MITIGATING SHORT-­‐TERM PV OUTPUT INTERMITTENCY Prepared by Richard Perez and Sergey Kivalov ASRC, University at Albany Thomas E. Hoff, John Dise and David Chalmers Clean Power Research 12/16/2013 GW University Solar Institute Contracts No. 1000178044 & 1000177911 This overview report describes the objectives, the approach, and the key results produced by the University at Albany and Clean Power Research on estimating the cost of mitigating the short-­‐term intermittency of solar power generation fed onto US power grids. Two appendices containing details on methodology and a complete set of results are appended. BACKGROUND AND OBJECTIVES The intermittency of the solar resource is an issue that cannot be ignored when planning for high penetration of PV on power grids. A considerable amount of research has been devoted to this subject over the last five years [1-16] and has led to a better understanding of short-term solar resource variability and how it is influenced by the considered temporal and spatial scales. However understood, intermittency must be addressed and appropriately dealt with. In this perspective, we approach the issue of short-term PV output intermittency from a management standpoint by determining the cost of actively mitigating it using “shockabsorbers” consisting of short-term energy storage buffers. Figure 1 shows an example of high-frequency (one-minute) fluctuations for a single solar system on partly cloudy day. The figure also illustrates how this short-term variability can be almost eliminated by operating an energy buffer taking in short-term output spikes and releasing energy during short-term output deficits. The central question of this report is: what is the cost of this buffer? 800 600 800 PV output 600 buffered PV 400 Buffer transit 500 200 400 0 300 -­‐200 -­‐400 200 100 0 -­‐600 Maximum 1 minute ramp rate: 400 W/kW Maximum 1 minute ramp rate: 10 W/kW -­‐800 ENERGY BUFFER IN/OUT TRANSIT (Watts per kW) PV SYSTEM OUTPUT (Watts per kW) 700 1000 clear sky PV -­‐1000 Figure 1: Illustrating how short-terms ramps on a partly cloudy day can be almost eliminated by operating a storage buffer whose output is set to equal the trailing running mean average of the PV system. Quantifying intermittency: Solar Resource variability can be quantified using several metrics. The authors and others have proposed the standard deviation of the changes in clear sky index [16] as a suitable metric to both quantify and model variability. However utilities and grid operators are concerned with a more tangible metric: the power output ramp rate quantifying the change (the ramp) in power output from one time interval to the next. Ramps have been observed to be in excess of 100% of installed capacity for short-term spikes [17]. Utilities are considering applying maximum ramp rate acceptance windows to solar power fed onto their grids. For instance the Puerto Rico’s Electric Power Authority imposes a limit of 10% of installed capacity for one-minute ramps. Cost of mitigation: Intermittency mitigation is quantified here by the cost of the energy buffer that is needed to achieve a given ramp rate reduction objective. This cost depends on the specs of the storage buffer – namely its power and its energy reserve capacity -and upon its technology. In the present context, considering ramps of one minute to two hours, these technologies would likely consists of lead-acid batteries for the upper end of the time scale range and super-capacitors or fly-wheels for the lower end. A simple “technology-agnostic” model was developed to estimate the per kW and per kWh storage capacity costs as a function of kW and kWh requirements. This model, derived from the specs of currently available storage technologies, is illustrated in Figure 2. 2 Figure 2: Buffer storage cost model used for the present investigation. The thick semi-transparent curve represents the model per se. It is applied here in the region corresponding to lead acid batteries fly-wheels and super-capacitors -- source [18]. The cost of PV output intermittency mitigation is determined as a function of several parameters that specify the mitigation requirements of the grid operators, the time scale of concern, the PV resource location and footprint, and the possibility to accurately forecast PV power output: Ramp rate reduction objective: the cost of intermittency mitigation depends upon the desired level of mitigation. Here we consider objectives for maximum allowable ramp rate ranging from 25% down to 1% of installed PV capacity. Time scale: Ramps must be placed in an appropriate temporal context to both understand their impact and implement appropriate solutions. Figure 3 contrasts one-minute and hourly ramp rates occurring on a given day at a particular location. At different time scales ramp rates have different causes, have different magnitudes, and engender different concerns which have different solutions. For instance one minute ramp rates are caused by individual clouds and cloud edge effects. These short-term ramp may impact local voltage regulation. Hourly ramp rates are caused by the evolution of entire cloud fields and are relevant to contingency power generation dispatching. We use a systematic approach to understand and quantify the impact of time scale on intermittency mitigation by analyzing ramp rate time scales ranging from one minute to two hours. Spatial Scale: The well-documented spatial smoothing of solar resource fluctuations affects ramp rates differently as a function of time scale [2]. Shortterm fluctuations are quickly smoothed out as the solar generation footprint increases to a few square km, while longer term fluctuations take more spatial distribution to be mitigated. 3 We also approach this question systematically by analyzing solar generation footprints ranging from one centralized location up to a resource distributed over a 200x200 km region representative of a utility service area. One Minute Max ramp = 400 W/kW One Hour Max ramp = 180 W/kW Figure 3: Comparing one-minute and hourly ramps for the same day/location Availability of solar resource forecasts: We explore whether knowing the future output of solar generators can be used to more effectively manage the shock absorbing energy buffers, hence reduce their required size and cost. Figure 4 illustrates how the buffering effect shown in Figure 1 can be optimized if perfect forecasts can be used to anticipate the intermittency mitigation performance of the buffer. In this report we contrast the mitigation costs achieved by operating the buffers without forecasts to the mitigation costs achieved when perfect forecasts are available. Influence of location: Through three case studies in Hawaii, California and the southeastern US which have very distinct climatic environments (respectively sub-tropical, arid and continental) we investigate the influence of the local solar climate upon the specs of short-term energy buffers, hence their cost. 4 REQUIRED BUFFER: 180 Wh / KW NO FORECAST AVAILABLE REQUIRED BUFFER: 70 Wh / KW PERFECT FORECAST AVAILABLE Figure 4: Intermittency buffering using historical-only PV production (top) and historical + ideally forecast PV production (bottom). because short and medium term spikes can be anticipated in the latter case, the size of the buffer needed to accomplish a given ramp reduction objective can be minimized. METHODOLOGY Our approach is empirical and based on the analysis of a large sample of data at the three selected locations illustrated in Figure 5. 5 For each site we analyze PV output simulated from a single point up to a 200x200km area surrounding this point. For the single point PV is simulated from one-­‐minute irradiance measurements. For the surrounding areas, PV is simulated from one minute high-­‐resolution (1 km) satellite-­‐derived irradiances from SolarAnywhere [19]. As explained in Appendix 1, the satellite-­‐derived irradiances are post-­‐calibrated to enhance their dynamic range so as to match measured ramp observations. The selected geometry for PV system is horizontal mount – i.e., not ideal from an energy output standpoint, but fully representative to capture the power output transients of interest to the current study. Goodwin Creek Mississippi Hanford California Kalaeola Hawaii Location Hanford, CA Goodwin Creek, MS Kalaeola, HI latitude 36.31° N 34.25° N 21.32° N Longitude Elevation Prevailing Climate 119.63° W 73 m Semi-­‐arid 89.87° W 98 m Warm continental 159.09° W 20 m Subtropical Data Source NOAA-­‐ISIS NOAA-­‐ SURFRAD NREL Figure 5: Selected experimental locations A total of 2,808 PV output simulations involving over 32 billion data points are performed for each possible temporal/spatial/mitigation/site/forecast combination -­‐-­‐ see Table 1. RESULTS OVERVIEW A comprehensive sample of the 2,808 simulations is presented and discussed in Appendix 1, and a complete set of results is presented in Appendix 2. Here we provide a high-­‐level view focusing on two key aspects of the study: 6 (1) Showing how variability at each location evolves as a function of time scale and footprint. (2) Extracting the cost of intermittency mitigation for a plausible operational scenarios. TABLE 1: Simulation case study overview Mitigation objective (Maximum acceptable ramp rate % of PV Capacity) 0.5% 1.0% 2.5% 5.0% 10.0% 15.0% 25.0% Tim resolution Spatial resolution (minutes) km 1 5 15 30 60 120 single point 1x1 2x2 3x3 5x5 8x8 13x13 30x30 50x50 80x80 130x130 200x200 Locations Forecast California South Central US Hawaii No Forecasts Ideal Forecasts Variability as a function of footprint and time scale: We examine both variability metrics mentioned above -­‐-­‐ the reference metric equal to standard deviation of the clear sky index changes, and the more pragmatic measure consisting of the highest observed ramp. Figure 6 illustrates the trends observed at each location for the first metric as a function of time scale and footprint. Consistent with earlier findings by the authors and others [e.g., 2] variability decreases as a function of footprint at a rate that is dependent upon the considered time scale – the decrease is more pronounced for the shorter time scales. Some differences between locations are noteworthy: Variability increases as a function of time scale at all locations with an exception for Hawaii, where the trend is reversed for small footprints. This is likely because of the frequent occurrence of puffy cloud conditions at that location resulting in high frequency variability at that site. As footprint increases beyond ~ 10 km, the trends are comparable at all locations, with highest overall values found for Goodwin Creek and lowest values found for Central California -- a likely results of the higher occurrences of intermediate conditions in the Southeastern US compared to California, combined with faster moving cloud systems in the continental US inducing a smaller decrease of variability with distance [16]. 7 Figure 7 illustrates highest observed ramps as a function of time scale and footprint. The trends are not as smooth and well defined as in Fig. 6 because this metric represents the highest ramp observation in each case – i.e., a one-time extreme event. Nevertheless strong tendencies do emerge: for small footprints, highest ramps are observed for high frequency ramps, while this tendency is reversed -- highest values for low frequency ramps -- beyond 1-5 km footprint. This is because high frequency ramps are quickly smoothed out as footprint increase. Hanford Goodwin Creek Kalaeola Figure 6: Variability (Watts per PV kW) as a function of footprint and time scale The similarity observed between all sites is remarkable for this metric, particularly for small footprints where ramp values are almost identical for all sites at all time scales Cost of ramp mitigation in an operational context: Operationally, grid operators will target different variability mitigation objectives as a function of time scale as well as PV generation footprint, depending on their ability to react via ancillary services for high frequency events and with contingency power generation for longer ramps. Ramp reduction targets are likely to be more stringent for the lowest time scales and more lenient as time scales increase and grid operators have time to plan and react. 