos. J. Dyer Co. v. Bishop International Engineering Co.,6 Cir., 303 F.2d 655 (1965). The reason is that the relationship between the parties is a common one and usually intent will not differ from transaction to transaction, although it may be differently expressed. The risk-shifting provisions are susceptible to only two possible interpretations as follows: “If a provision is clear and unambiguous, it is interpreted as setting a condition precedent to the general contractor’s obligation to pay. If a provision is ambiguous, it is interpreted as fixing a reasonable time for the general contractor to pay. In purported risk-shifting provision between a contractor and subcontractor, the burden of clear expression is the general contractor. Once a judge decides that a provision is ambiguous there is nothing for the jury to decide or interpret.” The court adopted the majority rule that payment by the owner to the general contractor is not condition precedent to the general contractor’s duty to pay the subcontractors. Small subcontractors, who must have payment for their work in order to remain in business, ordinarily would not assume the risk of the owner’s failure to pay the general contractor. 81 It was held that in order to properly shift the risk to the subcontractor, the subcontractor must unambiguously express such intention and burden of clear expression is on the general contractor. CASE 4 Sufficiently clear words will have to be used before a court will be prepared to construe that such a clause imposes as a condition payment to the main contractor which had to be fulfilled before the sub-contractor had the right to be paid as opposed to a clause limiting the time for payment. Wo Hing Engineering Limited v. Pekko Engineers Limited (unreported, No.A5561) had the opportunity to decide the legal effect of a “pay-when-paid” clause in a full trial. The defendant in this case was a subcontractor and the plaintiff was its sub-subcontractor. The relevant clause provided that “this contract is based on back to back basis including payment”. The court had to decide whether on a proper construction of the above-mentioned term in the contract, payment of the final balance was only due to the plaintiff from the defendant after the defendant received payment from the main contractor as contended by the defendant, or when the plaintiff was entitled to be paid after reasonable time had elapsed from the completion of the works as submitted by the plaintiff. 82 In giving judgment in favour of the plaintiff, Suffiad J. adopted the principle which can be gleaned from the decisions in United States, Australia and New Zealand, namely, when having to construe a “pay when paid” clause, sufficiently clear words will have to be used before a court will be prepared to construe that such a clause imposes as a condition payment to the main contractor (the sub-contractor in the Wo Hing case) which had to be fulfilled before the sub-contractor (the sub-sub-contractor in the Wo Hing case) had the right to be paid as opposed to a clause limiting the time for payment. Lordship agreed to the following passages in judgment Smith & Smith v. Winstone: “While I accept that in certain cases it may be possible for persons contracting with each other in relation to a major building contract to include in their agreement clear and unambiguous conditions which have to be fulfilled before a subcontractor has the right to be paid, any such agreement would have to make clear beyond doubt that the arrangement was to be conditional and not to be merely governing the time of payment. I believe that the ‘contra proferentem143 ’ principle would apply to such clause and that he who seeks to rely upon such a clause to show that there was a condition precedent before liability to pay arose at all should show that the clause relied upon contain no ambiguity.” “For myself I believe that unless the condition precedent is spelled out in clear and precise terms and accepted by both parties, then clauses such as the two particular ones identified in this proceeding to no more than identify the time at which certain things are required to be done, and should not be extended into the “if” category to prevent a subcontractor who has done the work from being paid merely because the party with whom he contracts has not been paid by someone higher up the chain.” 143 In general, if there is any genuine ambiguity in a exclusion contract (that is, if a contract provision is subject to at least two varying reasonable interpretations), it will be strictly construed against the party who drafted the contract. 83 Based on the above principle, the Lordship held that the payment clause in question merely provides for the time of payment and that the plaintiff’s right to be paid is not dependent upon the defendant getting paid first. CASE 5 Any such agreement would have to make clear be yond doubt that the arrangement was to be conditional and not to be merely governing the time of payment. “Contra Proferentum144 ” principle would apply to such clause and seeks to rely upon a clause to show that there was a condition precedent before a liability arose at all should show that the clause relied upon no ambiguity The Court of Appeal (Putrajaya) case of Antah Schindler Sdn Bhd v. Ssangyong Engineering & Construction Co. Ltd., [2008] 3 MLJ 204 provides some guidance as to the Malaysian position on “pay-when-paid” clauses. The respondent in the Court of Appeal, Ssangyong Engineering (“Ssangyong”), was the main contractor appointed by the employer (Yetcome Investment) to install lifts in respect of the Menara Landmark Johor Bahru Project. The appellant, Antah Schindler, was a subcontractor to Ssangyong. 144 In general, if there is any genuine ambiguity in an exclusion contract (that is, if a contract provision is subject to at least two varying reasonable interpretations), it will be strictly construed against the party who drafted the contract. 84 Antah Schindler carried out and completed the work and received some payments from Ssangyong, leaving an outstanding sum of approximately RM1.2 million based on 4 interim certificates. Antah Schindler sued Ssangyong for the outstanding sum, and applied for ‘summary judgment 145 ’. Antah Schindler’s position was based on Clause 11(b) of the Sub-Contract Agreement with Ssangyong, which reads as follows: “Within fourteen (14) days of the receipt by the Contractor of any certificate or duplicate copy thereof from the Architect the Contractor shall notify and pay to the Sub-Contractor the total value certified therein in respect of the Sub Contract Works and in respect of any authorized variations thereof and in respect of any amounts ascertained under cl 8(c) hereof less:…” Ssangyong resisted the application, relying on Clause 27(a) (vii) of the Main Contract: “The payment in respect of any work, materials or goods comprised in the subcontract shall be made within 14 days after receipt by the Contractor of payment from the Employer against the architect’s certificate under clause 30 of these Conditions which states as due in amount calculated by including the total value of such work, materials or goods, and shall when due be subject to the retention by the Contractor of the sums mentioned in sub-paragraph (viii) of para (a) of this Condition.” 145 A decision made on the basis of statements & evidence presented for the record without a trial. It is used when there is no dispute as to the fact of the case & one party is entitled to judgment as a matter of law 85 Ssangyong’s position was that this clause was incorporated into the SubContract pursuant to various provisions of the Sub-Contract. The Senior Assistant Registrar refused the application for summary judgment, holding that there were triable issues as there was sufficient evidence in the circumstances of the case. Antah Schindler appealed against the decision to the Judge in Chambers, who found that there was no dispute in respect of the quantum and thus allowed the appeal and entered summary judgment against Ssangyong. However, the Judge went on to hold that Ssangyong would only have to pay Antah Schindler as and when payment was received from the employer. Antah Schindler appealed to the Court of Appeal against this part of Judge’s decision. There was no cross appeal from Ssangyong. The Court of Appeal held that clause 27(a) (viii) of the Main Contractor had incorporated into the Sub-Contract and that Antah Schindler by the following provisions of the clause in seeking payment had acquiesced to it. Having characterized the broad issues as being one of a “pay-when-paid” clause, the Court then considered the effect of the clause, referring to the New Zealand case of Smith & Smith Glass Ltd v. Winstone Architectural Cladding System Ltd [1992] 2 NZLR 473, where Master Towle made the following observations. “While I accept that in certain cases it may be possible for persons contracting with each other in relation to a major building contract to include in their agreement clear and unambiguous conditions which have to be fulfilled before a subcontractor has the right to be paid, any such agreement would have to make clear beyond doubt that the arrangement was to be conditional and not to be merely governing the time of payment. I believe that the ‘contra proferentem146 ’ principle would apply to such clause and that he who seeks to rely upon such a 146 In general, if there is any genuine ambiguity in an exclusion contract (that is, if a contract provision is subject to at least two varying reasonable interpretations), it will be strictly construed against the party who drafted the contract. 86 clause to show that there was a condition precedent before liability to pay arose at all should show that the clause relied upon contain no ambiguity.” The Court of Appeal held that upon its proper construction, clause 27(a)(viii) did not restrict a claim by the Sub-Contractor but merely imposed a time limit on the main contractor to pay its Sub-Contractor. The Court of Appeal went on to allow the appeal, holding that on the facts of the case there was sufficient evidence that Ssangyong had in fact been paid. The apparent adoption of the observations of Master Towle is to be welcomed. It appears that the Malaysian Courts see no conceptual obstacle to the practice of “paywhen-paid” and are content to apply the ordinary rules of contractual interpretations to such clauses. It is understood that an application by Ssangyong for leave to appeal to the Federal Court has been refused. CASE 6 The mere fact that terms of a contract are in dispute is not evidence that the language is not clear and explicit and requires extrinsic evidence to aid in its construction. If the terms of the parties’ agreement are contained in a clear and explicit writing, that writing is the sole memorial of the contract and the sole evidence of the agreement. The court concludes that the phrases “after the Contractor receives payment from the Owner” and “has received payment from the Owner” constitute latent ambiguities in the contracts. That is, the phrases, while appearing perfectly clear at the time the contracts we re formed, because of 87 subsequently discovered or developed facts, may reasonably be interpreted in either of two ways (ambiguous contractual language) The Circuit Court of the City of Norfolk in Galloway Corporation v. S.B. Ballard Construction Co., et al., 250 Va. 493, 494 S.E.2d 349 (1995) , the appeal arises from a contract dispute between a general contractor and several of its subcontractors in a construction project following the project owner’s default in making payment on its contract with the general contractor. The issues are as follows: 1. Whether the terms of the subcontractors provide the general contractor an absolute “pay when paid” defense to its subcontractors’ breach of contract claims based upon the owner’s failure to pay. 2. Whether the terms of the subcontracts in question shift the risk of the owner’s default on payment for labor and materials from the general contractor to the subcontractors. On 17 August 1988, Galloway Corporation (“Galloway”), a construction contractor, entered into a contract with Rowe Properties – Bank Street Limited Partnership (“Rowe”) for the construction of the First American Financial Center, a fourteen-story commercial office complex in downtown Norfolk. Rowe and Galloway used a standard, pre-printed American Institute of Architects (AIA) contract with attachments to form the basis of their agreement. Within the general conditions of the contract was the following requirement: “The Contractor shall promptly pay each Subcontractor, upon receipt of payment from the Owner, out of the amount paid to the Contractor on 88 account of such Subcontractor’s Work, the amount to which said Subcontractor is entitled…” Galloway immediately commenced work on the construction project and let subcontracts to numerous suppliers of labor and materials. Galloway also used a standard, pre-printed AIA form in letting these subcontracts. Paragraph 11.3 contains the following pertinent language: “The Contractor shall pay Subcontractor each progress payment within three working days after the Contractor receives payment from the Owner. If the Architect does not issue a Certificate of Payment or the Contractor does not receive payment for any cause which is not the fault of the Subcontractor, the Contractor shall pay the Subcontractor, on demand, a progress payment computed as provided in Paragraphs 11.7 and 11.8” Paragraph 12.1, entitled “Final Payment,” contains the following pertinent language: “Final payment, constituting the entire unpaid balance of the Subcontract Sum, shall be made by the Contractor to the Subcontractor when the Subcontractor’s Work is fully performed in accordance with the requirements of the Contract Documents, the Architect has issued a Certificate of Payment covering the Subcontractor’s completed Work and the Contractor has received payment from the Owner. If, for any cause which is not the fault of the Subcontractor, a Certificate of Payment is not issued or the Contractor does not receive timely payment or does not pay the subcontractor within three working days after receipt of payment from the Owner, final payment to the Subcontractor shall be made upon demand.” 