EMPLOYER’S RIGHTS AND CONTRACTOR’S LIABILITIES IN RELATION TO CONSTRUCTION DEFECTS AFTER FINAL CERTIFICATE TAN PEI LING UNIVERSITI TEKNOLOGI MALAYSIA DEDICATION To my beloved father, mother, sister and Chee Siong Thank you for your support, guidance and everything. ACKNOWLEDGEMENTS This master project can be completed successfully due to the contribution of many people. First of all, I would like to express my highest gratitude to my supervisor, Assoc. Prof. Dr. Maizon Hashim for her patience, guidance, advice and support in order to complete this master project. Next, I would like to thank all the lecturers for the course of Master of Science (Construction Contract Management), for their patience and kind advice during the process of completing the master project. Besides that, I am deeply grateful to my family for their unconditional love and care through out the years. Unforgettable, I would like to thank Chee Siong who has given me full support during this study. Not forgetting my classmates, a token of appreciation goes to them for giving lots of advice on how to complete and write this project. ABSTRACT Most of the standard forms of contract contain provisions dealing with defective works. Defective works could be in the forms of design fault, defective building materials or bad workmanships. Any defects, shrinkages or other faults arising during construction and defects liability period due to defective materials or workmanship must be put right by the contractor at his own expense. The contract administrator will usually mark the end of the defects liability period with the issue of a further certificate, known as a Certificate of Making Good Defect. Subsequently, final certificate will be issued to the contractor stating amount finally due to him. Generally, final certificate will discharge the contractor’s liability for the defective works and the cost for remedying them. Employers will need to be wary as they can preclude the employer from claiming damages from the contractors for defects which appear after the issue of the final certificate. However, court will generally not regard a certificate as being final except where very clear words are used in the contract. This research intends to identify the legal position of the construction contract parties in relation to their rights and liabilities in defects after the issuance of Final Certificate. This research was carried out mainly through documentary analysis of law journals and law reports. Result shows that there are four circumstances to be considered when determining the liability of defects after final certificate, namely by referring to the conclusiveness evidence, consequential damages/loss, patent defects and fraud/concealment. ABSTRAK Kebanyakan borang kontrak standard mengandungi peruntukan mengenai kerja-kerja cacat. Kecacatan kerja adalah kesalahan reka bentuk, bahan binaan atau kemahiran kerja. Segala kecacatan, kekurangan atau kesalahan yang muncul semasa pembinaan dan tempoh liabiliti kecacatan yang disebabkan oleh kecacatan bahan atau kemahiran kerja mesti dibetulkan oleh kontraktor dengan perbelanjaannya sendiri. Pentadbir kontrak akan menandakan akhirnya tempoh liabiliti kecacatan dengan perakuan siap memperbaiki kecacatan. Kemudian, perakuan muktamad akan dikeluarkan dengan menyatakan jumlah akhir yang dijangka untuk kontraktor. Secara umum, perakuan muktamad akan melepaskan liabiliti kontraktor untuk kerjakerja cacat dan kos untuk memperbaikinya. Majikan perlu berhati-hati kerana ini boleh menghalang majikan daripada menuntut ganti rugi daripada kontraktor jika kecacatan berlaku selepas perakuan muktamad. Bagaimanapun, mahkamah tidak akan menganggap satu perakuan sebagai satu keterangan yang tidak boleh dipertikaikan kecuali perkataan yang jelas digunakan dalam kontrak. Kajian ini bertujuan untuk mengenalpasti kedudukan sah pihak-pihak kontrak pembinaan berkaitan dengan hak-hak dan liabiliti dalam kecacatan kerja yang berlaku selepas pengeluaran perakuan muktamad. Kajian ini telah dijalankan dengan menganalisis laporan undang-undang. Keputusan menghasilkan empat keadaan yang dipertimbangkan dengan liabiliti kecacatan kerja selepas perakuan muktamad, iaitu dengan merujuk kepada bukti jilid, kerosakan/kerugian akibat, kecacatan jenis ‘latent’ dan penipuan/penyembunyian yang jelas. TABLE OF CONTENTS CHAPTER 1 2 TITLE PAGE DECLARATION ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF TABLES xi LIST OF FIGURES xii LIST OF CASES xiii LIST OF ABBREVIATIONS xvi INTRODUCTION 1 1.1 Background Studies 1 1.2 Problem Statement 5 1.3 Objective of Research 7 1.4 Scope of Research 8 1.5 Importance of Research 8 1.6 Research Methodology 9 DEFECTIVE WORKS 11 2.1 Introduction 11 2.2 Type of Defects 13 CHAPTER TITLE 2.3 2.4 PAGE Nature of Defects 15 2.3.1 Standard of Design 17 2.3.2 Quality of the Building Materials 19 2.3.3 Quality of the Workmanship 20 Liability for Defects 21 2.4.1 Defects discovered during the Construction Period 23 2.4.2 Defects Discovered during Defects Liability 24 Period 2.5 2.6 3 2.4.3 Defects Discovered after the Final Certificate 25 Contractor Obligations after Completion 27 2.5.1 Defects Liability Period 27 2.5.2 Procedural Requirements 31 Conclusion 35 LIABILITY OF DEFECTS 36 3.1 Introduction 36 3.2 Certificate of Making Good Defects 38 3.3 Final Certificate 39 3.3.1 Express Contractual Provisions 41 3.3.2 Conclusiveness of Final Certificate 46 Defects Arising After Issue of Certificate of Making Good 47 3.4 Defects/Final Certificate 3.5 4 3.4.1 Cause of Action in Contract 49 3.4.1 Cause of Action in Tort 50 3.4.1 Postponement of the Limitation Period 52 Conclusion 53 EMPLOYER’S RIGHTS AND CONTRACTOR’S LIABILITIES 55 IN RELATION TO CONSTRUCTION DEFECTS AFTER FINAL CERTIFICATE 4.1 Introduction 55 CHAPTER TITLE 4.2 PAGE Conclusiveness of Final Certificate 56 4.2.1 James Png Construction Pte Ltd v Tsu Chin Kwan Peter 56 4.2.2 Shen Yuan Pai v Dato Wee Hood Teck & Ors 58 4.2.3 Sa Shee (Sarawak) Sdn Bhd v Sejadu Sdn Bhd 60 4.2.4 Chew Sin Leng Construction Co v Cosy Housing 61 Development Pte Ltd 4.2.5 Usahabina v Anuar Bin Yahya 62 4.2.6 P & M Kaye Ltd v Hosier & Dickinson Ltd 63 4.2.7 Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd 65 4.2.8 University Fixed Assets Limited v Architects 66 Design Partnership 4.2.9 Crown Estate Commissioners v John Mowlem and 68 Co Ltd 4.3 Consequential Loss 69 4.3.1 Teh Khem On & Anor v Yeoh & Wu 69 Development Sdn Bhd & Ors 4.3.2 James Png Construction Pte Ltd v Tsu Chin Kwan 71 Peter 4.3.3 Shen Yuan Pai v Dato Wee Hood Teck & Ors 72 4.3.4 P & M Kaye Ltd v Hosier & Dickinson Ltd 72 4.3.5 HW Nevill (Sunblest) Ltd v William Press & Son 73 Ltd 4.4 Latent Defects 75 4.4.1 P & M Kaye Ltd v Hosier & Dickinson Ltd 75 4.4.2 London Borough of Barking and Dagenham v 76 Terrapin Construction Ltd 4.5 4.4.3 Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd 77 Fraud / Concealment 79 4.5.1 Musselburgh and Fisherrow Co-operative Society 79 v Mowlem Scotland CHAPTER TITLE PAGE 4.5.2 William Hill Organisation Ltd v Bernard Sunley 81 and Sons Ltd 4.6 5 Conclusion 83 CONCLUSION AND RECOMMENDATION 85 5.1 Introduction 85 5.2 Summary of Research Findings 85 5.3 Problem Encountered During Research 88 5.4 Further Studies 89 5.5 Conclusion 89 REFERENCE 91 LIST OF TABLES TABLE NO. 5.1 TITLE Summary of Research Findings PAGE 86 LIST OF FIGURES FIGURE NO. TITLE PAGE 1.1 Practical Completion and Defects Liability 5 1.2 Flow chart of research methodology 10 LIST OF CASES CASES Abdul Gaffar v Chua Kwang Yong [1994] 2 SLR 546 53 Adcock’s Trustee v Bridge R.D.C.[1911] 75 J.P. 241 19 Archer v Moss [1971] 3 BLR 1 53 Aubum Municipal Council v ARC Engineering Pty Ltd [1973] NSWLR 513 18 Bagot v Stevens, Scanlan and Co [1964] 2 Lloyd’s Rep 353 49 Bolton v Mahadeva [1972] 2 All ER 1322 22 Carr v JA Berriman Pty Ltd [1953] 27 ALJR 273 32 Chew Sin Leng Construction Co v Cosy Housing Development Pte Ltd [1988] 1 MLJ 137 61 Crown Estate Commissioners v John Mowlem and Co Ltd [1994] 70 BLR 1 68 Dancom Engineering Pte Ltd v Takasago Thermal Engineering Co Ltd 1989 BLD [May] 606 Dutton v Bogner Regis United Building Co Ltd & Anor [1972] 1 QB 373 16 49, 50 Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1973] 3 WLR 42137 Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners [1975] 1 WLR 1095 17 H W Nevill (Sunblest) Ltd v William Press and Son Ltd [1981] 20 BLR 78 Hancock v Brazier [1966] 2 All ER 901 26, 73 37 Hancock v BW Brazier (Anerly) Ltd [1966] 2 All ER 901, [1966] 1 WLR 1317 20, 21 Hii Soo Chiong v Board of Management [1973] 2 MLJ 204 15 Hoenig v Issacs [1952] 2 All ER 176 21 IBA v EMI Electronics Ltd & BICC Construction Ltd [1980] 14 BLR 1 18 James Png Construction Pte Ltd v Tsu Chin Kwan Peter [1991] 1 MLJ 449 56, 71 Kabatasan Timber Extraction Co v Chong Fat Shing [1969] 2 MLJ 6 34 Kemayan Construction Sdn Bhd v Prestara Sdn Bhd [1997] 5 MLJ 608 30 Khong Seng v Ng Teong Kiat Biscuit Factory Ltd [1963] MLJ 388 20 Leo Teng Choy v Bectile Construction [1982] 2 MLJ 302 15 London Borough of Barking and Dagenham v Terrapin Construction Ltd [1972] 1 WLR 146 76 Lynch v Thorne [1956] 1 WLR 303 21 Martin v McNamara [1951] QSR 225.8 Butterworths 19 Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd [1997] 87 BLR 96 65, 77 Miller v Krupp [1992] 11 B.C.L.74 23 Musselburgh and Fisherrow Co-operative Society v Mowlem Scotland [2006] CSOH 39 79 Oldschool v Gleeson (Construction) Ltd [1976] 4 BLR 103, 131 18 P & M Kaye Ltd v Hosier & Dickinson Ltd [1972] 1 WLR 146 63, 72, 75 P&M Kaye Ltd v Hosier & Dickinson Ltd [1972] 2 All ER 121 39, 43, 46, 47 P&M Kaye Ltd v Hosier & Dickson Ltd [1972] 1 W.L.R. 146 25, 26, 29 Pearce & High Limited v Baxter [1969] 2 MLJ 6, [1999] BLR 101 32, 34, 35 Pirelli General Cable Works Ltd v Oscar Faber & Partners [1983] 2 AC 1 51 Rumbelows Ltd v Firesnow Sprinkler AMK and Installations Ltd [1980] 19 BLR 25 20 Sa Shee (Sarawak) Sdn Bhd v Sejadu Sdn Bhd [2000] 5 MLJ 414 60 Sequerah Stephen Patrick v Penang Port Commission [1990] 2 MLJ 232 53 Shen Yuan Pai v Dato Wee Hood Teck [1976] 1 MLJ 16 44, 58, 72 Sparham-Sounter v Town & Country Development (Essex Ltd) [1976] 3 BLR 70 50 Steven Phoa Cheng Loon &72 Ors v Highland Properties Sdn Bhd & 9 Ors [2000] AMR 3567 51 Sutcliffe v Chippendale & Edmondson [1971] 18 BLR 149 22 Teh Khem On & Anor v Yeoh & Wu Development Sdn Bhd & 3 ors [1995] 2 AMR 1558 by analogy 44, 69 University Fixed Assets Limited v Architects Design Partnership [1999] 64 Con LR 12 66 Usahabina v Anuar Bin Yahya [1998] 7 MLJ 691 62 William Hill Organisation Ltd v Bernard Sunley and Sons Ltd [1982] 22 BLR 1 81 William Tomkinson & Sons v Parochial Church Council of St Michael [1990] 6 Const. LJ 319, 814 Young and Marten Ltd v Mc Manus Child Ltd [1969] 1 AC 454 24, 30, 34 19, 20 LIST OF ABBREVIATIONS AC Appeal Cases, House of Lords All ER All England Law Reports ALJR Australia Law Journal Reports AMR All Malaysia Reports BCL Building and Construction Law Cases BLR Building Law Reports Con LR Construction Law Reports CSOH Court of Session (Outer House) ER Equity Reports ICR Industrial Cases Reports ILR International Law Reports IR Irish Reports JP Justice of the Peace / Justice of the Peace Reports LIL Rep Lloyd’s List Reports Lloyd’s Rep Lloyd’s List Reports MLJ Malayan Law Journal NSWLR New South Wales Law Reports QB Law Reports: Queen’s Bench Division QSR Queensland State Reports SC Session Cases SCR Supreme Court Reporter SLR Singapore Law Reports WLR Weekly Law Report 1 CHAPTER 1 INTRODUCTION 1.1 Background Studies Construction in Malaysia spans a wide spectrum of activities stretching from simple renovation works for private homes to massive construction projects. Every such building activity may create its own unique set of requirements and circumstance. The different sectors including employer groups, contractors, suppliers, manufacturers, professionals have their own interests which are very often divergent and competing in nature.1 Most formal building or engineering contracts contain an initial express obligation of the contractor in some such words as to “carry out and complete the works in accordance with the contract”. This is, in fact a dual obligation that is, both to carry out and to complete the works.2 The contractor’s basic obligation, so far as the standard of work is concerned, is to comply with the terms of the contract. This includes both express terms (such as the requirement of contract that work shall be of 1 Sundra Rajoo. “The Malaysian Standard Form of Building Contract (the PAM 1998 Form).” 2nd Edition. (Malayan Law Journal Sdn Bhd, 1999). pp. 3 2 I. N. Duncan Wallace. “Hudson’s Building and Engineering Contracts.” 11th Edition. (Sweet & Maxwell, 1995) pp. 472 2 the standards described in the bills) and implied terms (such as the principle that all materials shall be of ‘satisfactory quality’).3 In a construction contract, a contractor undertaking to do work and supply materials impliedly undertakes4: a) to do the work undertaken with care and skill or, as sometimes expressed, in a workmanlike manner; b) to use materials of good quality. In the case of materials described expressly this will mean good of their expressed kind and free from defects. (In the case of goods not described, or not described in sufficient detail, there will be reliance on the contractor to that extent, and the warranty (c) below will apply); c) that both the workmanship and materials will be reasonably fit for the purpose for which they are required, unless the circumstances of the contract are such as to exclude any such obligation (this obligation is additional to that in (a) and (b), and will only become relevant, for practical purposes in any dispute, if the contractor has fulfilled his obligations under (a) and (b)). The contractor’s obligation only comes to an end when the Certificate of Practical Completion is issued. Only defects due to workmanship and materials not in accordance with the contract are required to be made good at the contractor’s cost. In the context of defective work, the express or implied obligation to carry out and complete the works in accordance with the contract imposes a continuity dual obligation, and not merely, as in other contracts for work and materials where work is not carried out on and fixed to the owner’s land as it progresses, a single 3 Murdoch, J and Hughes, W. “Construction Contracts: Law and Management.” (London: Spon Press, 2000) pp. 147 4 I. N. Duncan Wallace. Supra 2. pp. 519. 3 ultimate obligation to handover and deliver a final conforming product or article on completion.5 In addition to this principal express or implied obligation to complete, formal English-style contracts may make express reference to “substantial completion” or “practical completion”. These definitions are often used in formal contracts to denote the start of the maintenance or “defects liability” period and to secure the release to the contractor of the first portion of any “retention moneys”. In general, what is contemplated by these expressions is a state of apparent completion free of known defects which will enable the owner to enter into occupation and make use of the project, with the result that they will usually bring any possible liability of the contractor for liquidated damages for delay to an end. The scheme of this type of contract thus contemplates the commencement of a period when the owner enters into occupation but at the end of which any then known omissions or defects will be made good by the contractor.6 In most of the standard form of building or engineering contract, there are provisions dealing with defective works. Defective works could be in the forms of design fault, defective building materials or bad workmanships. In construction contracts, the works cannot be said to have been practically completed, if the work is so defective that it would prevent the owner from using the building as intended by the contract. For example, sub-clause 15.1 of PAM 1998 form of contract specifies that the works shall be deemed to be practically completed if the architect is of the opinion that all necessary works specified by the contract have been completed and the defects existing in such works are ‘de minimis’.7 Clause 45(a) of JKR 203 form of contract specifies that the contractor is responsible for any defect, imperfection, shrinkage, or any other fault which appears during the Defects Liability Period, which will be six (6) months from the day named in the Certificate of Practical Completion issued, unless some other period is specified in the Appendix.8 Similarly in CIDB 2000 form of contract, Clause 27.1 specifies that the contractor shall 5 I. N. Duncan Wallace. Supra 2. pp. 473 I. N. Duncan Wallace. Supra 2. pp. 474 7 Mohd Suhaimi Mohd Danuri. “The Employer’s Rights and the Contractor’s Liabilities in Relation to the Defects Liability Period.” (The Malaysian Surveyor. 39.1, 2005). pp. 54 8 Lim Chong Fong. “The Malaysian PWD Form of Construction Contract.” (Malaysia: Sweet & Maxwell Asia, 2004) pp. 105 6 4 complete any outstanding work and remedying defects during the Defects Liability Period. Once the works have been practically completed and the Certificate of Practically Completion issued, the Defects Liability Period will begin. Any defects, shrinkages or other faults arising during this period due to defective materials or workmanship must be put right by the contractor at his own expense.9 For example, sub-clause 9(a) of PWD 203A requires the contractor to use materials and workmanships that comply with the specification, further, sub-clause 9(b) entitles the superintendent to instruct the contractor to demolish or open up the work done and the associated cost will be borne by the contractor if the works have not carried out in accordance with the contract. The contract administrator will usually mark the end of the defects liability period with the issue of a further certificate, known as a Certificate of Making Good Defect. This record the contract administrator’s opinion that defects appearing within the Defects Liability Period and notified to the Contractor have been duly made good. The contractor is then entitled to the remainder of the retention money. This last portion of the retention is the amount finally due to the contractor. It is the contract administrator’s obligation to issue the Final Certificate that signifies his satisfaction with the work. 9 Murdoch, J and Hughes, W. Supra 3. pp. 184 5 Contractor carries out and completes the works as stipulated in the contract Contractor’s work is to the reasonable satisfaction of the contract administrator CERTIFICATE OF PRACTICAL COMPLETION Contract administrator specifies all defects and requires defects to be made good CERTIFICATE OF MAKING GOOD DEFECTS FINAL CERTIFICATE Figure 1.1 1.2 Practical Completion and Defects Liability10 Problem Statement In Malaysia, section 74(3) of Contracts Act 1950 (Revised 1974) provides that the innocent party is entitled to get compensation for the failure of the defaulting party to discharge the obligation created by the contract. Therefore, the failure of the contractor to rectify the defects appear during Defect Liability Period (DLP) as required by the contract would constitute a breach of contract that entitles the employer to be remedied in the forms of damages. If the contractor has failed to rectify the defects as instructed by the contract administrator, the owner is entitled to 10 Sundra Rajoo. Supra 1. pp. 147 6 appoint another contractor and recover the cost of rectifying the defects to the original contractor.11 However, Employers will need to be wary of Final Certificates as they can preclude the Employer from claiming damages from the Contractor for defects which appear after the issue of the Final Certificate. Generally, a Final Certificate will be binding and conclusive and cannot be opened up except in the cause of fraud. However, court will generally not regard a certificate as being final except where very clear words are used. Therefore, the conclusiveness of the Final Certificate depends upon the terms of the particular contract.12 Both PAM 1998 (Clause 30.8) and JKR 203 (Clause 49) form of contract states that “No certificate….shall be considered as conclusive evidence as to the sufficiency of any work, materials or goods to which it relates ….” This clause primarily states that none of the certificates issued under the contract would be treated as conclusive evidence as to the sufficiency of any work done, or material or goods supplied, which is the subject matter of the certificate. The contents of the certificates will not be final and binding in any dispute between the parties either in arbitration or in court. In other words, all certificates can be opened up, reviewed and revised by the arbitrator or the court.13 However, the provision in the CIDB 2000 form of contract is different with PAM 1998 and JKR 203. Clause 43.2 of CIDB 2000 states that the Final Certificate, unless either party commences any mediation, arbitration or other proceedings within 30 days after such certificate, shall be conclusive evidence that the works are executed to the reasonable satisfaction of the Superintending Officer and/or Employer. 