8 Hanford Goodwin Creek Kalaeola Figure 7: Highest observed ramp (Watts per PV kW) as a function of footprint and time scale As an example of plausible operational scenario, results in Figure 8 illustrate operational ramp mitigation costs for the following maximum acceptable ramp targets: • 5% of installed PV capacity at one-­‐minute, • 10% at 5 minutes, • 15% at 15 minutes, • 25% at one hour. Costs are shown for five PV Generation footprints: • Point-­‐specific, • 5x5 km, • 20x20km, • 50x50 km, • 200x200 km. For a single point, the operational mitigation cost to meet all requirements at all time scales ranges from $500 per installed PV kW in California to $900 in South-­‐ 9 Central US. However this cost is reduced considerably and becomes comparable for all locations (~$400 per PV kW) if perfect forecasts are available to provide intelligence to the shock absorbing buffers. Hanford NO FORECAST PERFECT FORECAST Kalaeola Goodwin Creek Figure 8: Operational scenario intermittency mitigation buffer cost Mitigation costs decrease substantially with foot-­‐print. For instance a 50x50 km area corresponding to a small utility drives mitigation cost down to ~$ 100-­‐200 with forecasts, i.e., representing 5%-­‐15% of a PV installation’s cost. It is important to note that the cost figures presented here are dependent upon the technology model shown in figure 2 which is based upon current storage technology costs. It is likely that these costs will be driven down commensurately with, and possibly more, than PV costs. Another cost of operating buffers that should not be ignored is the loss that is incurred by circulating some of the energy produced in and out of the buffers. Figure 9 shows the fraction of PV energy that would lost for all cases analyzed assuming a mean 90% round-­‐trip efficiency. In all case this loss is negligible (0.5% in the worse case scenario: single point system in Hawaii with no forecasts available.) CONCLUSIONS AND RECOMMENDATIONS 10 The present analysis shows that ramp rate mitigation across multiple temporal scales from minutes can be mitigated with energy buffers at cost amounting to a small fraction of a PV installation cost. In addition, the study showed that: • Buffer energy losses are minimal in all case figures analyzed (<< 1%). • Accurate forecasts can reduce buffer capital cost by 40-­‐50%. • Reducing dispersed generation’s variability instead of focusing on single installations would be considerably more cost effective when conditions permit. • Bottom line differences between very different climatic environments are not considerable. An important continuation to this work will be to investigate to which extent non-­‐ ideal state of the art forecast could reduce buffer costs compared to ideal forecasts. Hanford NO FORECAST PERFECT FORECAST Kalaeola Goodwin Creek Figure 9: Operational scenario intermittency mitigation buffer roundtrip energy losses 11 REFERENCES [1] Hinkelman L., R. George and M. Sengupta, 2011: Differences between Along-Wind and Cross-Wind Solar Variability. Proc. Solar 2011, American Solar Energy Society Conf., Raleigh, NC [2] Hoff T., & R. Perez (2012): Modeling PV Fleet Output Variability, Solar Energy 86, 8, 2177-2189 [3] Hoff, T. E., Perez, R. 2010. “Quantifying PV power Output Variability.” Solar Energy 84 (2010) 1782–1793 [4] Jamaly, S., Bosch, J., Kleissl, J. 2012. “Aggregate Ramp Rates of Distributed Photovoltaic Systems in San Diego County.” IEEE Transactions on Sustainable Energy, in press [5] Lave, M., J. Kleissl, Arias-Castro, E., High-frequency fluctuations in clear-sky index, Solar Energy, doi:10.1016/j.solener.2011.06.031, 2011 [6] Lorenz E., T. Scheidsteger, J. Hurka, D. Heinemann and C. Kurz, (2011): Regional PV power prediction for improved grid integration. Progress in Photovoltaics, 19, 7, 757771. [7] Mills, A., Wiser, R. 2010. Implications of Wide-Area Geographic Diversity for ShortTerm Variability of Solar Power. Lawrence Berkeley National Laboratory Technical Report LBNL-3884E. [8] Murata, A., H. Yamaguchi, and K. Otani (2009): A Method of Estimating the Output Fluctuation of Many Photovoltaic Power Generation Systems Dispersed in a Wide Area, Electrical Engineering in Japan, Volume 166, No. 4, pp. 9-19 [9] Perez M., and V. Fthenakis, (2012): Quantifying Long Time Scale Solar Resource Variability. Proc. WREF, Denver, CO. [10] Perez, R., T. Hoff and S. Kivalov, (2011a): Spatial & temporal characteristics of solar radiation variability. Proc. of International Solar Energy (ISES) World Congress, Kassel, Germany [11] Perez, R., Kivalov, S., Schlemmer, J., Hemker Jr., C. , Hoff, T. E. (2011b): Parameterization of site-specific short-term irradiance variability, Solar Energy 85 (2011) 1343-1353 [12] Perez, R., Kivalov, S., Schlemmer, J., Hemker Jr., C. , Hoff, T. E. (2012): “Shortterm irradiance variability correlation as a function of distance.” Solar Energy 86, 8, pp. 2170-2176 [13] Wiemken E., H. G. Beyer, W. Heydenreich and K. Kiefer (2001): Power Characteristics of PV ensembles: Experience from the combined power productivity of 100 grid-connected systems distributed over Germany. Solar Energy 70, 513-519 [14] Woyte, A., Belmans, R., Nijs, J. (2007): Fluctuations in instantaneous clearness index. Solar Energy 81 (2), 195-206. [15] Marcos J., L. Morroyo, E. Lorenzo and M. Garcia, (2012): Smoothing of PV power fluctuations by geographical dispersion. Prog. Photovolt: Res. Appl. 2012; 20:226–237 [16] Perez, R., T. Hoff, (2013): Solar Resource Variability, in: Solar Resource Assessment & Forecasting (Ed. J. Kleissl), Elsevier, 2013 12 [17] Yordanov, G., O. Mitdgard, O. and L. Norum (2013): Overirradiance (Cloud Enhancement) Events at High Latitudes. IEEE Journal of Photovoltaics, 3, 1, 271-278. [18] Germa, J.M., & M. Perez, (2012): Energy Storage: Technology, Applications & trends. Cluster Maritime Français. 10/3/12 [19] SolarAnywhere (2013): http://www.cleanpower.com/products/solaranywhere/solaranywhere-data / 13 APPENDIX 1 MITIGATING SHORT-TERM PV OUTPUT INTERMITTENCY Richard Perez Sergey Kivalov University at Albany Albany, New York, USA Thomas E. Hoff John Dise David Chalmers Clean Power Research Napa, California, USA Our objective is to estimate the cost of mitigating the short-term variability of solar power generation fed onto US power grids. We approach the issue of short-term PV output intermittency from a management standpoint by determining the cost of actively mitigating it using “shock-absorbing” short-term energy buffers. Using three case studies in California, Hawaii and the southern US as experimental support, we determine this cost as a function of (1) the desired amount of variability mitigation; (2) the considered variability time scale, (3) the PV resource’s geographical footprint, and (4) the availability of accurate solar forecasts. We show that, in a plausible operational context, the cost of mitigating variability across time scales ranging from one minute to a couple of hours could be kept below 20-35 cents per installed PV kW. BACKGROUND Short-term PV output variability has been thoroughly studied in recent years as it became a concern associated with the increase of PV penetration on power grids [1-16]. It is now 14 better understood, and in particular the smoothing effect occurring with dispersed generation is well documented. 15 However understood, variability remains a concern to grid operators and utilities, who are at the receiving end of the variable resource, and who have to manage it appropriately. Therefore we frame the present inquiry from a grid operator’s standpoint by determining the cost of keeping the variable resource’s ramp rates below specified thresholds. This cost is quantified by the shock-absorbing hardware —an energy buffer—that receives the variable PV output and filters it to deliver an output with specific maximum ramp rate requirements. This cost is determined as a function of: (a) The considered ramp rate time scale—from one minute to two hours; (b) The footprint of the generating resource—from a single point to a PV resource distributed over 200x200 km; i.e., going from a resource with full site-specific variability including cloud’s edge intensification effects [e.g., 17], to a resource where variability is already smoothed by geographic distribution; (c) The solar climatic environment – including semi-arid, tropical and temperate locations; and, (d) The availability or not of solar forecasts. APPROACH Mitigating Variability The metrics used to quantify variability mitigation are the specs and the cost of the energy buffer needed to keep all ramp rates below a selected level. As PV output fluctuates, excess variability is filtered by the buffer that absorbs or releases energy appropriately so that the ramp rate of the PV+buffer ensemble seen by the grid does not exceed the selected ramp rate at any time. The buffer is driven by an algorithm that sets its output to equal the running mean of the unfiltered PV input. The running mean time window depends upon the desired degree of ramp rate reduction. Fig. 1 illustrates this buffering effect on a partly cloudy day. In this example, the maximum one-minute ramp rate seen by the grid (buffered PV) is less than 10 W per installed kW. Figure 1: Illustrating the buffering of PV output. 16 Forecast availability: Operationally the running mean algorithm can be a trailing running mean since this information could be readily available to the buffer. The running mean could also be centered on the current time if perfect forecasts are available (i.e. if future output is known). Predictable vs. unpredictable ramp rate: Ramp rates resulting from solar geometry are fully predictable and could therefore be accounted and planned for by grid operators (e.g., see the clear sky profile in Fig. 1). Therefore, we focus here on unpredictable ramp rates defined as the difference between the observed ramp rates and the ramp rates that would result from solar geometry alone (i.e., conserving the same clear sky index from one time interval to the next). For very short-term fluctuations (less than 10 minutes), the difference between the two is negligible. However, for longer time scales (one to two hours), the difference can be significant. Buffer specs and cost: The specs of the buffer —power and energy capacity — are determined experimentally by analyzing PV output time series over a one-year period. This analysis yields the maximum transfer of power in and out of the buffer, and the maximum cumulative energy to be stored in the buffer, so as to accommodate the selected ramp rate-specific output at all times. Depending on the buffer’s power and energy requirements, different technologies may be considered. Very small energy and high power requirements would be met by fly wheels or capacitors. As energy vs. power requirements augment, technologies would evolve toward supercapacitors and batteries. For this study, we built a simple “technology-agnostic” cost model based on current reported costs for state-of-the-art energy storage equipment. This cost model is illustrated in Fig. 2 Figure 2: Buffer storage cost model [18] 17 Data Analysis The experimental data used to determine buffer specs consist of one-year PV output time series for horizontally-mounted PV systems operating in three climatically distinct locations: Hanford, in Central California, Goodwin Creek in the southeastern US, and Kalaeloa in Hawaii. For each location, a total of 78 PV output time series are analyzed encompassing 13 geographical footprints—from a single point, to 200x200 km integrated output—and 6 time scales —from one minute to two hours. One-minute PV output time series are simulated from one-minute high-resolution SolarAnywhere irradiances [19] in each 1x1 km high-resolution point in the considered 200x200 km regions (i.e., a total of ~ 40,000 points per region). These time series are averaged appropriately in space and in time to produce the desired time scales and footprints. The single-point PV output located at the center of each 200x200km region is simulated from actual irradiance measurements [20]. For any selected ramp rate reduction target and for each of the 78 space/time configurations, the buffer’s energy and power requirements as well as the running mean window are determined by calculating the difference between the running mean PV and the unfiltered PV output. The power requirements correspond to the highest absolute difference between the two, while the energy requirements correspond to the largest sum of accumulated differences while accounting for storage efficiency set at 95%. For each simulation, two types of running mean windows are considered: (1) trailing—no forecasts available, and (2) centered—ideal forecasts available. Trailing windows are extended as necessary to meet the maximum allowable ramp rate objectives. The lowest ramp rate objectives considered for this analysis are a function of the considered time scale, and range from 0.5% of installed capacity for one-minute fluctuations, to 10% for two-hour fluctuations. Post-­‐calibration of satellite data Because satellite-based simulations are derived from irradiance models that are bound at the high end by clear sky, and at the low end by standard overcast conditions, they tend, at this stage of their development, to underestimate the dynamic range generated by highly variable conditions (e.g., see [10]). Short of producing a new satellite model with enhanced dynamics, we apply here post-calibration approach that ensures that simulation output discontinuities observed as a function of footprint from the single (measured) point to the extended (satellite) points are eliminated. This process is illustrated in Fig. 3 for one of the calculated variables: 15 minute PV output variability. The [underestimated] satellite-derived trend is adjusted upward so that it naturally converges to the (measured) single point without discontinuity. A similar post-result calibration is applied to all the simulated output variables including, in addition to variability, all the buffer specs— energy, power and cost —produced in the present analysis. 