89 Work on the project continued from August 1988 until May 1990, suffering severe financial difficulties, stopped making payment to Galloway. On 31 May 1990, Galloway informed Rowe and the architect that it would stop work on the project and notified its subcontractors to secure their tools, equipment, and materials on the job site anticipation of work being stopped. Work actually continued until 17 July 1990, when Galloway terminated its contract with Rowe. At that time Rowe had failed to make 3 progress payments to Galloway totaling slightly less that $3,000,000.00 On 21 January 1994, the trial court by letter to counsel, stated its finding that there remained unpaid balances on the contracts and that Galloway did not have an absolute “pay when paid” defense based on the contracts as written. The trial court found that the phrases “after the Contractor receives payment from the Owner” and “has received payment from the Owner” only permitted Galloway to “delay payment, but the contracts cannot be construed to say that each subcontractor must bear its own loss if Galloway never got paid on its contract with the owner.” The mere fact that terms of a contract are in dispute is not evidence that the language is not clear and explicit and requires extrinsic evidence to aid in its construction. If the terms of the parties’ agreement are contained in a clear and explicit writing, that writing is the sole memorial of the contract and the sole evidence of the agreement. The court concludes that the phrases “after the Contractor receives payment from the Owner” and “has received payment from the Owner” constitute latent ambiguities in the contracts. That is, the phrases, while appearing perfectly clear at the time the 90 contracts were formed, because of subsequently discovered or developed facts, may reasonably be interpreted in either of two ways. Here, the contract in question could be interpreted to require Galloway to pay a subcontractor only if it received a payment demanded from Rowe identifiable with the progress or completion of a subcontract, or merely to provide for a reasonable time to pay after such demand was made to Rowe. Because this ambiguity was not patently evident on the face of the contract, the trial court was permitted to look beyond the contract and determine the intent of the parties using parol and other extrinsic evidence. When resolving a dispute between the parties to a contract with a latent ambiguity, the court may first consider, among other things, whether negotiations and prior dealings of the parties manifested their intent with respect to the ambiguous term. If the parties both manifested the same intent with respect to the ambiguity, that intent will be enforced. If, on the other hand, the parties do not manifest the same intent regarding the ambiguity, there has been no meeting of the minds on that term of the contract and the intent of one party will no control. It is apparent from the record of this case that Galloway intent, in each case, that the contract would provide it with an absolute “pay when paid” defense. This, only if the subcontractor to each contract manifested the same intent will an absolute “pay when paid” defense. Thus, only if the subcontractor to each contract manifested the same intent will an absolute “pay when paid” defense be available to Galloway. The court holds that in the absence of a clear and unambiguous statement of the parties’ intent as to the meaning of the time of payment provision in a construction subcontract, an absolute “pay when paid” defense is available to a general contractor only if it can establish by parol evidence that the parties mutually intended the contract to 91 create such a defense. Supreme Court affirmed ruling of trial court rejecting “pay-whenpaid” defense of general contractor and awarding judgment to subcontractor. CASE 7 The court declined to construe a “pay-when-paid” clause as a valid condition precedent to the subcontractor’s receipt of payment because such a construction would result in a “significant forfeiture” to the subcontractor. In Brown & Kerr Inc. v. St. Paul Fire & Marine Insurance Co., 940 F.Supp. 1245, 1250 (N.D. lll. 1996), the court declined to construe a “pay-when-paid” clause as a valid condition precedent to the subcontractor’s receipt of payment because such a construction would result in a “significant forfeiture” to the subcontractor. The subcontract at issue Brown & Kerr stated: “The final payment would be made by the Contractor to the Subcontractor when… the Contractor has received final payment from the Customer under Prime Contract.” When the contractor failed to pay the subcontractor for work completed under the subcontract, the subcontractor brought an action against the contractor’s surety to receive payment under the payment bond. The surety argued that because the contractor was not paid by the owners, the surety was under no obligation to pay the subcontractor under its bond pursuant to the 92 “pay-when-paid” clause in the subcontract. See id. at 1248. The court rejected this argument, concluding that the “pay-when-paid” clause did not affect the contractor’s right to payment under the bond or create valid condition precedent to payment under the subcontract. See id. at 1250. Declining to follow A.A. Conte147 and instead relying on the dissenting opinion in that case, the court concluded that the “pay-when-paid” clause did not create a condition precedent, but rather a timing provision requiring the general contractor to pay the subcontractor within a reasonable time. See id. at 1250. CASE 8 When the subcontract was read in conjunction with the general contract and its conditions, a sufficient ambiguity existed which prevented the general contractor from effectively shifting the risk of the owner’s nonpayment to its subcontractor. To its dismay, the general contractor remained liable for the final payments owed to its subcontractor. In 1990, the Florida Supreme Court in OBS Company, Inc. v. Pace Construction Company dealt a blow to general contractors who relied on a “pay-when-paid” clause to avoid having to pay down its contractual chain to subs and suppliers absent payment from the owner. Pace was a general contractor on a bonded project. Pace subcontracted the drywall portion of work to OBS under a subcontract agreement that contained the following language: “In addition to any other requirements of this subcontract and the contract documents, final payment, shall not become due unless and until 147 A.A. Conte, Inc. v. Camphell-Lowrie-Lautermilch Corp., 132 lll.App. 3d 325, 477 N.E.2d 30 (1st Dist. 1985) 93 the following conditions precedent to final payment have been satisfied (c) receipt of final payment for subcontractor’s work by contractor from owner.” The above language was the contractor’s sole reason for refusing to make payment to OBS. The Pace subcontract defined the ‘contract documents’ to include the owner-general contractor agreement, and it incorporated the terms of the ‘prime contract’ into the subcontract with OBS. The contract between the general contractor and the subcontractor clearly provided that the subcontractor was to be paid only after the owner paid the general contractor. The contract between the general contractor and the owner, however, was a “cost plus” or reimbursement type of contract that required the gene ral contractor to pay its subcontractors before the owner reimbursed the general contractor. The owner general conditions also required that before final payment become due, the general contractor was to submit an affidavit certifying that all subcontractors had been paid. This inconsistency was construed against the general contractor. The court found that when the subcontract was read in conjunction with the general contract and its conditions, a sufficient ambiguity existed which prevented the general contractor from effectively shifting the risk of the owner’s nonpayment to its subcontractor. To its dismay, the general contractor remained liable for the final payments owed to its subcontractor. It is not surprising or unusual that the prime contract required Pace to pay OBS notwithstanding the failure of the owner to pay the Pace. This created a clear an ambiguity that the Florida Supreme Court agreed to examine when it accepted jurisdiction of OBS v. Pace. In it analysis, the Florida Supreme Court examined an earlier line of decisions. It already had decided that “pay-when-paid” clauses were going to be strictly construed with any ambiguity resolved in favor of unpaid subcontractor or supplier. In order to shift the burden of nonpayment to the subcontractor of supplier, the subcontract was required to contain a “clear an unequivocal expression” of that fact. The 94 decision was based on the ambiguity created by incorporation of the prime contract into the OBS subcontract. Pace had failed to meet its burden of a clear and unequivocal “paywhen-paid” clause. Although this ruling constituted another nail in the coffin of the general contractor, the true devastation was realized when the Supreme Court went on to look at Pace’s bond as issued by Transamerica Insurance Co. and Seaboard Surety. The opinion states that, “the payment bond is a separate agreement, and any ability to proceed against the general contractor with a subcontract “pay-when-paid” clause does not necessarily prevent recovery against the sureties under the bond.” It rejected earlier holding that sureties’ liability was coextensive of that of the principal. Even with an effective “pay-when-paid” provision, the surety must make payment to subcontractors and suppliers within a “reasonable time.” Anyone who has been around the construction site or the courthouse knows that the surety will look to its principal for reimbursement of any claims it is required to pay. The effect is that a general contractor on a bonded job who remains unpaid by the owner will be required to make payment to subcontractors and suppliers even in the presence valid pay-when-paid clause. 95 4.2.2 “Pay When Paid” As Condition Precedent CASE 1 The clause clearly specifies the condition governing the contractor’s legal entitlement to payment and not merely the time of payment. Under such clause, the subcontractor clearly assumes the risk of non-payment by the owner to the contractor. Since general contractor was not paid, it is not obliged to pay the subcontractors. In order to properly shift the risk to the subcontractor, the subcontractor must unambiguously express such intention and burden of clear expression is on the general contractor The Ontario Court of Appeal in Timbro Developments Ltd. v. Grimsby Diesel Motors Inc., (1998). 32 C.L.R. 32 (Ont. C.A.), allowed a general contractor to rely on a standard from clause providing as follows: “When used for sub-contract work the following terms will apply: Payment will made not more than thirty (30) days after the submission date or ten (10) days after certification or when we have been paid by the owner, whichever is the later. Holdback will be retained in accordance with the Mechanic’s Lien Act in effect at the time, and when released by the owner all payments will be made in Canadian Funds and will be payable at par in Welland (emphasis added by the Court)” 96 In a very short judgment, the Court held that: The Court is divided on the interpretation of the underlined words which were added to the standard form used by the Ontario contractors several months before execution by the subcontractors. The appellant contended that the added clause was ambiguous but the majority (Blair and Cory JJ.A.) reject this submission. In their opinion the clause clearly specifies the condition governing the contractor’s legal entitlement to payment and not merely the time of payment. Under the clause, the subcontractor clearly assumes the risk of non-payment by the owner to the contractor. Since Timbro was not paid, it is not obliged to pay the subcontractors and the appeal must fail. Finlayson J.A., dissenting, is of the view that the clause relates to the timing of payments due under the contract and in no sense puts the subcontractors at risk that they will not be paid if the contractor is not paid. They are not co-adventures or partners in this construction contract. Having done the work as found by the trial judge, they are entitled to be paid. There is a privity of contract between them and Timbro and the trial Judge was correct in awarding judgment in their favour. He would have allowed the appeal and restored the judgment of the trial Judge. Leave to appeal to the Supreme Court of Canada was dismissed148 . Timbro was followed by the Ontario General Division in Kor-Ban Inc. v. Pigott Construction Ltd149 . However, Bell J., in that case, also quoted from the 1874 case of McBrian v. Shanly 150 . There, a subcontract had provided for payment to the subcontractor within ten (10) days after the general contractor was paid by the owner. 148 Id. (1989). 99 N.R. 400 (note) (1993). 11 C.L.R. (2d) 160 (Ont. Gen. Div.) 150 (1984). 