11 Mohd Suhaimi Mohd Danuri. Supra 7. pp. 57 Mallesons Stephen Jaques, 2003. “Defects Liability Period - an introduction. Asian Projects and Construction Update.” http://www.mallesons.com/publications/Asian_Projects_and_Construction_Update/6881582W.htm 13 Lim Chong Fong. Supra 8. pp. 114 12 7 There is existence of problems arise in relation to the conclusiveness of the Final Certificate. The first is whether the Employer is prevented from recovering damages for any defects which appear after the issuance of the Final Certificate? The second is whether the contractor is liable for defects which come to light after the issuance of Final Certificate? And ultimately, whether the contractor or the employer is liable for defects which come to light after the issuance of Final Certificate? In view of the above, it is important for the contracting parties in the construction industry, especially the clients and the contractors, to have a complete understanding to their rights and liability in relation to the defects which appear after the issuance of Final Certificate. 1.3 Objective of Research From the problem statement above, this research is prepared with an objective: To identify the legal position of the construction contract parties in relation to employer’s rights and contractor’s liabilities in defects after the issuance of Final Certificate. 8 1.4 Scope of Research Given the legalistic nature of this research, the approach adopted in this research is based on case-law. The scope of this research will cover the following areas: a) Only construction cases will be discussed in the research. b) Court cases referred in this research include Malaysia, Singapore, and English cases. c) Standard forms of contract commonly referred to and examined in this research are Pertubuhan Arkitek Malaysia (PAM) (2nd Edition, 1998), Public Works Department (P.W.D) Form 203A and Construction Industry Development Board (CIDB) Standard Form of Contract for Building Works (2000 Edition). 1.5 Importance of Research This research will deal closely with specific issues or problems arise between the contract parties with regards to construction defect after expiry of Defect Liability Period (DLP). The author aims to assist both clients and contractors in the construction industry to understand their rights and liability in relation to defects which come to light after the issue of the Final Certificate. This research is also to increase the awareness of the construction parties about their legal position in the liability of defect, so that unnecessary disputes can be avoided and assuring project success and tie-up a better relationship among the contractual parties. 9 1.6 Research Methodology In order to achieve the research objectives, a systematic process of conducting this research had been organised. The detail methodology is divided into several essential steps as described below (see figure 1.2 also). Firstly, initial literature review was done in order to obtain the overview of the concept of this topic. Discussions with supervisor, lecturers, as well as course mates, were held so that more ideas and knowledge relating to the topic could be collected. The issues and problem statement of this research will be collected through books, journal, cases, articles and magazines. The objective of this research will be formed after the issue and problems had been identified. The next stage is the data collection stage. After the research issue and objectives have been identified, various documentation and literature review regarding to the research field will be collected to achieve the research objectives. Generally, primary data is collected from Malayan Law Journals and other law journals via UTM library electronic database, namely Lexis-Nexis Legal Database. The secondary sources include books, articles, seminar papers, newspaper as well as information from electronic media database on the construction contract law. These sources are important to complete the literature review chapter. After the data collection stage, the author will analyse all the collected cases, information, data, ideas, opinions and comments. This is started with the case studies on the related legal court cases. The analysis will be conducted by reviewing and clarifying all the facts and issues of the case. The final stage of the research process mainly involved the writing up and presenting the research findings. The author will review the whole process of the 10 research with the intention to identify whether the research objectives have been achieved. Conclusion and recommendations will be made based on the findings during the stage of analysis. Literature Review Books, articles, journals, internet sources INITIAL STAGE Brief Discussion Discussion with lecturers, supervisor and coursemates Formation of issues, objective and scope of research DATA COLLECTION & ANALYSIS STAGE Identify type of data needed and data sources Law Journals, e.g. Malayan Law Journal, Singapore law Report, Building Law Report, etc Books, articles, seminar papers, newspaper Internet sources Data Recording Data Arrangement Analyse data Research writing up and presenting findings FINAL STAGE Conclusion and recommendation Final report preparation and checking Figure 1.2 Flow chart of research methodology 11 CHAPTER 2 DEFECTIVE WORKS 2.1 Introduction Defective work can be described as work which fails to comply with the express descriptions or requirements of the contract, including very importantly any drawings or specifications, together with any implied terms as to its quality, workmanship, performance or design. By definition, therefore, defects are breaches of contract by the contractor14. Most standard forms of construction contract will contain express terms concerning the removal and replacement of defective work during construction. The usual scheme of such contracts is to confer express powers on the owner or his architect, engineer or the contract administrator for this purpose during the construction period up to the time of completion and handover.15 In addition to this, 14 15 Mallesons Stephen Jaques. Supra 11. I. N. Duncan Wallace. Supra 2. pp. 698. 12 these standard forms usually contain detailed provisions in respect of the employer’s remedies in respect of defective works, e.g.16: a) Defective work to be remedied by contractor b) Defective work to be remedied by employer if contractor fails to do so c) Employer may agree to a reduction of contract price instead of remedying the defect d) Employer may deduct the cost of remedial works from the contract price until the remedial works are carried out e) Employer to withhold retention monies, to be released upon issuance of the Certificate of Practical Completion and/or Certificate of Making Good Defects. In most situations, there is also a contract provision which requires the contractor to take full responsibility and liability for the rectification works if the defects are due to a breach of contract. Defective works are works which fails to comply with both the expressed descriptions or requirements and implied terms of the contract affecting the quality of the works, whether structural on one hand or merely decorative on the other, and whether due to faulty materials or workmanship or even design (if such design is part of contractor’s obligations under the contract).17 The general principle is that such defective works which amounts to a breach of contract would entitle the employer to claim for damages notwithstanding other contractual remedies which the employer may have under the contract or at common law. The common law, on the other hand, requires that the contractor carry out and complete the works in accordance with the contract. This obligation, whether express or implied, places an obligation on the contractor to hand over a final conforming product or article on completion. Failure to remedy the defect is a breach of contract, 16 Ong See Lian. 2005. “Defective Works.” International Conference on Construction Law & Arbitration. (26th – 28th April 2005, Kuala Lumpur.) pp. 1. 17 Ong See Lian. Ibid. pp. 1. 13 even if the defect occurred during the period of construction, i.e. prior to completion or handing over of the final works. The employer is entitles to damages.18 Once the works have been practically completed and the Certificate of Practical Completion issued, the Defect Liability Period (DLP) will begin. The Contractor will be liable to rectify the defects, which appear during DLP at the contractor’s own cost. For example, Clause 15 of PAM 1998 and Clause 45 of JKR 203 provide two ways of notifying the contractor for rectifying the defects during DLP as follows19: a) At any time during DLP, the Architect/Superintending Officer can request the contractor in writing to make good the defects within reasonable time; and b) Architect/Superintending Officer not later than 14 days after the expiry of DLP issues schedule of defects to be made good by the contractor within reasonable time; but in JKR 203 it clearly specifies that the defects to be made good by the contractor not later than 3 months after receiving the schedule. 2.2 Type of Defects Defects can be classified into two main categories, i.e. ‘Patent’ defects and ‘Latent’ defects. The first category encompasses the usual defects encountered in routine inspections. Professor Vincent Powell-Smith describes a ‘patent’ defect as20: 18 Ong See Lian. Supra 15. pp. 1. Mohd Suhaimi Mohd Danuri. Supra 7. pp. 54 20 Harbans Singh. “Engineering and Construction Contracts Management – Post Commencement Practice.” (Singapore: LexisNexis, 2003.) pp. 695 19 14 “A defect which is discoverable by reasonable inspection. In the context of engineering contracts, the term embraces all the items which the engineer or engineer’s representative must be expected to find and bring to the contractor’s attention so the remedial works can be carried out. Patent defects are plain to see, or at least, that is the theory. Whether the engineer could or should have seen defects on site during site visits has exercised more than one judicial mind…” In ‘Construction Law in Singapore and Malaysia’, the authors ascribe a rather simple definition to the term ‘patent defects’; this being21: “… a defect that can be discovered by normal examination or testing…” As to the second category of defects, i.e. ‘Latent’ defects, the same two references ascribe the following definitions/meanings22: “A defect which is not discoverable during the course of ordinary and reasonable examination but which manifests itself after a period of time. In building and civil engineering work the most common application is defects becoming apparent after the maintenance period expired.” Robinson and Lavers describe a ‘latent’ defect in the following words23: “… a defect that cannot be discovered by normal examination and testing…” In essence patent defects are defects that can be either seen or can be discovered by means of reasonable inspection, examination or testing. Hence, the 21 Nigel M Robinson. “Construction Law in Singapore and Malaysia.” 2nd Edition. (Butterworths Asia Malaysia, 1996) pp. 160 22 Harbans Singh. Supra 19. pp. 696 23 Nigel M Robinson. Supra 20. pp. 161 15 establishment of such defects is not merely confined to the defects that can be plainly seen or observed but encompasses also those that become apparent on reasonable inspection, examination and if necessary upon testing. The latter requirement to testing imposes a more onerous responsibility in terms of discoverability. In contrast, latent defects are the ones that are either inherent or those that do not manifest themselves upon reasonable examination, inspection and/or testing. These comprise defects which will become apparent or noticeable or capable of being discovered only when they become patent.24 In the definitions for both categories of defects, the emphasis is on the words ‘normal’ or ‘reasonable’ whether these can be in relation to any inspection or examination or testing in establishing the type of defect in question. The requirement therefore does not call for a meticulous or exhaustive process in establishing the said defects. The difference between these two types of defects also extends to their consequential effects especially in terms of duration of liability, with latent defects involving a longer duration both contractual and under various statutory provisions.25 2.3 Nature of Defects A ‘defect’ must be defined as a component supplied or constructed which is in some respect not in accordance with the contract, or as some action having consequences not authorised by the contract. Thus, the criteria of acceptability of performance must, in contract, be limited to those criteria expresses or implied in the contract: see Hii Soo Chiong v Board of Management26, Leo Teng Choy v Bectile Construction 27 and Dancom Engineering Pte Ltd v Takasago Thermal Engineering 24 Harbans Singh. Supra 19. pp. 696 Harbans Singh. Ibid. pp. 696 26 [1973] 2 MLJ 204 27 [1982] 2 MLJ 302 25 16 Co Ltd 28 . The implied terms require ‘merchantable quality’, ‘workmanlike’ workmanship and fitness for purpose.29 Express terms are commonly either30: a) Compliance with the contract’s specification content and the drawings; b) Satisfaction of the architect (or other supervisor); or c) Both these The construction work is defective when it does not accord with the standard that is required by the contract. For example, Clause 9(a) of JRK 203 and Clause 6.1 of PAM 1998 requires the contractor to use materials and workmanships that comply with the specifications. The obligation of the contractor to procure and achieve the specified kind and standard is an absolute one. If the contractor fails to do so, he would be in breach of contract unless the Superintending Officer is willing to permit a substitution by way of a variation instruction.31 Further, Clause 9(b) of JKR 203 and Clause 6.3 of PAM 1998 empowers the superintendent to require the contractor to demolish or open up the work done for inspection and associated cost will be borne by the contractor if the works have not been carried out in accordance with the contract. 32 The purpose for opening up and testing is to ensure that the works, materials, workmanship and goods are ‘in accordance to the contract’. If the contractor is not in default, he can recover the cost of opening up, testing and making good. He may also have a right under the contract to claim for extension of time and recover any direct loss and/or expense cause by the opening up and testing which disturb the regular progress of the works. This ensures the superintendent act with moderation.33 Generally, defects in the construction industry can be well divided into three (3) main categories34: 28 1989 BLD [May] 606 Nigel M Robinson. Supra 20. pp. 160 30 Nigel M Robinson. Ibid. pp. 160 31 Lim Chong Fong. Supra 8. pp. 29 32 Mohd Suhaimi Mohd Danuri. Supra 7. pp. 55 33 Sundra Rajoo. Supra 1. pp. 97 34 Mohd Suhaimi Mohd Danuri. Supra 7. pp. 55 29 17 2.3.1 a) Faulty design and work not in compliance with design b) Quality of the building materials c) Quality of the workmanship Standard of Design The term ‘design’ has been explained by Prof Vincent Powell-Smith as35: “A rather vague denoting a scheme or plan of action. In the construction and engineering industry, it may be applied to the works of the engineer in formulating the function, structure and appearance of a works or to a structural engineer in determining the sizes of structural members…” By that as it may, the undertaking of the design may not be confined to the employer’s designers but may be the obligation of the contractor whereby quality standards may be either36: a) Stipulated expressly in the contract, i.e. in the specifications, standards, codes of practice, etc and reaffirmed through specific clauses in the conditions of contract b) In the absence of express provisions, established by necessary implication, ie a contractor undertaking a contract on a design and build/design and construct basis implicitly warrants that where the purpose of the required works has been adequately brought to his notice, the design undertaken by him will be fit for that purpose37. 35 Harbans Singh. Supra 19. pp. 698 Harbans Singh. Ibid. pp. 698 37 Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners [1975] 1 WLR 1095 36 18 Therefore, design is wide enough to include (and include correctly) not merely structural calculations and the dimensions, shape and location of the work, but the choice of particular materials for particular functions and, similarly, the choice of particular work processes. In other words, in sophisticated contracts the designs includes the specification as well as the drawings.38 If the contractor is required to use a design and construct method, the contractor shall be responsible for the proposed design directly to the owner flowing from the breach. This is likely to arise where an architect or engineer is not engaged by the employer. Generally, design and build method imposes on the contractor a duty to ensure the building would be reasonably fit for its purpose39. However, in the traditional contracting method, the design responsibility shall remain under the responsibility of the consulting engineer or the architect. In Oldschool v Gleeson (Construction) Ltd40, Judge Stabb QC said: “The responsibility of the consulting engineer is for the design of the engineering components of the works and his supervisory responsibility is to his client to ensure the works are carried out in accordance with that design.” If the defects were proven to be faulty of engineer’s design, the owner can sue the engineer for breach of contract41. On the other hand, if the defect is flowing from the contractor’s fault such as departure from the actual design, the contractor should be liable to remedy the defect.42 38 I. N. Duncan Wallace. Supra 2. pp. 274. IBA v EMI Electronics Ltd & BICC Construction Ltd [1980] 14 BLR 1 40 [1976] 4 BLR 103, 131 41 Aubum Municipal Council v ARC Engineering Pty Ltd [1973] NSWLR 513 42 Mohd Suhaimi Mohd Danuri. Supra 7. pp. 55 39 19 2.3.2 Quality of the Building Materials Building and engineering contracts usually define with some precision in the specification or bills the materials to be used by the contractor. The contractor shall be held responsible if the building materials appear to be defective although its usage has been specified by the contract specification. Materials may be said to be of poor quality when what is meant is that they have been chosen for the wrong purpose, as common bricks for facing bricks, or iron cramps for zinc.43 The House of Lords in Young and Marten Ltd v Mc Manus Child Ltd44 held that, the Court of Appeal was correct when it decided that the contractor was liable for an implied warranty of the defective material bought from the manufacturer specified by the owner. In another case of Martin v McNamara45, the Full Court reversed the decision of the Magistrate Court and held that, the owner was relying on the skill and judgement of the contractor that the materials were fit for the intended purpose when the contractor had suggested to use a different type of roof tiles that turned out to be faulty. The owner should be entitled to the cost of removing and replacing the faulty materials if the repair work was unreasonably to be carried out. However, it would be unreasonable to put the liability on the contractor, if the owner has accepted the material to be used although the contractor has made known to the owner that the specified manufacturer excluded any warranty of quality. Undoubtedly, however, as a general rule the contractor’s obligation will not extend beyond supplying a material of good quality conforming to the express description of it in the contract documents, if the description is precise and the choice of the material is indeed the architect’s and engineer’s. 46 The quality standards expected of the contractor are either47: 43 I. N. Duncan Wallace. Supra 2. pp. 274. [1969] 1 AC 454 45 [1951] QSR 225.8 Butterworths 46 Adcock’s Trustee v Bridge R.D.C.[1911] 75 J.P. 241 47 Harbans Singh. Supra 19. pp. 697 44 20 a) Expressed in the contract, i.e. in the form of specifications, employer’s requirements, etc; these being reaffirmed vide appropriately drafted conditions of contract, e.g. Clause 1.1 of Pam 1998 Form, Clause 15.1 of CIDB 2000 Form; and/or b) Established by necessary implication, e.g. materials supplied must be of ‘merchantable quality’ and fit for their purpose 48 , these two criteria operating independently and exclusively49. 2.3.3 Quality of the Workmanship The standard of workmanship may be defined in considerable detail by the contract, for example by requiring it to comply with an appropriate code of practice. 