18 Figure 3: Illustration of the satellite data post-result calibration process. This example is shown for the 15-minute PV output variability observed in Hanford. RESULTS PV output variability Figs. 4 and 5 report respectively the PV output variability and maximum absolute ramps observed at each location as a function of time scale and geographic footprint. PV output variability is defined as the standard deviation of the ramps per Hoff and Perez, [16]. While these results are consistent with earlier findings by the authors and others [16] showing that variability decreases as a function of footprint at a rate that is dependent upon the considered time scale, they also show interesting site differences and similarities between locations: Variability increases as a function of time scale at all locations in the considered 1-minute to 2-hour domain, with an exception for Hawaii, where the trend is reversed for very small footprints. This is likely because of the frequent occurrence of puffy cloud conditions resulting in high frequency variability at that site. As footprint increases beyond ~ 10 km, the trends are very similar for all sites, with highest overall values found for Goodwin Creek and lowest values found for Central California -- a likely results of the higher occurrences of intermediate conditions in the Southeastern US compared to California combined to faster moving cloud systems inducing a smaller decrease of variability with distance [2, 12, 16]. 19 Figure 4: PV Output Variability (standard deviation of ramps) a Function of time scale and footprint When looking at maximum ramps as the metric for variability, the similarity observed between all sites is remarkable (see Fig. 5), particularly for small footprints where ramp values are almost identical for all sites at all time scales. For small footprints, highest values are observed for high frequency ramps, while this tendency is reversed -- highest values for low frequency ramps -- beyond 1-5 km footprint. 20 Figure 5: Maximum absolute ramp rate observed at each location as a function of time scale and footprint. Mitigating variability – buffer specs Buffer specifications were determined for each of the 78 space/time configuration at each location. For each simulation, up to seven ramp mitigation targets and two forecast 21 scenarios were considered. We present here a crosscut of these results that is representative of this work’s key findings, including: (a) Influence of time scale, foot print and forecast availability for a given ramp rate mitigation objective; (b) Influence of ramp rate mitigation objective for selected footprints and time scales; and (c) Determination of buffer specs for a plausible operational objective. Complete simulation results will be made available in a project report scheduled for publication at the end of 2013 [21]. Influence of time scale, foot print and forecast availability for a given ramp mitigation objective: The ramp objective selected to illustrate the results is 100Watts per kW PV (i.e., 10% of installed capacity). For all considered time scales, footprints, locations and forecast scenarios, we present the buffer specification required to meet this maximum output ramp rate objective. Results are presented in Figs. 6, 7 and 8 for Hanford, Goodwin Creek and Kalaeloa, respectively. Buffer Energy requirements are primarily influenced by the considered time scale. Energy requirements are insignificant for short time scales and gradually increase with the considered time scale. The impact of footprint is also noticeable but not as pronounced, particularly for the longer time scales. The influence of forecast availability is noteworthy: energy requirements are markedly smaller when forecasts are available to drive the buffer’s running mean algorithm. This is particularly visible for the longer time frames, where the non-forecast trailing window must reach into the previous day’s conditions to meet the 100 W/kW maximum ramp rate objective presented in this example. Interestingly, the forecast advantage for longer time frames is more pronounced in California than it is in Hawaii. A likely explanation is that cloud conditions in Hawaii do not evolve as they do in California or Goodwin Creek, driven by the passing of fronts and cloud structures, but tend to remain comparable and repetitive over time, (i.e., the future is not as different from the past in Hawaii as it may be in California or the continental US.) 22 Figure 6: Buffer energy (top), capacity (middle) and cost per PV kW as a function or ramp rate time scale, footprint and availability of forecast in Hanford, California. These specs correspond to a maximum acceptable ramp rate of 100W per PV kW at all time/spatial scales. 23 Figure 7: Same as Fig. 6, but for Goodwin Creek, Mississippi. 24 Figure 8: Same as Figs. 6 and 7, but for Kalaeloa, Hawaii. Buffer power requirements peak for short time scales and small footprints. As footprint increases, power requirements for short time scales decrease rapidly, while longer time scales decrease more slowly. Differences between sites are minor and so is advantage of forecasts which do not substantially reduce the required buffer power rating. Buffer cost is a function of both energy and capacity requirements. In this 10% rated capacity maximum ramp objective example, one minute ramp mitigation with perfect forecast availability would cost $300-$400 for all locations per PV kW for single point and decrease to zero within a few km. Hourly ramps could be mitigated at a cost of $400500 per PV kW for a single point system, gradually declining to $100-$150 for 200x200 km footprints representative of utility service areas. Mitigation costs are lowest for California, followed closely by Hawaii. Highest mitigation are found in the SE US – a likely combination of the frequent occurrence of partly cloudy conditions associated with fast moving fronts and cloud structures – this is consistent with the observation decorrelation distance between pairs of points increases with prevailing cloud speed (e.g. see [16]). Buffer cost would typically be $100-$250 higher in the absence of forecasts. Influence of ramp rate mitigation objective for selected footprints and time scales: In Fig. 9 we illustrate the impact of the ramp mitigation objective on 25 buffer cost for two time scales (1-minute and 15-minute) and two footprints (1x1 and 3x30 km). This sample shows that mitigation cost decreases significantly with the mitigation target—and can reach zero when the target is already met by the geographical smoothing effect – this is the case for Kalaeloa’s 30x30 km footprint where 15 minute ramp rates are below the desired 25% PV rated capacity at all times without any need for buffering. The results in Fig. 9 also show that forecast availability systematically leads to lower costs—an average of $50-300/PV kW across this illustrative sample. Operational ramp rate mitigation scenario: Operationally, grid operators will likely target different variability mitigation objectives as a function of time scale as well as PV generation footprint, depending on their ability to react via ancillary services and/or variable power generation. These targets are likely to be more stringent for the lowest time scales and more lenient as time scales increase and grid operators have time to plan and react. As an example of plausible operational scenario, results in Table I, II and III (respectively Hanford, Goodwin Creek and Kalaeloa) illustrate operational mitigation costs for the following ramp mitigation targets: 5% of installed PV capacity at one-minute, 10% at 5 minutes, 15% at 15 minutes and 25% at one hour. Costs are shown for five dispersion footprints: point-specific, 5x5, 20x20, 50x50 and 200x200 km. Also shown is the fraction of PV energy lost via round trip through the mitigation buffer. For a single point, this operational cost is of the order of $300-350 per PV kW with perfect forecasts and would be about 40% higher without. Dispersed at the level of a large substation covering 20x20 km, PV generation could be operationally mitigated for $150-250 / kW, but this cost would be nearly twice as much without forecasts. 26 Figure 9: Influence of ramp mitigation objective for selected footprints and time scales 27 W ITHOUT FORECASTS W ITH FORECASTS Table I: Operational scenario buffer cost – Hanford, California Max acceptable ramp (Watts/kW installed) One minute 50 5 minutes 100 15 minutes 150 one hour 250 Max acceptable Ramp Rate ramp time scale (Watts/kW installed) One minute 50 5 minutes 100 15 minutes 150 one hour 250 Ramp Rate time scale single point Buffer cost Losses $ 357 0.08% $ 370 0.10% $ 341 0.12% $ 251 0.09% single point Buffer cost Losses $ 458 0.13% $ 506 0.15% $ 492 0.18% $ 360 0.18% Footprint Dimension (km) 5x5 20x20 50x50 Buffer Buffer Buffer cost cost cost Losses Losses Losses $ 103 0.01% $ 43 0.00% -­‐-­‐ 0.00% $ 248 0.04% $ 123 0.02% $ 21 0.00% $ 277 0.05% $ 160 0.03% $ 63 0.01% $ 195 0.06% $ 146 0.05% $ 127 0.04% Footprint Dimension (km) 5x5 20x20 50x50 Buffer Buffer Buffer cost cost cost Losses Losses Losses $ 197 0.04% $ 83 0.01% -­‐-­‐ 0.00% $ 406 0.07% $ 326 0.05% $ 102 0.01% $ 466 0.08% $ 410 0.07% $ 205 0.03% $ 428 0.09% $ 397 0.09% $ 352 0.08% 200x200 Buffer cost Losses -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.00% 200x200 Buffer cost Losses -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.00% W ITHOUT FORECASTS W ITH FORECASTS Table II: Operational scenario buffer cost – Goodwin Creek, Mississippi Max acceptable ramp (Watts/kW installed) One minute 50 5 minutes 100 15 minutes 150 one hour 250 Max acceptable Ramp Rate ramp time scale (Watts/kW installed) One minute 50 5 minutes 100 15 minutes 150 one hour 250 Ramp Rate time scale single point Buffer cost Losses $ 406 0.18% $ 405 0.19% $ 405 0.19% $ 457 0.24% single point Buffer cost Losses $ 579 0.25% $ 602 0.27% $ 654 0.29% $ 919 0.40% Footprint Dimension (km) 5x5 20x20 50x50 200x200 Buffer Buffer Buffer Buffer cost cost cost cost Losses Losses Losses Losses $ 109 0.03% -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.00% $ 235 0.08% $ 122 0.04% $ 46 0.01% -­‐-­‐ 0.00% $ 351 0.11% $ 175 0.06% $ 153 0.04% $ 72 0.01% $ 362 0.11% $ 337 0.10% $ 251 0.08% -­‐-­‐ 0.00% Footprint Dimension (km) 5x5 20x20 50x50 200x200 Buffer Buffer Buffer Buffer cost cost cost cost Losses Losses Losses Losses $ 280 0.08% $ 74 0.02% -­‐-­‐ 0.00% -­‐-­‐ 0.00% $ 434 0.14% $ 305 0.09% $ 180 0.05% $ 94 0.01% $ 583 0.20% $ 442 0.13% $ 355 0.11% $ 171 0.00% $ 641 0.18% $ 630 0.17% $ 567 0.16% -­‐-­‐ 0.00% 28 W ITHOUT FORECASTS W ITH FORECASTS Table III: Operational scenario buffer cost – Kalaeloa, Hawaii Max acceptable ramp (Watts/kW installed) One minute 50 5 minutes 100 15 minutes 150 one hour 250 Max acceptable Ramp Rate ramp time scale (Watts/kW installed) One minute 50 5 minutes 100 15 minutes 150 one hour 250 Ramp Rate time scale single point Buffer cost Losses $ 421 0.42% $ 380 0.38% $ 359 0.34% $ 355 0.30% single point Buffer cost Losses $ 557 0.51% $ 549 0.44% $ 512 0.38% $ 618 0.29% Footprint Dimension (km) 5x5 20x20 50x50 Buffer Buffer Buffer cost cost cost Losses Losses Losses $ 182 0.06% -­‐-­‐ 0.00% -­‐-­‐ 0.00% $ 223 0.12% $ 56 0.03% -­‐-­‐ 0.01% $ 214 0.12% $ 144 0.06% $ 43 0.02% $ 229 0.11% $ 163 0.08% $ 120 0.05% Footprint Dimension (km) 5x5 20x20 50x50 Buffer Buffer Buffer cost cost cost Losses Losses Losses $ 277 0.14% $ 32 0.01% $ 31 0.01% $ 382 0.18% $ 160 0.07% $ 79 0.02% $ 381 0.18% $ 292 0.11% $ 143 0.04% $ 411 0.15% $ 378 0.12% $ 303 0.09% 200x200 Buffer cost Losses -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.00% 200x200 Buffer cost Losses -­‐-­‐ 0.00% -­‐-­‐ 0.00% -­‐-­‐ 0.04% -­‐-­‐ 0.00% CONCLUSIONS We asked the question: what is the cost of mitigating PV output intermittency to any desired level using short-term energy “shock absorbing” buffers? Through three case studies in California, the Southeastern US and Hawaii, we quantified this cost as a function of the maximum allowable ramp rate, the intermittency time scale, and the geographic dispersion of the PV resource. We showed that this cost was appreciably dependent upon the availability of solar forecasts that could be used to control the operation of the intermittency absorbing buffers. A plausible operational scenario setting acceptable ramp rate levels as a function of their time scale and PV footprint showed that: • • • • • • • Intermittency can be mitigated at a cost amounting to less than 10%-­‐15% of a PV installations for a 5 km footprint and 5-­‐10% for a 50 km footprint; Energy losses from energy buffer transfer are negligible (well below 1%); Accurate forecasts can reduce mitigation costs by nearly 40%. The forecast advantage is found to be largest in the continental US where cloud structures are driven by moving fronts. Reducing dispersed generation’s variability instead of focusing on single installations would be considerably more cost effective when operationally possible. Mitigation costs are found to be highest in the southeastern US, particularly for longer variability time scale, also noting that differences between very different climatic environments are not very large. The present mitigation approach could be generalized and used as a driver for control systems, by exploiting high resolution satellite-­‐derived solar resource forecast data such as SolarAnywhere [19]. 29 REFERENCES [1] Hinkelman L., R. George and M. Sengupta, 2011: Differences between Along-Wind and Cross-Wind Solar Variability. Proc. Solar 2011, American Solar Energy Society Conf., Raleigh, NC [2] Hoff T., & R. Perez (2012): Modeling PV Fleet Output Variability, Solar Energy 86, 8, 2177-2189 [3] Hoff, T. E., Perez, R. 2010. “Quantifying PV power Output Variability.” Solar Energy 84 (2010) 1782–1793 [4] Jamaly, S., Bosch, J., Kleissl, J. 2012. “Aggregate Ramp Rates of Distributed Photovoltaic Systems in San Diego County.” IEEE Transactions on Sustainable Energy, in press [5] Lave, M., J. Kleissl, Arias-Castro, E., High-frequency fluctuations in clear-sky index, Solar Energy, doi:10.1016/j.solener.2011.06.031, 2011 [6] Lorenz E., T. Scheidsteger, J. Hurka, D. Heinemann and C. Kurz, (2011): Regional PV power prediction for improved grid integration. Progress in Photovoltaics, 19, 7, 757771. [7] Mills, A., Wiser, R. 2010. Implications of Wide-Area Geographic Diversity for ShortTerm Variability of Solar Power. Lawrence Berkeley National Laboratory Technical Report LBNL-3884E. [8] Murata, A., H. Yamaguchi, and K. Otani (2009): A Method of Estimating the Output Fluctuation of Many Photovoltaic Power Generation Systems Dispersed in a Wide Area, Electrical Engineering in Japan, Volume 166, No. 4, pp. 9-19 [9] Perez M., and V. Fthenakis, (2012): Quantifying Long Time Scale Solar Resource Variability. Proc. WREF, Denver, CO. [10] Perez, R., T. Hoff and S. Kivalov, (2011a): Spatial & temporal characteristics of solar radiation variability. Proc. of International Solar Energy (ISES) World Congress, Kassel, Germany [11] Perez, R., Kivalov, S., Schlemmer, J., Hemker Jr., C. , Hoff, T. E. (2011b): Parameterization of site-specific short-term irradiance variability, Solar Energy 85 (2011) 1343-1353 [12] Perez, R., Kivalov, S., Schlemmer, J., Hemker Jr., C. , Hoff, T. E. (2012): “Shortterm irradiance variability correlation as a function of distance.” Solar Energy 86, 8, pp. 2170-2176 [13] Wiemken E., H. G. Beyer, W. Heydenreich and K. Kiefer (2001): Power Characteristics of PV ensembles: Experience from the combined power productivity of 100 grid-connected systems distributed over Germany. Solar Energy 70, 513-519 [14] Woyte, A., Belmans, R., Nijs, J. (2007): Fluctuations in instantaneous clearness index. Solar Energy 81 (2), 195-206. [15] Marcos J., L. Morroyo, E. Lorenzo and M. Garcia, (2012): Smoothing of PV power fluctuations by geographical dispersion. Prog. Photovolt: Res. Appl. 2012; 20:226–237 [16] Perez, R., T. Hoff, (2013): Solar Resource Variability, in: Solar Resource Assessment & Forecasting (Ed. J. Kleissl), Elsevier, 2013 [17] Yordanov, G., O. Mitdgard, O. and L. Norum (2013): Overirradiance (Cloud Enhancement) Events at High Latitudes. IEEE Journal of Photovoltaics, 3, 1, 271-278. 30 [18] Germa, J.M., & M. Perez, (2012): Energy Storage: Technology, Applications & trends. Cluster Maritime Français. 10/3/12 [19] SolarAnywhere (2013): http://www.cleanpower.com/products/solaranywhere/solaranywhere-data / [20] NOAA SURFRAD & ISIS Networks: http://www.esrl.noaa.gov [21] Perez R. and T. Hoff (2013): Final Report on PV Variability Mitigation. GW University Report on contract No. under contracts No. 1000178044 (in preparation) 31 APPENDIX 2 Complete result tables HANFORD Single Point IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.66 0.41 0.16 0.06 0.04 0.02 0.02 1.27 0.72 0.36 0.15 0.10 0.08 $ 614 $ 559 $ 446 $ 357 $ 314 $ 281 $ 262 0.18% 0.14% 0.12% 0.08% 0.06% 0.04% 0.04% 0.76 0.77 0.74 0.71 0.70 0.58 $ 607 $ 535 $ 450 $ 370 $ 347 $ 288 0.27% 0.19% 0.14% 0.10% 0.08% 0.07% 1.58 0.88 0.45 0.36 0.22 $ 654 $ 555 $ 375 $ 341 $ 300 0.30% 0.20% 0.14% 0.12% 0.09% $ 641 $ 553 $ 438 $ 325 0.29% 0.19% 0.14% 0.11% 0.42 $ 406 0.46 $ 365 0.34 $ 251 0.24% 0.15% 0.09% 0.78 0.76 0.56 0.52 0.50 1.56 0.90 0.59 0.37 0.76 0.75 0.63 0.49 1.36 0.78 0.44 2.65 2.07 0.92 5.24 2.14 1.22 0.63 0.40 0.28 $ 1,043 $ 707 $ 619 $ 506 $ 414 $ 359 0.53% 0.32% 0.23% 0.15% 0.13% 0.11% $ 965 $ 745 $ 634 $ 492 $ 438 0.53% 0.39% 0.25% 0.18% 0.14% $ 914 $ 718 $ 620 $ 554 0.51% 0.38% 0.27% 0.20% 0.56 $ 826 0.57 $ 678 0.37 $ 360 0.50% 0.40% 0.18% 0.87 0.77 0.79 0.75 0.65 0.59 5.13 3.00 1.60 0.97 0.71 0.78 0.71 0.74 0.63 0.59 5.08 2.96 1.90 1.27 0.72 0.67 0.66 0.67 5.29 3.35 1.25 120-­‐minute ramps 0.35 $ 484 0.39 $ 443 0.30 $ 282 0.39% 0.30% 0.14% 32 0.35% 0.20% 0.17% 0.13% 0.10% 0.07% 0.07% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 990 $ 764 $ 514 $ 458 $ 447 $ 351 $ 327 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 1.14 1.05 0.77 0.78 0.85 0.77 0.72 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 2.53 1.25 0.58 0.30 0.17 0.07 0.06 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 0.94 0.94 0.88 0.79 0.72 0.69 0.64 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.77 4.83 4.39 0.55 $ 929 0.56 $ 781 0.49 $ 699 0.58% 0.48% 0.37% HANFORD 1X1 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.38 0.18 0.06 0.02 0.01 0.01 0.00 1.12 0.39 0.20 0.11 0.05 0.03 0.54 0.49 0.46 0.39 0.34 0.32 0.26 $ 352 $ 284 $ 226 $ 173 $ 146 $ 131 $ 104 0.13% 0.10% 0.07% 0.04% 0.03% 0.02% 0.02% 0.86 0.66 0.57 0.51 0.40 0.35 $ 654 $ 416 $ 325 $ 267 $ 194 $ 159 0.21% 0.14% 0.10% 0.08% 0.06% 0.04% 1.23 0.66 0.27 0.18 0.10 1.51 0.80 0.37 0.21 0.67 0.58 0.47 0.43 0.33 $ 547 $ 423 $ 296 $ 255 $ 187 0.22% 0.17% 0.10% 0.08% 0.06% 1.31 0.90 0.47 0.68 0.58 0.47 0.35 $ 884 $ 668 $ 476 $ 333 0.23% 0.17% 0.12% 0.08% 0.55 $ 494 0.49 $ 410 0.35 $ 272 0.16% 0.13% 0.09% 2.34 1.96 0.84 4.01 1.71 0.94 0.41 0.27 0.14 $ 788 $ 528 $ 466 $ 319 $ 255 $ 196 0.32% 0.18% 0.14% 0.10% 0.08% 0.06% $ 821 $ 610 $ 415 $ 356 $ 266 0.32% 0.20% 0.14% 0.12% 0.08% $ 813 $ 673 $ 475 $ 332 0.38% 0.23% 0.18% 0.12% 0.63 $ 724 0.55 $ 593 0.42 $ 410 0.29% 0.25% 0.18% 0.69 0.57 0.60 0.47 0.40 0.34 4.84 2.68 1.33 0.91 0.46 0.67 0.58 0.46 0.43 0.36 4.44 2.95 1.61 0.89 0.64 0.60 0.48 0.37 3.40 2.51 1.38 120-­‐minute ramps 0.58 $ 602 0.51 $ 515 0.35 $ 309 0.23% 0.20% 0.11% 33 0.15% 0.12% 0.09% 0.06% 0.04% 0.03% 0.02% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 580 $ 471 $ 367 $ 286 $ 229 $ 198 $ 151 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.66 0.61 0.57 0.51 0.45 0.41 0.33 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.57 0.89 0.37 0.15 0.07 0.05 0.02 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.89 5.70 4.88 0.59 $ 962 0.51 $ 809 0.45 $ 705 0.38% 0.34% 0.22% HANFORD 2X2 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.38 0.18 0.06 0.02 0.01 0.01 0.00 1.16 0.45 0.20 0.09 0.06 0.03 0.51 0.45 0.36 0.32 0.18 0.18 0.13 $ 338 $ 262 $ 179 $ 144 $ 75 $ 75 $ 53 0.12% 0.09% 0.06% 0.03% 0.01% 0.01% 0.01% 0.85 0.76 0.66 0.46 0.38 0.29 $ 654 $ 480 $ 367 $ 236 $ 190 $ 136 0.21% 0.14% 0.10% 0.07% 0.05% 0.03% 1.27 0.68 0.34 0.18 0.11 1.40 0.83 0.38 0.22 0.66 0.57 0.52 0.45 0.35 $ 551 $ 421 $ 334 $ 268 $ 197 0.21% 0.16% 0.11% 0.08% 0.06% 1.33 0.91 0.48 0.65 0.57 0.46 0.34 $ 834 $ 656 $ 465 $ 333 0.22% 0.17% 0.12% 0.08% 0.57 $ 508 0.51 $ 427 0.36 $ 275 0.16% 0.13% 0.08% 1.86 1.48 0.87 3.94 1.85 0.96 0.41 0.28 0.14 $ 820 $ 543 $ 443 $ 331 $ 285 $ 206 0.31% 0.18% 0.14% 0.09% 0.08% 0.05% $ 830 $ 597 $ 426 $ 363 $ 270 0.32% 0.20% 0.14% 0.12% 0.08% $ 871 $ 577 $ 470 $ 326 0.38% 0.21% 0.17% 0.12% 0.66 $ 748 0.57 $ 611 0.44 $ 422 0.29% 0.25% 0.18% 0.73 0.57 0.56 0.49 0.45 0.36 4.80 2.62 1.35 0.92 0.47 0.69 0.58 0.47 0.44 0.37 4.36 2.25 1.65 0.90 0.72 0.54 0.47 0.36 3.44 2.52 1.39 120-­‐minute ramps 0.56 $ 547 0.49 $ 463 0.36 $ 312 0.19% 0.16% 0.11% 34 0.14% 0.11% 0.08% 0.05% 0.03% 0.03% 0.02% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 569 $ 460 $ 319 $ 243 $ 175 $ 175 $ 123 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.64 0.60 0.49 0.42 0.35 0.35 0.26 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.57 0.88 0.32 0.15 0.05 0.05 0.02 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.02 4.79 3.21 0.53 $ 858 0.45 $ 698 0.35 $ 511 0.25% 0.21% 0.17% HANFORD 5X5 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.31 0.16 0.05 0.01 0.00 0.00 0.00 1.08 0.37 0.20 0.08 0.05 0.02 0.52 0.45 0.25 0.19 0.11 0.11 0.11 $ 329 $ 260 $ 132 $ 84 $ 43 $ 43 $ 43 0.10% 0.07% 0.04% 0.01% 0.00% 0.00% 0.00% 0.85 0.73 0.64 0.42 0.28 0.18 $ 641 $ 450 $ 359 $ 215 $ 141 $ 86 0.19% 0.12% 0.08% 0.05% 0.04% 0.02% 1.21 0.65 0.26 0.18 0.10 1.31 0.78 0.36 0.21 0.66 0.56 0.45 0.41 0.31 $ 537 $ 412 $ 283 $ 243 $ 176 0.21% 0.15% 0.09% 0.07% 0.05% 1.27 0.87 0.44 0.65 0.56 0.46 0.33 $ 822 $ 646 $ 462 $ 320 0.21% 0.16% 0.11% 0.07% 0.52 $ 469 0.46 $ 389 0.32 $ 247 0.16% 0.13% 0.08% 1.81 1.44 0.81 3.76 1.59 0.79 0.40 0.27 0.13 $ 804 $ 511 $ 402 $ 309 $ 249 $ 158 0.30% 0.17% 0.12% 0.08% 0.07% 0.04% $ 827 $ 599 $ 397 $ 339 $ 256 0.32% 0.19% 0.13% 0.11% 0.07% $ 858 $ 576 $ 459 $ 329 0.37% 0.20% 0.17% 0.11% 0.60 $ 707 0.53 $ 583 0.39 $ 391 0.28% 0.24% 0.17% 0.73 0.56 0.52 0.46 0.39 0.26 4.67 2.63 1.30 0.89 0.45 0.70 0.57 0.44 0.41 0.35 4.21 2.25 1.59 0.87 0.72 0.54 0.46 0.37 3.41 2.55 1.38 120-­‐minute ramps 0.55 $ 537 0.49 $ 453 0.35 $ 300 0.19% 0.16% 0.11% 35 0.13% 0.10% 0.06% 0.04% 0.01% 0.01% 0.01% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 505 $ 423 $ 286 $ 177 $ 93 $ 93 $ 93 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.55 0.55 0.44 0.30 0.19 0.19 0.19 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.50 0.81 0.29 0.12 0.02 0.02 0.02 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.00 4.86 3.24 0.53 $ 856 0.46 $ 712 0.35 $ 515 0.24% 0.21% 0.17% HANFORD 8X8 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.29 0.15 0.04 0.01 0.00 0.00 0.00 1.08 0.34 0.18 0.07 0.04 0.02 0.51 0.44 0.23 0.16 0.10 0.10 0.10 $ 318 $ 249 $ 116 $ 70 $ 39 $ 39 $ 39 0.09% 0.06% 0.03% 0.01% 0.00% 0.00% 0.00% 0.80 0.68 0.60 0.38 0.25 0.12 $ 611 $ 417 $ 334 $ 196 $ 127 $ 58 0.19% 0.11% 0.07% 0.04% 0.03% 0.01% 1.19 0.57 0.25 0.17 0.09 1.28 0.77 0.35 0.19 0.61 0.49 0.41 0.37 0.28 $ 508 $ 359 $ 265 $ 226 $ 157 0.20% 0.14% 0.08% 0.06% 0.04% 1.24 0.86 0.40 0.60 0.52 0.40 0.28 $ 763 $ 604 $ 418 $ 274 0.21% 0.15% 0.10% 0.07% 0.50 $ 452 0.45 $ 376 0.29 $ 225 0.15% 0.12% 0.08% 1.80 1.44 0.80 3.95 1.58 0.78 0.40 0.27 0.13 $ 792 $ 484 $ 372 $ 289 $ 240 $ 150 0.22% 0.16% 0.11% 0.08% 0.06% 0.04% $ 806 $ 559 $ 373 $ 334 $ 253 0.31% 0.19% 0.13% 0.10% 0.07% $ 838 $ 616 $ 440 $ 296 0.37% 0.22% 0.16% 0.11% 0.59 $ 702 0.52 $ 581 0.39 $ 387 0.28% 0.24% 0.17% 0.69 0.52 0.48 0.42 0.37 0.24 4.59 2.57 1.28 0.87 0.45 0.68 0.53 0.40 0.40 0.34 4.13 2.82 1.58 0.86 0.70 0.53 0.43 0.32 3.41 2.54 1.36 120-­‐minute ramps 0.55 $ 531 0.48 $ 453 0.35 $ 298 0.19% 0.16% 0.10% 36 0.12% 0.09% 0.05% 0.03% 0.01% 0.01% 0.01% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 486 $ 388 $ 258 $ 144 $ 85 $ 85 $ 85 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.54 0.50 0.40 0.25 0.17 0.17 0.17 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.40 0.75 0.26 0.09 0.02 0.02 0.02 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.01 4.85 3.24 0.53 $ 852 0.46 $ 711 0.35 $ 513 0.24% 0.20% 0.16% HANFORD 13X13 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.26 0.11 0.03 0.00 0.00 0.00 0.00 0.97 0.31 0.13 0.06 0.03 0.00 0.34 0.27 0.19 0.12 0.09 0.09 0.00 $ 226 $ 159 $ 95 $ 53 $ 34 $ 34 $ 0 0.08% 0.05% 0.02% 0.00% 0.00% 0.00% 0.00% 0.71 0.49 0.37 0.23 0.16 0.00 $ 545 $ 316 $ 213 $ 123 $ 82 $ 0 0.18% 0.10% 0.06% 0.04% 0.02% 0.00% 1.05 0.52 0.23 0.15 0.07 1.22 0.51 0.33 0.18 0.54 0.44 0.31 0.27 0.19 $ 450 $ 322 $ 206 $ 172 $ 111 0.19% 0.13% 0.07% 0.05% 0.03% 1.19 0.82 0.38 0.55 0.45 0.38 0.26 $ 714 $ 497 $ 395 $ 255 0.20% 0.12% 0.10% 0.06% 0.46 $ 424 0.40 $ 348 0.24 $ 196 0.15% 0.12% 0.07% 1.73 1.40 0.79 3.57 1.48 0.74 0.38 0.25 0.00 $ 699 $ 425 $ 348 $ 275 $ 225 $ 0 0.21% 0.15% 0.10% 0.07% 0.05% 0.00% $ 765 $ 534 $ 346 $ 321 $ 243 0.31% 0.18% 0.12% 0.10% 0.06% $ 809 $ 519 $ 422 $ 281 0.36% 0.19% 0.16% 0.10% 0.56 $ 679 0.51 $ 574 0.38 $ 379 0.27% 0.24% 0.16% 0.61 0.45 0.44 0.40 0.34 0.00 4.45 2.51 1.21 0.82 0.42 0.64 0.49 0.37 0.39 0.33 3.98 2.16 1.49 0.81 0.68 0.48 0.42 0.30 3.49 2.59 1.38 120-­‐minute ramps 0.54 $ 518 0.48 $ 440 0.35 $ 296 0.19% 0.15% 0.10% 37 0.12% 0.08% 0.05% 0.02% 0.01% 0.01% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 414 $ 345 $ 242 $ 100 $ 76 $ 76 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.44 0.45 0.37 0.17 0.15 0.15 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.32 0.66 0.25 0.07 0.02 0.02 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.08 4.88 3.26 0.52 $ 844 0.47 $ 720 0.35 $ 513 0.23% 0.20% 0.16% HANFORD 20X20 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.22 0.08 0.02 0.00 0.00 0.00 0.00 0.91 0.25 0.10 0.05 0.01 0.00 0.31 0.20 0.13 0.09 0.07 0.07 0.00 $ 202 $ 119 $ 66 $ 35 $ 27 $ 27 $ 0 0.07% 0.04% 0.01% 0.00% 0.00% 0.00% 0.00% 0.70 0.43 0.28 0.20 0.06 0.00 $ 532 $ 272 $ 158 $ 107 $ 29 $ 0 0.16% 0.08% 0.04% 0.03% 0.01% 0.00% 0.99 0.38 0.20 0.13 0.06 1.16 0.49 0.32 0.17 0.52 0.43 0.27 0.22 0.14 $ 432 $ 293 $ 180 $ 141 $ 83 0.18% 0.11% 0.06% 0.05% 0.03% 1.14 0.80 0.36 0.53 0.42 0.36 0.24 $ 685 $ 467 $ 373 $ 237 0.19% 0.11% 0.09% 0.05% 0.40 $ 377 0.35 $ 314 0.23 $ 185 0.14% 0.11% 0.07% 1.67 1.36 0.77 3.29 1.31 0.58 0.35 0.12 0.00 $ 629 $ 400 $ 306 $ 248 $ 116 $ 0 0.20% 0.14% 0.08% 0.06% 0.03% 0.00% $ 706 $ 476 $ 325 $ 298 $ 227 0.31% 0.16% 0.12% 0.09% 0.06% $ 739 $ 507 $ 416 $ 267 0.36% 0.19% 0.15% 0.10% 0.53 $ 659 0.48 $ 552 0.35 $ 362 0.26% 0.23% 0.16% 0.53 0.43 0.41 0.36 0.18 0.00 4.38 2.18 1.14 0.77 0.39 0.56 0.45 0.35 0.36 0.31 3.91 2.10 1.45 0.75 0.59 0.47 0.41 0.29 3.50 2.59 1.37 120-­‐minute ramps 0.51 $ 489 0.45 $ 424 0.33 $ 284 0.18% 0.15% 0.10% 38 0.11% 0.07% 0.04% 0.01% 0.01% 0.01% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 398 $ 315 $ 212 $ 74 $ 63 $ 63 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.43 0.41 0.32 0.13 0.12 0.12 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.22 0.56 0.23 0.04 0.02 0.02 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.10 4.88 3.26 0.51 $ 841 0.46 $ 717 0.34 $ 510 0.23% 0.19% 0.16% HANFORD 30X30 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.20 0.07 0.01 0.00 0.00 0.00 0.00 0.80 0.24 0.09 0.03 0.00 0.00 0.26 0.17 0.07 0.04 0.04 0.00 0.00 $ 175 $ 99 $ 37 $ 18 $ 18 $ 0 $ 0 0.06% 0.03% 0.01% 0.00% 0.00% 0.00% 0.00% 0.64 0.38 0.23 0.11 0.00 0.00 $ 477 $ 240 $ 135 $ 60 $ 0 $ 0 0.15% 0.07% 0.03% 0.01% 0.00% 0.00% 0.96 0.37 0.18 0.12 0.05 1.12 0.47 0.30 0.16 0.49 0.37 0.24 0.19 0.11 $ 407 $ 259 $ 159 $ 124 $ 67 0.17% 0.10% 0.05% 0.04% 0.02% 1.09 0.78 0.34 0.49 0.36 0.30 0.20 $ 645 $ 408 $ 325 $ 205 0.18% 0.10% 0.08% 0.05% 0.39 $ 364 0.34 $ 303 0.23 $ 179 0.14% 0.11% 0.06% 1.61 1.32 0.75 2.98 1.27 0.54 0.22 0.00 0.00 $ 563 $ 387 $ 272 $ 178 $ 0 $ 0 0.20% 0.13% 0.08% 0.04% 0.00% 0.00% $ 618 $ 462 $ 318 $ 269 $ 202 0.30% 0.16% 0.11% 0.08% 0.05% $ 622 $ 490 $ 401 $ 257 0.24% 0.18% 0.14% 0.09% 0.47 $ 609 0.43 $ 509 0.34 $ 353 0.26% 0.22% 0.15% 0.48 0.42 0.35 0.27 0.00 0.00 4.31 2.11 1.10 0.74 0.37 0.46 0.44 0.34 0.31 0.27 3.46 2.02 1.40 0.72 0.48 0.45 0.40 0.28 3.39 2.51 1.35 120-­‐minute ramps 0.46 $ 454 0.41 $ 391 0.29 $ 258 0.18% 0.14% 0.09% 39 0.10% 0.06% 0.03% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 373 $ 279 $ 161 $ 44 $ 44 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.41 0.37 0.25 0.08 0.08 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.11 0.51 0.16 0.02 0.02 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 5.94 4.76 3.19 0.49 $ 806 0.44 $ 690 0.33 $ 496 0.22% 0.19% 0.15% HANFORD 50X50 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.16 0.04 0.00 0.00 0.00 0.00 0.00 0.73 0.19 0.05 0.01 0.00 0.00 0.22 0.11 0.03 0.00 0.00 0.00 0.00 $ 146 $ 65 $ 12 $ 0 $ 0 $ 0 $ 0 0.04% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.56 0.31 0.15 0.04 0.00 0.00 $ 426 $ 199 $ 86 $ 19 $ 0 $ 0 0.13% 0.05% 0.02% 0.01% 0.00% 0.00% 0.83 0.27 0.09 0.04 0.00 1.03 0.44 0.26 0.12 0.43 0.26 0.16 0.09 0.00 $ 355 $ 185 $ 101 $ 55 $ 0 0.14% 0.07% 0.03% 0.02% 0.00% 1.04 0.75 0.33 0.44 0.31 0.24 0.16 $ 575 $ 354 $ 259 $ 160 0.16% 0.09% 0.06% 0.03% 0.37 $ 344 0.32 $ 283 0.20 $ 160 0.12% 0.09% 0.05% 1.51 1.24 0.66 2.46 0.98 0.41 0.10 0.00 0.00 $ 499 $ 306 $ 198 $ 78 $ 0 $ 0 0.19% 0.11% 0.06% 0.02% 0.00% 0.00% $ 541 $ 377 $ 227 $ 149 $ 0 0.20% 0.13% 0.07% 0.04% 0.00% $ 544 $ 442 $ 354 $ 222 0.21% 0.17% 0.13% 0.08% 0.40 $ 538 0.40 $ 471 0.31 $ 321 0.25% 0.21% 0.14% 0.44 0.33 0.26 0.11 0.00 0.00 3.53 1.62 0.68 0.35 0.00 0.42 0.37 0.26 0.19 0.00 2.82 1.84 1.27 0.66 0.44 0.41 0.35 0.24 3.17 2.28 1.22 120-­‐minute ramps 0.39 $ 398 0.33 $ 335 0.28 $ 243 0.17% 0.13% 0.08% 40 0.09% 0.05% 0.01% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 302 $ 220 $ 74 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.33 0.29 0.11 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.89 0.42 0.08 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 4.13 2.95 2.95 0.29 $ 518 0.29 $ 440 0.29 $ 440 0.18% 0.14% 0.14% HANFORD 80X80 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.09 0.01 0.00 0.00 0.00 0.00 0.00 0.61 0.11 0.01 0.00 0.00 0.00 0.18 0.06 0.00 0.00 0.00 0.00 0.00 $ 110 $ 31 $ 0 $ 0 $ 0 $ 0 $ 0 0.03% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.43 0.25 0.06 0.00 0.00 0.00 $ 331 $ 152 $ 32 $ 0 $ 0 $ 0 0.10% 0.04% 0.01% 0.00% 0.00% 0.00% 0.73 0.24 0.03 0.03 0.00 0.90 0.22 0.09 0.00 0.34 0.21 0.08 0.08 0.00 $ 291 $ 150 $ 48 $ 48 $ 0 0.12% 0.05% 0.01% 0.01% 0.00% 0.94 0.30 0.30 0.35 0.18 0.15 0.00 $ 477 $ 204 $ 140 $ 1 0.14% 0.05% 0.03% 0.00% 0.33 $ 310 0.16 $ 132 0.16 $ 132 0.11% 0.04% 0.04% 1.51 1.17 0.55 2.29 0.76 0.20 0.00 0.00 0.00 $ 414 $ 230 $ 105 $ 0 $ 0 $ 0 0.17% 0.08% 0.03% 0.00% 0.00% 0.00% $ 424 $ 277 $ 113 $ 113 $ 0 0.17% 0.10% 0.03% 0.03% 0.00% $ 460 $ 302 $ 187 $ 0 0.19% 0.11% 0.07% 0.00% 0.38 $ 507 0.33 $ 406 0.24 $ 262 0.23% 0.19% 0.12% 0.34 0.25 0.14 0.00 0.00 0.00 2.89 1.24 0.33 0.33 0.00 0.32 0.26 0.13 0.13 0.00 2.65 1.22 0.64 0.00 0.35 0.28 0.19 0.00 3.00 2.15 1.16 120-­‐minute ramps 0.46 $ 398 0.27 $ 281 0.27 $ 220 0.19% 0.12% 0.07% 41 0.07% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 234 $ 128 $ 0 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.25 0.17 0.00 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.72 0.21 0.00 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 3.75 2.61 2.61 0.29 $ 495 0.24 $ 378 0.24 $ 378 0.16% 0.13% 0.13% HANFORD 130X130 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.04 0.01 0.00 0.00 0.00 0.00 0.00 0.49 0.05 0.01 0.00 0.00 0.00 0.12 0.05 0.00 0.00 0.00 0.00 0.00 $ 70 $ 29 $ 0 $ 0 $ 0 $ 0 $ 0 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.30 0.18 0.05 0.00 0.00 0.00 $ 243 $ 100 $ 29 $ 0 $ 0 $ 0 0.08% 0.02% 0.01% 0.00% 0.00% 0.00% 0.62 0.14 0.02 0.00 0.00 0.69 0.18 0.08 0.00 0.25 0.18 0.08 0.00 0.00 $ 225 $ 121 $ 43 $ 0 $ 0 0.11% 0.03% 0.01% 0.00% 0.00% 0.77 0.24 0.00 0.27 0.17 0.14 0.00 $ 361 $ 184 $ 129 $ 1 0.11% 0.04% 0.02% 0.00% 0.26 $ 252 0.12 $ 100 0.00 $ 0 0.09% 0.03% 0.00% 1.51 1.11 0.00 2.32 0.48 0.19 0.00 0.00 0.00 $ 372 $ 151 $ 100 $ 0 $ 0 $ 0 0.15% 0.04% 0.02% 0.00% 0.00% 0.00% $ 374 $ 199 $ 107 $ 0 $ 0 0.14% 0.07% 0.03% 0.00% 0.00% $ 446 $ 258 $ 160 $ 0 0.18% 0.09% 0.05% 0.00% 0.25 $ 334 0.18 $ 221 0.00 $ 0 0.16% 0.10% 0.00% 0.28 0.17 0.13 0.00 0.00 0.00 2.59 0.93 0.32 0.00 0.00 0.28 0.18 0.12 0.00 0.00 2.86 1.19 0.62 0.00 0.32 0.22 0.15 0.00 2.01 1.11 0.00 120-­‐minute ramps 0.37 $ 389 0.20 $ 232 0.00 $ 1 0.16% 0.10% 0.00% 42 0.04% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 163 $ 121 $ 0 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.18 0.16 0.00 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.48 0.21 0.00 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 3.67 2.47 0.00 0.26 $ 467 0.20 $ 335 0.00 $ 1 0.16% 0.10% 0.00% HANFORD 200X200 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.11 0.02 0.00 0.00 0.00 0.00 0.04 0.02 0.00 0.00 0.00 0.00 0.00 $ 23 $ 12 $ 0 $ 0 $ 0 $ 0 $ 0 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.17 0.05 0.02 0.00 0.00 0.00 $ 107 $ 29 $ 8 $ 0 $ 0 $ 0 0.03% 0.01% 0.00% 0.00% 0.00% 0.00% 0.44 0.03 0.00 0.00 0.00 0.53 0.05 0.00 0.00 0.17 0.09 0.00 0.00 0.00 $ 155 $ 53 $ 0 $ 0 $ 0 0.08% 0.01% 0.00% 0.00% 0.00% 0.37 0.15 0.00 0.18 0.09 0.00 0.00 $ 255 $ 84 $ 1 $ 1 0.09% 0.02% 0.00% 0.00% 0.15 $ 132 0.07 $ 63 0.00 $ 0 0.05% 0.03% 0.00% 1.13 0.93 0.00 2.37 0.27 0.09 0.00 0.00 0.00 $ 358 $ 94 $ 43 $ 0 $ 0 $ 0 0.13% 0.02% 0.01% 0.00% 0.00% 0.00% $ 235 $ 124 $ 0 $ 0 $ 0 0.09% 0.04% 0.00% 0.00% 0.00% $ 252 $ 132 $ 0 $ 0 0.11% 0.04% 0.00% 0.00% 0.14 $ 182 0.14 $ 182 0.00 $ 0 0.08% 0.08% 0.00% 0.26 0.11 0.05 0.00 0.00 0.00 1.65 0.60 0.00 0.00 0.00 0.17 0.11 0.00 0.00 0.00 1.62 0.59 0.00 0.00 0.18 0.11 0.00 0.00 1.06 1.06 0.00 120-­‐minute ramps 0.25 $ 264 0.17 $ 193 0.00 $ 1 0.11% 0.08% 0.00% 43 0.02% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 99 $ 67 $ 0 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.12 0.09 0.00 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.24 0.13 0.00 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 2.27 2.27 0.00 0.20 $ 318 0.20 $ 318 0.00 $ 1 0.08% 0.08% 0.00% GOODWIN CREEK Single Point IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.80 0.39 0.16 0.08 0.04 0.02 0.02 2.00 0.73 0.36 0.18 0.11 0.08 0.87 0.93 0.85 0.79 0.75 0.71 0.65 $ 696 $ 617 $ 483 $ 406 $ 351 $ 314 $ 280 0.37% 0.30% 0.23% 0.18% 0.13% 0.11% 0.09% 0.78 0.77 0.73 0.67 0.63 0.56 $ 858 $ 621 $ 501 $ 405 $ 356 $ 304 0.46% 0.32% 0.25% 0.19% 0.16% 0.14% 2.68 1.05 0.51 0.32 0.22 2.28 1.09 0.64 0.42 0.65 0.64 0.61 0.57 0.54 $ 858 $ 603 $ 475 $ 405 $ 356 0.49% 0.33% 0.24% 0.19% 0.16% 2.44 1.47 0.97 0.59 0.53 0.47 0.45 $ 760 $ 535 $ 419 $ 361 0.43% 0.30% 0.23% 0.19% 0.62 $ 798 0.52 $ 590 0.44 $ 457 0.41% 0.31% 0.24% 3.72 2.75 1.91 5.98 3.18 1.63 0.75 0.45 0.30 $ 1,511 $ 1,105 $ 807 $ 602 $ 504 $ 453 0.74% 0.49% 0.36% 0.27% 0.23% 0.19% $ 1,440 $ 1,146 $ 816 $ 654 $ 554 0.73% 0.51% 0.37% 0.29% 0.24% $ 1,416 $ 1,123 $ 862 $ 678 0.70% 0.48% 0.37% 0.30% 0.77 $ 1,347 0.71 $ 1,121 0.63 $ 919 0.66% 0.48% 0.40% 0.95 0.89 0.80 0.73 0.69 0.67 6.32 4.19 2.23 1.35 0.90 0.83 0.77 0.68 0.64 0.61 6.31 4.12 2.63 1.78 0.80 0.76 0.67 0.58 5.92 4.44 3.33 120-­‐minute ramps 0.67 $ 1,012 0.57 $ 805 0.52 $ 651 0.52% 0.42% 0.34% 44 0.53% 0.41% 0.31% 0.25% 0.20% 0.16% 0.14% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 1,234 $ 924 $ 774 $ 579 $ 462 $ 411 $ 364 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 1.00 0.95 1.04 0.89 0.81 0.77 0.72 