Management Control of Projects Nature of Projects • A project is a set of activities intended to accomplish a specified end result of sufficient importance to be of interest to management. Projects include construction projects, the production of a sizable unique product (such as turbine), rearranging a plant, developing and marketing a new product . • A project begins when management has approved the general nature of what is to be done and has authorized the approximate amount of resources that are to be spent in doing this work. • The project ends when its objective has been accomplished or it has been cancelled. • Projects vary greatly. Nature of Projects Contrast With Ongoing Operations Characteristics of projects that make the management control of projects different from the management control of ongoing activities : • Single Objective The project usually has a single objective • Organization Structure The project organization is superimposed on an ongoing operation organization and its management control systems is superimposed on the management control systems of that organization. • Focus on the project Project control focuses on the project, whose objective is to produce a satisfactory product, within a specified a specified time period, and at an optimum cost Nature of Projects Contrast With Ongoing Operations • Need for Trade Offs Projects usually involve trade offs between scope, schedule and cost. • Less Reliable Standards Performance standards tend to be less reliable for projects than for ongoing organizations. • Frequent Changes in Plans Plans for projects tend to be changed frequently and drastically. • Different Rhythm The rhythm of a project differs from that of ongoing operations Nature of Projects Contrast With Ongoing Operations • Greater Environmental Influence Projects tend to be influenced more by the external environment than is the case with operations in a factory. • Exceptions In some projects, team members are hired for the job, they are not associated with functional departments in an on going organizations. Projects in a research laboratory are conducted on the premises rather than in outside facilities. The Control Environment Project Organization Structure • A project organization is a temporary organization. • Team members may be employees of the sponsoring organization, they may be hired for the purpose, or some or all of them may be engaged under a contract with an outside organization. Matrix Organizations • If members of the project team are employees of the sponsoring organization they have two “bosses” : the project manager and the manager of the functional department to which they are permanently assigned. • The project manager, therefore, has less authority over personnel than the manager of a production department, whose employees have an undivided loyalty to that department. The Control Environment Project Organization Structure Evolution of Organization Structure • Different types of management personnel and management methods may be appropriate at different stages of the project. Contractual Relationships Contracts are of two general types: fixed price and cost reimbursement. Fixed Price Contracts • The contractor agrees to complete the specified work by a specified date at a specified price. • The sponsor is responsible for auditing the quality and quantity of the work to ensure that it is done as specified The Control Environment Contractual Relationships Cost Reimbursement Contracts • The sponsor agrees to pay reasonable costs plus a profit (often with a “not to exceed” upper limit) • The sponsor has considerable responsibility for the control of costs and therefore needs a management control system and associated control personnel. The Control Environment Contractual Relationships Contrasts in Contract Types Fixed Price Contracts Cost Reimbursement Contracts • The contract is bid by or proposed by the contractor • The profit component, • The contracts are or fee, usually should appropriate when the scope be a fixed monetary of the project can be amount. closely specified in advance and when uncertainties are low. The Control Environment Contractual Relationships Variations • In an incentive contract, completion dates or cost targets, or both, are defined in advance, and the contractor is rewarded for completing the project earlier than the target date or for incurring less than the target cost. • Different contract types may be used for different activities on the project. Project Planning In the planning phase : • Takes as a starting point the rough estimates that were used as the basis for the decision to undertake the project • Refines estimates into detailed specifications for the product, detailed schedules and a cost budget • Develops a management control system and underlying task control systems and an organization chart Project Planning Nature of the Project Plan The final plan consists of three related parts : a. The scope States the specifications of each work package and the name of the person or organization unit responsible b. The schedule States the estimated time required to complete each work package and the interrelationships among work packages, that is, which work package must be completed before another can be started (network) c. Cost Stated in the project budget, usually called the control budget. Project Planning Network Analysis Several tools are available for constructing the time schedule for the project. a. PERT (Program Evaluation and Review Technique) b. CPM (Critical Path Method) Each technique has three basic steps : • Estimating the time required for each work package • Identifying the interdependencies among work packages • Calculating the critical path Project Planning Critical Path (X-A, A-B & B-C Indicate Critical Path) A Time (week) 2 5 B X 4 A 3 Project Planning Estimating Costs • For practical reasons, cost estimates are often made at a level of aggregation that incorporates several work packages. • Cost estimates for most projects tend to be less accurate than those for manufactured goods, because projects are less standardized. Preparing the Control Budget • The control budget is prepared close to the inception of the work, allowing just enough time for approval by decision makers • The control budget is an important link between planning and the control of performance. Project Planning Other Planning Activities • During the planning phase, other activities are performed : material is ordered, permits are obtained, preliminary interviews are conducted, personnel are selected, and so on. • All these activities must be controlled and integrated into the overall effort. Project Execution Basically, both the sponsor and the project manager are concerned with these questions : 1. Is the project going to be finished by the scheduled completion date ? 2. Is the completed work going to meet the stated specifications ?. 3. Is the work going to be done within the estimated cost ?. Project Execution Nature of Reports Managers need three somewhat different types of reports : trouble reports, progress reports and financial reports. 1. Trouble Reports Report both on trouble that has already happened and also anticipated future trouble 2. Progress Reports Compare actual schedule and costs with planned schedule and costs for the work done. 3. Financial Reports Are accurate reports of projects cost that must be prepared as a basis for progress payments if there is a cost reimbursement contract, and a basis they usually are necessary as a basis for financial accounting entries Project Execution Use of Reports 1. Trouble Reports the manager has to decide which problems will get his or her personal attention, which will be delegated to someone else, and which will be disregarded on the assumption that operating personnel will take the necessary corrective action. 2. Progress Reports The approach to analyzing progress reports is “Management By Exception”. If progress in a particular are is satisfactory, no attention needs to be paid to the area. Project Execution Informal Sources of Information • Written report usually are less important than information that the manager gathers from talking with people who actually do the work, from members of his or her staff. • From these sources, the managers learns of potential problems and of circumstances that may cause actual progress to deviate from the plan. • Nevertheless, formal reports are necessary. Project Execution Project Auditing • In many projects, the audit of quality must take place as the work is being done. • In general, auditing as the work progresses is preferable, it may uncover potential errors that can be corrected before they become serious. • Internal auditors have expanded their function into what is called operational auditing. Project Evaluation The evaluation of projects has two separate aspects : 1. An evaluation of performance in executing the project. Carried out shortly after the project has been completed 2. An evaluation of the results obtained from the project. May not be feasible until several years later. Evaluation for Performance The evaluation of performance is executing the project has two aspects : 1. An evaluation of project management The purpose is to assist in decisions regarding project managers, incl. rewards, promotions or reassignment 2. An evaluation of the process of managing the project. The purpose is to discover better ways to conducted future projects. Project Evaluation Evaluation of Results • The success of a project cannot be evaluated until enough time has elapsed to permit measurement of its actual benefits and costs. • For many projects, evaluation of results is complicated by the fact that the expected benefits were not stated in objective, measurable terms, and the actual benefits also were not measurable. • The results of relatively few projects are subjected to a formal evaluation (often called a post completion audit) Summary The most important difference between the management control on ongoing operations and the management control of projects is that the ongoing operations continue definitely, whereas a project ends. The End