50 Under PAM 1998, such a requirement would appear in the contract document, and would have contractual force by virtue of Clause 6.1. Clause 6.1 of the PAM 1998 provides that the specification of the works contain in the contract document will specify the kinds and standard of materials, goods and workmanship. Where the standards are described in the contract documents, the materials, goods and workmanship must be of those standards. Where the standards are not expressly described in the contract documents, then the implied duties of the contractor apply.51 In a situation where the contract document do not so specify, there will be an implied term that the materials or goods will be of merchantable quality and that the workmanship will be carried out with reasonable care and skill: see Lord Denning in Hancock v BW Brazier (Anerly) Ltd52 and Lord Reid in Young and Marten Ltd v Mc Manus Childs Ltd53. The owner can still accept minor defective workmanship as a substantial performance of the contractor’s work. Indeed, the owner can bring an action to 48 Khong Seng v Ng Teong Kiat Biscuit Factory Ltd [1963] MLJ 388 Rumbelows Ltd v Firesnow Sprinkler AMK and Installations Ltd [1980] 19 BLR 25 50 Murdoch, J and Hughes, W. Supra 3. pp. 148 51 Sundra Rajoo. Supra 1. pp. 95 52 [1966] 2 All ER 901 53 [1969] 1 AC 454 49 21 counterclaim the cost of the repair works and set-off from the money due under the building contract. In Hoenig v Issacs54, the Court of Appeal agreed with the official referee’s finding that the contract has been substantially performed even though there were some defects and held that the contractor was entitled to be paid the balance due, less only a deduction for the cost of making good the defects. The standards of workmanship to which the contractor must aspire to work towards are either55: a) Prescribed in the contract in an express manner. These are usually contained in the form of the specifications, standards, code of practice, etc, and endorsed by the relevant express clauses, e.g. clause 4 of JKR 203 Form, and/or b) Implied under the general corpus of the law, e.g. workmanship has to be of ‘workmanlike’ standard, i.e. that which an employer could reasonably expect of an ordinarily skilled and experienced contractor of the type the employer has elected to employ and having regard to any relevant claims made by the contractor as to his level of competence56. It is to be noted that where a contractor has complied exactly with a detail express specification, there is no room for implication of further provision as to the standard required to be achieved 57. 2.4 Liability for Defects As a general principal, defects in the work do not entitle the employer to terminate the contract and refuse payment altogether. The employer’s remedy is to 54 [1952] 2 All ER 176 Harbans Singh. Supra 19. pp. 698 56 Hancock v BW Brazier (Annerley) Ltd [1966] 1 WLR 1317 57 Lynch v Thorne [1956] 1 WLR 303 55 22 claim damages for the cost of rectification. However, very serious defects may justify the conclusion that there has nor been ‘substantial performance’ by the contractor. Where this can be established, the employer need pay nothing.58 In Bolton v Mahadeva 59, the installation of a central heating system at an inclusive price of £560 was defectively carried out. The system was only 90% efficient (70% in some rooms) and gave off fumes in the living room. The Court of Appeal held that the claimant was entitled to nothing for this work; the defendant was not limited to setting of the £174, which it would cost to put right the defects. It is even possible that an accumulation of lesser defects may amount to a repudiatory breach of contract, even though none of them would be sufficient on their own.60 It was thus held in the case Sutcliffe v Chippendale & Edmondson61 that the contractors’ ‘manifest inability to comply with the completion date requirements, the nature and number of complaints from sub-contractors and their own admission that…the quality of work was deteriorating and the number of defects was multiplying’ entitled the employer to terminate the contract and to order the contractors to leave the site. The employer had justifiably concluded that the contractors had neither the ability, competence nor the will to complete the work accordance with the contract. Timing wise, the contractor’s liability for defects can be demarcated along three principal stages of a typical contract, namely during construction, during defects liability period and post defects liability period. 58 Murdoch, J and Hughes, W. Supra 3. pp. 328 [1972] 2 All ER 1322 60 Murdoch, J and Hughes, W. Supra 3. pp. 329 61 [1971] 18 BLR 149 59 23 2.4.1 Defects discovered during the Construction Period This stage encompasses the period from the commencement of the contract up to the issue of the certificate of practical completion or sectional completion. During this stage, the general rule is that the contractor is entitled or has a contractual right to remedy any patent defect or latent defect becoming patent, at anytime up to the date of handing over of the works to the employer. Should he fail to remedy to rectify such defects either on his own or upon instruction of the contract administrator, he is culpable of breach of contract.62 The architect, engineer or the contract administrator in most standard forms has extensive powers in respect of63 (i) opening up and investigation of works; and (ii) remedial of defects, e.g. to have defects remedied including removal and substitution of defective materials and removal and re-execution of defective work. Notwithstanding the engineer or the contract administrator supervisory role, the contractor is solely responsible for compliance with the contract. Failure of the engineer or the contract administrator to give notice or investigate defects is not sufficient ground to construe the engineer or the contract administrator has accepted the works64. In Miller v Krupp65, NSW, Giles J. said: “Krupp’s [defendant contractor] submission requires that Miller’s [plaintiff employer] agent for the purpose of supervising Krupp’s performance of the contract owed a duty to take care to prevent Krupp from falling properly to perform: a duty to save it from breach of the very contract it had to perform to 62 Harbans Singh. Supra 19. pp. 709 Ong See Lian. Supra 15. pp. 2. 64 Ong See Lian. Ibid. pp. 2. 65 [1992] 11 B.C.L.74 63 24 Miller’s satisfaction. In my view there was not the requisite proximity, a view confirmed by notions of what is fair and reasonable.” It should be noted that the commensurate redress is usually stipulated under the contract itself, i.e. for mere trivial breaches amounting to breach of warranty, the employer’s right being confined normally to the use of third parties or a financial adjustment and for a more serius default constituting a breach of a condition, the remedy being determination of employment. 66 In William Tomkinson & Sons v Parochial Church Council of St Michael67, it was held that the employer was entitle to recover damages for the defective work as it was still a breach of contract, despite occurring during the construction period. Damages which the employer would be entitle to recover however is not his outlay in remedying the damage but the cost which the contractor would have incurred in remedying it if they had not been required to do so; the sum is anticipated to be much less than the actual remedial costs. 2.4.2 Defects Discovered during Defects Liability Period The instant stage normally covers the period from the date of completion or handing over up to the certification by the contract administrator of the contractor’s obligation to remedy defects, i.e. by the issue of the Certificate of Making Good Defects.68 During the defects liability period, which starts on the completion of the works, standard forms of contract generally give the contractor a licence to return to the site for the purpose of remedying defects. In effect, such condition of contract confers upon the contractor a right to repair or make good its defective works, which can (usually) be carried out more cheaply and (possibly) more efficiently than by some outside contractor bought in by the employer69. 66 Harbans Singh. Supra 19. pp. 711 [1990] 6 Const. LJ 319 68 Harbans Singh. Supra 19. pp. 711 69 Ong See Lian. Supra 15. pp. 3. 67 25 Lord Diplock, commenting on RIBA/JCT defects liability clause in the case of P&M Kaye Ltd v Hosier & Dickson Ltd70, said: “Condition 15 imposes upon the contractor a liability to mitigate the damage caused by his breach by making good the defects of construction at his own expense. It confers upon him the corresponding right to do so. It necessary implication from this that the employer cannot, as he otherwise could, recover from the contractor the difference between the value of the works if they had been constructed in conformity with the contract and their value in their defective condition, without first giving the contractor the opportunity of making good the defects.” It follows that an employer who chose to repair the defects himself without giving the contractor an opportunity to do so would thereby be in breach of contract71. 2.4.3 Defects Discovered after the Final Certificate The post “correction” period starts at the end of the defects liability period. The contractor will no longer have a right of entry or a right to remedy his own defects, although many standard forms provide a short transition period for the contractor to enter and remedy defects notified up to the end of the defects liability period72. In the absence of words to the contrary in the contract, the contractor’s liability for not completing the works in accordance with the contract continues until statute barred. The Malaysia Limitation Act 1953 Section 6(1) provides that the 70 [1972] 1 W.L.R. 146, at p.166 Ong See Lian. Supra 15. pp. 3. 72 Ong See Lian. Ibid. pp. 3. 71 26 limitation period for a breach of contract and tort are six year from the date on which the cause of action accrued. A cause of action for ordinary failure to build in accordance with the contract normally arises at practical completion. A cause of action for failure to comply with defects liability obligations normally arises at the end of the defects liability period or such period prescribed by the contract for carrying out these defects obligations.73 Note, however, the exception under section 29 of the Act, where the action is based upon the fraud of the defendant or his agent or of any person through whom he claims or his agent, or the right of action is concealed by the fraud of any such person, then the period of limitation shall not begin to run until the plaintiff has discovered the fraud or the mistake (as the case may be) or could with reasonable diligence have discovered it.74 It appears following H W Nevill (Sunblest) Ltd v William Press and Son Ltd 75 that the satisfactory making good of defects does not amount to an exclusion of claims in respect of their consequences. The measure of damages will therefore not only be the cost of repair of the defect, but also such compensation as the loss of the use of the plant during repairs in accordance with the ordinary rules governing remoteness of damage. Where there is a conclusive final certificate of satisfaction given by the architect, engineer or the contract administrator, the contractor’s liability for the defective works ends upon the end of Defects Liability Period, notwithstanding that the certificate may have been granted after the commencement of legal proceedings in respect of the defects in question76. 73 Ong See Lian. Supra 15. pp. 3. Ong See Lian. Ibid. pp. 4. 75 [1981] 20 BLR 78 76 Kaye (P&M) Ltd v Hosier & Dickinson [1972] 1 W.L.R. 147 (HL) 74 27 2.5 Contractor Obligations after Completion There are further obligations imposed on the contractor after completion, notably by JKR 203, PAM 1998 and CIDB 2000. Clause 45 of JKR 203 governs the rights and obligations of the parties on defects, imperfections, shrinkages and other faults in the works which arises during the Defects Liability Period (DLP) after achievement of practical completion of the works. Clause 45(a) specifies that the contractor is responsible for any defect, imperfection, shrinkage and other fault appears during the DLP, which will be six months from the day named in the Certificate of Practical Completion (CPC), unless some other period is specified in the Appendix. 77 Clause 15.2 under PAM 1998 also specifies the liabilities of the contractor after the CPC has been issued. It establishes a formal DLP and a procedure for dealing with defects within that period. 78 CIDB 2000 also has the similar provision under Clause 27.1. 2.5.1 Defects Liability Period The exact status of the ‘Defects Liability Period’ (or ‘Maintenance Period’), is of a period defined in the construction contract during which the appearance of defects is at the contractor’s own risk in that he may be called upon to return to site to correct them as nessasary. This was traditionally a period of six months but is now commonly specified as 12 months. 79 Under the Housing Developers (Control and Licensing) Act 1966, the standard pro-forma agreement which must be used for the sale of units within building projects contains the following basic provision: (the wording is from Clause 23 of Schedule G in the Housing Developers Regulations) 77 Lim Chong Fong. Supra 8. pp. 105. Sundra Rajoo. Supra 1. pp. 145. 79 Nigel M Robinson. Supra 20. pp. 170 78 28 “Any defects, shrinkage or other faults in the said Building which shall become apparent within a period of eighteen (18) calendar months after the date of handing over of vacant possession, to which water and electricity supply are ready for connection to the said building, to the purchaser and which are due to defective workmanshio or materials or the said Building not having been constructed in accordance with the plans and description as specified in the Second and Fourth Schedule as approved or amended by the Appropriate Authority, shall be repaired and made good by the Vendor at its own cost and expenses within thirty (30) days of its having received written notice thereof from the Purchaser and if the said defects, shrinkage or other faults in the said Building have not been made good by the Vendor, the Purchaser shall be entitled to recover from the Vendor the cost of repairing abd making good the same and the Purchaser may deduct such costs from any sum which has been held by the Vendor’s solicitor as stakeholder for the Vendor: Provided that the Purchaser shall, at any time after the expiry of the said period of theirty (30) dais, notify the Vendor of the cost of repairing and making good the said defects, shrinkage or other faults before the commencement of the works shall give the Vendor an opportunity to carry out the works himself within fourteen (14) days from the date of the Purchaser has notified the Vendor of his intention to carry out the said works.” Note that this contractual term deriving from the Housing Developers Regulations is operative only as between the purchaser of the housing unit and the vendor (developer); where the developer has contracted with a contractor for the construction of the building, the terms of that contract may be quite different.80 The requirement in the Housing Developers Regulations is limited to “any defect, shrinkage or other fault … which shall become apparent …”. The sufficiency or that requirement depends on the definition of completion adopted within the contract and on the strict enforcement of it. It is not necessary the case that items pf work required by the contract but remaining outstanding at the date of acceptance ov completion are 80 Nigel M Robinson. Supra 20. pp. 170-171 29 to be classified as defects or faults, but the Defects Liability Period nay be used also for the completion of such items.81 It is to be noted that under most of the construction contracts, the issue of the “Certificate of Practical Completion” marks the start of the “Defects Liability Period”. Any defects, shrinkages or other faults arising during this period due to defective materials or workmanship must be put right by the contractor at its own expense. The contractual procedure for dealing with defects arising during the Defects Liability Period is that the contract administrator should issue a schedule of such defects to the contractor not later than fourteen days after the end of the defects liability period, and the contractor then has a reasonable time to put them right. Once this has been done, the contract administrator will issue a ‘Certificate of Completion of Making Good Defects’, following which the contractor becomes entitled to the remaining part of the retention money. It may be noted that, if no schedule of defects is issued, the employer retains the right to claim damages for breach of contract.82 It is the contractor’s obligation under the contract to rectify the defects appears during DLP. According to Lord Diplock in P&M Kaye Ltd v Hosier & Dickinson Ltd83, the DLP’s clause is included in the contract with an intention of giving opportunity to the contractor to make good the defects appear during that period. Lord Diplock’s interpretation is easy to understand as we could see that most of the construction contracts require the superintendent to issue notice to the contractor for rectifying the defects appear during DLP. Further Lord Diplock said that: “…the contractor is under an obligation to remedy the defects in accordance with the architect’s instructions. If he does not do so, the employer can recover as damages the cost of remedying the defects, even though this cost is greater than the diminution in value of the works as a result of the unremedied defects.” 81 Nigel M Robinson. Supra 20. pp. 171 Murdoch, J and Hughes, W. Supra 3. pp. 185. 83 [1972] 1 WLR 146 82 30 During a defects liability period, the contractor has the right as well as the obligation to put right any defects that appear. What this means is that an employer who discovers defects should operate the contractual defects liability procedure, rather than appoint another contractor to carry out the repairs. In William Tompkinson v Parochial Church Council of St Michael84 , an employer refused to allow the original contractor access to the site to remedy defects, but instead sued the contractor for the cost of having these rectified by another contractor. It was held that the employer’s decision amounted to an unreasonable failure to mitigate the loss suffered, and the damages were reduced by the amount by which the employer’s costs exceeded what it would have cost the original contractor to carry out the work. The Court of Appeal has since approved this decision. Therefore, in the event that the contractor is fails to rectify the defects after being given notice or the owner is not satisfied with the remedial works, the owner is entitled to appoint another contractor to undertake the remedial work and claim the cost of doing it to the original contractor.85 This has been correctly decided by the High Court of Malaya, Kuala Lumpur in Kemayan Construction Sdn Bhd v Prestara Sdn Bhd 86 where the owner is entitled to recover the cost of rectification of the defective building works from the original contractor who failed to rectify the defects after being instructed by the Architect. It was held that the owner is entitles to engage independent contractor to rectify the defects and deducted the rectification cost from the original contractor’s account. Kamalanathan JC agreed that the owner may recover from the contractor or may deduct any money due or to become due to the contractor provided that the architect has issued a written notice to the contractor to rectify the defects and that at the expiry of seven days notice, it has been shown that the contractor has failed to rectify the defects. 84 [1990] 6 Const LJ 814 Mohd Suhaimi Mohd Danuri. Supra 7. pp. 56 86 [1997] 5 MLJ 608 85 31 It is also worth noting that defects liability clauses do not act as exclusion clauses. If a defect is not included on a schedule of defects, and is not noticed by the contractor or contract administrator before the end of the period, the contractor is still liable for it. Since the period has expired, the contractor has no right to return to the site to repair the defect, but is liable to the employer for damages.87 2.5.2 Procedural Requirements In all cases, the strict entirety of the contract is modified and provision is made for the making good of defects by the contractor subsequent to handing over possession. The employer’s right to have defects remedied within a stipulated period after completion is in substitution for his rights to a damages claim in respect of the cost of remedial work dine by another contractor, i.e. the provision for the making good of defects by the contractor is mandatory on both parties and gives the contractor the right to make good defects notified to him rather than be sued by breach.88 Where the contract stipulates the procedural requirements, the parties must observe the requirements to preserve their respective rights. Failure of the employer to comply with procedural requirements in respect of defects rectification may be detrimental to his later claim for damages.89 Accordingly, it is generally accepted that the owner would be entitled to appoint another contractor to rectify the defects if the original contractor had failed to comply with the said notice. However, the issue would be much difficult if the owner employ another contractor to rectify the defects without first giving the required notice to the original contractor. In another words, it deprives the original contractor 87 Murdoch, J and Hughes, W. Supra 3. pp. 185. Nigel M Robinson. Supra 20. pp. 171 89 Ong See Lian. Supra 15. pp. 4. 88 32 from having the opportunity to undertake the remedial works himself. It must be noted that the owner cannot employ another contractor to do work that the original contractor is obliged to do under the contract. 