24 U.C.C.P. 28 (C.A.) 149 97 However, the jury concluded that the owner had terminated the contract because of the general contractor’s default. Hagarty C.J. held that: I think the true intent and meaning of such a contract must be that the best the defendant [general contractor] can say: “If I duly perform my contract with the company [the owners], and though I be entitled to the money from them, if from any cause, not arising from any act or default of mine, they [the owners] do not pay, you [the subcontractor] cannot call on me to pay.” In cases where default of the general contractor caused the non-payment by the owner, Bell J. concluded, the general contractor should not be allowed to rely on the paywhen-paid clause. This reasoning was used in Applied Insulation Co. v. Megatech Contracting Ltd.151 , where the defendant general contractor was in default and the plaintiff subcontractor had in no way contributed to the problems. The general contractor was not allowed to rely on the clause. Other provinces’ appeal courts decided not to follow Timbro. In Arnoldin Construction & Forms Ltd. v. Alta Surety Co.152 , the payment clause in a subcontract was summarized by the Court as follow: After deduction for a 10% mechanic’s lien holdback and previous payments the balance of the amount of the requisition as approved by the contractor “shall be due to the subcontractor on or about one day after receipt by the Contractor of payment from the owners”. The final payment under the subcontract is to be made on acceptance of the work “and 151 (1994), 22 C.L.R. (2d) 251 (Ont. Gen. Div.) (1995), 19 C.L.R. (2d) 1 (N.S. C.A.), leave to appeal to the Supreme Court of Canada refused (1995), 22 C.L.R. (2d) 131 (note) 152 98 within thirty (30) days after payment has been received by the contractor”. The Nova Scotia Court of Appeal argued that this was not clear enough language to impose a standard term on the subcontractor. Hallett J.A. held that: In my opinion, in order for a general contractor to impose a term on a subcontractor pursuant to a standard form of a contract, that payment for its work is conditional on the contractor being paid by the owner the contract would require mush clearer language than that contained in the subcontract between [the respondent] and [the appellant]. An intention so important cannot be buried in obscure language that would not alert the subcontractor that payment for the subcontract work was conditional on the owner paying the subcontractor… Had the respondent intended that nothing would owe or payable to a subcontractor upon completion of the work unless payment was received from the owner, the contract ought to have contained clear words to denote such an intention. Appropriate words would have been that the balance claimed by the subcontractor for the completion of the work pursuant to terms of the subcontract would only be paid “if” the owner paid the contractor. The word “if” is defined in the Oxford Dictionary as meaning “on the condition or suppos ition that.” To impose on a subcontractor a term that payment was conditional on the contractor receiving payment from the owner would require the clear language of the nature I have identified. In Nova Scotia, therefore, it appears that the use of the word “if” will imply a condition precedent. The Manitoba Court of Appeal, after reviewing both Timbro and 99 Arnoldin, preferred the latter. In Winfield Construction Ltd. v. B.A. Robinson Co.153 , Scott C.J.M. held that: I am also attracted to the reasoning of the Nova Scotia Court of Appeal in Arnoldin …, in which the Court chose to limit the effect of the decisions in Timbro and Kor-Ban by concluding that it would require very clear and specific words before it could be said that a “pay-when-paid” provision could govern the sub-contractor’s entitlement to payment. In a 1997 decision, the Prince Edward Island Supreme Court in the case of R&G Masonry Ltd. v. Maxim Construction Inc.154 chose to follow Arnoldin and Winfield. A clause in the contract between general contractor and subcontractor stated: “IV (b) The subcontractor shall make applications for payment together with supporting Statutory Declarations and/or other documents when required by the Contract Documents on or before the 25th day of each month to the Contractor for approval and due processing covering the value of the products delivered at the site and the work performed by the Subcontractor proportionate to the Subcontract Price up to the last day of the month, whereupon payment to the Subcontractor by the Contractor in the amount of 85% shall become due and payable not more than five (5) days after receipt of the monies by the Contractor from the Owner. Where the Contractor or the Consultant makes any changes to the amount of the applications for payment as submitted by the Subcontractor, the Subcontractor shall be so notified promptly in writing by the Contractor of changes and given the opportunity to defend his submission without delay.” 153 154 (1996), 27 C.L.R. (2d) 78 (Man. C.A.) (1997), 36 C.L.R. (2d) 300 100 DesRoches J. held that while being aware of jurisprudence tending to support the contractor’s attempt to rely on this clause, the substantial weight of authority in Canada and the United States supported the conclusion that in order for a general contractor to be able to rely on a “pay-when-paid” clause, the language ought to be much clearer than that contained in Article IV (b). Based on Arnoldin and Winfield, the Court held that: An intention so important cannot be buried in obscure language which would not alert the subcontractor that payment was subject to a condition precedent that the owner pays the contractor. CASE 2 The subcontract unambiguously required payment from the owner to general contractor before payment become due to the subcontractor. The Supreme Court of the State of Florida in DEC Electric, Inc., v. Raphael Construction Corporation 558 So. 2d 963 (Fla. 4th DCA 1989) deals with the issue of either must all payment provisions in contracts between contractors and subcontractors or suppliers that concern a condition or time of payment provision be construed as a matter of a law? This suit involves a subcontractor’s claim for money due for work done on a construction project when the general contractor refused to pay because it had not been paid by the owner. DEC Electric, Inc. (“DEC”), subcontracted with Raphael Construction 101 Corporation (“Raphael Construction”), the general contractor, to perform various electrical job on a construction project. The owner subsequently shut down the project. It is undisputed that DEC satisfactorily performed its work and is owed a total of $25, 612 plus interest. Raphael Construction refused to pay DEC, however, because it has not been paid by the owner. To support its refusal to pay DEC, Raphael Construction relied upon paragraph 6 of the subcontract, which states: “… Your payments are made in accordance with our interims draws as we show you on our sworn statement with your percentage of completion as we estimate it at the time of our billing to the Owner … No funds will be owed to the subcontractor unless the General Contractor is paid by the Owner in accordance to the sworn statement. The subcontractor fully understands that in event of non payment by the owner to the General Contractor, the subcontractor has legal recourse against the owner through the Mechanics Lien Laws or other legal procedures for their correct monies due.” The trial court held, as matter of law, that DEC was not entitled to payment from Raphael Construction because paragraph 6 of the subcontract unambiguously required payment from the owner to Raphael Construction before payment become due to DEC. In reaching its decision the district court expressed concern that the trial court decided the issue as matter of law rather than submitting it to the jury. Raphael Construction argues that, when the terms of a contract are ambiguous, the actual intention of the parties becomes a question of fact to be resolved by the jury. Although this principle of law is correct between contractors and subcontractor, the court declined to apply it to contracts between contractors and subcontractors in reference to risk-shifting provisions. In Peacock, the court held that the interpretation of contract provisions relative to time and conditions of payment between a contractor and 102 subcontractor is a question of law and not of fact. The Supreme Court rejected submitting the issue to the jury because: “If an issue of contract interpretation concerns the intention of the parties, that intention may be determined from the written contract, as a matter of law, when the nature of the transaction lends itself to judicial interpretation. A number of courts, with whom we agree, have recognized that contracts between small subcontractors and general contractor on large construction are such transaction. The reason is that the relationship between the parties is a common one and usually their intent will not differ from transaction to transaction, although it may be differently expressed.” “The intent in most cases is that payment by the owner to the general contractor is not a condition precedent to the general contractor’s duty to pay the subcontractors. This is because small subcontractors, who must have payment for their work in order to remain in business, will not ordinarily, assume the risk of the owner’s failure to pay the general contractor.” McDonald J. found, as matter of law, that the language was a condition precedent and that the subcontractor was not entitled to payment from the general contractor because the general contractor has not been paid by the owner. 103 CASE 3 An unambiguous “pay-when-paid” clause may block a subcontractor’s right to recover in a breach of contract suit against the general contractor. Based on the unambiguous language in the subcontract, the court strictly enforced plain language of the agreement, stating that it “may not rewrite a contract to suit one of the parties but must enforce the term as written.” In A.A. Conte, Inc. v. Camphell-Lowrie-Lautermilch Corp, the Illinois Appellate Court held that “pay-when-paid” clauses are enforceable under Illinois law as a valid form of what is known as a “condition precedent.” A condition precedent is an event that must occur before one party to a contract is obligated to perform his or her obligations pursuant to that contract. See Premier Elec. Constr. Co. v. American Nat’l Bank, 658 N.E.2d 877, 885 (lll.App. Ct. 1995). If there is a valid condition precedent in a contract, the party in whose favor the condition exists is not obligated to perform an action required by the contract until the condition has been satisfied. See John J. Calnan Co. v. Talsma Builders, Inc., 395 N.E.2d 1076, 1080 (lll App. Ct. 1979). In A.A. Conte, the general contractor and the subcontractor entered into a written agreement which stated that the subcontractor would be paid “if payment … has been received by [the general contractor] under its general contract [with the owner] .” After the subcontractor had performed substantial work pursuant to the subcontract, the project owner became insolvent and failed to pay the general contractor. Because the general contractor did not receive payment from the owner, the general contractor, in reliance on the “pay-when-paid” clause, made no payment to the subcontractor. In addition to asserting a mechanics lien against the project, the subcontractor brought an action against the general contractor to recover payment for the work performed under the subcontract. 104 The general contractor denied that it owed any debt to the payment clause in the subcontract was a valid condition precedent – the condition being that the contractor had to receive payment from the owner of the project under the general contract before it was obligated to pay the subcontractor for its work. The Illinois Appellate Court held that the payment clause was an enforceable condition precedent and that because the owner had not paid the contractor, the subcontractor was no entitled to payment from the general contractor. Id. at 33. In holding that the payment clause was a valid condition precedent, the court expressly rejected the subcontractor’s argument that the clause created a limitation only as to the timing of payment. In other words, the court held that payment clause did not simply control when the subcontractor was paid by the general contractor – it controlled the subcontractor’s right to be paid under the subcontractor’s right to be paid under the subcontract. Based on the unambiguous language in the subcontract, the court strictly enforced plain language of the agreement, stating that it “may not rewrite a contract to suit one of the parties but must enforce the term as written.” The court in A.A. Conte also deemed it significant that the subcontract was entered into by two business entities experienced in the construction industry and that, presumably, the parties had entered into many other contracts of a similar nature in the course of their business. Thus, at least one Illinois court decision supports enforcement of “pay-when-paid” language in an agreement, despite a harsh result for the subcontractor. However, other courts have not similarly construed “pay-when-paid” clauses. In fact, the highest courts of California and New York have held that any clause purporting 105 to make payment by the owner to the contractor a true condition precedent to contractor’s obligation to pay the subcontractor is unenforceable as contrary to public policy155 . The A.A. Conte decision does not necessarily mean that am subcontractor facing a “pay-when-paid” is left without remedy. The subcontractor still may file a mechanics lien Section 21 of the Illinois Mechanics Lien Act, 770 ILCS 60/12, expressly provides that any subcontract provision conditioning payment from a contractor to a subcontractor upon receipt of payment from the owner is not a defense to subcontractor’s lien claim. In short, under current Illinois law, an unambiguous “pay-when-paid” clause may block a subcontractor’s right to recover in a breach of contract suit against the general contractor. As s result, a general contractor may find the “pay-when-paid” clause an effective method of avoiding payment to a subcontractor for work when the owner has not paid the general contractor. A “pay-when-paid” clause does not prevent a subcontractor from filling a mechanics lien, but if a subcontractor is concerned about preserving its contract rights, the subcontractor, before signing a subcontract presented by the general contractor, should review or have its attorney review the subcontract to see if it includes a “pay-when-paid” clause. If it does, the subcontractor may want to consider whether it wants to share the risk of owner nonpayment. 