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 3.49 1.73 0.72 0.34 0.16 0.10 0.06 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.63 7.15 4.80 0.72 $ 1,593 0.65 $ 1,367 0.56 $ 1,036 0.82% 0.65% 0.47% GOODWIN CREEK 1X1 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.48 0.22 0.07 0.03 0.02 0.01 0.00 0.55 0.54 0.52 0.48 0.42 0.31 0.24 1.54 0.59 0.27 0.13 0.06 0.03 $ 436 $ 356 $ 281 $ 230 $ 189 $ 134 $ 99 0.22% 0.17% 0.11% 0.08% 0.06% 0.04% 0.03% 1.76 0.83 0.43 0.31 0.11 0.86 0.74 0.62 0.49 0.42 0.33 $ 856 $ 575 $ 418 $ 296 $ 231 $ 170 0.40% 0.26% 0.19% 0.14% 0.10% 0.06% $ 717 $ 516 $ 399 $ 362 $ 182 0.42% 0.29% 0.20% 0.18% 0.10% $ 1,082 $ 710 $ 507 $ 335 0.42% 0.27% 0.18% 0.11% 0.57 $ 742 0.55 $ 655 0.40 $ 375 0.38% 0.33% 0.16% 0.64 0.57 0.51 0.50 0.28 2.25 0.97 0.50 0.24 0.56 0.47 0.38 0.29 2.27 1.74 0.60 3.61 3.13 2.21 5.48 2.22 1.11 0.55 0.28 0.14 $ 1,271 $ 829 $ 580 $ 440 $ 319 $ 244 0.57% 0.38% 0.28% 0.20% 0.14% 0.10% $ 1,235 $ 968 $ 685 $ 584 $ 342 0.64% 0.43% 0.31% 0.27% 0.14% $ 1,291 $ 999 $ 702 $ 465 0.67% 0.43% 0.30% 0.20% 0.72 $ 1,252 0.71 $ 1,157 0.53 $ 641 0.61% 0.58% 0.34% 0.79 0.73 0.61 0.55 0.45 0.38 5.96 3.74 1.87 1.39 0.48 0.75 0.70 0.62 0.56 0.41 5.45 3.67 1.85 0.95 0.78 0.67 0.59 0.45 5.51 4.73 1.75 120-­‐minute ramps 0.65 $ 982 0.62 $ 892 0.55 $ 716 0.51% 0.45% 0.36% 45 0.29% 0.22% 0.15% 0.11% 0.08% 0.06% 0.04% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 816 $ 622 $ 433 $ 347 $ 300 $ 211 $ 142 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.73 0.69 0.60 0.55 0.52 0.39 0.28 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 2.00 0.98 0.38 0.18 0.10 0.05 0.03 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.37 7.33 4.56 0.69 $ 1,532 0.69 $ 1,420 0.47 $ 928 0.80% 0.77% 0.39% GOODWIN CREEK 2X2 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.47 0.22 0.07 0.03 0.01 0.01 0.00 1.53 0.57 0.26 0.12 0.06 0.03 $ 422 $ 308 $ 231 $ 185 $ 132 $ 104 $ 69 0.22% 0.16% 0.10% 0.06% 0.03% 0.03% 0.02% 0.85 0.74 0.61 0.48 0.37 0.27 $ 849 $ 569 $ 408 $ 288 $ 206 $ 142 0.40% 0.25% 0.18% 0.14% 0.09% 0.05% 1.75 0.83 0.42 0.31 0.11 $ 715 $ 509 $ 392 $ 354 $ 171 0.41% 0.29% 0.20% 0.17% 0.10% $ 1,083 $ 708 $ 515 $ 337 0.42% 0.27% 0.18% 0.11% 0.57 $ 741 0.55 $ 656 0.41 $ 377 0.38% 0.33% 0.16% 0.64 0.56 0.50 0.48 0.26 2.23 0.96 0.49 0.24 0.57 0.47 0.40 0.29 2.26 1.74 0.61 3.58 3.11 2.20 5.07 2.22 1.10 0.55 0.28 0.14 $ 1,240 $ 835 $ 590 $ 444 $ 324 $ 217 0.66% 0.38% 0.27% 0.19% 0.14% 0.09% $ 1,208 $ 969 $ 688 $ 588 $ 337 0.63% 0.43% 0.31% 0.26% 0.14% $ 1,360 $ 992 $ 691 $ 457 0.53% 0.43% 0.30% 0.20% 0.72 $ 1,253 0.71 $ 1,157 0.54 $ 643 0.61% 0.58% 0.34% 0.81 0.74 0.62 0.56 0.46 0.33 5.70 3.73 1.87 1.39 0.47 0.75 0.70 0.62 0.57 0.41 6.29 3.67 1.85 0.94 0.75 0.66 0.57 0.44 5.51 4.72 1.74 120-­‐minute ramps 0.65 $ 978 0.62 $ 889 0.55 $ 713 0.51% 0.45% 0.36% 46 0.31% 0.22% 0.14% 0.10% 0.06% 0.05% 0.03% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 823 $ 617 $ 436 $ 349 $ 248 $ 194 $ 119 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.74 0.68 0.60 0.56 0.44 0.36 0.23 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 2.00 0.99 0.37 0.18 0.08 0.05 0.03 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 0.53 0.45 0.41 0.37 0.30 0.24 0.17 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.22 7.18 4.54 0.69 $ 1,513 0.68 $ 1,402 0.47 $ 926 0.80% 0.77% 0.38% GOODWIN CREEK 3X3 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.48 0.21 0.07 0.03 0.01 0.00 0.00 1.52 0.58 0.26 0.12 0.06 0.03 0.54 0.44 0.35 0.28 0.18 0.10 0.00 $ 424 $ 299 $ 198 $ 142 $ 85 $ 42 $ 0 0.21% 0.15% 0.09% 0.05% 0.03% 0.01% 0.00% 0.87 0.74 0.62 0.42 0.35 0.25 $ 856 $ 573 $ 411 $ 260 $ 194 $ 132 0.40% 0.25% 0.18% 0.13% 0.08% 0.05% 1.75 0.83 0.42 0.31 0.11 2.23 0.96 0.50 0.24 0.64 0.57 0.51 0.49 0.27 $ 713 $ 516 $ 398 $ 358 $ 177 0.41% 0.29% 0.20% 0.17% 0.09% 2.26 1.75 0.60 0.55 0.46 0.39 0.29 $ 1,069 $ 705 $ 507 $ 336 0.41% 0.27% 0.17% 0.11% 0.57 $ 740 0.55 $ 654 0.40 $ 371 0.38% 0.32% 0.16% 3.58 3.11 2.20 5.10 2.23 1.11 0.55 0.28 0.14 $ 1,237 $ 828 $ 579 $ 438 $ 311 $ 225 0.66% 0.38% 0.27% 0.19% 0.14% 0.09% $ 1,233 $ 966 $ 684 $ 583 $ 337 0.64% 0.43% 0.31% 0.26% 0.14% $ 1,299 $ 997 $ 701 $ 466 0.67% 0.43% 0.30% 0.20% 0.72 $ 1,253 0.71 $ 1,157 0.53 $ 641 0.61% 0.57% 0.34% 0.80 0.73 0.61 0.55 0.43 0.35 5.95 3.73 1.87 1.39 0.47 0.75 0.70 0.61 0.56 0.41 5.51 3.67 1.85 0.95 0.78 0.67 0.59 0.45 5.51 4.72 1.75 120-­‐minute ramps 0.65 $ 978 0.62 $ 889 0.55 $ 711 0.50% 0.44% 0.36% 47 0.31% 0.22% 0.14% 0.10% 0.06% 0.02% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 807 $ 597 $ 421 $ 333 $ 217 $ 94 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.72 0.65 0.58 0.53 0.38 0.17 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.98 0.96 0.37 0.18 0.08 0.03 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.35 7.31 4.55 0.69 $ 1,531 0.69 $ 1,419 0.47 $ 928 0.80% 0.76% 0.38% GOODWIN CREEK 5X5 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.47 0.21 0.06 0.02 0.01 0.00 0.00 1.52 0.57 0.26 0.12 0.06 0.03 0.53 0.43 0.27 0.22 0.11 0.00 0.00 $ 416 $ 294 $ 155 $ 109 $ 54 $ 0 $ 0 0.20% 0.14% 0.08% 0.03% 0.02% 0.00% 0.00% 0.84 0.74 0.60 0.37 0.29 0.19 $ 840 $ 568 $ 403 $ 235 $ 163 $ 101 0.39% 0.24% 0.16% 0.12% 0.07% 0.04% 1.75 0.83 0.42 0.31 0.10 1.99 0.95 0.50 0.24 0.63 0.57 0.51 0.48 0.26 $ 702 $ 514 $ 395 $ 351 $ 169 0.40% 0.28% 0.19% 0.16% 0.09% 2.26 1.75 0.59 0.55 0.46 0.39 0.29 $ 1,021 $ 698 $ 511 $ 339 0.39% 0.26% 0.17% 0.10% 0.56 $ 732 0.54 $ 646 0.39 $ 362 0.38% 0.32% 0.16% 3.46 2.99 2.11 5.09 2.22 1.10 0.55 0.28 0.14 $ 1,231 $ 824 $ 573 $ 434 $ 309 $ 197 0.67% 0.39% 0.27% 0.18% 0.13% 0.08% $ 1,203 $ 966 $ 684 $ 583 $ 332 0.62% 0.41% 0.30% 0.25% 0.13% $ 1,334 $ 998 $ 702 $ 467 0.52% 0.42% 0.30% 0.19% 0.72 $ 1,252 0.71 $ 1,157 0.53 $ 641 0.61% 0.57% 0.34% 0.80 0.72 0.60 0.54 0.43 0.29 5.71 3.73 1.87 1.39 0.47 0.74 0.70 0.61 0.56 0.40 6.01 3.66 1.85 0.94 0.76 0.67 0.59 0.45 5.50 4.72 1.75 120-­‐minute ramps 0.65 $ 963 0.62 $ 874 0.55 $ 699 0.50% 0.44% 0.35% 48 0.30% 0.21% 0.13% 0.08% 0.05% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 801 $ 573 $ 393 $ 280 $ 187 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.71 0.62 0.54 0.44 0.31 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.97 0.96 0.35 0.15 0.08 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.35 7.31 4.54 0.69 $ 1,530 0.69 $ 1,419 0.47 $ 926 0.80% 0.77% 0.38% GOODWIN CREEK 8X8 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.46 0.20 0.05 0.01 0.00 0.00 0.00 1.51 0.56 0.25 0.11 0.05 0.02 0.51 0.39 0.22 0.14 0.00 0.00 0.00 $ 402 $ 271 $ 130 $ 72 $ 0 $ 0 $ 0 0.19% 0.13% 0.06% 0.02% 0.00% 0.00% 0.00% 0.82 0.71 0.57 0.36 0.22 0.13 $ 824 $ 552 $ 380 $ 225 $ 125 $ 72 0.38% 0.22% 0.15% 0.10% 0.06% 0.03% 1.74 0.82 0.42 0.30 0.10 1.98 0.94 0.49 0.24 0.60 0.55 0.49 0.45 0.23 $ 679 $ 501 $ 380 $ 333 $ 152 0.39% 0.27% 0.18% 0.15% 0.08% 2.25 1.74 0.58 0.55 0.46 0.39 0.28 $ 1,020 $ 690 $ 507 $ 332 0.38% 0.26% 0.16% 0.10% 0.55 $ 719 0.52 $ 634 0.38 $ 353 0.37% 0.32% 0.16% 3.44 2.97 2.09 5.03 2.22 1.10 0.41 0.28 0.14 $ 1,215 $ 817 $ 569 $ 373 $ 301 $ 182 0.66% 0.37% 0.26% 0.15% 0.11% 0.07% $ 1,211 $ 965 $ 685 $ 456 $ 312 0.62% 0.40% 0.29% 0.19% 0.12% $ 1,328 $ 993 $ 700 $ 465 0.51% 0.42% 0.29% 0.19% 0.76 $ 1,292 0.71 $ 1,154 0.53 $ 641 0.60% 0.57% 0.33% 0.78 0.71 0.59 0.49 0.42 0.27 5.80 3.72 1.86 0.92 0.47 0.74 0.70 0.62 0.48 0.37 6.00 3.66 1.84 0.93 0.75 0.67 0.59 0.45 5.50 4.71 1.74 120-­‐minute ramps 0.65 $ 960 0.63 $ 872 0.55 $ 697 0.50% 0.44% 0.35% 49 0.29% 0.20% 0.11% 0.07% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 786 $ 551 $ 368 $ 229 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.70 0.58 0.49 0.34 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.94 0.96 0.35 0.15 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.34 7.29 4.53 0.74 $ 1,572 0.68 $ 1,411 0.47 $ 922 0.79% 0.76% 0.38% GOODWIN CREEK 13X13 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.45 0.18 0.04 0.01 0.00 0.00 0.00 1.50 0.55 0.23 0.07 0.04 0.00 0.47 0.35 0.14 0.04 0.00 0.00 0.00 $ 378 $ 242 $ 85 $ 24 $ 0 $ 0 $ 0 0.17% 0.11% 0.04% 0.01% 0.00% 0.00% 0.00% 0.74 0.66 0.51 0.23 0.16 0.00 $ 767 $ 519 $ 347 $ 144 $ 96 $ 0 0.36% 0.20% 0.13% 0.07% 0.04% 0.00% 1.73 0.80 0.41 0.29 0.09 1.97 0.91 0.48 0.23 0.56 0.51 0.44 0.40 0.20 $ 654 $ 473 $ 350 $ 300 $ 133 0.38% 0.26% 0.16% 0.13% 0.06% 2.23 1.72 0.57 0.53 0.44 0.36 0.24 $ 989 $ 669 $ 475 $ 296 0.38% 0.25% 0.15% 0.09% 0.53 $ 701 0.50 $ 617 0.37 $ 349 0.37% 0.31% 0.15% 3.42 2.95 2.08 5.20 2.22 1.09 0.41 0.28 0.00 $ 1,209 $ 803 $ 564 $ 330 $ 262 $ 0 0.53% 0.35% 0.24% 0.13% 0.10% 0.00% $ 1,207 $ 960 $ 680 $ 448 $ 290 0.60% 0.39% 0.28% 0.18% 0.12% $ 1,320 $ 995 $ 700 $ 464 0.51% 0.41% 0.29% 0.18% 0.74 $ 1,274 0.71 $ 1,152 0.53 $ 638 0.60% 0.56% 0.33% 0.76 0.69 0.59 0.41 0.35 0.00 5.80 3.72 1.86 0.92 0.47 0.73 0.69 0.61 0.46 0.33 5.99 3.65 1.84 0.93 0.74 0.67 0.59 0.45 5.49 4.71 1.74 120-­‐minute ramps 0.65 $ 954 0.62 $ 868 0.55 $ 693 0.49% 0.43% 0.35% 50 0.28% 0.18% 0.10% 0.04% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 774 $ 541 $ 316 $ 153 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.68 0.58 0.41 0.23 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.94 0.93 0.32 0.10 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.31 7.26 4.53 0.67 $ 1,501 0.63 $ 1,359 0.46 $ 918 0.52% 0.49% 0.38% GOODWIN CREEK 20X20 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.42 0.16 0.03 0.00 0.00 0.00 0.00 1.47 0.52 0.21 0.06 0.03 0.00 0.39 0.27 0.10 0.02 0.00 0.00 0.00 $ 322 $ 191 $ 59 $ 10 $ 0 $ 0 $ 0 0.15% 0.09% 0.03% 0.00% 0.00% 0.00% 0.00% 0.68 0.55 0.40 0.20 0.14 0.00 $ 724 $ 446 $ 279 $ 122 $ 82 $ 0 0.34% 0.18% 0.11% 0.05% 0.03% 0.00% 1.71 0.78 0.38 0.16 0.07 1.95 0.89 0.46 0.22 0.50 0.44 0.35 0.24 0.15 $ 605 $ 426 $ 290 $ 175 $ 103 0.36% 0.24% 0.15% 0.09% 0.05% 2.19 1.68 0.56 0.51 0.43 0.33 0.21 $ 968 $ 656 $ 440 $ 258 0.36% 0.24% 0.14% 0.08% 0.52 $ 690 0.48 $ 595 0.36 $ 337 0.36% 0.30% 0.14% 3.41 2.94 2.07 5.33 2.07 0.95 0.41 0.27 0.00 $ 1,207 $ 767 $ 518 $ 305 $ 235 $ 0 0.51% 0.32% 0.21% 0.12% 0.09% 0.00% $ 1,187 $ 945 $ 669 $ 442 $ 277 0.59% 0.37% 0.26% 0.17% 0.10% $ 1,249 $ 992 $ 680 $ 447 0.49% 0.40% 0.28% 0.18% 0.70 $ 1,238 0.69 $ 1,141 0.52 $ 630 0.58% 0.55% 0.32% 0.74 0.67 0.55 0.37 0.30 0.00 5.75 3.71 1.86 0.92 0.46 0.72 0.68 0.59 0.45 0.31 5.61 3.64 1.84 0.91 0.71 0.67 0.56 0.43 5.50 4.70 1.74 120-­‐minute ramps 0.66 $ 964 0.62 $ 866 0.55 $ 693 0.49% 0.43% 0.34% 51 0.26% 0.17% 0.08% 0.02% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 749 $ 526 $ 253 $ 74 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.66 0.56 0.33 0.11 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.85 0.90 0.27 0.05 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.31 7.24 4.50 0.63 $ 1,456 0.62 $ 1,342 0.46 $ 910 0.51% 0.48% 0.37% GOODWIN CREEK 30X30 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.38 0.12 0.01 0.00 0.00 0.00 0.00 1.44 0.48 0.15 0.05 0.01 0.00 0.32 0.20 0.07 0.00 0.00 0.00 0.00 $ 272 $ 144 $ 39 $ 0 $ 0 $ 0 $ 0 0.14% 0.07% 0.02% 0.00% 0.00% 0.00% 0.00% 0.62 0.45 0.29 0.14 0.04 0.00 $ 678 $ 379 $ 206 $ 90 $ 24 $ 0 0.32% 0.16% 0.08% 0.04% 0.01% 0.00% 1.68 0.75 0.34 0.14 0.06 1.93 0.86 0.42 0.19 0.45 0.42 0.29 0.22 0.12 $ 562 $ 403 $ 246 $ 160 $ 84 0.35% 0.22% 0.13% 0.07% 0.04% 2.15 1.64 0.53 0.48 0.42 0.27 0.17 $ 921 $ 638 $ 378 $ 212 0.35% 0.22% 0.13% 0.07% 0.51 $ 680 0.46 $ 570 0.33 $ 311 0.35% 0.29% 0.13% 3.39 2.92 2.05 5.36 1.91 0.94 0.40 0.14 0.00 $ 1,176 $ 711 $ 493 $ 282 $ 127 $ 0 0.47% 0.29% 0.19% 0.10% 0.04% 0.00% $ 1,155 $ 909 $ 542 $ 417 $ 259 0.57% 0.35% 0.21% 0.16% 0.09% $ 1,229 $ 974 $ 648 $ 409 0.47% 0.39% 0.27% 0.17% 0.69 $ 1,225 0.67 $ 1,114 0.50 $ 611 0.57% 0.54% 0.31% 0.70 0.62 0.52 0.34 0.17 0.00 5.78 3.68 1.37 0.91 0.45 0.68 0.63 0.51 0.42 0.29 5.58 3.62 1.82 0.91 0.69 0.65 0.52 0.38 5.45 4.67 1.72 120-­‐minute ramps 0.68 $ 974 0.62 $ 860 0.54 $ 689 0.48% 0.42% 0.33% 52 0.23% 0.15% 0.06% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 694 $ 486 $ 213 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.61 0.52 0.27 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.71 0.84 0.24 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.25 7.20 4.47 0.63 $ 1,455 0.61 $ 1,324 0.45 $ 895 0.50% 0.47% 0.36% GOODWIN CREEK 50X50 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.30 0.08 0.00 0.00 0.00 0.00 0.00 1.34 0.34 0.10 0.02 0.00 0.00 0.27 0.18 0.03 0.00 0.00 0.00 0.00 $ 228 $ 119 $ 14 $ 0 $ 0 $ 0 $ 0 0.10% 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.54 