90 The common law principle has justified that the works under the contract cannot be omitted with an intention of giving it to another contractor.91 In considering this issue, it is essential to appreciate that the requirement of such notices impliedly imposing a duty to mitigate the loss on the owner. Refer to the decision of the Court of Appeal in Pearce & High Limited v Baxter92 , P&H, the building contractor sued Baxter, the employer for amounts including the sum of BGP 3,919.23 outstanding under an architect’s certificate for workdone under a contract in the JCT form for Minor Building Works. Defects had become apparent before the end of the defects liability period, but these were not notified to the contractor. The Court of Appeal held that the owner was under a duty to mitigate the loss by giving the opportunity to the original contractor to undertake the remedial works himself. The judge justified that the cost of employing another contractor to remedy the defects would be much higher than the cost to the original contractor. Evans LJ said that: “The cost of employing a third party repairer is likely to be higher that the cost to the contractor doing the work himself would have been. So the right to return in order to repair the defects is valuable to him. The question arises whether, if he is denied that right, the employer is entitled to employ another party and to recover the full cost of doing so as damages for the contractor’s original breach. In my judgement, the contractor is not liable for the full cost of repairs in those circumstances. The employer cannot recover more than the amount which it would have cost the contractor himself to remedy the defects. Thus, the employer’s failure to comply with clause 2.5 (the clause relating to rectification of defects), whether by refusing to allow the contractor to carry out the repair or 90 Mohd Suhaimi Mohd Danuri. Supra 7. pp. 56 Carr v JA Berriman Pty Ltd [1953] 27 ALJR 273 92 [1999] BLR 101 91 33 by failing to give notice of defects, limits the amount of damages which he is entitled to recover. The result is achieved as a matter of legal analysis by permitting the contractor to set off against the employer’s damages the amount which he, the contractor, has been disadvantaged by not being able or permitted to carry out the repairs himself, or more simply, by reference to the employer’s duty to mitigate his loss.” The employer’s failure to comply Clause 2.5 of the JCT form for minor works, whether by refusing to allow the contractor to carry out the repairs or by failing to give notice of the defects, limits the amount of damages whish he is entitled to recover. As a matter of legal analysis this is either93: a) By permitting the contractor to set-off against the employer’s damages claim the amount by which he, the contractor, has been disadvantaged by not being able or permitted to carry out the repairs himself, or b) By reference to the requirement for the employer to mitigate the loss for which is entitled to recover damages The measurement of damages was therefore the cost of repairs by the contractor if he remedied the defects himself on the assumption that this is lower than the cost of repair by a third party. The absence of notice of the defect does not raise the possibility that the measure of damages in some circumstances may only be the diminution of the value of the property by reason of the defect, on normal principles. The decision was not concerned with this aspect however and left the question open.94 In Malaysia, the principle of mitigating the damages is stipulated in the explanation to section 74 of the Contracts Act 1950 (revised 1974). It has been 93 94 Ong See Lian. Supra 15. pp. 5 Ong See Lian. Ibib. pp. 5 34 decided in the case of Kabatasan Timber Extraction Co v Chong Fat Shing95 that the respondent is under a duty to mitigate the damages, when the appellant had failed to deliver some of the timbers to the designated site. Macintyre FJ in that case has said that: “In the instant case, there was no need for the respondent to have gone to the expense and trouble of buying logs from elsewhere when the logs were lying a few hundred feet away from the sawmill for the mere taking and all that was required was additional expense for hauling them up to the sawmill.” Furthermore, Macintrye FL also quoted the following passage from Anson’s Principles of the English Law of Contract: “it also follows from the rule that damages are compensatory only that one who has suffered loss from a breach of contract must take any reasonable steps that are available to him to mitigate the extent of the damage caused by the breach. He cannot claim to be compensated by the party in default for loss which is really due not to the breach but to his own failure to behave reasonably after the breach.”96 Therefore, the probability is that the courts in Malaysia will follow the same principles developed in the case of Pearce & High Limited v Baxter97 by imposing the owner a duty to mitigate the damages for defects appear during Defects Liability Period. It has to be noted that the failing of the superintendent to issue the required notice during DLP shall not bar the owner from appointing another contractor to rectify the defects and recovering the remedial cost. In this regards, Evans LJ has agreed with the judgement of Judge Stannard in William Tokinson v St Michaels’s Parochial Church Council 95 98 that the owner’s common law right to recover for [1969] 2 MLJ 6 Kabatasan Timber Extraction Co v Chong Fat Shing [1969] 2 MLJ 6 97 [1969] 2 MLJ 6 98 [1990] CLJ 319 96 35 damages is not excluded by failing to issue such a notice, however, it would limit the damages recoverable by the owner due to the principle of mitigating the damages.99 2.6 Conclusion It is important to understand the precise nature of the defects obligations under the contract. It involves basically the right to recall the contractor to return to the site to carry out rectification works even if the site was returned to the employer for occupation. The contractor should be given the right to rectify the defects at his own costs which may appear during the Defect Liability Period. Thus if an employer who discovers such defects and has rectify them without giving the opportunity to the contractor to do the making good himself, he may not be able to recover the additional cost of doing the work by a third party contractor. In most of the contracts in use today, the certificate by the architect, engineer or contract administrator is an important instrument to determine whether the work is accepted or approved. However, such certificate may not be conclusive as often such contracts also provide for the review of such certificate by an arbitrator. As such the certificate of the architect, engineer or contract administrator looses its binding effect unless the express provisions of the contract otherwise provides. 99 Pearce & High Limited v Baxter[1969] 2 MLJ 6 36 CHAPTER 3 LIABILITY OF DEFECTS 3.1 Introduction There are provisions in most standard form building contracts requiring the rectification of residue defects by the contractor within a stipulated period after completion, a period generally described as the ‘defects liability’ or ‘maintenance’ period. Most such contracts also provide for the withholding of retention money until the expiry of the period, for release only when the contract administrator has certified his satisfaction that the works are finally in conformity with the contract.100 During the defects liability period, the contract administrator is empowered to require the contractor to make good the defects, and, in the event of the contractor’s default in this, to engage another contractor to do so at the expense of the former. Since these powers of the contract administrator are exercisable until the end of the defects liability period, contractors (and others) have tended to assume that the contractor ceases to be liable for defects at the moment that the defects liability period expires. Similarly, most housing developers assume that they cease to be 100 Nigel M Robinson. Supra 20. pp. 263 37 responsible for defects under the defects liability provisions in their sale and purchase agreements. Much confusion has arisen out of misunderstanding of the nature of the obligations embodied in defects liability provisions in contracts.101 The defects liability period (or maintenance period) is by no means definitive of the duration of rights and liabilities even as between the parties to the contract. For example, a contractor could still be sue in respect of defective concrete work by the owner two years or more after the end of the defects liability period, if the defect was one which was knowingly or recklessly covered up by the contractor so as to amount to fraud. It is also vital to understand that the period is a contractual provision. It is not therefore binding upon a subsequent purchaser who suffers loss and damage after acquiring the property and he would not be prevented from pursuing tortuous remedies against the original contractor. Similarly, the period cannot be relied upon by professionals such as architects or engineers to determine the duration of their liability, since they were not parties to the contract.102 The contractor’s liability in damages for defects is not relieved by the defects liability clause (in the absence of clear words to the contrary): see Hancock v Brazier103, Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd104. Lord Denning in Hancock v Brazier indicated that the expiry of the period of defects liability does not suspend or extinguish the rights of the employer to general damages for defective work. The result is that, subject to any clear contractual provisions to the contrary, a contractor’s liability in damages continues until it becomes statutebarred. 101 Nigel M Robinson. Supra 20. pp. 263 Nigel M Robinson. Ibid. pp. 263-264 103 [1966] 2 All ER 901 104 [1973] 3 WLR 421 102 38 3.2 Certificate of Making Good Defects The contractor’s satisfactory discharge of his obligation to make good any reported defects within the defect liability period has to be certified by the contract administrator; a milestone expressly spelt out in all the standard forms of conditions of contract.105 A classic example of the latter is clause 27.6(a) CIDB 2000 Form which reads: “at the expiry of the Defects Liability Period and when all the Defects notified by the Superintending Officer to the Contractor under clause 27 have either been made good by the Contractor in compliance with the Superintending Officer’s instructions or have been dealt with by the Superintending Officer under clause 27.4 the Superintending Officer under clause 27.4 the Superintending Officer shall issue a certificate to that effect. Such certificate shall be referred to as the ‘Certificate of Making Good Defects’.” Similarly worded clauses are included in all the other standard form used locally, e.g. clause 15.4 PAM 1998 and clause 45(e) JKR 203 Form. In summary, the principal effects of such a certificate are106: a) It officially brings to an end the defect liability period stipulated in the contract b) It finally discharges any remaining contractual rights of the contractor to physically attend to the defects, i.e. to enter the site and remedy defects c) It establishes the commencement of the contractually stipulated period for the preparation of final account and the issue of the Final Certificate by the contract administrator d) It contractually obliges the employer to release the second moiety of any retention fund or sum withheld 105 106 Harbans Singh. Supra 19. pp. 755 Harbans Singh. Ibid. pp. 758 39 e) It discharges the liability of the guarantor or the body issuing the performance security deposit and thereby released the same, and f) It releases the insurers from any obligations and/or liabilities under the various insurances issued which are valid up to such milestone only Contrary to popular belief, the said certificate is not conclusive but of limited effect only; such effects being adverted to above. It does not derogate in any way the contractor’s liability for defective work at law, i.e. it does not prejudice the employer’s rights in regard to latent defects and/or other breaches of the contract in terms of defective work or otherwise. The contractor continues to be liable for such defects for the duration of the applicable statutory period of limitation.107 3.3 Final Certificate Final certificates, which frequently are certificates both of satisfaction with the work of the final balance due to the contractor upon his final discharge of his obligations under the contract. However, in many earlier contracts, not usually found at the present day in the UK but still common in commonwealth countries, an earlier certificate at the beginning of the maintenance period is made the definitive certificate of satisfaction, but subject to a defects liability during the subsequent maintenance period.108 Completion of the contract is evidenced by the issuing of the Final Certificate. Under most contracts, (except in cases of fraud, dishonesty or fraudulent concealment relating to the works, or any defect or omission in the works which was not apparent or would not have been disclosed upon reasonable inspection at the time 107 108 Harbans Singh. Supra 19. pp. 758 I.N. Duncan Wallace. Supra 2. pp. 829 40 of issuing the Final Certificate) the Final Certificate is evidence that the works have been completed in accordance with the terms of the contract. Accordingly, where the exceptions described above do not apply, the employer is unlikely to have any recourse against the contractor for breach of contract and the employer may proceed to rectify the works at its own cost.109 In cases of fraud, dishonesty or fraudulent concealment relating to the works, or where there is a defect or omission in the works which was not apparent and would not have been disclosed upon reasonable inspection at the time of issuing the final certificate, the employer will have recourse against the contractor. However, as the contract has come to an end, there are no longer any remedies under the contract which are available to the employer and, if the contractor fails to rectify the defect or omission, it will be necessary to seek relief through legislation, the common law (via the courts) or by exercising rights of set off where it is possible to do so.110 Therefore, it can be noted that the Final Certificate exhibits the following characteristic111: a) It is issued upon the expiry of the contract period b) The certificate is issued by the authorised person, i.e. the contract administrator c) It is the last of the various certificates issued during the currency of the contract d) Form the contractual point of view, the issue of such certificate, prima facie, signifies discharge of the contract by performance e) It is also generally renders the contract administrator ‘functus officio’, and f) The actual effect of such a certificate is dictated by the precise wording of the particular term(s) of the applicable conditions of contract 109 Julia Willis. 2006. “Rectification of Building Defects or Omissions after Final Completion.” http://www.build.qld.gov.au/amps/AmpsDocs/pan-rec-of-bldg-defects.pdf 110 Julia Willis. Ibid. 111 Harbans Singh. Supra 19. pp. 829 41 As can be gleaned from the earlier discussion, the Final Certificate on a broad brush approach, is generally of the following effect112: a) It signifies the contract administrator’s satisfaction that the work carried out by the contractor conforms with the contract, i.e. it is sufficient and the completion criteria had been achieved, etc; and/or b) It certifies the amount which is finally due to the contractor; and/or c) It renders the contract administrator ‘functus officio’ i.e. he has discharged his duties under the contract and has exhausted his authority with the result that he cannot thereafter issue any valid certificate under the contract. Hence, consequently the contract administrator’s decision as contained in the Final Certificate on the matters contained therein, i.e. sufficiency of work and amount finally payable is often binding and conclusive on the parties. However, whether it is in actual effect really binding and conclusive is not that clear cut, there being no comprehensive test to establish the same. Much depends in the intentions of the contracting parties as to such terms. Additionally it may be necessary to look beyond the contract itself at collateral matters such as possible grounds of challenging the certificate, the conduct of the contract administrator, etc113. 3.3.1 Express Contractual Provisions Before the contract administrator issues the Final Certificate to the contractor, he must ensure that the relevant pre-conditions as expressly stipulated in the particular terms of the conditions of the contract has been satisfied. As can be observed from the various standard forms of conditions of contract employed in this 112 113 Harbans Singh. Supra 19. pp. 837 Harbans Singh. Ibid. pp. 837 42 country, such pre-conditions vary markedly between these forms. However, in general the following pre-conditions can be elicited from these forms114: a) Certification of the satisfactory completion of the making good of defects, e.g. the issue of Certificate of Making Good Defects, etc b) Official expiry of the Defects Liability Period inclusive of any official extension thereof c) Certification of the satisfactory completion of the carrying out of the relevant servicing and maintenance, e.g. issue of Certificate of Completion of Maintenance, etc d) Preparation and finalization of the Final Account e) Formal application for Final Certificate by the contractor, and f) Satisfaction of all other obligations under the contract, e.g. submission of warranties, guarantees, indemnities, authority approvals, records, documents, etc. Notwithstanding the listing out of the abovementioned general pre-conditions, the practitioner must be aware of and strictly comply with the particular provisions of the contract being implemented, as such stipulations actually govern the rights and obligations of the parties to the contract115. Clause 15.4 of PAM 1998 is important since it provides for the architect to issue what is called the ‘Certificate of Making Good Defects’ when the instruction contained in the schedule of defects or given under Clause 15.3 has been complied with. This is an important certificate because116: a) One of the alternative events which must occur before the second half of the retention money is payable (Clause 30.5(iv)); 114 Harbans Singh. Supra 19. pp. 829 Harbans Singh. Ibid. pp. 829 116 Sundra Rajoo. Supra 1. pp. 146-147 115 43 b) One of the events which must have occurred before the period within which the Final Certificate is due begins to run (Clause 30.7). There seems to be no advantage in issuing the Certificate of Making Good Defects earlier that at the end period stipulated as it can lead to some defects being undetected by the architect. Although the certificate means that the contractor is no longer obliged to return and remedy defects, it does not discharge him finally of liability for defects and the cost for remedying them. No competent architect is likely to issue a final certificate under Clause 30.7 unless all the work is to his reasonable satisfaction.117 Clause 30.7 in PAM 1998 provides that no certificate issued by the Architect is conclusive evidence that any work, materials or goods are in accordance with the contract (Clause 30.8). On examining the above provision in relation to the Final Certificate, it is clear that the contents of this sub-clause precludes finality only to the matters as mentioned thereon, i.e. satisfaction with any work, material;s or goods. It however, does not avoid the conclusiveness, evidence wise of the other essential matters contained in the Final Certificate, i.e. the balance due between the parties. Hence, the non-conclusiveness of the Final Certificate is limited to certain matters only and is not all encompassing.118 Clause 30(7) in the PAM/ISM 1969 Form had been criticized as being inimical to the interest of the employer as it provides that the Final Certificate is to be conclusive with regard to the sufficiency of the work by the contractor except for three exceptions namely, fraud, defects not shown up by reasonable inspection, and accidental inclusion or exclusion unless notice of arbitration is given by either party before its issue or by the contractor within 14 days after its issue. It was held in P&M Kaye Ltd v Hosier & Dickinson Ltd119, that the words in Clause 30(7) of the JCT 117 Sundra Rajoo. Supra 1. pp. 147 Harbans Singh. Supra 19. pp. 841 119 [1972] 2 All ER 121 118 44 1963 prevented any further legal action, including legal proceedings started before the certificate was issued. The certificate is not reviewable by the arbitrator under clause 34.0 because it is ‘conclusive evidence that any necessary effect has been given to all the terms of this Contract which require an adjustment to the Contract Sum’.120 The case has been followed in the Malaysian case of Shen Yuan Pai v Dato Wee Hood Teck121. It excuses the contractor from liability for what could be breaches of contract and obviates the operation of the Limitation Act 1953 providing that actions founded in contract and tort shall not be brought after the expiration of six years from the date on which the cause of action accrued. As the Final Certificate under Clause 30(7) of the PAM/ISM 1969 Form is ‘conclusive evidence’ not only of the adjustment of the Contract Sum, but also ‘that the Works have been properly carried out and completed in accordance with the terms of these Contract’, it is, to say the least, hardly in the employer’s interest since effectively it excuses the contractor from liability for what could be serious breaches of contract (subject to the limited exception). In line with the risk apportionment philosophy of the PAM 1998 Form, Clause 30(7) is amended to remove the conclusiveness of the Final Certificate.122 JKR 203 adopted a similar approach to the PAM 1998, Clause 45 governs the rights and obligations of the parties on defects, imperfections, shrinkages and othe faults in the works which arise during the Defects Liability Period after the achievement of practical completion of the Works. This provision is not in derogation of the Government’s rights and remedies for breach of contract on the part of the Contractor in not executing the Works in accordance with the Contract, which is subject to the limitation period as set out in the Limitation Act 1953123, see Teh Khem On & Anor v Yeoh & Wu Development Sdn Bhd & 3 ors124. 