155 See Wm. R. Clarke Corp. v. Safeco Ins. Co. of Am., 938 P.2d 372 (Cal. 1997); West-Fair Elec. Contractors v. Aetna Cas. & Sur. Co., 661 N.E.2d 967, 971 (N.Y.1995) 106 4.3 Conclusion The above discussion show eleven (11) judgment for the application to the “pay when paid” provisions in sub-contact and the principle laying behind that drove the judge to come a judgment that the “pay when paid” provisions constitute time for payment and waiving the subcontractor right to payment (condition precedent of payment by the owner to the main contractor). It shows that the “pay when paid” pr ovisions in construction subcontract may constitute as waiving the subcontractor right to be paid and as timing mechanism. This is because the wording of the contractual language in the sub-contract is critical. Unambiguously and sufficiently clearly cont ractual language must have been used in order for a court to construe such a clause imposed payment to the main contractor as condition precedent to the subcontractor’s right to be paid, rather than limiting the time for payment. Once a judge decides that provision is ambiguous there is nothing for the jury to decide or interpret. Overall, the findings are found to be parallel with the literature review. It shows that the risk-shifting provisions are susceptible to only two possible interpretations which are: if a provision is clear and unambiguous; it is interpreted as setting a condition precedent to the general contractor’s obligation to pay. If a provision is ambiguous, it is interpreted as fixing a reasonable time for the general contractor to pay. In purported risk shifting, provision between a contractor and subcontractor, the burden of clear expression is to the general contractor. Whether the “pay when paid” clause is to be construed as a conditional promise to pay, enforceable only when and if the conditions precedent has taken place or is to be construed as an unconditional promise to pay with the time of payment being postponed until the happening of a certain event, or for a reasonable period of time if it develops that 107 such event does not take place. To construe it as requiring the subcontractor to wait to be paid for an indefinite period of time until the general contractor has been paid by the owner, which may never occur, is to give to it an unreasonable construction which the parties did not intend at the time the subcontractor was entered into. Hence, the court suggest that “Contra Proferentum156 ” principle would apply to such clause and seeks to rely upon a clause to show that there was a condition precedent before a liability arose at all should show that the clause relied upon no ambiguity. The controlling factor as whether the “pay when paid” clause was conditional or unconditional promise was the intention of the parties. The court declined to construe a “pay-when-paid” clause as a valid condition precedent to the subcontractor’s receipt of payment when such a construction would result in a “significant forfeiture” to the subcontractor and when the subcontract was read in conjunction with the general contract and its conditions, a sufficient ambiguity existed which prevented the general contractor from effectively shifting the risk of the owner’s nonpayment to its subcontractor As mentioned above, there is only one principle laying behind the drove the judge to come a judgment the “pay when paid” provisions as timing mechanism or waiving the subcontractor’s right to payment, which is the contractual language. The apparent adoption of the observations of Master Towle in the case of Smith & Smith Glass Ltd v. Winstone Architectural Cladding System Ltd157 is to be welcomed. It 156 In general, if there is any genuine ambiguity in an exclusion contract (that is, if a contract provision is subject to at least two varying reasonable interpretations), it will be strictly construed against the party who drafted the contract. 157 [1992] 2 NZLR 473 108 appears that the Malaysian Courts see no conceptual obstacle to the practice of “paywhen-paid” and are content to apply the ordinary rules of contractual interpretations to such clauses. Master Towle made the following observations: “While I accept that in certain cases it may be possible for persons contracting with each other in relation to a major building contract to include in their agreement clear and unambiguous conditions which have to be fulfilled before a subcontractor has the right to be paid, any such agreement would have to make clear beyond doubt that the arrangement was to be conditional and not to be merely governing the time of payment. I believe that the ‘contra proferentem158 ’ principle would apply to such clause and that he who seeks to rely upon such a clause to show that there was a condition precedent before liability to pay arose at all should show that the clause relied upon contain no ambiguity.” . 158 In general, if there is any genuine ambiguity in an exclusion contract (that is, if a contract provision is subject to at least two varying reasonable interpretations), it will be strictly construed against the party who drafted the contract. 109 CHAPTER 5 CONCLUSION AND RECOMMENDATIONS 5.1 Introduction This chapter is the last chapter that summarizes the finding of the research according to the research objective. It also contains the problems encounter during the research as well as the recommendations of future researches. 5.2 Summary of Research Finding Overall, the objective this research had been achieved through documentary analysis of law journal and law report. In this research, eleven (11) cases were analysis. From analysis, it is found in this research that there are eight (8) matters lying behind that drove the judge to come a judgment that “pay when paid” provisions as timing 110 mechanism or waiving the subcontractor’s right (condition precedent). The findings are shown in the Table 5.1. as follow: 111 Table 5.1: Judgment on the Application of the ‘Pay When Paid Provisions In Construction Sub-Contracts No. 1 Case Law Thomas J. Dyer Co. v. Bishop International Engineering Co., 303 F.2d 655, 661 (6th Cir. 1962) “Pay When Paid” Suggest Time of Payment X “Pay When Paid” as Condition Precedent Matter/Subject Judgment The Intention of the Contractual Parties - The controlling factor as to whether the “pay when paid” clause was a conditional or unconditional promise was the intention of the pa rties. - To determine the parties’ intent, the court looked beyond the plain meaning of the terms of the contract to consider the usual and customary expectations of parties in the construction industry. - The allocation of risk could be varied by terms of the subcontract but only if unequivocal language was used to express the parties’ intention to shift risk of nonpayment. - It was the intention of the parties that the subcontractor would be paid by the general contractor. If such was not the intention of the parties it could have been so expressed in unequivocal terms dealing with the possible insolvency of the owner. - A reasonable provision designed to postpone payment for a reasonable period of time after the work was completed during 112 No. 2 Case Law Hong Kong Case: Falcon Building Materials Company Limited v. Fine View Engineering Limited [2008] HKCU 16. “Pay When Paid” Suggest Time of Payment X “Pay When Paid” as Condition Precedent Matter/Subject Judgment The Subcontractor had Carried out its Work Satisfactory according to Terms of the Subcontract which the general contractor would be afforded the opportunity of procuring from the owner the funds necessary to pay the subcontractor. - To construe it as requiring the subcontractor to wait to be paid for an indefinite period of time until the general contractor has been paid by the owner, which may never occur, is to give to it an unreasonable construction which the parties did not intend at the time the subcontractor was entered into. - The intent of the parties still recognize a general presumption against the enforcement of the clause and require that the presumption can be overcome only by the use of clear and unambiguous contract language. "Payment terms: … (b) 80% to be settled by [Fine View’s] receipt of final payment from [the employer] within 45 days of the completion of testing and commissioning and the acceptance of the works by the [employer] …”“This contract shall be executed on a back-to-back basis in accordance with the relevant clauses 113 No. 3 Case Law The Ontario Court of Appeal: Timbro Development Ltd. v. Grimsby Diesel Motors, Inc. (1998). 32 C.L.R 32 (Ont. C.A) “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent X Matter/Subject Under the Clause the Subcontractor Clearly Assume the Risk of Nonpayment by the Owner to the Contractor Judgment within the main contract ." - The court found that the clause (b) "did not detract from the subcontractor's right to be paid if it had satisfactorily completed the works according to the contractual requirements " - Provided that the subcontractor has carried out its work satisfactorily according to the terms of its subcontract, it is entitled to payment within a reasonable time of completing its works, notwithstanding a paywhen-paid clause and the question of whether the main contractor has been paid by the employer. - The Court allowed a general contractor to rely on a standard from clause providing as follows: “…Payment will made not more than thirty (30) days after the submission date or ten (10) days after certification or when we have been paid by the owner, whichever is the later …” - Blair and Cory JJ.A opinion: The clause clearly specifies the condition governing the contractor’s legal 114 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Unambiguous Contractual Language entitlement to payment and not merely the time of payment. Under the clause, the subcontractor clearly assumes the risk of non-payment by the owner to the contractor. Since Timbro was not paid, it is not obliged to pay the subcontractors and the appeal must fail. - The general rule is that interpretation of a document is a question of law rather than of fact. If an issue of contract interpretation concerns the intention of the parties, that intention may be determined from the written contract, as a matter of law, when the nature of the transaction lends itself to judicial interpretation. - It was held that in order to properly shift the risk to the subcontractor, the subcontractor must unambiguously express such intention and burden of clear expression is on the general contractor - Under the Clause the Subcontractor Clearly Assume - The court also held that on the evidence, it was apparent that the subcontractor had been made aware of the pay-when-paid clause in contract. As discuss in the Timbro case: Kor-Ban Inc. v. Pigott Construction Ltd(1993). 11 C.L.R. (2d) 160 (Ont. Gen. Div.) X Judgment 115 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment the Risk of Nonpayment by the Owner to the Contractor - Hagarty C.J. held that: I think the true intent and meaning of such a contract must be that the best the defendant [general contractor] can say: “If I duly perform my contract with the company [the owners], and though I be entitled to the money from them, if from any cause, not arising from any act or default of mine, they [the owners] do not pay, you [the subcontractor] cannot call on me to pay.” Applied Insulation Co. v. Megatech Contracting Ltd. (1994), 22 C.L.R. (2d) 251 (Ont. Gen. Div.) X The General Contractor Caused the Nonpayment by the Owner -Where the defendant general contractor was in default and the plaintiff, subcontractor, had in no way contributed to the problems. The general contractor was not allowed to rely on the clause. Arnoldin Construction & Forms Ltd. v. Alta Surety Co. (1995), 19 C.L.R. (2d) 1 (N.S. C.A.), leave to appeal to the Supreme Court of Canada refused (1995), 22 C.L.R. (2d) 131 (note) X Ambiguous Contractual Language -The payment clause in a subcontract was summarized by the Court as follow: “…Payments the balance of the amount of the requisition as approved by the contractor “shall be due to the subcontractor on or about one day after receipt by the Contractor of payment from 116 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment the owners”. The final payment under the subcontract is to be made on acceptance of the work “and within thirty (30) days after payment has been received by the contractor”. - The Nova Scotia Court of Appeal argued that this was not clear enough language to impose a standard term on the subcontractor. - The respondent intended that nothing would owe or payable to a subcontractor upon completion of the work unless payment was received from the owner, the contract ought to have contained clear words to denote such an intention. - Appropriate words would have been that the balance claimed by the subcontractor for the completion of the work pursuant to terms of the subcontract would only be paid “if” the owner paid the contractor. - An intention so important cannot be buried in obscure language which would not alert the subcontractor that payment was subject to a condition precedent that the owner pays the contractor. 