0.38 0.26 0.08 0.00 0.00 $ 603 $ 308 $ 172 $ 46 $ 0 $ 0 0.28% 0.12% 0.05% 0.02% 0.00% 0.00% 1.63 0.70 0.20 0.12 0.05 1.89 0.82 0.35 0.16 0.43 0.36 0.26 0.22 0.12 $ 538 $ 357 $ 197 $ 153 $ 80 0.32% 0.20% 0.08% 0.05% 0.03% 2.10 1.58 0.47 0.46 0.38 0.22 0.12 $ 899 $ 579 $ 312 $ 161 0.33% 0.20% 0.11% 0.05% 0.50 $ 664 0.45 $ 557 0.25 $ 251 0.33% 0.27% 0.11% 2.53 2.05 2.05 4.79 1.75 0.80 0.26 0.00 0.00 $ 1,077 $ 596 $ 381 $ 180 $ 0 $ 0 0.41% 0.25% 0.15% 0.06% 0.00% 0.00% $ 1,150 $ 784 $ 467 $ 355 $ 228 0.55% 0.31% 0.19% 0.14% 0.08% $ 1,189 $ 921 $ 602 $ 384 0.46% 0.37% 0.25% 0.15% 0.68 $ 1,200 0.62 $ 1,062 0.44 $ 567 0.55% 0.52% 0.29% 0.65 0.49 0.38 0.21 0.00 0.00 5.82 3.20 1.36 0.90 0.45 0.67 0.54 0.40 0.33 0.24 5.50 3.57 1.80 0.90 0.66 0.59 0.47 0.34 5.35 4.59 1.70 120-­‐minute ramps 0.59 $ 792 0.54 $ 682 0.54 $ 682 0.38% 0.32% 0.32% 53 0.20% 0.12% 0.02% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 590 $ 379 $ 91 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.49 0.39 0.12 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.62 0.72 0.09 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.09 7.08 4.39 0.65 $ 1,453 0.59 $ 1,291 0.43 $ 866 0.49% 0.46% 0.35% GOODWIN CREEK 80X80 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.24 0.06 0.00 0.00 0.00 0.00 0.00 1.25 0.28 0.07 0.01 0.00 0.00 0.27 0.16 0.02 0.00 0.00 0.00 0.00 $ 214 $ 104 $ 10 $ 0 $ 0 $ 0 $ 0 0.08% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.49 0.38 0.22 0.03 0.00 0.00 $ 556 $ 291 $ 140 $ 20 $ 0 $ 0 0.24% 0.09% 0.03% 0.01% 0.00% 0.00% 1.43 0.63 0.16 0.09 0.00 1.80 0.76 0.31 0.13 0.40 0.29 0.26 0.22 0.00 $ 493 $ 296 $ 188 $ 145 $ 0 0.28% 0.17% 0.06% 0.04% 0.00% 2.00 1.49 0.42 0.44 0.26 0.17 0.09 $ 859 $ 450 $ 250 $ 119 0.30% 0.17% 0.09% 0.04% 0.48 $ 636 0.43 $ 531 0.17 $ 185 0.30% 0.25% 0.10% 2.47 2.00 0.89 4.48 1.60 0.66 0.13 0.00 0.00 $ 1,005 $ 507 $ 301 $ 99 $ 0 $ 0 0.37% 0.21% 0.11% 0.03% 0.00% 0.00% $ 1,082 $ 731 $ 421 $ 324 $ 0 0.37% 0.29% 0.17% 0.12% 0.00% $ 1,128 $ 719 $ 542 $ 351 0.43% 0.30% 0.23% 0.13% 0.60 $ 1,026 0.51 $ 813 0.37 $ 507 0.49% 0.42% 0.27% 0.61 0.40 0.30 0.12 0.00 0.00 5.80 3.13 1.35 0.90 0.00 0.60 0.49 0.34 0.29 0.00 5.30 2.65 1.77 0.89 0.61 0.48 0.40 0.30 4.44 3.24 1.67 120-­‐minute ramps 0.57 $ 766 0.51 $ 657 0.39 $ 407 0.36% 0.30% 0.18% 54 0.16% 0.09% 0.01% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 490 $ 317 $ 64 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.39 0.31 0.08 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.41 0.66 0.07 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 8.41 6.82 4.26 0.66 $ 1,497 0.57 $ 1,249 0.41 $ 837 0.51% 0.44% 0.33% GOODWIN CREEK 130X130 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.13 0.04 0.00 0.00 0.00 0.00 0.00 1.06 0.16 0.05 0.01 0.00 0.00 0.25 0.11 0.00 0.00 0.00 0.00 0.00 $ 175 $ 71 $ 0 $ 0 $ 0 $ 0 $ 0 0.05% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.44 0.35 0.17 0.03 0.00 0.00 $ 485 $ 240 $ 107 $ 19 $ 0 $ 0 0.21% 0.05% 0.02% 0.00% 0.00% 0.00% 1.27 0.54 0.08 0.04 0.00 1.60 0.65 0.10 0.10 0.36 0.28 0.21 0.12 0.00 $ 444 $ 277 $ 140 $ 74 $ 0 0.24% 0.14% 0.03% 0.01% 0.00% 1.78 1.31 0.33 0.40 0.21 0.08 0.08 $ 773 $ 372 $ 101 $ 101 0.26% 0.14% 0.03% 0.03% 0.44 $ 576 0.39 $ 472 0.13 $ 146 0.27% 0.21% 0.08% 2.23 1.81 0.81 3.88 1.14 0.50 0.13 0.00 0.00 $ 853 $ 379 $ 255 $ 98 $ 0 $ 0 0.34% 0.15% 0.08% 0.02% 0.00% 0.00% $ 901 $ 570 $ 284 $ 182 $ 0 0.34% 0.24% 0.10% 0.06% 0.00% $ 1,025 $ 624 $ 460 $ 304 0.40% 0.27% 0.20% 0.11% 0.49 $ 894 0.44 $ 724 0.31 $ 446 0.45% 0.38% 0.24% 0.51 0.31 0.26 0.12 0.00 0.00 4.76 2.53 0.86 0.43 0.00 0.50 0.37 0.24 0.18 0.00 4.86 2.48 1.69 0.85 0.55 0.39 0.31 0.25 4.09 3.01 1.59 120-­‐minute ramps 0.53 $ 707 0.47 $ 599 0.34 $ 360 0.33% 0.27% 0.15% 55 0.12% 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 381 $ 263 $ 0 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.32 0.28 0.00 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.04 0.45 0.00 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.68 6.24 3.94 0.54 $ 1,306 0.49 $ 1,109 0.36 $ 754 0.47% 0.41% 0.31% GOODWIN CREEK 200X200 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.07 0.03 0.00 0.00 0.00 0.00 0.00 0.70 0.09 0.03 0.01 0.00 0.00 0.19 0.10 0.00 0.00 0.00 0.00 0.00 $ 121 $ 63 $ 0 $ 0 $ 0 $ 0 $ 0 0.02% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.32 0.28 0.12 0.03 0.00 0.00 $ 340 $ 178 $ 74 $ 19 $ 0 $ 0 0.15% 0.03% 0.01% 0.00% 0.00% 0.00% 0.96 0.21 0.07 0.03 0.00 1.13 0.20 0.00 0.00 0.29 0.27 0.21 0.12 0.00 $ 348 $ 205 $ 134 $ 72 $ 0 0.20% 0.06% 0.02% 0.01% 0.00% 1.08 0.64 0.00 0.31 0.10 0.00 0.00 $ 579 $ 150 $ 1 $ 1 0.19% 0.05% 0.00% 0.00% 0.31 $ 382 0.21 $ 246 0.00 $ 1 0.18% 0.12% 0.00% 1.97 1.57 0.68 3.06 0.66 0.33 0.11 0.00 0.00 $ 673 $ 293 $ 205 $ 94 $ 0 $ 0 0.29% 0.09% 0.05% 0.02% 0.00% 0.00% $ 720 $ 370 $ 265 $ 171 $ 0 0.30% 0.16% 0.09% 0.05% 0.00% $ 792 $ 369 $ 0 $ 0 0.35% 0.18% 0.00% 0.00% 0.42 $ 757 0.36 $ 606 0.00 $ 0 0.41% 0.34% 0.00% 0.40 0.28 0.23 0.12 0.00 0.00 3.83 1.46 0.74 0.37 0.00 0.40 0.26 0.23 0.17 0.00 3.74 1.44 0.00 0.00 0.43 0.24 0.00 0.00 3.46 2.55 0.00 120-­‐minute ramps 0.50 $ 645 0.39 $ 504 0.26 $ 284 0.30% 0.24% 0.13% 56 0.07% 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 299 $ 223 $ 0 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.29 0.26 0.00 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.61 0.31 0.00 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.52 5.29 3.32 0.46 $ 1,107 0.41 $ 930 0.32 $ 658 0.44% 0.37% 0.28% KALAEOLA Single Point IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.73 0.37 0.16 0.08 0.05 0.03 0.02 1.69 0.70 0.34 0.18 0.12 0.09 0.93 0.96 0.99 0.89 0.88 0.80 0.73 $ 625 $ 560 $ 501 $ 421 $ 388 $ 343 $ 295 0.65% 0.59% 0.50% 0.42% 0.36% 0.31% 0.23% 0.73 0.73 0.75 0.70 0.64 0.61 $ 636 $ 513 $ 450 $ 380 $ 332 $ 306 0.63% 0.53% 0.46% 0.38% 0.33% 0.29% 2.06 0.85 0.50 0.32 0.22 1.94 0.80 0.61 0.40 0.65 0.63 0.60 0.57 0.50 $ 623 $ 478 $ 407 $ 359 $ 300 0.57% 0.45% 0.39% 0.34% 0.29% 1.83 1.21 0.84 0.59 0.51 0.46 0.45 $ 575 $ 402 $ 345 $ 312 0.49% 0.37% 0.34% 0.30% 0.54 $ 530 0.41 $ 387 0.43 $ 355 0.41% 0.34% 0.30% 3.01 2.38 1.81 4.12 2.24 1.37 0.69 0.43 0.29 $ 954 $ 751 $ 637 $ 549 $ 484 $ 423 0.73% 0.52% 0.50% 0.44% 0.40% 0.36% $ 853 $ 785 $ 571 $ 512 $ 444 0.67% 0.44% 0.41% 0.38% 0.34% $ 846 $ 646 $ 563 $ 471 0.60% 0.37% 0.35% 0.32% 0.62 $ 769 0.64 $ 733 0.58 $ 618 0.48% 0.30% 0.29% 0.87 0.82 0.79 0.81 0.78 0.72 4.37 3.26 1.71 1.15 0.80 0.70 0.73 0.62 0.62 0.58 4.32 2.43 1.96 1.43 0.71 0.63 0.57 0.51 4.08 3.51 2.54 120-­‐minute ramps 0.61 $ 675 0.48 $ 532 0.41 $ 440 0.42% 0.36% 0.32% 57 0.64% 0.62% 0.56% 0.51% 0.45% 0.40% 0.32% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 825 $ 716 $ 613 $ 557 $ 479 $ 434 $ 360 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.91 0.91 0.96 0.99 0.93 0.88 0.78 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 2.38 1.43 0.61 0.32 0.17 0.12 0.06 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 5.13 4.57 3.94 0.55 $ 793 0.56 $ 757 0.56 $ 708 0.60% 0.42% 0.25% KALAEOLA 1X1 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.50 0.26 0.09 0.05 0.02 0.02 0.01 1.28 0.55 0.30 0.13 0.09 0.06 0.79 0.77 0.75 0.63 0.46 0.42 0.34 $ 506 $ 438 $ 366 $ 288 $ 200 $ 178 $ 140 0.35% 0.30% 0.24% 0.16% 0.10% 0.08% 0.07% 1.05 0.98 0.89 0.76 0.71 0.64 $ 781 $ 618 $ 505 $ 383 $ 348 $ 302 0.48% 0.38% 0.33% 0.26% 0.23% 0.18% 1.46 0.78 0.43 0.32 0.21 1.58 0.91 0.73 0.28 0.64 0.63 0.61 0.53 0.42 $ 555 $ 466 $ 399 $ 337 $ 257 0.46% 0.37% 0.30% 0.28% 0.24% 2.07 1.00 0.53 0.63 0.59 0.62 0.44 $ 843 $ 699 $ 685 $ 426 0.42% 0.34% 0.31% 0.20% 0.56 $ 575 0.43 $ 385 0.35 $ 277 0.35% 0.25% 0.19% 2.28 1.81 0.97 #N/A 2.03 1.12 0.52 0.40 0.27 #N/A $ 739 $ 592 $ 423 $ 365 $ 295 #N/A 0.45% 0.38% 0.30% 0.28% 0.25% $ 884 $ 713 $ 553 $ 503 $ 405 0.54% 0.42% 0.35% 0.32% 0.28% $ 923 $ 740 $ 665 $ 421 0.53% 0.39% 0.37% 0.25% 0.69 $ 846 0.66 $ 786 0.49 $ 487 0.53% 0.42% 0.30% #N/A 0.86 0.78 0.63 0.56 0.48 5.38 3.04 1.72 1.32 0.90 0.72 0.70 0.62 0.60 0.51 5.24 3.09 2.46 0.91 0.71 0.68 0.64 0.50 4.37 3.96 1.74 120-­‐minute ramps 0.59 $ 598 0.46 $ 472 0.34 $ 314 0.35% 0.30% 0.21% 58 0.34% 0.30% 0.25% 0.21% 0.15% 0.13% 0.10% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 780 $ 627 $ 496 $ 397 $ 295 $ 294 $ 250 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.92 0.84 0.79 0.70 0.57 0.59 0.52 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.96 1.05 0.46 0.23 0.11 0.08 0.06 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.65 6.81 3.88 0.54 $ 971 0.55 $ 926 0.45 $ 640 0.71% 0.49% 0.27% KALAEOLA 2X2 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.46 0.22 0.08 0.04 0.02 0.02 0.00 1.21 0.53 0.26 0.12 0.09 0.03 0.74 0.71 0.70 0.57 0.41 0.33 0.13 $ 473 $ 401 $ 340 $ 259 $ 182 $ 144 $ 55 0.31% 0.26% 0.20% 0.11% 0.07% 0.05% 0.03% 0.98 0.91 0.84 0.66 0.61 0.41 $ 732 $ 577 $ 469 $ 339 $ 303 $ 186 0.45% 0.35% 0.29% 0.23% 0.20% 0.09% 1.41 0.76 0.40 0.19 0.19 1.52 0.88 0.71 0.27 0.62 0.61 0.56 0.38 0.38 $ 534 $ 451 $ 373 $ 235 $ 235 0.44% 0.36% 0.28% 0.22% 0.22% 2.02 0.98 0.54 0.61 0.58 0.60 0.39 $ 816 $ 681 $ 662 $ 388 0.40% 0.32% 0.30% 0.19% 0.58 $ 578 0.43 $ 379 0.34 $ 274 0.35% 0.24% 0.18% 2.15 1.70 0.94 4.64 1.93 1.00 0.52 0.39 0.14 $ 938 $ 695 $ 539 $ 405 $ 354 $ 201 0.55% 0.42% 0.34% 0.28% 0.25% 0.16% $ 864 $ 694 $ 546 $ 401 $ 401 0.53% 0.41% 0.33% 0.26% 0.26% $ 902 $ 727 $ 552 $ 414 0.52% 0.38% 0.32% 0.24% 0.69 $ 847 0.59 $ 667 0.49 $ 489 0.52% 0.38% 0.30% 0.83 0.81 0.72 0.60 0.54 0.35 5.52 3.00 1.72 0.89 0.89 0.68 0.68 0.60 0.50 0.50 5.21 3.07 1.74 0.91 0.69 0.66 0.57 0.49 4.39 3.02 1.75 120-­‐minute ramps 0.57 $ 576 0.45 $ 454 0.33 $ 300 0.35% 0.29% 0.21% 59 0.35% 0.29% 0.23% 0.18% 0.12% 0.10% 0.04% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 748 $ 605 $ 447 $ 361 $ 276 $ 249 $ 133 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.88 0.82 0.71 0.64 0.53 0.49 0.28 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.83 0.98 0.42 0.19 0.10 0.08 0.03 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.59 6.76 3.83 0.52 $ 954 0.53 $ 911 0.41 $ 610 0.70% 0.49% 0.27% KALAEOLA 3X3 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.46 0.23 0.09 0.04 0.02 0.01 0.00 1.20 0.54 0.25 0.12 0.09 0.03 0.76 0.71 0.64 0.52 0.32 0.19 0.10 $ 484 $ 402 $ 314 $ 233 $ 144 $ 80 $ 42 0.30% 0.25% 0.18% 0.10% 0.05% 0.03% 0.02% 1.01 0.93 0.84 0.64 0.59 0.42 $ 746 $ 587 $ 471 $ 328 $ 294 $ 189 0.44% 0.34% 0.27% 0.22% 0.19% 0.08% 1.43 0.76 0.41 0.20 0.20 1.58 0.89 0.71 0.27 0.61 0.60 0.57 0.39 0.39 $ 529 $ 450 $ 379 $ 240 $ 240 0.44% 0.35% 0.28% 0.21% 0.21% 2.06 0.98 0.53 0.61 0.58 0.61 0.42 $ 822 $ 685 $ 671 $ 407 0.40% 0.32% 0.29% 0.19% 0.56 $ 575 0.42 $ 373 0.34 $ 273 0.34% 0.24% 0.17% 2.23 1.77 0.95 4.66 1.92 1.00 0.52 0.39 0.14 $ 948 $ 703 $ 560 $ 420 $ 361 $ 207 0.55% 0.42% 0.33% 0.27% 0.24% 0.15% $ 870 $ 694 $ 539 $ 482 $ 401 0.52% 0.40% 0.33% 0.30% 0.26% $ 916 $ 734 $ 656 $ 419 0.51% 0.38% 0.35% 0.24% 0.69 $ 850 0.59 $ 667 0.49 $ 486 0.52% 0.37% 0.29% 0.84 0.82 0.75 0.63 0.56 0.36 5.42 3.03 1.72 1.32 0.89 0.69 0.67 0.59 0.56 0.50 5.26 3.08 2.45 0.91 0.70 0.67 0.63 0.50 4.43 3.02 1.73 120-­‐minute ramps 0.57 $ 579 0.45 $ 457 0.33 $ 303 0.34% 0.29% 0.21% 60 0.35% 0.29% 0.22% 0.17% 0.11% 0.07% 0.04% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 755 $ 616 $ 430 $ 350 $ 278 $ 200 $ 128 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.90 0.84 0.68 0.62 0.54 0.41 0.27 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.79 1.00 0.42 0.19 0.10 0.05 0.03 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.64 6.80 3.85 0.52 $ 957 0.53 $ 914 0.43 $ 627 0.69% 0.48% 0.26% KALAEOLA 5X5 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.42 0.19 0.07 0.03 0.01 0.00 0.00 1.16 0.51 0.24 0.11 0.05 0.03 0.71 0.65 0.51 0.40 0.19 0.08 0.00 $ 446 $ 363 $ 248 $ 182 $ 82 $ 33 $ 0 0.26% 0.20% 0.13% 0.07% 0.03% 0.01% 0.00% 0.94 0.87 0.80 0.59 0.44 0.34 $ 700 $ 549 $ 446 $ 303 $ 213 $ 153 0.41% 0.30% 0.24% 0.18% 0.11% 0.05% 1.34 0.74 0.30 0.19 0.10 1.54 0.88 0.50 0.25 0.60 0.58 0.47 0.37 0.25 $ 519 $ 434 $ 304 $ 231 $ 145 0.40% 0.32% 0.22% 0.18% 0.13% 1.67 0.97 0.53 0.59 0.56 0.56 0.40 $ 798 $ 667 $ 582 $ 387 0.38% 0.30% 0.23% 0.17% 0.51 $ 500 0.41 $ 363 0.33 $ 267 0.30% 0.22% 0.16% 2.13 1.69 0.91 4.57 1.87 1.01 0.52 0.26 0.13 $ 887 $ 663 $ 533 $ 396 $ 265 $ 185 0.54% 0.39% 0.31% 0.24% 0.18% 0.12% $ 843 $ 658 $ 466 $ 396 $ 265 0.50% 0.37% 0.27% 0.23% 0.17% $ 903 $ 699 $ 534 $ 412 0.50% 0.36% 0.29% 0.22% 0.69 $ 856 0.59 $ 662 0.49 $ 484 0.51% 0.36% 0.27% 