120 Sundra Rajoo. Supra 1. pp. 309 [1976] 1 MLJ 16 122 Sundra Rajoo. Supra 1. pp. 309-310 123 Lim Chong Fong. Supra 8. pp. 105 124 [1995] 2 AMR 1558 by analogy 121 45 Clause 49 primarily states that none of the certificates of the Superintending Officer issued under the Contract would be treated as conclusive evidence as to the sufficiency of any work done, or material or goods supplied, which is the subject matter of the certificate. The contents of the certificates will not be final and binding in any dispute between the parties either in arbitration or in court. In other words, all certificates can be opened up, reviewed and revised by the arbitrator or the court.125 The CIDB Form approaches the matter of conclusiveness of the Final Certificate by first holding vide sub-clause 43.1 that all certificates issued by the Superintending Officer (SO) shall not be considered as conclusive evidence as to the sufficiency of any design works executed and/or any equipment, materials or goods to which it relates. It then proceeds vide sub-clause 43.2 to stipulate the effect of the Final Certificate in various situations involving mediation, arbitration or other proceedings pursuant to the particular provision of the contract. For instance, subclause 43.2(a), renders such certificate as conclusive evidence for matters listed hereunder in any proceedings arising out of or in connection with the contract in accordance with clause 47126: a) Satisfaction of the completion criteria where it is expressly stipulated to be to the reasonable satisfaction of the SO and/or employer; b) That all and only such extensions of time as are contractually due have been given; and c) That all the contractor’s financial claims, eg loss and expense have been properly accounted for. Clause 27.6(c) of CIDB 2000 Form also states that the Certificate of Making Good Defects shall discharge the contractor from any physical attendance upon the works for the purpose of remedying defects. Where there is a conclusive final certificate of satisfaction given by the Superintending Officer, the contractor’s 125 126 Lim Chong Fong. Supra 8. pp. 114 Harbans Singh. Supra 19. pp. 842 46 liability for the defective works ends upon the end of defect liability period, notwithstanding that the certificate may have been granted after the commencement of legal proceedings in respect of the defects in question.127 This means that the Final Certificate will be binding and conclusive and is not reviewable or opened up by the arbitrator or court except in the case of fraud, dishonesty or fraudulent concealment relating to the works. 3.3.2 Conclusiveness of Final Certificate In order for the satisfaction or certificate of an architect or engineer to be conclusive and binding on the parties, the following conditions must exist128: (a) The matter in dispute must be one which the contract confers jurisdiction on the architect or engineer to express his satisfaction or certify. That jurisdiction will usually be narrowly construed. (b) The contract must on its true construction provide that the certificate or satisfaction is intended to be binding. If so, there will be at least a tendency to regard it as being bilaterally binding, that is to say, both parties will be bound by the certificates. There are, however, cases, apart from the example of interim certificates, where the certificate may only be intended to bind unilaterally. But in either case a provision enabling a party to go behind or question or dispute the decision will destroy the conclusiveness of the satisfaction or certificate, in particular any applicable arbitration clause, either in general terms containing no express restrictions on the disputes to be referred, and a fortiori if “open up review and revise” or other express wording showing an intention to confer an overriding or appellate jurisdiction on the arbitrator used, (c) The certificate or satisfaction must be honestly given, and if not this will be a breach of warranty by the owner. It must be given without collusion, interference or undue influence, and the certifier must preserve his 127 128 P&M Kaye Ltd v Hosier & Dickinson Ltd [1972] 2 All ER 121 I.N. Duncan Wallace. Supra 2. pp. 868-869 47 independence and not act in a way that suggests that he has lost his independence. Whether or not a breach of contract by the owner sounding in damages is involved, the certificate in such cases will cease to be binding and can be disregarded. (d) The provisions of the contract regulating the matter to be certified must be adhered to; the approval or certificate must be given by the correct person at the correct time, and must not take into account any matters extraneous to the stipulated requirements of the contract, although there may be a class of satisfaction provision where the architect or engineer may bona fide impose a stricter standard, for example, of quality, on the party bound than the contract documents otherwise require. (e) The owner must have done nothing, by breach of contract or otherwise, to prevent the contractor from obtaining the certificate or satisfaction. Where there is a defects clause and the end of the defects liability period a binding and conclusive final certificate of satisfaction is given by the architect then, in the absence of fraud or other special circumstances, the contractor’s liability in contract for any defects which may have been granted after the commencement of legal proceedings in respect of the defects in question129. 3.4 Defects Arising After Issue of Certificate of Making Good Defects/Final Certificate Upon the issue of the Certificate of Making Good Defects and subsequently the Final Certificate, the contract is deemed to lapse and with it the attendant liability under the said contract for defective work. The contractor’s liability for defective works is basically under two principal heads, namely130: 129 130 Kaye (P&M) Ltd v Hosier & Dickinson [1972] 1 W.L.R. 147 (HL) Harbans Singh. Supra 19. pp. 715 48 a) Contractual liability, i.e. under the express or implied provisions of the particular contract; and b) Common law liability, i.e. for breach of contract, tort of negligent, etc. In regards to the first category, the duration of the liability is merely over the defects liability period; which period may be six months, twelve months, etc. Accordingly, one such period has officially lapsed, i.e. upon the relevant certification by the contract administrator, the employer is not entitled contractually to pursue any defect arising and/or reported after the said date, i.e. his claim for contractual redress for defective work being out of time and therefore unenforceable. However, his common law rights may be still valid depending on the circumstances.131 As for the second category, there are time limits imposed by statutes such as the Limitation Act 1953 (Rev 1981), Limitation Ordinances (Sabah and Sarawak), the Public Authorities Protection Act 1948 (Rev 1978), etc beyond which a cause of action founded on contract or on a tort cannot be brought, subject to statutorily prescribed exceptions for matter such as fraudulent concealment, mistakes, etc. hence, claims arising from defective work cannot be pursued successfully by employers once these are out of the stipulated times, i.e. they become ‘statute’ barred.132 A cause of action for ordinary failure to build in accordance with the contract normally arises at practical completion. A cause of caution for failure to comply with defects liability obligations normally arises at such later date after practical completion as the contract prescribes for carrying out those obligations. If defects are concealed by the contractor, this may result in an extension of the time limitation 131 132 Harbans Singh. Supra 19. pp. 708 Harbans Singh. Ibid. pp. 708 49 period. A contractor may be liable under express terms of a guarantee, warranty or indemnity for many years.133 3.4.1 Cause of Action in Contract Section 6(1) of the Limitation Act 1953 (Rev 1981) reads: “Save as hereinafter provided the following actions shall not be brought after the expiration of six years from the date on which the cause of action accrued, that is to say: (a) actions founded on a contract or on tort; …….” Pursuant to section 6(1)(a) of the Limitation Act 1953, the date on which the cause of action accrued is the date on which the contract was breached, for example, by the execution of work not conforming the specification. In Bagot v Stevens, Scanlan and Co134, Diplock LJ held that the limitation period ran from the time when the drains were improperly built, because the plaintiff at that time was landed with property which had bad drains. 135 For defective work, the date of the breach of contract is the date the defective work was carried out.136 As the exact timing of the particular breach may be difficult to establish from the evidential point of view, a general approach that has been advocated by authorities is to the effect that in the case of lump sum contracts, the date for the accrual of the cause of action was to be taken to be the date of handing over to the employer of the works in its defective state. Hence, commencing from this date, the 133 Furst S and Ramsey, V. “Keating on Building Contracts.” 5th Edition. (London: Sweet & Maxwell, 1991) pp. 248 134 [1964] 2 Lloyd’s Rep 353 135 Nigel M Robinson. Supra 20. pp. 269 136 Bagot v Stevens Scanlon & Co. [1966] 1 QB 197 & Dutton v Bogner Regis United Building Co Ltd & Anor [1972] 1 QB 373 50 contractor carries liability for a further six years; upon the expiry of which period the employer’s cause of action then becomes statute barred.137 3.4.2 Cause of Action in Tort As can be gleaned from section 6(1)(a) of the Limitation Act 1953, actions founded on a tort shall not be brought after the expiration of six years from the date on which the cause of action accrued; the most common torts encountered for defective work being in relation to negligence, i.e. breach of the duty of care in terms of workmanship, design, etc. Furthermore, the bulk of the claims for defective work under this head pertain to latent defects.138 The difficulty for the instant head of claim lies in establishing exactly when the time starts running, i.e. the actual date when the cause of action accrued. There are three approaches establishing the actual time for the accrual of a cause of action in tort under the limitation act, which are139: a) “DUTTON’ Test As per Lord Denning in Dutton v Bognor Regis United Building Co 140, the cause of action does not occur until the defective work or damages was done. b) “Discoverability” Test As per Lord Denning in Sparham-Sounter v Town & Country Development (Essex Ltd)141, the cause of action does not accrue and time does not begin to 137 Harbans Singh. Supra 19. pp. 716 Harbans Singh. Ibid. pp. 716 139 Harbans Singh. Ibid. pp. 718 140 [1972] 1 QB 373 141 [1976] 3 BLR 70 138 51 run until such time as the plaintiff that the defect has done damage, or ought, with reasonable diligence to have discovered it. c) “PIRELLI” Test As per Lord Fraser in Pirelli General Cable Works Ltd v Oscar Faber & Partners142, the plaintiff’s cause of action will not accrue until the date when the damage actually occurs even though the signs of the damage or defect may be discovered or undiscoverable. It is apparent that English case law has discounted the first approach in favour of the later tests. However, the ‘discoverability’ test also seems to have been expressly disproved and not adopted in subsequent cases. But the situation seems far from clear in the local context as the local courts are not bound by the said decisions; these being more of a persuasive nature. Owing to the harshness of the ‘Pirelli’ decisions, it is submitted that it may not find favour with the local courts who may prefer the application of the ‘discoverability test’ after all. In situations where the latent defect manifests itself into the patent from in a dramatic fashion, e.g. resulting in a catastrophic failure of the likes of the infamous ‘Highland Towers’ case in Steven Phoa Cheng Loon &72 Ors v Highland Properties Sdn Bhd & 9 Ors143, there can be little doubt as to the exact commencement of the limitation period. However, where the transformation into the patent form is less obvious and occurs over a period of time during which it may not discovered or discoverable with reasonable diligence, the application of the discoverability’ test in lieu of the Pirelli test may yield a more equitable result.144 142 [1983] 2 AC 1 [2000] AMR 3567 144 Harbans Singh. Supra 19. pp. 718 143 52 3.4.3 Postponement of the Limitation Period Another provision in the Limitation Acts which requires consideration is section 29, which states that: “Where, in case of any action for which a period of limitation is prescribed by this Act, either: a) The action is based upon the fraud of the defendant or his agent or any person through whom he claims or his agent; or b) The right of action is concealed by the fraud of any such person as aforesaid; or c) The action is for relief from the consequence of a mistake the period of limitation shall not begin to run until the plaintiff has discovered the fraud or the mistake, as the case may be, or could with reasonable diligence have discovered it.” A number of observations pertaining to the effects of the above provision needs to be taken cognizance of. In essence, according to section 29, the limitation period prescribed for, amongst others, a cause of action founded on contract and tort does not apply when there is fraudulent concealment. Accordingly, where defective work or workmanship or design have been knowingly covered up or concealed so as to constitute fraud, the commencement of the limitation period may be delayed. The said period may be delayed until discovery actually occurs; or at least the defect could have been discovered with reasonable diligence, whichever is earlier.145 The word ‘fraud’ as employed in section 29 is not used in the common law sence of ‘deceit’ but in the equitable sense of being unconscionable; see Abdul 145 Harbans Singh. Supra 19. pp. 719-720 53 Gaffar v Chua Kwang Yong146, thereby prescribing a lower standard of proof. The term ‘his agent’ may in certain circumstances even apply to independent contractors engaged by a party, e.g. in Archer v Moss147 a builder was held to be the developer’s agent. Hence, if such a builder were to be the perpetrator of the fraudulent concealment, his principal could be implicated thereby losing the protection of the relevant statutory period of limitation.148 In all territories, there are likely to be special statutes and regulations on diverse matters of an administrative nature and that include particular requirements for periods of validity of permissions granted, cut-off dates for applications and claims, and the like. Where such restrictive provisions are challenged, the courts are vigilant to ascertain the validity of the special rule, and that it is administered fairly and in the stipulated manner. The case of Sequerah Stephen Patrick v Penang Port Commission149 provides an example of an injured party having recourse to common law rules to successfully challenge the application to his claim of a time-limit clause in secondary legislation.150 3.5 Conclusion The defects liability period/maintenance period is sometimes confused with limitation periods. The relationship can be briefly explained. Limitation periods are imposed by statute to bar the enforcement of state claims, basically after six tears from the accrual of the cause of action (the breach of contract or, in tort, occurrence of damage). Within that framework, it is possible and usual for the parties to regulate their rights and obligations by contract. Thurs, although the limitation period would 146 [1994] 2 SLR 546 [1971] 3 BLR 1 148 Harbans Singh. Supra 19. pp. 720 149 [1990] 2 MLJ 232 150 Nigel M Robinson. Supra 20. pp. 268 147 54 not protect the contractor until six years was past, there is nothing to prevent the building contract limiting specific rights of recovery within that period. A contract clause which stipulates that an action of a particular type must be brought within a specified time is prima facie valid, since the general rule is that the content of the contract is for the parties to decide. So the parties to the most common forms of building contract agree that a specified duration will apply to certain rights/obligations under the contract, being less than six years which govern their general rights of recovery. Neither party can choose to ignore the defects liability/maintenance period; both have contracted on that basis. Beyond the provisions of that clause, the normal rules of limitation apply. 151 151 Nigel M Robinson. Supra 20. pp. 171-172 55 CHAPTER 4 EMPLOYER’S RIGHTS AND CONTRACTOR’S LIABILITIES IN RELATION TO CONSTRUCTION DEFECTS AFTER FINAL CERTIFICATE 4.1 Introduction In construction industry, all construction work is done within a contract except that done by a person for himself.152 The essence of a construction contract is that the contractor agrees to supply work and materials for the erection of a building or other works for the benefit of the employer. The design of the work to be carried out is often supplied by or on behalf of the employer, but may also be supplied in whole or in part by the contractor. In legal terms there is no difference between a building and an engineering contract, and the term construction contracts is adopted to cover both.153 There are various classes of conditions which are inserted in building and engineering contract as to defects, repairs and maintenance. Under a covenant to repair from the date of final certificate, a builder is not bound to do more than repair 152 Keith Collier. “Construction Contracts.” 3rd Edition. (New Jersey : Merrill Prentice Hall, 2001.) pp. 3. 153 John Uff. “Construction law: Law and Practice Relating to the Construction Industry.” 5th Edition, (London: Sweet & Maxwell, 1991) pp. 152. 56 the structure, including making good the effects of ordinary wear and tear; also he is bound to make good damage from other causes and to keep the premises in the condition they were in at the beginning if the period over which the repair obligation extends. 154 Hence, after reviewing the concepts of defective work and defects liability in the previous chapters, this chapter will identify and analyse the circumstances which will render the liability of defective works. Those circumstances are based on decided court cases, which mainly were held under Malaysia Law and laws in other commonwealth countries. 4.2 Conclusiveness of Final Certificate Contractor's liability in relation to defects in the construction works following the issue of a Final Certificate. Generally, a conclusive and binding final certificate discharges the liability of the contractor for defects in the work both to the employer and in any third party contribution proceedings. 4.2.1 James Png Construction Pte Ltd v Tsu Chin Kwan Peter155 In James Png Construction Pte Ltd v Tsu Chin Kwan Peter 156, the plaintiffs, building contractors, agreed with the defendant, the owner of a single-storey detached house to construct and complete an additional storey thereon for a lump sum payment of $118,800. The agreement incorporated the Singapore Institute of Architects Conditions of Contract (1979 Ed). Due to disputes over defects rectification between the defendant and his architect, payment of the balance due 154 William H. Gill. Emden and Gill’s Building Contracts and Practice. 