117 No. 4 Case Law Florida Supreme Court Peacock Construction Co., Inc. v. Modern Air Conditioning, Inc. , 353 So.2d 840 (Fla. 1977) “Pay When Paid” Suggest Time of Payment X “Pay When Paid” as Condition Precedent Matter/Subject Small Subcontractor Ordinarily Would Not Assume the Risk Owner’s Failure to Pay the General Contractor Judgment - Provision calling for payments after written acceptance by the architect and full payment by the owner do not set condition precedent. They constitute absolute promises to pay, fixing payment by the owner as a reasonable time for making payment to the subcontractor. - The Supreme Court conclude: A number of courts, with whom we agree, have recognized that contracts between small subcontractors and general contractors on large construction projects are such transactions. Cf. Thos. J. Dyer Co. v. Bishop International Engineering Co.,6 Cir., 303 F.2d 655 (1965). The reason is that the relationship between the parties is a common one and usually intent will not differ from transaction to transaction, although it may be differently expressed. - Small subcontractors, who must have payment for their work in order to remain in business, ordinarily would not assume the risk of the owner’s failure to pay the general 118 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment contractor. - In order to properly shift the risk to the subcontractor, the subcontractor must unambiguously express such intention and burden of clear expression is on the general contractor. 5 Wo Hing Engineering Limited v. Pekko Engineers Limited (unreported, No.A5561) X 6 The Court of Appeal (Putrajaya), Malaysia Antah Schindler Sdn Bhd v. Ssangyong Engineering & Construction Co. Ltd., [2008] 3 MLJ 204 X Ambiguous Contractual Language - Suffiad J. cited: “sufficiently clear words will have to be used before a court will be prepared to construe that such a clause imposes as a condition payment to the main contractor (the sub-contractor in the Wo Hing case) which had to be fulfilled before the subcontractor (the sub-sub-contractor in the Wo Hing case) had the right to be paid as opposed to a clause limiting the time for payment.” - The Court considered the effect of the clause, referring to the New Zealand case of Smith & Smith Glass Ltd v. Winstone Architectural Cladding System Ltd [1992] 2 NZLR 473, where Master Towle made the following observations. 119 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment “While I accept that in certain cases it may be possible for persons contracting with each other in relation to a major building contract to include in their agreement clear and unambiguous conditions which have to be fulfilled before a subcontractor has the right to be paid, any such agreement would have to make clear beyond doubt that the arrangement was to be conditional and not to be merely governing the time of payment. I believe that the ‘contra proferentem159 ’ principle would apply to such clause and that he who seeks to rely upon such a clause to show that there was a condition precedent before liability to pay arose at all should show that the clause relied upon contain no ambiguity.” Clause 27(a) (vii) of the Main Contract: “The payment in respect of any work, materials or goods comprised in the subcontract shall be made within 14 days after receipt by the Contractor of payment from 159 In general, if there is any genuine ambiguity in an exclusion contract (that is, if a contract provision is subject to at least two varying reasonable interpretations), it will be strictly construed against the party who drafted the contract. 120 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment the Employer...” - The Court of Appeal held that upon its proper construction, clause 27(a)(viii) did not restrict a claim by the Sub-Contractor but merely imposed a time limit on the main contractor to pay its Sub-Contractor. 7 The Supreme Court of the State of Florida DEC Electric, Inc., v. Raphael Construction Corporation 558 So. 2d 963 (Fla. 4th DCA 1989) X Unambiguous Contractual Language - Raphael Construction relied upon paragraph 6 of the subcontract, which states: “… No funds will be owed to the subcontractor unless the General Contractor is paid by the Owner in accordance to the sworn statement. The subcontractor fully understands that in event of non payment by the owner to the General Contractor, …” - The trial court held, as matter of law, that DEC was not entitled to payment from Raphael Construction because paragraph 6 of the subcontract unambiguously required payment from the owner to Raphael Construction before payment become due to DEC. 121 No. 8 Case Law The Circuit Court of the City of Norfolk John E. Clarkson, Judge Galloway Corporation v. S.B. Ballard Construction Co., et al., 250 Va. 493, 494 S.E.2d 349 (1995) “Pay When Paid” Suggest Time of Payment X “Pay When Paid” as Condition Precedent Matter/Subject Ambiguous Contractual Language (Latent Ambiguity in the Contracts) Judgment - Paragraph 11.3 of Subcontract contains the following pertinent language: “The Contractor shall pay Subcontractor each progress payment within three working days after the Contractor receives payment from the Owner…” - The mere fact that terms of a contract are in dispute is not evidence that the language is not clear and explicit and requires extrinsic evidence to aid in its construction. If the terms of the parties’ agreement are contained in a clear and explicit writing, that writing is the sole memorial of the contract and the sole evidence of the agreement. - The court concludes that the phrases “after the Contractor receives payment from the Owner” and “has received payment from the Owner” constitute latent ambiguities in the contracts. That is, the phrases, while appearing perfectly clear at the time the contracts were formed, because of subsequently discovered or developed facts, may reasonably be interpreted in either of two ways. - The court holds that in the absence of a clear and unambiguous statement of the 122 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment parties’ intent as to the meaning of the time of payment provision in a construction subcontract, an absolute “pay when paid” defense is available to a general contractor only if it can establish by parol evidence that the parties mutually intended the contract to create such a defense - - Supreme Court held that the phrase in the subcontract only permitted Galloway to “delay payment, but the contracts cannot be construed to say that each subcontractor must bear its own loss if Galloway never got paid on its contract with the owner.” 9 Illinois Courts A.A. Conte, Inc. v. CamphellLowrie-Lautermilch Corp., 132 lll.App. 3d 325, 477 N.E.2d 30 (1st Dist. 1985). X Unambiguous Contractual Language - In A.A. Conte, the general contractor and the subcontractor entered into a written agreement which stated that the subcontractor would be paid “if payment … has been received by [the general contractor] under its general contract [with the owner].” - The Illinois Appellate Court held that the payment clause was an enforceable condition precedent and that because the owner had not paid the contractor, the subcontractor was no entitled to payment from the general 123 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment contractor. - The court held that payment clause did not simply control when the subcontractor was paid by the general contractor – it controlled the subcontractor’s right to be paid under the subcontractor’s right to be paid under the subcontract. Based on the unambiguous language in the subcontract, the court strictly enforced plain language of the agreement, stating that it “may not rewrite a contract to suit one of the parties but must enforce the term as written.” - An unambiguous “pay-when-paid” clause may block a subcontractor’s right to recover in a breach of contract suit against the general contractor 10 Brown & Kerr Inc. v. St. Paul Fire & Marine Insurance Co., 940 F.Supp. 1245, 1250 (N.D. lll. 1996) X “Pay-WhenPaid” Clause Result in “Significant Forfeiture” to the Subcontractor. - The subcontract at issue Brown & Kerr stated: “The final payment would be made by the Contractor to the Subcontractor when… the Contractor has received final payment from the Customer under Prime Contract.” - The court declined to construe a “pay-when- 124 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment paid” clause as a valid condition precedent to the subcontractor’s receipt of payment because such a construction would result in a “significant forfeiture” to the subcontractor - The court concluded that the “pay-whenpaid” clause did not create a condition precedent, but rather a timing provision requiring the general contractor to pay the subcontractor within a reasonable time. 11 Florida Supreme Court OBS Company, Inc. v. Pace Construction Company X Ambiguity Existed When the Subcontract was Read in Conjunction with The General Contract - Subcontract agreement that contained the following language: “… final payment, shall not become due unless and until the following conditions precedent to final payment have been satisfied (c) receipt of final payment for subcontractor’s work by contractor from owner.” - The court found that when the subcontract was read in conjunction with the general contract and its conditions, a sufficient ambiguity existed which prevented the general contractor from effectively shifting the risk of the owner’s nonpayment to its subcontractor. To its dismay, the general 125 No. Case Law “Pay When Paid” Suggest Time of Payment “Pay When Paid” as Condition Precedent Matter/Subject Judgment contractor remained liable for the final payments owed to its subcontractor. - The Florida Supreme Court agreed to examine when it accepted jurisdiction of OBS v. Pace. In it analysis, the Florida Supreme Court examined an earlier line of decisions. It already had decided that “pay-when-paid” clauses were going to be strictly construed with any ambiguity resolved in favor of unpaid subcontractor or supplier. In order to shift the burden of nonpayment to the subcontractor of supplier, the subcontract was required to contain a “clear an unequivocal expression” of that fact. The decision was based on the ambiguity created by incorporation of the prime contract into the OBS subcontract. Pace had failed to meet its burden of a clear and unequivocal “paywhen-paid” clause. 126 The summary above shows eleven (11) judgment for the application to the “pay when paid” provisions in sub-contact and the principle laying behind that drove the judge to come a judgment that the “pay when paid” provisions constitute time for payment and waiving the subcontractor right to payment (condition precedent of payment by the owner to the main contractor). Overall, the findings are found to be parallel with the literature review which shows that the risk-shifting provisions are susceptible to only two possible interpretations which are: if a provision is clear and unambiguous; it is interpreted as setting a condition precedent to the general contractor’s obligation to pay. If a provision is ambiguous, it is interpreted as fixing a reasonable time for the general contractor to pay. In purported risk shifting, provision between a contractor and subcontractor, the burden of clear expression is to the general contractor. Instead of that, Judges from most of the cases cited that the wording of the contractual language in the sub-contract is critical. The words may convey the “pay when paid” as timing mechanism or such condition precedent. Unambiguously and sufficiently clearly contractual language must have been used in order for a court to construe such a clause imposed payment to the main contractor as condition precedent to the subcontractor’s right to be paid, rather than limiting the time for payment. Once a judge decides that provision is ambiguous there is nothing for the jury to decide or interpret. In a nutshell there are eight (8) matters laying behind that drove the judge to come a judgment that “pay when paid” provisions as timing mechanism or waiving the subcontractor right to payment (condition precedent). The matters are as follows: 1. Contractual language (ambiguous or unambiguous); 2. The intention of the contractual parties; 3. Under the clause, the subcontractor assumption of the risk of nonpayment by the owner to the contractor; 127 4. Compliance to the terms of the sub-contract, e.g. the subcontractor had carried out its work satisfactorily according to terms of the sub-contract; 5. The general contractor caused the nonpayment by the employer; 6. Small subcontractor ordinarily would not assume the risk of the owner’s failure to pay the general contractor; 7. “Pay when paid” clause result in significant forfeiture to the subcontractor; and 8. Ambiguity existed when the sub-contract was read in conjunction with the general contract. Hence, the court suggest that “Contra Proferentum 160 ” principle would apply to such clause and seeks to rely upon a clause to show that there was a condition precedent before a liability arose at all should show that the clause relied upon no ambiguity. The controlling factor as whether the “pay when paid” clause was conditional or unconditional promise was the intention of the parties. Any such agreement would have to make clear beyond doubt that the arrangement was to be conditional and not to be merely governing the time of payment. Therefore, failure of the contractor to express his intention unambiguously in the provision will lead the contractor to make payment to the subcontractor in the event of nonpayment or insolvency of the owner. 