0.76 0.76 0.70 0.58 0.42 0.32 5.56 3.04 1.33 0.90 0.46 0.65 0.62 0.54 0.50 0.36 5.12 3.07 1.74 0.91 0.69 0.62 0.55 0.49 4.48 3.00 1.72 120-­‐minute ramps 0.54 $ 555 0.43 $ 438 0.33 $ 304 0.33% 0.28% 0.20% 61 0.32% 0.25% 0.18% 0.14% 0.07% 0.03% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 703 $ 562 $ 371 $ 282 $ 190 $ 85 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.83 0.76 0.58 0.48 0.36 0.17 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.75 0.93 0.38 0.19 0.08 0.03 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.58 6.75 3.83 0.52 $ 953 0.53 $ 909 0.43 $ 617 0.69% 0.48% 0.25% KALAEOLA 8X8 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.38 0.16 0.05 0.01 0.00 0.00 0.00 1.13 0.46 0.19 0.10 0.04 0.02 0.56 0.50 0.31 0.11 0.00 0.00 0.00 $ 363 $ 280 $ 154 $ 49 $ 0 $ 0 $ 0 0.21% 0.16% 0.09% 0.02% 0.00% 0.00% 0.00% 0.85 0.77 0.63 0.46 0.29 0.20 $ 650 $ 489 $ 351 $ 243 $ 146 $ 92 0.36% 0.25% 0.18% 0.14% 0.08% 0.04% 1.28 0.64 0.27 0.17 0.09 1.61 0.86 0.49 0.24 0.57 0.56 0.44 0.34 0.23 $ 495 $ 408 $ 281 $ 207 $ 134 0.36% 0.27% 0.19% 0.15% 0.11% 1.65 0.95 0.52 0.59 0.54 0.52 0.37 $ 811 $ 643 $ 545 $ 360 0.36% 0.27% 0.20% 0.14% 0.50 $ 494 0.39 $ 351 0.31 $ 253 0.28% 0.21% 0.15% 2.06 1.63 0.85 4.57 1.67 0.89 0.52 0.26 0.13 $ 824 $ 552 $ 430 $ 335 $ 246 $ 151 0.50% 0.33% 0.25% 0.20% 0.15% 0.09% $ 810 $ 621 $ 446 $ 379 $ 243 0.47% 0.33% 0.24% 0.20% 0.14% $ 885 $ 674 $ 518 $ 393 0.48% 0.34% 0.27% 0.20% 0.67 $ 845 0.58 $ 657 0.48 $ 480 0.39% 0.34% 0.26% 0.68 0.61 0.56 0.48 0.38 0.25 5.50 2.69 1.32 0.89 0.45 0.61 0.60 0.51 0.47 0.32 5.15 3.03 1.72 0.90 0.66 0.59 0.52 0.46 4.58 2.96 1.70 120-­‐minute ramps 0.56 $ 557 0.44 $ 439 0.35 $ 305 0.31% 0.27% 0.18% 62 0.27% 0.21% 0.14% 0.07% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 572 $ 452 $ 321 $ 141 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.65 0.59 0.49 0.24 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.58 0.81 0.33 0.10 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.50 6.68 3.77 0.52 $ 947 0.53 $ 904 0.42 $ 604 0.67% 0.46% 0.24% KALAEOLA 13X13 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.33 0.13 0.03 0.00 0.00 0.00 0.00 1.07 0.40 0.17 0.06 0.03 0.00 0.47 0.33 0.17 0.02 0.00 0.00 0.00 $ 308 $ 193 $ 87 $ 10 $ 0 $ 0 $ 0 0.17% 0.12% 0.05% 0.01% 0.00% 0.00% 0.00% 0.75 0.67 0.45 0.27 0.21 0.00 $ 579 $ 422 $ 262 $ 142 $ 107 $ 0 0.31% 0.20% 0.15% 0.09% 0.06% 0.00% 1.26 0.69 0.25 0.16 0.07 1.45 0.82 0.45 0.22 0.53 0.51 0.40 0.32 0.20 $ 467 $ 384 $ 259 $ 197 $ 118 0.33% 0.25% 0.15% 0.12% 0.08% 1.61 0.91 0.48 0.53 0.50 0.48 0.34 $ 730 $ 597 $ 502 $ 332 0.32% 0.24% 0.18% 0.12% 0.49 $ 483 0.35 $ 320 0.26 $ 220 0.26% 0.19% 0.13% 1.99 1.58 0.80 3.74 1.63 0.87 0.38 0.26 0.00 $ 705 $ 516 $ 401 $ 269 $ 209 $ 0 0.41% 0.29% 0.22% 0.15% 0.12% 0.00% $ 793 $ 590 $ 422 $ 341 $ 226 0.44% 0.29% 0.21% 0.18% 0.12% $ 870 $ 657 $ 494 $ 353 0.46% 0.32% 0.25% 0.18% 0.63 $ 751 0.57 $ 634 0.47 $ 467 0.36% 0.32% 0.24% 0.60 0.57 0.51 0.39 0.32 0.00 5.28 2.60 1.28 0.87 0.44 0.60 0.56 0.48 0.41 0.30 5.10 2.93 1.65 0.87 0.66 0.58 0.50 0.40 3.74 2.84 1.62 120-­‐minute ramps 0.53 $ 537 0.42 $ 423 0.34 $ 297 0.30% 0.25% 0.17% 63 0.23% 0.17% 0.10% 0.01% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 506 $ 394 $ 239 $ 33 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.56 0.51 0.37 0.05 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.45 0.74 0.25 0.02 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.29 6.48 3.65 0.51 $ 921 0.52 $ 879 0.42 $ 598 0.66% 0.45% 0.22% KALAEOLA 20X20 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.25 0.09 0.01 0.00 0.00 0.00 0.00 0.94 0.32 0.11 0.03 0.00 0.00 0.39 0.24 0.08 0.03 0.00 0.00 0.00 $ 251 $ 137 $ 41 $ 12 $ 0 $ 0 $ 0 0.13% 0.09% 0.02% 0.00% 0.00% 0.00% 0.00% 0.65 0.56 0.33 0.15 0.00 0.00 $ 508 $ 351 $ 188 $ 76 $ 0 $ 0 0.26% 0.16% 0.10% 0.04% 0.00% 0.00% 1.12 0.62 0.21 0.13 0.06 1.21 0.57 0.38 0.18 0.47 0.43 0.34 0.25 0.15 $ 409 $ 334 $ 218 $ 156 $ 87 0.28% 0.21% 0.12% 0.09% 0.06% 1.20 0.84 0.44 0.46 0.42 0.39 0.28 $ 626 $ 476 $ 415 $ 268 0.27% 0.18% 0.15% 0.10% 0.37 $ 360 0.32 $ 294 0.23 $ 190 0.21% 0.17% 0.11% 1.93 1.53 0.77 3.44 1.44 0.70 0.24 0.00 0.00 $ 667 $ 475 $ 317 $ 166 $ 0 $ 0 0.36% 0.24% 0.17% 0.09% 0.00% 0.00% $ 782 $ 534 $ 379 $ 303 $ 184 0.41% 0.25% 0.18% 0.15% 0.10% $ 843 $ 577 $ 477 $ 310 0.44% 0.26% 0.22% 0.15% 0.57 $ 688 0.54 $ 604 0.45 $ 445 0.34% 0.30% 0.22% 0.57 0.53 0.40 0.24 0.00 0.00 5.24 2.19 1.20 0.81 0.41 0.59 0.53 0.42 0.36 0.23 5.03 2.18 1.56 0.81 0.63 0.55 0.49 0.35 3.50 2.66 1.53 120-­‐minute ramps 0.53 $ 528 0.42 $ 416 0.33 $ 287 0.27% 0.23% 0.15% 64 0.20% 0.14% 0.07% 0.01% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 467 $ 323 $ 147 $ 33 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.52 0.41 0.22 0.06 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.31 0.65 0.17 0.02 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.17 6.38 3.43 0.49 $ 902 0.50 $ 861 0.40 $ 575 0.63% 0.44% 0.21% KALAEOLA 30X30 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.18 0.05 0.01 0.00 0.00 0.00 0.00 0.80 0.23 0.06 0.02 0.00 0.00 0.27 0.18 0.06 0.03 0.00 0.00 0.00 $ 178 $ 101 $ 30 $ 13 $ 0 $ 0 $ 0 0.10% 0.05% 0.01% 0.00% 0.00% 0.00% 0.00% 0.47 0.38 0.23 0.14 0.00 0.00 $ 386 $ 242 $ 124 $ 69 $ 0 $ 0 0.22% 0.12% 0.06% 0.03% 0.00% 0.00% 0.99 0.47 0.17 0.04 0.00 1.14 0.47 0.30 0.15 0.37 0.32 0.25 0.13 0.00 $ 334 $ 250 $ 162 $ 77 $ 0 0.24% 0.16% 0.09% 0.04% 0.00% 1.14 0.74 0.37 0.37 0.31 0.28 0.21 $ 530 $ 361 $ 305 $ 206 0.24% 0.15% 0.12% 0.07% 0.35 $ 344 0.31 $ 276 0.20 $ 169 0.19% 0.15% 0.10% 1.90 1.50 0.74 3.30 1.34 0.56 0.23 0.00 0.00 $ 652 $ 442 $ 253 $ 151 $ 0 $ 0 0.31% 0.21% 0.12% 0.07% 0.00% 0.00% $ 752 $ 498 $ 340 $ 165 $ 0 0.38% 0.22% 0.16% 0.08% 0.00% $ 800 $ 534 $ 437 $ 274 0.42% 0.24% 0.20% 0.13% 0.53 $ 644 0.51 $ 564 0.42 $ 409 0.33% 0.28% 0.20% 0.57 0.49 0.32 0.21 0.00 0.00 5.19 2.03 1.10 0.38 0.00 0.56 0.49 0.37 0.21 0.00 4.91 2.01 1.40 0.74 0.59 0.51 0.45 0.30 3.32 2.47 1.39 120-­‐minute ramps 0.48 $ 489 0.38 $ 385 0.31 $ 272 0.25% 0.22% 0.14% 65 0.17% 0.09% 0.05% 0.01% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 435 $ 251 $ 142 $ 38 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.49 0.33 0.21 0.07 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.23 0.46 0.17 0.02 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 7.08 6.30 3.36 0.46 $ 879 0.47 $ 839 0.39 $ 561 0.62% 0.43% 0.20% KALAEOLA 50X50 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.15 0.03 0.00 0.00 0.00 0.00 0.00 0.65 0.20 0.04 0.01 0.00 0.00 0.20 0.10 0.03 0.03 0.00 0.00 0.00 $ 132 $ 58 $ 14 $ 11 $ 0 $ 0 $ 0 0.07% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.42 0.29 0.12 0.03 0.00 0.00 $ 336 $ 190 $ 65 $ 18 $ 0 $ 0 0.16% 0.08% 0.03% 0.01% 0.00% 0.00% 1.30 0.32 0.09 0.04 0.00 0.90 0.39 0.26 0.13 0.40 0.27 0.13 0.08 0.00 $ 387 $ 200 $ 87 $ 47 $ 0 0.23% 0.11% 0.05% 0.03% 0.00% 1.11 0.68 0.31 0.32 0.27 0.23 0.13 $ 444 $ 312 $ 253 $ 143 0.19% 0.12% 0.09% 0.05% 0.35 $ 340 0.25 $ 234 0.17 $ 140 0.17% 0.13% 0.07% 1.83 1.45 0.73 3.02 1.19 0.31 0.10 0.00 0.00 $ 588 $ 348 $ 179 $ 82 $ 0 $ 0 0.26% 0.16% 0.06% 0.03% 0.00% 0.00% $ 615 $ 442 $ 228 $ 148 $ 0 0.26% 0.19% 0.10% 0.06% 0.00% $ 638 $ 475 $ 378 $ 230 0.28% 0.21% 0.16% 0.10% 0.53 $ 654 0.45 $ 513 0.36 $ 356 0.34% 0.26% 0.17% 0.50 0.37 0.24 0.12 0.00 0.00 3.84 2.00 0.70 0.35 0.00 0.49 0.42 0.26 0.18 0.00 3.35 1.98 1.37 0.69 0.51 0.43 0.37 0.24 3.46 2.32 1.26 120-­‐minute ramps 0.42 $ 447 0.33 $ 353 0.25 $ 234 0.23% 0.19% 0.12% 66 0.13% 0.06% 0.01% 0.01% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 348 $ 206 $ 41 $ 31 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.37 0.28 0.07 0.05 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 1.09 0.33 0.04 0.02 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 6.74 6.00 3.30 0.47 $ 856 0.48 $ 817 0.37 $ 538 0.59% 0.41% 0.18% KALAEOLA 80X80 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.11 0.03 0.00 0.00 0.00 0.00 0.00 0.58 0.13 0.03 0.01 0.00 0.00 0.17 0.10 0.03 0.03 0.00 0.00 0.00 $ 107 $ 55 $ 14 $ 11 $ 0 $ 0 $ 0 0.03% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.44 0.24 0.11 0.03 0.00 0.00 $ 333 $ 148 $ 63 $ 17 $ 0 $ 0 0.12% 0.04% 0.02% 0.01% 0.00% 0.00% 1.23 0.29 0.08 0.03 0.00 0.88 0.36 0.13 0.13 0.38 0.29 0.14 0.07 0.00 $ 365 $ 204 $ 87 $ 44 $ 0 0.20% 0.08% 0.03% 0.02% 0.00% 1.05 0.64 0.28 0.33 0.29 0.15 0.15 $ 453 $ 321 $ 151 $ 151 0.15% 0.09% 0.03% 0.03% 0.33 $ 320 0.22 $ 210 0.16 $ 133 0.14% 0.10% 0.06% 1.78 1.41 0.73 3.01 0.97 0.39 0.10 0.00 0.00 $ 562 $ 313 $ 207 $ 81 $ 0 $ 0 0.24% 0.11% 0.06% 0.02% 0.00% 0.00% $ 578 $ 397 $ 231 $ 148 $ 0 0.25% 0.16% 0.07% 0.04% 0.00% $ 606 $ 438 $ 232 $ 232 0.27% 0.18% 0.08% 0.08% 0.51 $ 638 0.43 $ 490 0.30 $ 315 0.33% 0.24% 0.15% 0.47 0.35 0.27 0.12 0.00 0.00 3.68 1.92 0.67 0.34 0.00 0.45 0.36 0.26 0.19 0.00 3.21 1.93 0.68 0.68 0.49 0.39 0.25 0.25 3.47 2.30 1.24 120-­‐minute ramps 0.43 $ 449 0.34 $ 354 0.18 $ 184 0.20% 0.17% 0.10% 67 0.09% 0.04% 0.01% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 304 $ 204 $ 40 $ 31 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.34 0.28 0.07 0.05 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.83 0.31 0.03 0.02 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 4.93 4.39 3.13 0.38 $ 649 0.39 $ 619 0.34 $ 500 0.32% 0.22% 0.16% KALAEOLA 130X130 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.06 0.02 0.00 0.00 0.00 0.00 0.00 0.43 0.07 0.03 0.01 0.00 0.00 0.12 0.09 0.01 0.00 0.00 0.00 0.00 $ 76 $ 47 $ 6 $ 0 $ 0 $ 0 $ 0 0.02% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.38 0.17 0.10 0.03 0.00 0.00 $ 279 $ 99 $ 57 $ 16 $ 0 $ 0 0.09% 0.02% 0.01% 0.00% 0.00% 0.00% 0.57 0.15 0.07 0.03 0.00 0.60 0.21 0.11 0.11 0.29 0.20 0.12 0.06 0.00 $ 242 $ 136 $ 76 $ 39 $ 0 0.11% 0.04% 0.02% 0.01% 0.00% 0.91 0.54 0.00 0.28 0.21 0.12 0.12 $ 360 $ 223 $ 129 $ 129 0.11% 0.05% 0.02% 0.02% 0.25 $ 255 0.20 $ 189 0.00 $ 0 0.12% 0.08% 0.00% 1.53 1.21 0.62 2.34 0.53 0.27 0.09 0.00 0.00 $ 449 $ 223 $ 158 $ 73 $ 0 $ 0 0.21% 0.06% 0.03% 0.01% 0.00% 0.00% $ 479 $ 284 $ 204 $ 133 $ 0 0.22% 0.11% 0.06% 0.03% 0.00% $ 508 $ 295 $ 207 $ 207 0.24% 0.12% 0.07% 0.07% 0.44 $ 554 0.36 $ 438 0.00 $ 0 0.27% 0.21% 0.00% 0.38 0.27 0.22 0.11 0.00 0.00 3.07 1.22 0.61 0.31 0.00 0.38 0.28 0.23 0.17 0.00 2.86 1.24 0.62 0.62 0.39 0.27 0.22 0.22 3.04 2.25 0.00 120-­‐minute ramps 0.38 $ 387 0.30 $ 305 0.15 $ 155 0.17% 0.15% 0.08% 68 0.05% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 230 $ 173 $ 17 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.28 0.24 0.03 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.50 0.25 0.02 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 4.58 4.08 2.80 0.34 $ 597 0.35 $ 570 0.31 $ 445 0.29% 0.20% 0.14% KALAEOLA 200X200 km IDEAL FORECAST Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) Buffer losses One-­‐minute ramps Maximum acceptable ramp (% installed PV capacity) 0.5% 1% 3% 5% 10% 15% 25% 0.05 0.02 0.00 0.00 0.00 0.00 0.00 0.28 0.07 0.03 0.00 0.00 0.00 0.11 0.07 0.00 0.00 0.00 0.00 0.00 $ 66 $ 38 $ 0 $ 0 $ 0 $ 0 $ 0 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.32 0.15 0.09 0.00 0.00 0.00 $ 222 $ 90 $ 52 $ 0 $ 0 $ 0 0.06% 0.02% 0.01% 0.00% 0.00% 0.00% 0.39 0.10 0.03 0.00 0.00 0.48 0.10 0.10 0.00 0.25 0.15 0.06 0.00 0.00 $ 198 $ 96 $ 35 $ 0 $ 0 0.09% 0.02% 0.01% 0.00% 0.00% 0.43 0.20 0.00 0.25 0.11 0.11 0.00 $ 310 $ 114 $ 114 $ 1 0.09% 0.02% 0.02% 0.00% 0.18 $ 164 0.14 $ 110 0.00 $ 0 0.07% 0.03% 0.00% 1.22 0.97 0.46 2.00 0.47 0.24 0.00 0.00 0.00 $ 379 $ 198 $ 141 $ 0 $ 0 $ 0 0.20% 0.05% 0.03% 0.00% 0.00% 0.00% $ 409 $ 217 $ 118 $ 0 $ 0 0.21% 0.07% 0.03% 0.00% 0.00% $ 455 $ 179 $ 179 $ 0 0.23% 0.06% 0.06% 0.00% 0.30 $ 373 0.19 $ 214 0.00 $ 0 0.20% 0.11% 0.00% 0.32 0.24 0.19 0.00 0.00 0.00 2.69 0.80 0.27 0.00 0.00 0.32 0.23 0.15 0.00 0.00 2.52 0.54 0.54 0.00 0.35 0.19 0.19 0.00 1.93 1.00 0.00 120-­‐minute ramps 0.26 $ 287 0.21 $ 226 0.12 $ 124 0.16% 0.13% 0.07% 69 0.04% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 60-­‐minute ramps 120-­‐minute ramps 10% 15% 25% $ 197 $ 145 $ 0 $ 0 $ 0 $ 0 $ 0 30-­‐minute ramps 60-­‐minute ramps 10% 15% 25% 0.25 0.21 0.00 0.00 0.00 0.00 0.00 15-­‐minute ramps 30-­‐minute ramps 5% 10% 15% 25% 0.41 0.20 0.00 0.00 0.00 0.00 0.00 5-­‐minute ramps 15-­‐minute ramps 3% 5% 10% 15% 25% Buffer losses One-­‐minute ramps 5-­‐minute ramps 1% 3% 5% 10% 15% 25% NO FORECASTS Buffer Buffer energy power Buffer capacity capacity cost (kWh) (kW) 2.59 2.30 2.30 0.23 $ 371 0.24 $ 354 0.24 $ 354 0.20% 0.14% 0.14%