7th Edition. London: Butterworths, 1969) pp. 255 155 [1991] 1 MLJ 449 156 [1991] 1 MLJ 449 57 under the Interim Certificate No. 4 and the amounts due under the penultimate and final certificate to the plaintiffs amounting to $37,157.50 were not made. Upon the plaintiffs' application for summary judgment, the deputy registrar gave judgment for $11,342.13 and allowed $ 25,615.37 to proceed to trial. Both parties appealed. On appeal, the defendant contended that no valid final certificate was issued as it was issued prematurely before the end of the defects liability period. The defendant's claims were for damages for defective work and consequential losses and thus not covered by the conclusiveness of the final certificate. Karthigesu J said that the architect would not or should not issue the final certificate until after the end of the defects liability period because once the final certificate is issued before the end of the defects liability period and defects occur during the defects liability period the architect will have to assume the risk on account of the conclusiveness of the final certificate both as to completion and as to the quality of the workmanship. The final certificate issued by the architect was perfectly valid. Its conclusiveness cannot be impugned. The claims for damages for defective work and consequential losses do not constitute damages for defective work by the plaintiffs, which in any case cannot be maintained in view of the conclusiveness of the final certificate. It was held that according to Clause 30(6) of the conditions of contract does not impose by express words a prohibition on the architect that he shall not issue a final certificate before the end of the periods (whichever is the latest) therein limited. Nor can it be implied. It simply sets out the latest period by which the architect must issue his final certificate. It was open to the architect to issue his final certificate at any time provided that he was satisfied the defects listed had been made good by the plaintiffs to his satisfaction. Therefore, the final certificate issued by the architect was perfectly valid and its conclusiveness cannot be impugned. 58 The defendant's claim for $ 25,615 when broken down to its component parts cannot be said to be a claim for damages for defective work or consequential losses. This amount constituted sums that had been spent by the defendant in rectifying defects, work done and loss caused by the plaintiffs' delay in rectifying defects. These sums do not constitute damages for defective work as they did not relate to the architect's list of defects and which in any case cannot be maintained in view of the conclusiveness of the final certificate. 4.2.2 Shen Yuan Pai v Dato Wee Hood Teck & Ors 157 In Shen Yuan Pai v Dato Wee Hood Teck & Ors 158 , the defendants had contracted with the plaintiff for the construction of certain works in relation to an office building in Thomson Road, Kuching. The plaintiff claimed that in spite of repeated requests he had not received payment from the defendants and he commenced action by a specially indorsed writ against them for the sum of $106,918. This is the balance which he alleged to be due to him for the completion of the construction of the building. The defence and counterclaim of the defendants was founded on, inter alia, delay in the completion of the construction work by the plaintiff, failure on the part of the architect to re-measure the reinforced concrete work in the building upon completion and the validity of the alleged final certificate issued and accordingly claimed for loss of profits and damages for non-completion of works contracted for within the time specified in the contract. It was held that as the architect in this case had issued his final certificate, thereby showing his satisfaction with the works carried out by the plaintiff, the plaintiff was entitled to the amount claimed. The certificate issued by the architect in this case was conclusive. On conclusiveness of a final certificate, Bth Lee J said that 157 158 [1976] 1 MLJ 16 [1976] 1 MLJ 16 59 "The first question is whether, on the true construction of the conditions, a final certificate issued by the architect is conclusive evidence as to the sufficiency of the works subject only to the exceptions mentioned in clause 24(f) of the contract. Melford Stevenson, J., came to the conclusion that it was not, but thought that it was only conclusive evidence as between the building owner and the builder until power to re-open it vested in an arbitrator appointed pursuant to clause 27. In the Court of Appeal, reversing Melford Stevenson, J., on this point, it was unanimously decided that a final certificate was final and conclusive save as to the exceptions stated in the sub-clause." In Halsbury's Laws of England Volume 4, 4th Edition, page 616, it is provided that except in cases where there is an arbitration clause entitling an arbitrator to review the decisions of the architect as to the amount due or as to whether the works are in accordance with the contract, or where the architect is disqualified from certifying or where the certificate may otherwise be dispensed with, the final certificate will be conclusive. In this judgment the intention of the parties was expressed in terms by the Agreement that the satisfaction of the Architect was to be expressed in his final certificate which unless there has been a request for arbitration is conclusive evidence that the works had been properly carried out and completed in accordance with the terms of the contract. In this case, it excuses the contractor from liability for what could be breaches of contract and obviates the operation of the Limitation Act 1953 providing that actions founded in contract and tort shall not be brought after the expiration of six years from the date on which the cause of action accrued. The Final Certificate shall be conclusive evidence as to the sufficiency of the said works and materials. It prevented any further legal action, including legal proceedings started before the certificate was issued. The certificate is not reviewable by the arbitrator because it is ‘conclusive evidence that any necessary effect has been given to all the terms of this Contract which require an adjustment to the Contract Sum’. 60 4.2.3 Sa Shee (Sarawak) Sdn Bhd v Sejadu Sdn Bhd159 In Sa Shee (Sarawak) Sdn Bhd v Sejadu Sdn Bhd 160, the plaintiff (builder) was engaged by the defendant to do some works on a sea wall and some land reclamation. A final account and final certificate with regard to the project was issued in April 1996. The parties had some disputes but was amicably settled when the plaintiff accepted an offer of the defendant in full and final settlement of the claim of the plaintiff subject to the defendant reserving their rights to counter claim or seek recompense. In December 1997, the defendant complained and demanded rectification of cracks in certain rooms and a sea wall, and also of sink-holes on the reclaimed land. As the plaintiff disputed liability, the defendant proceeded to have the matter referred to arbitration under the contract. The plaintiff however took up this action and sought for a declaration that there was no dispute to be referred to arbitration on the ground that the plaintiff was under no liability to the defendant. The plaintiff contended that even though clause 44 of the contract provided that no certificate should be considered as conclusive evidence as to the sufficiency of any design, works, materials or goods to relieve the contractor of liability, it should be read subject to clause 43.7 which provided the final certificate and final account would become conclusive to the balance due to the parties, otherwise clause 43.7 would be repugnant. The defendant contended that clause 43.7 should be read with other related clauses of clause 43.6.5 and clause 43.10 and that the payment of the defendant was not conclusive evidence of any design, works, materials or goods in the contract. The plaintiff's application is accordingly dismissed with costs to the defendant. It was held that the final certificate did not resolve all the disputes 159 160 [2000] 5 MLJ 414 [2000] 5 MLJ 414 61 between the parties but only in relation to the amount due under the certificate leaving claims relating to the designs, works, materials and goods still open. Clause 43.7 was concerned with a certificate being conclusive as to the balance due between the parties as it only dealt with the balance due and was further shown by clause 43.6.5 which spoke only of the conclusiveness of the balance due. These two provisions contrasted with clause 43.10, which dealt with payment for the interim certificate or final certificate, and not being conclusive evidence as to the 'design, works, materials or goods'. There is no conflict between clause 43.7 and clause 44 as they dealt with separate matters, that is, one with a balance and the other with designs, works, materials or goods. Therefore, there is no inconsistency as to require harmonization. 4.2.4 Chew Sin Leng Construction Co v Cosy Housing Development Pte Ltd161 In Chew Sin Leng Construction Co v Cosy Housing Development Pte Ltd 162, the plaintiffs and the defendants entered into a contract to carry out and complete the construction of 20 units of condominium housing for a sum of $1,550,000. Pursuant to the contract, the defendants sought the payment to them of a certain sum of money which was supposed to be paid under an architect's certificate of final payment. In furtherance of their claim, the plaintiffs took out an Order 14 summons for final judgment. The learned Deputy Registrar dismissed the defendants' application for a stay. The defendants appealed against the Registrar's decision. Thean J., who heard the appeal, set aside the order of the learned Deputy Registrar and stayed all proceedings pending arbitration. The plaintiffs appealed to the Court of Appeal. In the process of the appeal, two affidavits were allowed to be admitted on behalf of the plaintiffs. 161 162 [1988] 1 MLJ 137 [1988] 1 MLJ 137 62 The points for decision in the present appeal were whether in the circumstances of the instant case, the certificate of final payment was a final certificate within the meaning of clause 30(6), and whether even if the said certificate of final payment was found to be a final certificate under clause 30(6), it was not conclusive at least in one aspect, there being defects falling within exception (b) to clause 30(7). Appeal was allowed. On the first point the court was of the view that had these affidavits, particularly that of the architect, been before the learned appeal judge, he would not have set aside the learned Deputy Registrar's order. On the second point the court accepted the submission that the defects relied on were those which the purchasers of the units had raised with the developer and these were not the defects contemplated by this provision. One must look at the contract between the developer and the contractor and not at any contract between the developer and the purchasers of the units. 4.2.5 Usahabina v Anuar Bin Yahya163 In this case, the plaintiff entered into an agreement with the defendant for the construction of a house according to drawings and specifications prepared by the architect. The plaintiff then commenced proceedings against the defendant for the recovery of the amount due under the agreement. The defendant entered an unconditional appearance. The defendant failed to file the defence despite being given an extension of time to do so. The plaintiff entered a judgment in default against the defendant on 15 July 1997. 163 [1998] 7 MLJ 691 63 By letter dated 25 July 1997, the defendant informed the plaintiff that the dispute should be referred to arbitration according to clause 34 of the agreement. The defendant then filed an application praying, inter alia, for the judgment in default be set aside and the matter be stayed pending reference to arbitration. It was submitted that on the basis of the plaintiff's case, i.e. the architect's certificate were not final and could be challenge and since there was a dispute and as the defendant was ready and willing to go for arbitration, in accordance with clause 34, the onus was on the plaintiff to show why the matter ought not to be referred as required. The issue before the court was whether the defendant had satisfied the conditions under s6 of the Arbitration Act 1952. The defendant’s application dismissed. In this case the defendant's complaints are against defective workmanship and the use of sub-standard materials. There was no provision in the agreement whereby the plaintiff must execute the works to the satisfaction of the defendant. The only instructions that the plaintiff must comply with were those of the architect. The conclusiveness of a final certificate could be challenged only if a request for arbitration was sought within the period specified in the agreement. In that event, the final certificate ceased to be final and may be reopened for resolution. Therefore, unless a written request to concur in the appointment of an arbitrator shall have been given under clause 34 of these conditions by either party before the final certificate has been issued or by the contractor within 14 days after such issue, the said certificate shall be conclusive evidence in any proceedings arising out of this contract. 4.2.6 P & M Kaye Ltd v Hosier & Dickinson Ltd164 This was an appeal by the employers, P & M Kaye Ltd, against an order of the Court of Appeal allowing the appeal of the contractors, Hosier & Dickinson Ltd, from the judgment on the trial of a preliminary issue in two actions brought by the 164 [1972] 1 WLR 146 64 contractors for sums due to them for work carried out under a building contract, held that the employers' counterclaim for loss of profits due to defective work and materials was not barred by the terms of the contract. An agreement was made in between the contractors and the employers, where the contractors undertook to build a warehouse and offices. The contract was in the standard form of the RIBA and included an arbitration clause (clause 35) which provided that any dispute arising as to the construction of the contract was to be referred to an arbitrator. Work on the warehouse was substantially complete by June 1967 although, with the consent of the contractors, the employers had taken possession in the previous April. Interim certificates were issued by the architect in April and July following which the employers paid sums on account, leaving a balance unpaid of £14,861. They complained that the floor of the warehouse was faulty. The contractors relaid the floor and completing the work in August and started proceedings to recover the £14,861. however, the employers put in an affidavit of defence which alleged that the flooring was still faulty and that the previous defects had resulted in a loss of profits amounting to £13,500. Following further correspondence, the architect issued the final certificate for the balance of money due to the contractor. Clause 30 (7) of the contract provided that 'Unless a written request to concur in the appointment of an arbitrator shall have been given... by either party before the Final Certificate has been issued... the said certificate shall be conclusive evidence in any proceedings arising out of this Contract... that the Works have been properly carried out and completed in accordance with the terms of this Contract...' Employers requested the contractors to concur in the appointment of an arbitrator. The contractors pointed out that it was too late and they issued a second writ for the amount due on the final certificate. The action on the interim certificate was still on the file and the employers put in a defence and counterclaim in each action claiming £13,500 loss of profits because of the defective floor. 65 The two actions were consolidated and the official referee directed the following preliminary issue to be tried: whether in view of the terms of clause 30(7) and the issue of the architect's final certificate the employers were 'estopped from relying on their Defence and Counterclaim'. The employers appealed from a decision of the Court of Appeal that their counterclaim for bad work was barred in both actions. They contended that it had been impliedly agreed between the parties to vary the contract by the exclusion of clause 30(7), or that the contractors had waived their right to rely on it, or were estopped from relying on it. They further contended that the meaning of the words in clause 30(7) 'the said certificate shall be conclusive evidence in any proceedings arising out of this Contract' should be understood as being limited to proceedings begun after the issue of the final certificate and that, if proceedings in a court were pending, a final certificate would not be conclusive evidence. Although in the Court of Appeal had been accepted that in the event of a decision on the preliminary issue in favour of the contractors the litigation would be concluded in their favour, during the hearing of the appeal an entirely new argument was sought to be introduced on behalf of the employers to the effect that, although clause 30(7) made the final certificate conclusive as to the state of affairs existing at its date, it had no effect as regards a pre-existing and vested right to damages including particularly consequential damages arising in respect of breaches of contract before its date. 4.2.7 Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd165 In Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd 166 , Matthew Hall carried out the work and it was alleged by Tarmac Roadstone that 22 steel bunkers were suffering from what appeared to be structural damage as a result of design and construction deficiencies emanating from Matthew Hall’s breaches of contract. The 165 166 [1997] 87 BLR 96 [1997] 87 BLR 96 66 responsibility for issuing the final certificate lay with Tarmac Roadstone, but no such certificate was ever issued. Matthew Hall argued that a final certificate should have been issued, and if it had been, it would have acted as a bar to any claim from Tarmac Roadstone. It was Tarmac’s argument, even if they had issued a final certificate, they would not be prevented from bringing a claim against Matthew Hall. This matter was referred to arbitration. It was held by the arbitrator that a final certificate would bar contractual claims against Matthew Hall for defects which it was accused of not correcting, but would not prevent either a contractual claim for defects allegedly put right, but later discovered to have been done badly, or a claim for latent defects. The court did not fully agree with the arbitrator. It was considered that there would appear to be commercial justification for the contract to provide a definite cutoff point once plant has been constructed, tested, provided and made good in all respects in conformity with the contract. The court considered that Matthew Hall were correct in their contention that a final certificate is conclusive evidence that all work has been completed in accordance with the requirement of the contract. 4.2.8 University Fixed Assets Limited v Architects Design Partnership167 In Oxford University Fixed Assets Limited v Architects Design Partnership 168 the University had entered into a contract with Wimpey Construction Limited for the construction of building to house the Department of Pharmacology and the 167 168 [1999] 64 Con LR 12 [1999] 64 Con LR 12 67 Anatomical Neurapharmocology Unit. The form of contract was JCT 1980 without Amendment 15. The Architect was ADP. The University alleged that partition walls of blockwork were not protected from weather and kept dry, so that when they dried out widespread cracking was caused. ADP issued a list of defects after Practical Completion, to be made good in the Defects Liability Period, which included cracking in the plaster to the blockwork. Remedial works were carried out and the Final Certificate issued under Clause 30.9 of the building contract. The University sought damages from ADP for the cost of rectifying the problem of cracking walls. It alleged that ADP had negligently issued the Final Certificate. ADP denied liability and issued a third party notice against Wimpey claiming that Wimpey was liable to the University due to breaches of the building contract. It was assumed in the proceedings that the defects in the blockwork constituted damage which occurred prior to the issue of the Final Certificate. In order to decide the issue, His Honour Judge Humphry Lloyd QC examined the nature and effect of the Final Certificate. He recognised that the JCT Form envisaged that within a specific period from practical completion of the works, finality would be achieved both as regards the final account and also the contractor’s liability for the extent and quality of the work, material and services which it undertook to provide. It was held that the effect of the Final Certificate was not that it left Wimpey with no liability in law, but that it operates only as an evidential bar which would preclude an employer from being able to prove the facts necessary to establish such liability. Once the Final Certificate has been issued, no liability could be established by the University against Wimpey, since a claim by the University in respect of the same damage for which ADP sought contribution from Wimpey (the defects in the 68 blockwork) would have been defeated. In any ordinary and natural meaning of the word, liability could not have been established. The issue of the Final Certificate is thus tantamount to a decision discharging the liability of the contractor. It would be rank injustice for the Civil Liability (Contribution) Act 1978 to permit the person who by its own negligence to the common client procured that liability could not be established by that client, to then claim contribution as if that act had not occurred and as if the client could have done so. It was held that although the Final Certificate did not constitute a cessation of liability for the purposes of the Act, liability could not be established so that the Final Certificate afforded a defence to Wimpey to the action for contribution. 