160 In general, if there is any genuine ambiguity in an exclusion contract (that is, if a contract provision is subject to at least two varying reasonable interpretations), it will be strictly construed against the party who drafted the contract. 128 5.3 Problem Encountered during Research The major problem in writing up this project report is the insufficiently of time. There is only 8 weeks’ time provided for this research. Everything needs to be done in very fast manner, especially during the data collection process. Besides, it is lack of time to refer more sources of literature review from others university. 5.4 Conclusion As a conclusion for all, the court requires language of a more specific nature of “pay when paid” provisions in construction sub-contract. Short of any precise terms, such as “condition precedent”, the contractual language could not be construed as anything but merely fixing the time for payment. The subcontractor may take the legal action to challenge the enforceability of the clause to seek immediate payment when they have suffering the risk of non-payment due to the performance problems unrelated to their own work. 129 REFERENCES Andrea Beckwith, Pay-When-Paid Clauses: Risk Allocation and the need for Careful Dafting. Miller Thomson Construction Law Newsletter Summer 2002. Miller Thomson LLP:Washington DC. Pg 1 Ahlers J.P. (2008). “Pay When Paid” vs. “Pay If Paid” Clauses: Mystery vs. Myth. Ashworth, A. (1986). Contractual Procedures in the Construction Industry. London and New York: Logman. Pg 8 Atkinson, D (2001). Payment-Pay-When-Paid Clauses. England: Daniel Atkinson Limited. Beckwith, A (2002). Pay-When-Paid Clauses: Risk Allocation and the need for Careful Drafting. Miller Thomson Construction Law Newsletter Summer 2002, Miller Thomson LLP:Washington DC, Pg 1 Brown McCarroll (2006). The Construction Process From Start To Finish in Texas. Texas: Lorman Education Services. Pg4-5 Bruner, P.L. and Haley, T.L. Managing and Litigating the Complex Surety Case. American Bar Association. Tort Trial and Insurance. Pg 749 Crushman, R.F. and Myers, J.J. (1999). Construction Law Handbook. Published by Aspen Publishers Online. Pg 891 Daniel Atkinson (2001). Payment-Pay-When-Paid Clauses. England: Daniel Atikinson Limited. Danner, P.D. Enforceability of Pay-When-Paid and Pay-If-Paid Clauses May Vary From State to State. 130 Devine, P. (2006). When Must A Subcontractor Be Paid Under A “Pay-When-Paid” Clause. Business Credit July/August 2006. National Association of Credit Management Felin, M.S. and Philips, S.M. (2003). Understanding Payment Provisions. Roofing Magazine February 2003 Fullerton J.D. (2008). Changes, Delays and Other Claims. http://www.fullertonlaw.com/4Cha ngesDelaysandOtherClaims.php Goodin, P.W. and Dickinson, J.C.. Who Bears the Risks of Owner Non-Payment?. Midwest Construction Law, Contracts and Claims Gurney, D.S. (2007). “Pay-When-Paid” Clauses: What Happens When the Owner Doesn’t Pay?. Published in The Constructor. Ohio: Frost Brown Todd LLC Hess, S.A. & Bales, J.V. (2007). Design Professional and Construction Manager Law. American Bar Association - Forum on the Construction Industry. Chapter 15 Pg 500 Hill, K.B. & Ritter (2008). Contingent Payment Clauses in the 50 States. Ohio: Foundation of the American Subcontractors Association Hughes, T.R. (2008). To Pay or Not to Pay. Hughes & Associates P.L.L.C. Ir. Oong Chee Keng (2004). Institution of Engineering Public Forum On “Pay-WhenPaid” Clauses in Construction Sub-Contracts-Held on 27 November 2004. Kuala Lumpur: IEM Jenkins Marzban Logan LLP. Pay-When-Paid Clauses, Canada: Construction Law. pg1 Koprince, S.J. (2008). Is Your Pay-When-Paid Clause Worthless?. The Constructor January/February 2008. McGraw Hill Construction Logan, J.M. Pay-When-Paid Clauses-Construction Law. Canada. Pg1 Lybeck, K.L. and Shreves, H.B. (1998). The Law of Payment Bonds. American Bar Association. Pg 26 131 Lim Chong Fong . The Malaysian Construction Industry-The Present Dilemmas of the Unpaid Contractors. McCarroll, B. (2006). The Construction Process from Start to Finish in Texas. Lorman Education Services, Texas. Pg4-5 Micheal L. Chapman, Payment Rights and Obligations. http://www.chapmanfirm.com/payment.html Mootz, F.Z. (1990). The Enforceability of Pay When Paid Clauses in Construction Contracts, 64 Conn.B.J. 257,265 Murdoch J. and Hughes W. (2008). Construction Contracts: Law and Management 4th Edition. London and Newyork: Taylor & Francis. Pg 3 Murphey, D.R. (1999). Surety’s Reliance on Pay-When-Paid Clause Rejected. Smith, Currie & Hancock LLP. Nadine H. G. and Patrick C. B., Waiting to Get Paid: Pay When Paid Provisions a Matter of When or If, The Florida Bar Journal Volume LXXII No.9 October 1999. pg 64 Ng Chu Yin (2006). Problems Associated With Nominated Subcontractor in Malaysian Construction Industry. Johor: Universiti Teknologi Malaysia. Pg1,2 Pettigraw, R. (2005). Payment Under Construction Contracts Legislation.Thomas. London: Telford Ltd. Pg 2 Perlmuter, G.E. (2007). Michigan’s Winning Economy Wallops Construction Contractors. Has the Sting of a Pay-When-Paid Clause Gotten Your Attention?. Foster, Swift, Collins & Smith Construction Law Newsletter, November 2007Aspen Publishers Online. Pg 895 Reeves, G.D. (1999). Enforceability of Conditional Payment Provisions in Construction Subcontracts. CAM Magazine August 1999 Edition Rippeon, Z. (2007). Conditional Payment Clauses in Construction Contracts. Georgia: Georgia State University College of Law. 132 Rosenberg, T.L. (2007). Essential Construction Contract Terms: Avoiding Future Problems by Addressing Key Issues. The Real Estate Finance Journal/Spring 2007. Pg 8 Russell, R. (2003). The Right Contract Means Preserving Cashflow. Builder Exchange Magazine Vol 8 Issue 03 Sternlieb (2007). Subcontractor’s Right to Payment. New Jersey Law Journal Vol. CXCNo.4-Index 399 October 22, 2007. Sienicki, J. and Roth, J. (2007). The Prevention Doctrine and Its Effect on ‘Pay-If-Paid’ and ‘Pay-When-Paid’ Clauses. Snell & Wilmer L.L.P. Sr Nourshad Ali Naseem Ameer Ali (2006). A “Construction Industry Payment and Adjudication Act”: Reducing Payment-Default And Increasing Dispute Resolution Efficiency In Construction. Master Builders Journal 3rd Quarter 2006. Pg 4. Sklar, A.J. & Sternlieb, M. (2007). The “Pay-If-Paid” Clause-A Suspect Subcontract Provision. Cole Schotz Docket, Fall 2007 Tate, T.C. . “If” or “When” What a Difference a Word. California: Crowford & Bangs. http://www.builderslaw.com/news/if_or_when.htm Teresa Cheng, Evia Wong and Gry Soo (2004). Construction Law and Practice in Hong Kong. Sweet & Maxwell Asia. Pg 7 Zack Rippeon (2007). Conditional Payment Clauses in Construction Contracts. Georgia: Georgia State University College of Law. II, R.L. (2005). Nos. 31869 and 31870. Supreme Court of Appeals of West Virginia. Pg 8 . 133 APPENDIX A Contingent Payment Clauses in the 50 States Published by: Foundation of the American Subcontractors Association, Inc. 1004 Duke Street Alexandria, VA 22314-3588 Telephone: (888) 374-3133 Fax: (888) 374-3133 e-mail: ASAOffice@asa-hq.com Web site: www.fasaonline.com part of the Capitol Square, Suite 1800 65 E. State Street Columbus, Ohio 43215-4294 Donald W. Gregory, Esq. (dgregory@keglerbrown.com) General Counsel to the American Subcontractors Association Copyright 2008 American Subcontractors Association, Inc. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without obtaining prior written permission from the copyright owner. DISCLAIMER: This publication does not contain legal advice. Individual circumstances vary widely, so readers should consult legal counsel before acting on the information provided herein. Acknowledgments We want to recognize the contributions of Kegler, Brown, Hill & Ritter, LPA summer associate Jeremiah Thomas to this publication. About ASA and FASA The American Subcontractors Association amplifies the voice of and leads trade contractors to improve the business environment for the construction industry and to serve as a steward for the community. The ideals and beliefs of ASA are ethical and equitable business practices, quality construction, a safe and healthy work environment, integrity and membership diversity. The Foundation of the American Subcontractors Association, Inc., a section 501(c)(3) organization under the U.S. Internal Revenue Code, is the educational arm of ASA. FASA is an independent entity devoted to development of quality educational information, providing financial support to develop manuals, videotapes, CD-ROMs, seminars and other materials. ii Preface provisions. Additionally, a growing number of states have enacted legislation that declares such contractual provisions void and against public policy. A contingent payment clause is a contractual provision that makes payment contingent upon the happening of some event. In construction subcontracts, the typical contingent payment clause makes the subcontractor's payment contingent upon the payment of the contractor by the owner. This article attempts to summarize the basic stance of each of the fifty states with respect these two types of contingent payment clauses. The following information is displayed for all states that have applicable law on this issue: Contingent payment clauses take on one of two forms in subcontract agreements. Some clauses link the timing of the subcontractor's payment to the time when payment is made by the owner. These are called "pay-whenpaid" clauses. Other clauses specify that the owner must pay the contractor in order for the subcontractor to ever receive payment. These provisions that shift entitlement to payment are called "pay-if-paid" clauses. Even though most states distinguish between the two types of clauses, a few jurisdictions find that the provisions have the same exact legal effect. • • • • For over thirty years, most state courts have held that contractors cannot indefinitely withhold payment from subcontractors based upon a "pay-when-paid" clause. Instead, "pay-when-paid" clauses require a contractor to pay its subcontractors within a "reasonable time" of the completion of satisfactory work. Whether a "pay-if-paid" clause will be enforced in that state if it is unambiguously drafted. Whether the state distinguishes between "pay-if-paid" and "pay-whenpaid" provisions. Whether "pay-when-paid" clauses allow a contractor in the state to only delay payment to its subcontractors for a reasonable time. Key statutes and cases that describe the states' positions on contingent payment clauses. This publication is designed as a summary of the basic principles of state law, but is not a comprehensive legal treatment of the law in the states. This publication does not contain legal advice. Because individual circumstances may vary widely, and because state laws are constantly changing, readers should consult their local attorneys for specific advice. In contrast, "pay-if-paid" clauses often allow contractors to permanently withhold payment from their subcontractors where the owner has failed to pay the contractor. Because of the harshness of such a provision, most states only enforce "pay-if-paid" clauses if the contract unambiguously expresses that the parties intended for the subcontractor to only be paid if the contractor is paid. As states have moved toward protecting the rights of subcontractors, some state courts have decided not to enforce "pay-if-paid" iii CONTINGENT PAYMENT CLAUSES IN THE 50 STATES Table of Contents Acknowledgments ................................................................................................................. ii Preface ...................................................................................................................................iii States (and Washington, D.C.) Alabama..................................................................................................................... 1 Alaska ........................................................................................................................ 1 Arizona ...................................................................................................................... 1 Arkansas .................................................................................................................... 1 California ................................................................................................................... 1 Colorado .................................................................................................................... 2 Connecticut ................................................................................................................ 2 Delaware .................................................................................................................... 2 District of Columbia .................................................................................................. 2 Florida........................................................................................................................ 3 Georgia....................................................................................................................... 