4.2.9 Crown Estate Commissioners v John Mowlem and Co Ltd169 In Crown Estate Commissioners v John Mowlem & Co. Ltd 170, the issue was the interpretation of Clause 30.9.1.1 of the JCT 80 form before Amendment 15171. The clause provided that the Final Certificate was conclusive evidence that where the quality of materials or the standard of workmanship are to be to the reasonable satisfaction of the Architect the same are to such satisfaction. It was recognised that there are three different criteria for the standards and quality of work. First the criteria could be stipulated in the contract documents, for example British Standard Specifications. Second the standard and quality may not be stated in the contract documents but by terms implied. Third the standards and quality may be expressed to be to the Architect’s satisfaction. It was therefore necessary to decide whether the conclusive effect of Clause 30.9.1.1 applied only to those standards expressed to be to the Architect’s satisfaction or whether it extended to all works on which the Architect was required to form an opinion. 169 [1994] 70 BLR 1 [1994] 70 BLR 1 171 Amendment 15 to the JCT 80 Form, incorporated in JCT 1998, makes the Final Certificate conclusive only of the Architects satisfaction, where it so expressly provides, but not conclusive that the works have been carried out in accordance with the contract. 170 69 It was held that the conclusive effect of clause 30.9.1.1 applied not only to such materials and workmanship as are expressly reserved by the contract to the opinion of the Architect but includes all approvals of materials and workmanship which is inherently something for the opinion of the Architect. It was a matter of fact and degree in each case whether the quality of materials or the standard of workmanship is inherently a matter for the Architect. 4.3 Consequential Loss Generally, the satisfactory making good of defects does not amount to an exclusion of claims in respect of their consequences. The measure of damages will therefore not only be the cost of repair of the defect, but also such compensation as the loss of the use of the premises during repairs in accordance with the ordinary rules governing remoteness of damage. 4.3.1 Teh Khem On & Anor v Yeoh & Wu Development Sdn Bhd & Ors 172 In Teh Khem On & Anor v Yeoh & Wu Development Sdn Bhd & Ors 173, the plaintiffs (purchasers) entered into a sale and purchase agreement with the first defendant (builder) to purchase a house. After the purchasers took possession of the house, they found that the house was defective, i.e. there were cracks on the walls and floor, and the house had tilted and was sinking. The purchasers then moved out from the house. The builder admitted the liability to repair the defects and carried out 'cement-grouting' to remedy the problems, but this proved ineffective. 172 173 [1995] 2 MLJ 663 [1995] 2 MLJ 663 70 In the High Court, the purchasers had claimed against the builder, inter alia, for rescission of the agreement, refund of the purchase price and damages. The purchasers have further claimed against the second defendant (architect) and the third defendant ('the engineer') for damages in negligence. As a defence, the defendants argued that they were not liable, as the damage had occurred after the 12-month defect liability period under clause 23 of the agreement. It was held that the builder was liable for breach of contract, and that the architect and the engineer were not liable. The court found that the damage which occurred was principally due to settlement of the house. The settlement happened as the fill of the building site was too thick, the material used as the fill was unsuitable, and the foundations of the house were inadequate. The court further found that the damage was extensive and ongoing, and that cement-grouting had not stopped the settlement. The builder who was in direct contractual relations with the purchasers by virtue of the agreement, was in breach of the express condition in clause 12 of the agreement which provided that the house must be constructed in a good and workmanlike manner. Apart from that, the builder was also in breach of the three implied conditions of the agreement, i.e. that it would do its work in a good and workmanlike manner, that it would supply good and proper materials, and that the house would be reasonably fit for human habitation. The builder was therefore liable to the purchasers under both the express and implied conditions of the agreement, in the absence of any provision which exempted its liability in such circumstances. Clause 23 of the agreement which provided for the 12-month defect liability period would not take away the right of the purchaser to sue for defects which were not discoverable within that period. As for defects which were discovered within the 12-month period, although clause 23 had expressly provided for the remedy of repairing the defects, that would not exclude the purchasers' right to sue for breach of contract at common law. The purchasers in this case were only entitled to claim 71 damages for breach of contract as the settlement of the house had only appeared after the conveyance of the house to the purchasers had been completed. The measure of damages was based on the cost of remedying the defect, i.e. the cost of micropiling. The cost of investigation of the damage by the experts engaged by the plaintiff which had been pleaded and proved would also be allowed. 4.3.2 James Png Construction Pte Ltd v Tsu Chin Kwan Peter 174 In this case, the plaintiffs, building contractors, entered into an agreement in writing, agreed with the defendant, the owner of a single-storey detached house to construct and complete an additional storey. The agreement incorporated the Singapore Institute of Architects Conditions of Contract (1979 Ed) ('the conditions'). The defendant's appeal dismissed with costs. The defendant's claims were for damages for defective work and consequential losses and thus not covered by the conclusiveness of the final certificate. The defendant's claim for $25,615 when broken down to its component parts cannot be said to be a claim for damages for defective work or consequential losses. This amount constituted sums that had been spent by the defendant in rectifying defects, work done and loss caused by the plaintiffs' delay in rectifying defects. These sums do not constitute damages for defective work as they did not relate to the architect's list of defects and which in any case cannot be maintained in view of the conclusiveness of the final certificate. Karthigesu J said: “In my view these two sums do not constitute damages for defective work by the plaintiffs, which in any case cannot be maintained in view of the conclusiveness of the final certificate. Quite clearly they constituted payments for work outside the contract and are not claimable by the defendant.” 174 [1991] 1 MLJ 449 72 4.3.3 Shen Yuan Pai v Dato Wee Hood Teck & Ors 175 In this case, the defence and counterclaim of the defendants is founded on, inter alia, delay in the completion of the construction work by the contractor, failure on the part of the architect to remeasure the reinforced concrete work in the building upon completion and the validity of the alleged final certificate issued and accordingly claimed for loss of profits and damages for non-completion of works contracted for within the time specified in the contract. The counterclaimed $101,400 and $ 122,850 respectively is for prospective loss of rental. Bth Lee J said: “In my judgment the intention of the parties was expressed in terms by the Agreement that the satisfaction of the Architect was to be expressed in his final certificate which unless there has been a request for arbitration is conclusive evidence that the works had been properly carried out and completed in accordance with the terms of the contract.” If there is a loss it was not sustained in consequence of the delay on the part of the plaintiff while in fact it arose from the neglect and inactivity of the defendants themselves which the delay was entirely a consequence from the default of the defendants in not appointing the specialists to do their work in time. Therefore, the defendants are not entitled to the damages sought. In the result there will be judgment for plaintiff with costs and the defendant's counterclaim must be dismissed. 4.3.4 P & M Kaye Ltd v Hosier & Dickinson Ltd 176 In this case, during the construction of the works or during the defects liability period defective work had been done by the contractor in breach of contract, which had caused consequential damage to the employer before the defects were 175 176 [1976] 1 MLJ 16 [1972] 1 WLR 146 73 made good. The new contention raised by the employers in argument on appeal was a sound one and ought to be admitted since it raised a pure point of construction of words which formed part of a single paragraph of the clause which was the subject of the dispute and it would be intellectually baffling to attempt to construe the remainder of clause 30(7) on the assumption that one of the most important phrases in it meant something different from what it clearly did mean. The provision in clause 30(7) that the final certificate should be conclusive evidence 'that the Works have been properly carried out and completed in accordance with the terms of this Contract' dealt, not with the activities of the contractors, but with the state of the works at the time of the issue of the certificate as a result of the activities of the contractors. The issue of the final certificate was not to be taken as conclusive evidence that at no time previously had there been defects in the works which required remedying; it was merely conclusive evidence that any remedial measures which had been necessitated by reason of defects in the works had been executed by the time of its issue. The final certificate was irrelevant to any claims for consequential damage in respect of defects which had been found after the employers had taken possession and before the issue of the final certificate. Accordingly the employers should not be debarred from pursuing their claims for consequential loss. 4.3.5 HW Nevill (Sunblest) Ltd v William Press & Son Ltd 177 By a contract dated 7 December 1973, the plaintiffs agreed that the defendants should carry out works consisting of site clearance, piling, foundation and drainage works prior to the erection of a bakery at Walthamstow, London. The contract was in the JCT standard form, private edition with quantities, 1963 edition, July 1973 revision. The work was carried out between September 1973 and April 1974, when new contractors (Trenthams) commenced work. Certificate of Practical Completion, Certificate of making good defects and Final Certificate were issued. In November 1974 the plaintiffs' architect discovered that the drains laid by the defendants were defective and that there were defects in the hard-standing. The 177 20 Build LR 78 74 defendants returned to the site and the defects were remedied. However Trenthams had been delayed by four weeks and the plaintiffs had to pay them for that delay and for additional work consequent on the defects in the defendants' work. The plaintiffs also incurred additional architects' fees and losses because the bakery was late in opening. The plaintiffs commenced proceedings claiming that the defendants were in breach of contract and they were therefore liable for the plaintiffs' additional costs and other consequential losses. The defendants maintained that the plaintiffs were precluded by the Final Certificate issued under Clause 30(7) of the contract from bringing any claim in respect of the alleged breach of contract and/or that the plaintiffs' remedies in respect of the alleged defective work were limited to those remedies set out in Clause 15 of the contract. The court held that the final certificate was only conclusive that the work complied with the contract at the date when it was given. It did not follow that the original construction had been in accordance with the terms of the contract and therefore, the employer was justified in arguing that the defects constituted breaches of contract. The plaintiffs' remedies were not limited to the remedies specified in Clause 15 since the defects in the works were breaches of contract. Clause 15 merely created a simple way of dealing with part of a situation created by breaches of contract and was not to be read as depriving the injured party of his other rights. The plaintiffs could therefore claim damages for breach of contract to include consequential loss. Further, the plaintiffs were not precluded by the terms of the Final Certificate and by Clause 30(7) from pursuing claims for breach of contract in respect of consequential loss because the architect was not required to decide whether the employer had suffered consequential loss or to assess the amount of such loss. The architect at the time of giving his final certificate was not dealing with consequential 75 loss. The final certificate was not conclusive as to such matters: P & M Kaye Ltd v Hosier & Dickinson Ltd 178 distinguished; dicta of Lord Diplock ibid, followed. There was no representation by the defendants to the plaintiffs of a willingness to accept liability for consequential loss (and not merely admissions as to liability for defects). If, contrary to the findings with regard to the above issues it would avail the defendants to rely on the Final Certificate and Clause 30(7), they would not be estopped from doing so. 4.4 Latent Defects Latent Defect means a defect in the work which would not ordinarily be observed during a walk-through inspection. Naturally, contractors take comfort from a final certificate and assume that no new or further claims can be made against them for defective or incomplete works under the final certificate, other than latent defects. 4.4.1 P & M Kaye Ltd v Hosier & Dickinson Ltd 179 In the judgement of Lord Diplock, it is stated that if latent defects are discovered during defects liability period it is extended until the contractor has made them good and the architect has so certified. During this period the contractor's obligation is to make good to the satisfaction of the architect any latent defects that may become apparent. After the end of this period the contractor is not liable to remedy any further defects; but the contract sum may be adjusted by reason of any 178 179 [1972] 1 WLR 146 [1972] 1 WLR 146 76 defects which would not have been apparent on reasonable inspection or examination before the issue of the final certificate. 4.4.2 London Borough of Barking and Dagenham v Terrapin Construction Ltd180 In this case, the contractor (Terrapin) contracted with the employer (Barking & Dagenham) for new build and refurbishment work at a school in Dagenham under JCT 1981 Design and Build Conditions. Barking & Dagenham considered that there were a substantial number of defects in the building and started an action claiming damages for breach of contract, breach of statutory duty and negligence. Terrapin argued that they had a 'conclusive evidence' defence, following the agreement of the final account and final statement. His Honour Judge Newman QC held that: 'All the claims advanced by the plaintiff are subject to a defence of conclusive evidence by reason of the operation of clause 30.8.1181 of the JCT conditions, save and except for those claims which are based upon any failure to meet any statutory requirements which, under the provisions of clause 6 of the conditions, are the responsibility of the defendant.' Terrapin appealed and Barking & Dagenham cross-appealed. It was held that on its proper construction, clause 30.8.1 made no distinction between patent and latent defects (save in so far as bad work may have been fraudulently concealed). Although the assumption of the responsibility for the design was fundamental to a 180 74 ConLR 100, [2000] Build LR 479 'The Final Account and Final Statement when they are agreed or become conclusive as to the balance due between the parties in accordance with clause 30.5.5. or the Employer's Final Account and Employer's Final Statement when they become conclusive as to the balance due between the parties in accordance with clause 30.5.8 shall, except as provided in clauses 30.8.2 and 30.8.3 (and save in respect of fraud), have effect in any proceedings arising out of or in connection with this contract (whether by arbitration under article 5 or otherwise).’ 181 77 'with Contractor's design' Standard Form of Contract, the employer has supervisory responsibility (or expertise) when retaining a contractor on a design and build contract. The Standard Form assigns several functions to the employer which require him to form an opinion. The employer had retained the right, and the responsibility, of satisfying themselves as to the works 'in all aspects' (save as to design). Therefore, agreeing the final account and final statement provided conclusive evidence of their satisfaction as to the quality of all materials and the standard of workmanship including (in the absence of their exclusion) all defects, patent or latent (save for fraud). 4.4.3 Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd182 In this case, Matthew Hall contracted with Tarmac for the design, erection and commissioning of a mineral processing plant under the IChemE Red Book 1981 edition. The main issue in this case was whether the final certificate prevented claims for defects that were latent at the time of issue of the certificate. The contract incorporated the IChemE Red Book 1981 revision. The relevant contractual provision is Clause 38.5 of the form, which has the following key words: "The issue of the final certificate ... shall constitute conclusive evidence for all purposes and in any proceedings whatsoever between the purchaser and the contractor that the contractor has completed the works and made good all defects therein in all respects in accordance with his obligations under the contract." Tarmac commenced arbitration proceedings to recover the cost of rectification of defects and other related costs, which it alleged it had incurred as a result of Matthew Hall's breaches of contract. Matthew Hall argued that Tarmac had failed to issue a Final Certificate when it was properly due under the contract, and as a consequence they were deprived of the immunity from Tarmac's claim that the Final Certificate would have given. The arbitrator therefore had to examine whether 182 [1997] 87 BLR 96 78 the claim for such defects would have been barred by the Final Certificate had it been issued. The arbitrator concluded that Tarmac was not prevented from bringing its claim for latent defects since the Final Certificate was only conclusive evidence that the contractor had physically made good the defects drawn to its attention. On appeal to the Court this decision was set aside. The judge carefully explained his reasons. He firstly explained that in interpreting Clause 38.5, no distinction was to be made between latent and patent defects. In any event, he explained that the defects complained of in this case were patent. A latent defect is one which has not manifested itself but which will, over time, become apparent and give rise to damage to the works. In this case the defect was a patent shortcoming in the design or workmanship which, as a consequence, had given rise to structural damage. The judge concluded that Tarmac's claim was based upon a failure to complete the works in accordance with the contract. The conclusive evidence provision in Clause 38.5 extended to a presumption that all work and services provided were completed in accordance with the Contractor's obligations under the contract. This arose not as a consequence of the words "in all respects in accordance with his obligations under the contract" found in Clause 38.5, but as a consequence of the definition of the 'Works' found elsewhere in the contract. Nevertheless, the effect was the same. Tarmac would be prevented from bringing its present claims in contract, or alternatively tort, because of its failure to issue a Final Certificate. Clause 38.5 of the contract operated to provide an evidential bar to Tarmac's claims in contract and/or tort. Therefore, once the Final Certificate is issued under this form of contract the employer is prevented from bringing claims for defects in the works arising from a breach of contract and/or tort irrespective of whether those defects may be said to be latent or patent. 79 4.5 Fraud / Concealment Where defects first come to light after completion, the statutory limitation or prescription period will begin to run from the different dates of awareness of any distinct defect. If defects are concealed by a contractor, this may result in an extension to the limitation period. Section 29 of the Limitation Act provides that where an action is based upon the fraud of the defendant, or any fact relevant to the plaintiff's right of action has been deliberately concealed by the defendant, the period of limitation does not begin to run until the plaintiff has discovered the fraud or concealment or could, with reasonable diligence, have discovered it. Accordingly, where defective work or workmanship or design have been knowingly covered up or concealed so as to constitute fraud, the commencement of the limitation period may be delayed. 4.5.1 Musselburgh and Fisherrow Co-operative Society v Mowlem Scotland183 In the case of Musselburgh and Fisherrow Co-operative Society v Mowlem Scotland 184, the claim concerned the costs of putting right defects in the works. In early 1991, Mowlem had entered into a building contract with Musselburgh to design and construct Quayside Leisure Centre at Musselburgh. The contract was the SBCC Standard Form of Building Contract With Contractor's Design, the Scottish version of the JCT 98 WCD form. The leisure centre opened to the public in May 1992. It included function suites, a bar and restaurant and a swimming pool. The swimming pool was later discovered leaked. There were three primary reasons for the leak. Firstly, the design of the perimeter overflow channel to the pool and the adjacent walkway around the pool was poor. Watertightness relied upon a sealant at the joint between the overflow 183 184 [2006] CSOH 39 [2006] CSOH 39 80 channel and the walkway. The sealant had failed. Secondly, leaks were occurring at the joints between the overflow channel and the drainage pipework. Thirdly, there was seepage of moisture from the swimming pool through the wall of the swimming pool itself. Whilst the amount of water leaking out of the pool in this way was thought to be quite small, Musselburgh was particularly concerned that this defect threatened the structural integrity of the swimming pool tank. In all three cases, water was accumulating in a duct which ran under the walkway around the perimeter of the pool and was being drained by a sump pump which had been installed for this purpose. On evidence it was disclosed that Musselburgh had been aware of the first two sources of leak since shortly after practical completion of the works. Lord Eassie concluded that in respect of these two defects, Musselburgh could, with reasonable diligence, have ascertained from early 1993 that they were suffering loss in respect of an act, neglect or default of the builder. Since proceedings had not been commenced within five years of that date, it was too late for Musselburgh to recover damages in respect of those defects. In Lord Eassie's view, however, the third defect was quite different. It was plain from the evidence that nobody had actual knowledge of the existence of the seepage problem through the wall of the swimming pool until an expert had completed an intrusive survey in November 2002. He was satisfied that there was nothing prior to that date that would have reasonably alerted Musselburgh to the seepage problem. Nor did he accept the argument put forward by Mowlem, to the effect that awareness of the building owner of one defect was sufficient to start the time running for all defects for which the contractor might be responsible. The proper approach for the purposes of the five-year prescription period was to examine each distinct defect and its failure in construction or design separately. In consequence, Musselburgh was entitled to press its claim for damages in respect of the third defect, since the prescription period in respect of that claim had not expired. 81 4.5.2 William Hill Organisation Ltd v Bernard Sunley and Sons Ltd185 In this case, the plaintiffs (the employer) entered into a contract under seal with the defendants (the contractor) for the construction of an office block in Blackfriars Road, London. The contract incorporated the RIBA Conditions 1939 edition (revised 1957). Clause 24 of the contract conditions proved inter alia that: "(g) Unless notice in writing of a dispute or difference shall have been given . . . before the final certificate has been issued the final certificate shall be conclusive evidence in any proceedings arising out of this contract (whether by arbitration under clause 26 hereof or otherwise) that the Works have been properly carried out and completed . . . in accordance with the terms of this Contract save in so far as it is proved in the said proceedings that any sum mentioned in the said certificate is erroneous by reason of (i) fraud, dishonesty or fraudulent concealment relating to the Works or any part thereof or to any matter dealt with in the said certificate; or (ii) any defects (including any omission in the Works) which reasonable inspection or examination at any reasonable time during the course of the Works or before the issue of the said certificate would have not disclosed: . . . (h)Save as aforesaid no certificate of the Architect shall of itself be conclusive evidence that any works or instructions to which it relates are in accordance with the Contract." The building had a reinforced concrete frame with reinforced concrete walls, clad externally in part with stone, and in part with glass mosaic. The cladding was erected by nominated sub-contractors. Many defects in the cladding, namely corrosion of the fixings, which were defective, and the absence of compression beds, first came to light in late 1971 and early 1972. It was considered that they were isolated instances, and not grounds for suspecting more widespread defects. 185 [1982] 22 BLR 1 82 In the summer of 1974 signs of movement in the cladding were observed and defective fixings exposed. Further areas were opened up, exposing similar defects, and the plaintiffs decided to remove all the cladding. On 11 March 1975 the plaintiffs issued a writ claiming damages for breach of contract and for negligence in respect of the stone cladding. The defendants denied liability and pleaded that the plaintiffs' claim was statute barred by section 2 of the Limitation Act 1939, as practical completion took place in or before 1962 and that under clause 24(g) of the Conditions, the Final Certificate was conclusive evidence that the works were properly carried out. In reply the plaintiffs alleged that the fixings were fraudulently concealed by the defendants within the meaning of section 26(2) or section 27(b) of the Limitation Act 1939 and relied on clause 24(g), so that the Final Certificate did not operate as a contractual bar. They further contended that the defects first manifested themselves in 1972 and it was then that the plaintiffs first discovered or could reasonably have discovered them. The trial judge dismissed the plaintiffs' claim holding that the failure of the stone cladding was caused by defects in the fixings and the lack of provision for differential movement. The use of defective materials and workmanship in the fixings was in breach of contract and contributed substantially to the damage. The stone cladding defects were not fraudulently concealed because the plaintiffs had failed to discharge the burden of proof that lay on them to show that the plaintiffs' supervisors, in exercising reasonable skill, could not have been expected to have observed the defects. Accordingly the claim was statute barred. He held further that the Final Certificate barred any action in contract since none of the matters referred to in Clause 24(g) had occurred; and that no action lay in tort because there was no special relationship, all the alleged breaches arose out of the Contract. 83 The plaintiffs appealed. The defendants served a respondents' notice specifying five further grounds. It was held that the plaintiffs were wrong to argue that since the defendants were contractually obliged to provide their own supervision the plaintiffs were entitled to rely upon the defendants' own supervisory team and that that was sufficient to defeat a plea of fraudulent concealment. The question to be asked in relation to fraudulent concealment was: in all the circumstances were the facts such that the conscience of the defendant or the sub-contractor, for whose acts or omissions the defendant was vicariously liable, should have been affected that it was unconscionable to proceed with the work or so to cover up the defect without putting it right? Counsel for the plaintiffs submitted that whenever a builder under contract does shoddy or incompetent work, which was subsequently covered up in the due succession of building work, so that when the building was complete the bad work was hidden from view, this did not constitute fraudulent concealment within the meaning of equitable fraud. Simply getting on with the work after something shoddy or inadequate has been done or omitted does not necessarily give rise to a legal inference of concealment or of equitable fraud. 4.6 Conclusion After discuss all the related court cases reported under the Malaysia Law Journal, the writer found that the head of claim for defective works are often link to the conclusiveness of the final certificate. Once a conclusive final certificate is issued under the contract, the contractor will discharged from the liability for defective work at law. However, it appears that the satisfactory making good of defects does not amount to an exclusion of claims in respect of their consequences. The measure of damages will therefore not only be the cost of repair of the defect, but also such 84 compensation as the loss of the use of the premises during repairs in accordance with the ordinary rules governing remoteness of damage. 85 CHAPTER 5 CONCLUSION AND RECOMMENDATION 5.1 Introduction This is the final chapter which summarizes the finding of the research in accordance with the research objective. Problems encountered during the research as well as the recommendations of future research are also discussed in this chapter. 5.2 Summary of Research Findings The writer would like to emphasize that this research is not intended to make a thorough comparison on the various forms of contract available in the construction industry. This research is prepared with an objective of reviewing the legal position of the rights of the employers and liabilities of the contractors in relation to the defective work after the issuance of Final Certificate. 86 The findings are summarised in Table 5.1, as follow:- Item Findings Remarks 1. Generally, a conclusive and binding final certificate discharges the liability of the contractor for defects in the work both to the employer and in any third party contribution proceedings. • The superintendent should not issue the final certificate until after the end of the defects liability period because once the final certificate is issued and defects occur, the superintendent will have to assume the risk on account of the conclusiveness of the final certificate both as to completion and quality of the workmanship. • When superintendent issued his final certificate, thereby showing his satisfaction with the works carried out by the contractor, it excuses the contractor from liability for breaches if contract and obviates the operation of the Limitation Act 1953. It prevent any further legal action and the conclusiveness evidence make the certificate is not reviewable. • Where there is a binding and conclusive final certificate of satisfaction is given by the superintendent, the contractor’s liability in contract for any defects lapsed. The employer is not entitled contractually to pursue any defect arising and/or reported after the said date. • When the contractor is in direct contractual relationship with the purchasers, he was therefore liable to the purchasers under both express and implied conditions in the agreement. • Defect liability period will not take away the right of the purchaser to sue for defects which were not discovered within that period. He would entitled to claim for cost of remedying the defect as well as the cost of investigation of damages. • Damages for defective work and its consequential loss is not covered by the conclusiveness if the final certificate. If the sums do not constitute damages for defective work and did not relate to the list of defects, it is not claimable by the employer. Discussed court cases: • James Png Construction Pte Ltd v Tsu Chin Kwan Peter • Shen Yuan Pai v Dato Wee Hood Teck & Ors • Sa Shee (Sarawak) Sdn Bhd v Sejadu Sdn Bhd • Chew Sin Leng Construction Co v Cosy Housing Development Pte Ltd • Usahabina v Anuar Bin Yahya • P & M Kaye Ltd v Hosier & Dickinson Ltd • Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd • University Fixed Assets Limited v Architects Design Partnership • Crown Estate Commissioners v John Mowlem and Co Ltd 2. Generally, the satisfactory making good of defects does not amount to an exclusion of claims in respect of their consequences. Discussed court cases: • Teh Khem On & Anor v Yeoh & Wu Development Sdn Bhd & Ors • James Png Construction Pte Ltd v Tsu Chin Kwan Peter • Shen Yuan Pai v Dato Wee Hood Teck & Ors • P & M Kaye Ltd v Hosier & Dickinson Ltd • HW Nevill (Sunblest) Ltd v William Press & Son Ltd 87 Item Circumstances Remarks 2. Generally, the satisfactory making good of defects does not amount to an exclusion of claims in respect of their consequences. (Cont’d) 3. Naturally, contractors take comfort from a final certificate and assume that no new or further claims can be made against them for defective or incomplete works under the final certificate, other than latent defects. • The superintendent was not required to decide whether the employer had suffered consequential loss or to access the amount of such loss. Therefore, the superintendent at the time of giving his final certificate is not dealing with consequential loss. • The final certificate was irrelevant to any claims for consequential damages in respect of defects which had been found after the employer had taken possession. It is the right of the employer to claims for consequential loss. • If latent defects are discovered during defects liability period, the period is to be extended until the contractor has made them good and the superintendent has so certified. • After a conclusive final certificate issued, the contractor is not liable to remedy any further defects. Discussed court cases: • P & M Kaye Ltd v Hosier & Dickinson Ltd • London Borough of Barking and Dagenham v Terrapin Construction Ltd • Matthew Hall Ortech Ltd v Tarmac Roadstone Ltd 4. If defects are concealed by a contractor, this may result in an extension to the limitation period until the plaintiff has discovered the fraud or concealment or could, with reasonable diligence, have discovered it. Discussed court cases: • Musselburgh and Fisherrow Cooperative Society v Mowlem Scotland • William Hill Organisation Ltd v Bernard Sunley and Sons Ltd • If defective work or workmanship or design have been knowingly covered up or concealed so as to constitute fraud, the commencement of the limitation period may be delayed. The said period may be delayed until discovery actually occurs; or at least the defect could have been discovered with reasonable diligence, whichever is earlier. Table 5.1: Summary of Research Findings 88 Some standard forms of contract identify the Final Certificate as conclusive evidence of the completion of a specified obligation. In practice the Final Certificate will prevent the Employer from establishing the Contractor’s liability, even if it is subsequently found that the Final Certificate should not have been issued. CIDB 2000 form of contract make the final certificate conclusive evidence that work has been satisfactorily carried out. Action under the CIDB wording must be commenced within 30 days of the issue of the final certificate. This will discharge the Contractor from liability to the Employer for defective work. PAM 1998 and PWD 203 form of contract gives the final certificate no such effect and the Limitation Act periods apply. During the limitation period, the contractor carries liability of defect works for a further six years; upon the expiry of which period the employer’s cause of action then becomes statute barred. 5.3 Problem Encountered During Research Constraint and insufficiency of time was the main and only problem encountered when writing up the report for this research. Only eight (8) weeks’ time was available for this research and hence every process has been carried out in a very fast manner, especially during the data collection process, which involved collecting and sorting court cases from different law journals. This limitation led to less cases being found to support the findings, especially those cases decided in Malaysia courts. If there were more time given, the study can be done in more comprehensive and thorough way. 89 5.4 Further Studies Section 6(1)(a) of the Limitation Act 1953 states that actions founded on a contract and tort shall not be brought after the expiration of six years from the date on which the cause of action accrued. The difficulty for the instant head of claim lies in establishing exactly when the time starts running. Thus, a further study about the approaches establishing the actual time for the accrual of a cause of action in tort under the limitation act can be done. Another future study on the test of reasonableness in assessing the proper damages for remedying defective works can be held. The contractual requirement that the works shall be done to the reasonable satisfaction of the superintendent is too subjective to be used as a basis for evaluating the contractor’s work. In practice, disagreements do occur in evaluating the defective work done by the contractor on a reasonable satisfaction basis. 5.5 Conclusion As a conclusion for this research, where there is a defects clause and at the end of the defects liability period a binding and conclusive final certificate of satisfaction is given by the architect, the contractor’s liability in contract for any defects lapsed. The employer is not entitled contractually to pursue any defect arising and/or reported after the said date. If the final certificate is not conclusive, it does not derogate in any way the contractor’s liability for defective work at law. The contractor continues to be liable for such defects for the duration of the applicable statutory period of limitation. 90 Once a conclusive final certificate is issued under the contract, the employer is prevented from bringing claims for defects in the works arising from a breach of contract and/or tort irrespective of whether those defects may be said to be latent or patent. In the circumstances where defective work or workmanship have been knowingly covered up or concealed so as to constitute fraud, the commencement of the limitation period may be delayed until discovery actually occurs. However, it appears that the satisfactory making good of defects does not amount to an exclusion of claims in respect of their consequences. The measure of damages will therefore not only be the cost of repair of the defect, but also such compensation as the loss of the use of the premises during repairs in accordance with the ordinary rules governing remoteness of damage. This research perhaps is not comprehensive; but the writer hopes that it may provide assistance to both employers and contractors to understand their rights and liabilities in relation to defects which appear after the issue of the Final Certificate. This may avoid unnecessary disputes and assuring project success and tie-up a better relationship among the contractual parties. 91 REFERENCES Collier, K. (2001). Construction Contracts. 3rd ed. New Jersey: Merrill Prentice Hall. Furst, S and Ramsev, V. (1991). Keating on Building Contracts. 5th ed. London: Sweet & Maxwell. Harbans Singh. (2003). Engineering and Construction Contracts Management – Post-Commencement Practice. Singapore: LexisNexis. Kok, S Y. (1998). Law Governing the Housing Industry. Malaysia: Malayan Law Journal Sdn Bhd. Lim, Chong Fong. (2004). The Malaysian PWD Form of Construction Contract. Malaysia: Sweet & Maxwell Asia. Mohd Suhaimi Mohd Danuri. (2005). The Employer’s Rights and the Contractor’s Liabilities in Relation to the Defects Liability Period. The Malaysian Surveyor. 39.1. Murdoch, J and Hughes, W. (2000). Construction Contracts: Law and Management. London: Spon Press. Ong, See Lian. (2005). Defective Works. International Conference on Construction Law & Arbitration. 26th – 28th April 2005. Kuala Lumpur. 92 Robinson, N. (1996). Construction Law in Singapore and Malaysia. 2nd ed. Malaysia: Butterworths Asia. Sundra Rajoo. (1999). The Malaysian Standard Form of Building Contract (the PAM 1998 Form). 2nd ed. Malaysia: Malayan Law Journal Sdn Bhd. Wallace, D. (1970). Hudson’s Building and Engineering Contracts. 10th ed. London: Sweet & Maxwell. Wallace, D. (1995). Hudson’s Building and Engineering Contracts. 11th ed. London: Sweet & Maxwell. William, G. (1969). Emden and Gill’s Building Contracts and Practice. 7th ed. London: Butterworths Co.. William, A. and Guest, A.G. (1975) Anson's Law of Contract. 24th ed. Oxford: Clarendon Press. Uff, J. (1991). Construction law: Law and Practice Relating to the Construction Industry. 5th ed. London: Sweet & Maxwell.