3 Hawaii........................................................................................................................ 3 Idaho .......................................................................................................................... 4 Illinois ........................................................................................................................ 4 Indiana ....................................................................................................................... 4 Iowa ........................................................................................................................... 4 Kansas........................................................................................................................ 4 Kentucky.................................................................................................................... 5 Louisiana.................................................................................................................... 5 Maine ......................................................................................................................... 5 Maryland.................................................................................................................... 5 Massachusetts ............................................................................................................ 5 Michigan .................................................................................................................... 5 Minnesota .................................................................................................................. 6 Mississippi ................................................................................................................. 6 Missouri ..................................................................................................................... 6 Montana ..................................................................................................................... 6 Nebraska .................................................................................................................... 7 Nevada ....................................................................................................................... 7 New Hampshire ......................................................................................................... 7 New Jersey................................................................................................................. 7 New Mexico............................................................................................................... 7 New York ................................................................................................................... 8 North Carolina ........................................................................................................... 8 North Dakota ............................................................................................................. 8 Ohio ........................................................................................................................... 8 Oklahoma................................................................................................................... 9 Oregon ....................................................................................................................... 9 Pennsylvania .............................................................................................................. 9 iv CONTINGENT PAYMENT CLAUSES IN THE 50 STATES Rhode Island .............................................................................................................. 9 South Carolina ........................................................................................................... 9 South Dakota ............................................................................................................. 9 Tennessee ...................................................................................................................10 Texas ..........................................................................................................................10 Utah............................................................................................................................10 Vermont......................................................................................................................10 Virgin Islands.............................................................................................................10 Virginia ......................................................................................................................11 Washington ................................................................................................................11 West Virginia ........................................................................................................... . 11 Wisconsin................................................................................................................. . 12 Wyoming.................................................................................................................. . 12 v CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State "PAY IF PAID" Enforced If Explicit "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment STATUTORY PROVISIONS Ala. Code 8-29-2: All contracts between parties must specify a date of payment. Alabama X Alaska X Arizona X Arkansas California X Ark. Code Ann. § 22-9-205: Recognizes the enforceability of a "pay-when-paid" provision in a public contract. It does not address whether a "pay-when-paid" clause would create a condition precedent to the subcontractor's payment. Pay-when-paid clause in the subcontract did not create a condition precedent to payment, but that it was merely a timing mechanism for payment. The parties did not "clearly indicat[e] that the subcontractor assumed the risk of nonpayment." Fed. Ins. Co. v. I. Kruger, Inc., 829 So. 2d 732, 741 (Ala. 2002) The pay-when-paid clause is enforced as creating a valid condition precedent to payment for the subcontract. Industrial Indem. Co. v. Wick Constr. Co., 680 P.2d 1100 (Alaska 1984). "In order to create a condition precedent [to the subcontractor's payment], there must be contractual language demonstrating the parties' unequivocal intent" that the subcontractor will only be paid if the contractor is paid. L. Harvey Concrete v. Agro Constr. & Supply Co., 189 Ariz. 178, 181 (Ariz. Ct. App. 1997) A condition that sets out events to happen before payment may be construed to link the existence of the debt to fulfillment of the conditions. Brown v. Maryland Casualty Co., 246 Ark. 1074, 1082 (Ark. 1969). Cal Civ Code § 3262: Statute preventing a waiver of lien rights has been interpreted to also prohibit "pay-if-paid" provisions for the indirect effect on lien rights. Clause that required payment "immediately on the completion of the work" established a valid condition precedent to payment. Manuel v. Campbell, 3 Ark. 324 (1841). California courts will not enforce "pay-if-paid" clauses as they unlawfully inhibit subcontractor's mechanic's lien rights. William R. Clark Corp. v. Safeco Ins. Co., 938 P.2d 372 (Cal. 1997). X X X X X CASE LAW 1 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State Colorado Connecticut "PAY IF PAID" Enforced If Explicit "PAY WHEN PAID" And "PAY IF PAID" Treated Same X X Conn. Gen. Stat. 158 (j): Contractor cannot withhold payment from a subcontractor because of a dispute with another contractor, subcontractor, or vendor. X X X STATUTORY PROVISIONS X Delaware D.C. "PAY WHEN PAID" Suggests Time for Payment X Del. Code. Ann. tit. 6 § 3507 (e): Makes void any clause in a Subcontract that makes payment by the owner a condition precedent to the subcontractor's payment. This statute does not apply to public contracts. CASE LAW Pay-if-paid provisions must unequivocally express the party's intent to establish a condition precedent to payment in order to be enforceable. "[A] pay-whenpaid clause . . . is an unconditional promise by the general contractor to pay its subcontractor even if the owner becomes insolvent." Main Elec., Ltd. v. Printz Servs. Corp., 980 P.2d 522 (Colo. 1999). Contract language that specifies payment shall be made to the subcontractor at the time it is made to the contractor effectively establishes a valid condition precedent to payment. Star Contracting Corp. v. Manway Constr. Co., 337 A.2d 669 (Conn. 1973). No cases have yet to interpret the bounds of the statutory prohibition of "pay-if-paid" clauses. The statute was passed in 2002. "Pay-when-paid" provision established a valid condition precedent. Subcontractor still prevailed in claim for damages as the court imposed a duty on contractor to attempt to recover payment, and contractor had settled with owner without accounting for the subcontractor's entitlement. Urban Masonry Corp. v. N&N Contractors, Inc., 676 A.2d 26 (D.C. 1996). 2 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State "PAY IF PAID" Enforced If Explicit Florida X Georgia X Hawaii X Idaho X "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment STATUTORY PROVISIONS X X HRS § 444-25: If payment is contingent upon receipt of funds, the contractor shall clearly state this fact in the contractor's solicitation of bids. X CASE LAW "Risk-shifting provisions are susceptible to only two possible interpretations. If a provision is clear and unambiguous, it is interpreted as setting a condition precedent to the general contractor's obligation to pay. If a provision is ambiguous, it is interpreted as fixing a reasonable time for the general contractor to pay. In purported risk-shifting provisions between a contractor and subcontractor, the burden of clear expression is on the general contractor." DEC Electric, Inc. v. Raphael Constr. Corp., 558 So. 2d 427, 429 (Fla. 1990). A clause that says the subcontractor only receives money when the contractor is itself paid will bar recovery by the subcontractor until the contractor is paid. United States ex rel. McKenney's, Inc. v. Gov't Tech. Servs., LLC, 531 F. Supp. 2d 1375, 1378 (N.D. Ga. 2008) (citing St. Paul Fire & Marine Ins. Co. v. Ga. Interstate Elec. Co., 187 Ga. App. 579 (Ga. Ct. App. 1988)). There are no cases from courts regarding this statute, but the language of the statute appears to contemplate the enforcement of a contingent payment clause. Contract terms setting the timing of payment of subcontractor after the payment of the prime contractor creates a valid condition precedent. Hoff Cos. v. Danner, 822 P.2d 558 (Idaho 1991). 3 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State Illinois Indiana "PAY IF PAID" Enforced If Explicit X X "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment X X Iowa X X Kansas X X Kentucky X X STATUTORY PROVISIONS 770 Ill.Comp. Stat. 60/21: "Any provision in a contract, agreement, or understanding, when payment from a contractor to a subcontractor or supplier is conditioned upon receipt of the payment from any other party including a private or public owner, shall not be a defense by the party responsible for payment to a claim" if that party is other than the contractor. Burns Ind. Code Ann. § 32-28-318: An obligor's receipt of payment from a third person may not: (1) be a condition precedent to; (2) limit; or (3) be a defense to; the provider's right to record or foreclose a lien against the real estate that was improved by the provider's labor, material, or equipment. CASE LAW Pay-when-paid language may establish a condition precedent to payment if the intent of the parties was to create such a condition. Premier Elec. Constr. Co. v. American Nat'l Bank of Chicago, 656 N.E. 2d 157 (Ill. Ap. Ct. 1995). Clause setting the time to pay subcontractor after the last payment received by the contractor merely established a reasonable time for payment and did not create a condition precedent to payment. Midland Eng. Co. v. John A. Hall Constr. Co., 398 F. Supp. 981 (N.D. Ind. 1975) Clause setting a time for payment after payment by the owner establishes a reasonable time for payment by the contractor to the subcontractor. Grady v. S.E. Gustafson Constr. Co., 103 N.W.2d 737 (Iowa 1960) Clause setting a time for payment after payment by the owner establishes a reasonable time for payment by the contractor to the subcontractor. Shelley Electric, Inc. v. United States Fidelity & Guaranty Co., 1992 U.S. Dist. LEXIS 16978 (D. Kan. Oct. 16, 1992). Clause setting a time for payment after payment by the owner establishes a reasonable time for payment by the contractor to the subcontractor. A. L. Pickens Co. v. Youngstown Sheet & Tube Co., 650 F.2d 118, 120 (6th Cir. 1981) 4 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State Louisiana "PAY IF PAID" Enforced If Explicit X "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment STATUTORY PROVISIONS Pay when paid clause sets a reasonable time for payment and does not set a condition precedent to payment of a subcontractor. Southern States Masonry, Inc v. J.A. Jones Constr. Co., 507 So. 2d 198 (La. 1987). X Maine Maryland X X Massachusetts X X Michigan X X CASE LAW Md. REAL PROPERTY Code Ann. § 9-113: Contingent Payment clauses will not prevent collection from other sources such as a property owner or a contractor's bond. Properly worded "pay-if-paid" clause will create a condition precedent to the subcontractor's payment. Imagine Constr., Inc. v. Centex Landis Constr. Co., Inc., 707 So. 2d 500 (La. App. 1998). No cases or statutes concerning contingent payment clauses. In order to shift the risk of owner non-payment to the subcontractor, the subcontract must have an express unambiguous provision shifting that risk. Gilbane Bldg. Co. v. Brisk Waterproofing Co., 585 A.2d 248 (Md. 1991). Pay when paid clause does not create a condition precedent for payment to subcontractor but establishes reasonable time for payment. Pay-if-paid clause would create a condition precedent if the language were sufficiently clear. A.J. Wolfe Co. v. Baltimore Contractors, Inc., 244 N.E.2d 717 (Mass. 1969) Language specifying that "receipt of payments…being a condition precedent to payments of the subcontractor" enforced as a valid "pay-if-paid" clause. Berkel & Co. Contractors v. Christman Co., 210 Mich App. 416 (1995). 5 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State Minnesota "PAY IF PAID" Enforced If Explicit X "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment STATUTORY PROVISIONS X Minn. Stat. § 337.10 (3): Provisions contained in, or executed in connection with, a building and construction contract requiring a contractor, subcontractor, or material supplier to waive the right to a mechanics lien or to a claim against a payment bond before the person has been paid for the labor or materials or both that the person furnished are void and unenforceable. Mississippi X X Missouri X X Montana Mo. Rev. Stat. § 429.005:"Pay if paid" clauses will not provide protection to land owners, as prepayment waivers of lien rights are void as against public policy. Mont. Code Ann. § 28-2-2103 (2) (a): Within 7 days after a contractor receives payment from an owner, the contractor shall pay the subcontractor. CASE LAW Conditions precedent are not favored in the law and a contract that does not explicitly create a condition precedent will be construed to merely establish a reasonable time for payment. Mrozik Constr., Inc. v. Lovering Assoc., Inc., 461 N.W.2d 49 (Minn. Ct. App. 1990). Conflicting payment language in a contract will not allow contractor to delay payment for more than a reasonable time following the completion of subcontractor's work. Nicholas Acoustics & Specialty Co. v. H.M. Constr. Co., Inc., 695 F. 2d 839 (5th Cir. 1983) (applying Mississippi law). Even where the "pay if paid" clause is itself unambiguous, other seemingly contradictory clauses in a contract can cause the "pay if paid" clause to merely establish a reasonable time for payment. Meco Sys., Inc. v. Dancing Bear Entertainment, 42 S.W.3d 794, 808 (Mo. Ct. App. 2001). Montana courts have yet to address this issue, but the strongly written statutory language is similar to that in states, such as California, that have found "payif-paid" clauses unenforceable. Mont. Code Ann. § 28-2-723: "A construction contract may not contain provisions requiring a [party] to waive the right to a construction lien or … payment bond before the [party] has been paid." 6 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State Nebraska "PAY IF PAID" Enforced If Explicit X Nevada "PAY WHEN PAID" Suggests Time for Payment X New Jersey X STATUTORY PROVISIONS X X New Hampshire New Mexico "PAY WHEN PAID" And "PAY IF PAID" Treated Same The Nevada Supreme Court interprets Nev. Rev. Stat. Ann. §§ 624.624-624.626 as making void any contractual provision that conditions payment to a subcontractor upon the receipt of payment by the prime contractor. CASE LAW Clause that does not unambiguously create a condition precedent for payment merely establishes a reasonable time for the contractor to pay the subcontractor. D. K. Meyer Corp. v. Bevco, Inc., 292 N.W.2d 773 (Neb. 1980). Lien waiver and pay-if-paid provisions are unenforceable based upon Nevada's public policy favoring the statutory right to a mechanic's lien. Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 2008 Nev. LEXIS 46 (Nev. 2008) Courts require specific language such as "if" or "on the condition that" to find that a contract contains a condition precedent. Holden Eng. and Surveying Inc. v. Pembroke Rd. Realty Trust, 137 N.H. 393 (1993). X X Contractor cannot withhold payment from subcontractor where contractor fails to seek approval of subcontractor's work from architect. D.M. Holden, Inc. v. Contractors' Crane Service, Inc. 121 N.H. 831 (1981). Clause setting time for payment to subcontractor after the contractor received payment merely establishes a reasonable time for payment from the contractor to the subcontractor. Seal Title Corp. v. Ehret. Inc., 589 F. Supp. 701 (D. N.J. 1984). No court in New Mexico has yet to address the issue of contingent payment clauses. 7 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State "PAY IF PAID" Enforced If Explicit "PAY WHEN PAID" And "PAY IF PAID" Treated Same New York "PAY WHEN PAID" Suggests Time for Payment X North Carolina X STATUTORY PROVISIONS NY Lien Law § 34: Any contractual provision waiving a subcontractor's right to a lien against a property is void. The Court of Appeals has interpreted these provisions to void all "pay if paid" clauses in subcontracts. N.C. Gen. Stat. § 22C-2: "Payment by the owner to a contractor is not a condition precedent for payment to a subcontractor…and an agreement to the contrary is unenforceable." N.C. Gen. Stat. § 22C-3: "The contractor shall pay to his subcontractor…within seven days of receipt by the contractor…of each periodic or final payment." North Dakota Ohio X X Ohio Rev. Code § 4113.62(E): "Pay if paid" contract provisions will not prevent the subcontractor from filing a mechanic's lien. CASE LAW Two sophisticated commercial entities can overcome New York's public policy against "pay if paid" clauses by including a choice of law clause that favors the law of a jurisdiction that permits such contingent payment clauses. (If the contract was entered into before the Prompt Payment Act's prohibition of choice of law clauses went into effect in 2003). Welsbach Elec. Corp. v. MasTec N. Am., Inc., 2006 NY Slip Op 8632, 1 (N.Y. 2006). "Pay-when-paid" clauses, like "pay-if-paid" clauses, are unenforceable. Am. Nat'l Elec. Corp. v. Poythress Commer. Contrs., Inc., 167 N.C. App. 97, 101 (N.C. Ct. App. 2004). North Dakota courts have yet to address contingent payment clauses. "Pay when paid" clause of a contract establishes a reasonable time for payment but does not set a condition precedent for payment to a subcontractor. Chapman Excavating Co. v. Fortney & Weygandt, Inc., 2004 Ohio 3867 (2004) (following the rationale from Thos. J. Dyer Co. v. Bishop International Engineering Co., 303 F.2d 655 (6th Cir. 1962)). 8 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State "PAY IF PAID" Enforced If Explicit "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment Oklahoma X X Oregon X X Pennsylvania X Rhode Island X South Carolina South Dakota X STATUTORY PROVISIONS Okla. Stat. tit. 61 § 224: "If a subcontractor … has performed … the prime contractor shall make payment to the subcontractor … no later than ten (10) calendar days after the prime contractor receives its corresponding payment for the work performed." Or. Rev. Stat. § 701.630: "The original contractor shall pay to the subcontractor …the full amount received for such subcontractor's work and for materials and products supplied based on the subcontract or purchase order terms and conditions within seven days of receipt by the original contractor." 62 Pa. Cons. Stat. § 3933 (c): The subcontractor shall be paid "the full or proportional amount received for each subcontractor's work and material…14 days after receipt of a progress payment." X S.C. Code Ann. § 29-6-230: Owner payment to the contractor cannot be a condition precedent to the subcontractor's payment. CASE LAW Clause setting the time for payment of a subcontractor after the contractor has received payment does not create a condition precedent to payment. It merely establishes a reasonable time for payment from the contractor to the subcontractor. Byler v. Great American Ins. Co. 395 F.2d 273 (10th Cir. 1968) (applying Oklahoma law). Any intention to shift the risk of a construction project from the contractor to the subcontractor must be evidenced by unambiguous language. Language that appears only to set a time for payment will not be construed to establish a condition precedent for payment. Mignot v. Park Hill, 391 P.2d 755 (Oregon 1964). If the intent of the parties is unambiguous, a "pay-if-paid" clause will establish a condition precedent to payment. C.M. Eichenlaub Co. v. Fid. & Deposit Co., 437 A.2d 965 (Pa. Super. Ct. 1981). When there is clear evidence that the parties intended to establish a condition precedent, no payment must be made until that condition has been satisfied. Rotelli v. Catanzaro, 686 A. 2d 91 (R.I. 1996). Clause setting the time for payment of a subcontractor after the contractor has received payment merely establishes a reasonable time for payment from the contractor to the subcontractor. Elk & Jacobs Drywall v. Town Contractors, Inc., 229 S.E.2d 260 (1976). South Dakota courts have yet to address contingent payment clauses. 9 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State "PAY IF PAID" Enforced If Explicit "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment Tennessee X X Texas X X Utah Vermont Virgin Islands X X X STATUTORY PROVISIONS Utah Code Ann. § 13-8-4 (3)(a): The existence of a contingent payment contract is not a defense to a claim to enforce a mechanics' lien filed under Title 38, Chapter 1, Mechanics' Liens. Vt. Stat. tit. 9 § 4003: "Notwithstanding any contrary agreement, when a subcontractor has performed in accordance with the provisions of its contract, a contractor shall pay to the subcontractor…the full or proportional amount…seven days after receipt of each progress or final payment or seven days after receipt of the subcontractor's invoice, whichever is later." V.I. CODE ANN. tit. 28, §§ 251 270: Courts in the Virgin Islands have interpreted the construction lien law in that district to preclude any contractual defense in actions to recover payment for completed work. CASE LAW Clause setting the time for payment of a subcontractor after the contractor has received payment does not create a condition precedent to payment. It merely establishes a reasonable time for payment from the contractor to the subcontractor. Koch v. Construction Tech., 924 S.W.2d 68 (Tenn. 1996). Clause reading "contractor will pay [for work for which] payment has been made by the owner] does not establish a condition precedent to payment. Sheldon L. Pollack Corp. v. Falcon Industries, Inc., 794 S.W.2d 380, 383 (Tex. App. Corpus Christi 1990). "Pay when paid" provisions do not create conditions precedent to the payment of subcontractors. Zions First Nat'l Bank v. Christiansen Bros., Inc., 66 F.3d 1560 (10th Cir. 1995). Vermont courts have not yet interpreted the prompt payment statute. It is unclear whether a "pay-if-paid" clause would be enforced in the state. When a subcontract includes a clause that makes payment to the subcontractor contingent upon payment by the owner to the contractor, that clause is void and against the public policy enumerated in Construction Lien Law. Shearman & Assocs. v. Continental Cas. Co., 901 F. Supp. 199. 10 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State "PAY IF PAID" Enforced If Explicit "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment Virginia X X Washington X X West Virginia X STATUTORY PROVISIONS CASE LAW In the absence of evidence of contrary intent, a "pay when paid" provision will be treated to only establish a reasonable time for payment from the contractor to the subcontractor, and not to create a condition precedent to payment. James River Iron, Inc. v. Turner Constr. Co., 2004 Va. Cir. LEXIS 230 (Va. Cir. Ct. Sept. 30, 2004). Contract specifying that the subcontractor would receive payment only "to the extent that the Contractor has received payment" did not create a condition precedent to the subcontractor's payment. It simply established a reasonable time in which the subcontractor could be paid. Amelco Elec. v. Donald M. Drake Co., 20 Wn. App. 899 (Wash. Ct. App. 1978). "Pay if paid" provisions in a subcontract will not only insulate the contractor from liability to the subcontractor if the contractor is not paid, but the provision will also protect the contractor's surety. Wellington Power Corp. v. CNA Sur. Corp., 217 W. Va. 33, 41 (W. Va. 2005). 11 CONTINGENT PAYMENT CLAUSES IN THE 50 STATES State Wisconsin Wyoming "PAY IF PAID" Enforced If Explicit "PAY WHEN PAID" And "PAY IF PAID" Treated Same "PAY WHEN PAID" Suggests Time for Payment X STATUTORY PROVISIONS Wis. Stat. § 779.135: "The following provisions in contracts for the improvement of land in this state are void: (1) Provisions requiring any person entitled to a construction lien to waive his or her right to a construction lien…before he or she has been paid for the labor. (2) Provisions making the contract subject to the laws of another state or requiring that any litigation, arbitration or other dispute resolution process on the contract occur in another state. (3) Provisions making a payment to a prime contractor…a condition precedent to a prime contractors payment to a subcontractor. This subsection does not prohibit contract provisions that may delay a payment to a subcontractor until the prime contractor receives payment." Wyo. Stat. § 16-6-602: For a public contract, contractors must be paid within 45 days of the receipt of the invoice. CASE LAW A "pay when paid" provision will not provide a defense to a contractor in a suit with a subcontractor once the contractor has been paid, at least in part. Marino Constr. Co. v. Renner Architects, 214 Wis. 2d 589 (Wis. Ct. App. 1997). Wyoming courts have not addressed whether contingent payment clauses are enforceable. 12